REKAPITULASI RENCANA ANGGARAN BIAYA MEBELER

PEKERJAAN PERENCANAAN MEBELER GEDUNG DISHUB PARKIR KOTA BANDUNG

NO URAIAN JML HARGA


BIAYA PERSIAPAN PEKERJAAN 700,000.00
LANTAI 1 172,866,477.50
LANTAI 2 186,797,775.00
JUMLAH SUB TOTAL 360,364,252.50
PPN 10% 36,036,425.25
JUMLAH TOTAL ANGGARAN 396,400,677.75

HARGA PERKIRAAN SENDIRI BIAYA INTERIOR GEDUNG DISHUB PARKIR BANDUNG

PEKERJAAN : PERENCANAAN MEBELER GEDUNG DISHUB PARKIR KOTA BANDUNG


LOKASI : JL. BANDUNG

HARGA
NO URAIAN PEKERJAAN VOL SAT JUMLAH
SATUAN
BIAYA PERSIAPAN PEKERJAAN
Dokumentasi dan pelaporan 1.00 ls 700,000.00 700,000.00
JUMLAH BIAYA PERSIAPAN PEKERJAAN 700,000.00

PEKERJAAN INTERIOR LANTAI SATU


I RUANG CS dan HALL
Kursi Hadap 3.00 bh 1,300,000.00 3,900,000.00
Meja Tamu 1.00 bh 1,000,000.00 1,000,000.00
Meja CS 1.00 unit 15,000,000.00 15,000,000.00
Credenza 1.00 unit 8,770,950.00 8,770,950.00
Jumlah I 28,670,950.00
II RUANG RAPAT
Meja Rapat 1,2x4,2m 1.00 bh 21,200,256.00 21,200,256.00
Kursi Rapat 13.00 bh 1,785,000.00 23,205,000.00
Kursi Pimpinan Rapat 1.00 bh 1,785,000.00 1,785,000.00
Kursi Rapat Belakang 28.00 bh 500,000.00 14,000,000.00
Credenza 3m 1.00 unit 10,963,687.50 10,963,687.50
Pertikal Blaind 18.36 M2 303,450.00 5,571,342.00
Jumlah II 76,725,285.50
III RUANG KEUANGAN
Kursi Kerja 4.00 bh 1,300,000.00 5,200,000.00
Credenza 2,1m 1.00 unit 8,770,950.00 8,770,950.00
Kursi Hadap 2.00 bh 945,000.00 1,890,000.00
Meja setengah biro 120x60 3.00 unit 2,325,000.00 6,975,000.00
Pertikal Blaind 18.36 M2 303,450.00 5,571,342.00
Jumlah III 28,407,292.00
IV RUANG CC-ROOM
Meja setengah biro 120x60 1.00 unit 2,325,000.00 2,325,000.00
Kursi Kerja 1.00 1,300,000.00 1,300,000.00
HARGA
NO URAIAN PEKERJAAN VOL SAT JUMLAH
SATUAN
Jumlah IV 3,625,000.00
V RUANG STAFF FUNGSIONAL
Kursi Kerja 17.00 bh 1,300,000.00 22,100,000.00
Pertikal Blind 11.00 M2 303,450.00 3,337,950.00
Jumlah V 25,437,950.00
VI RUANG KASIR HARIAN
Meja Counter 1.00 5,000,000.00 5,000,000.00
kursi kerja 3.00 1,300,000.00 3,900,000.00
Jumlah VI 8,900,000.00
VII MUSHOLA
Pas. Karpet mushola 10.00 m2 110,000.00 1,100,000.00
Jumlah VII 1,100,000.00
PEKERJAAN INTERIOR LANTAI DUA
I RUANG KEPALA
Kursi Kerja 1.00 bh 2,730,000.00 2,730,000.00
sofa 1 set 1.00 unit 15,000,000.00 15,000,000.00
Credensa 1.00 unit 8,770,950.00 8,770,950.00
Kursi Hadap 2.00 bh 1,785,000.00 3,570,000.00
Pas. Karpet Ruangan 34.40 m2 350,000.00 12,040,000.00
Pertikal Blaind 7.50 M2 303,450.00 2,275,875.00
Jumlah I 44,386,825.00
II RUANG WAKIL KEPALA
Meja kerja 1.00 unit 5,420,000.00 5,420,000.00
Credensa 1.00 unit 8,770,950.00 8,770,950.00
Kursi Kerja 1.00 bh 2,730,000.00 2,730,000.00
Kursi Hadap 2.00 bh 945,000.00 1,890,000.00
Jumlah II 18,810,950.00
III RUANG SATUAN PENGAWAS INTERNAL
Kursi Kerja 2.00 bh 1,300,000.00 2,600,000.00
Jumlah III 2,600,000.00
IV RUANG KORWIL
Kursi Kerja 4.00 bh 1,300,000.00 5,200,000.00
Jumlah IV 5,200,000.00
V RUANG STAFF FUNGSIONAL
Meja Work Station 4 meja 6.00 unit 9,300,000.00 55,800,000.00
Meja Work Station 2 meja 1.00 unit 4,650,000.00 4,650,000.00
Meja setengah biro 120x60 2.00 unit 2,325,000.00 4,650,000.00
Kursi Kerja 38.00 bh 1,300,000.00 49,400,000.00
Jumlah V 114,500,000.00
VI RUANG HALL
Kursi Kerja 1.00 bh 1,300,000.00 1,300,000.00
Jumlah VI 1,300,000.00
REKAPITULASI RENCANA ANGGARAN BIAYA FISIK GEDUNG
PEKERJAAN PERENCANAAN INTERIOR GEDUNG DISHUB PARKIR KOTA BANDUNG

NO URAIAN JML HARGA

BIAYA PERSIAPAN PEKERJAAN 6,405,000.00


LANTAI 1 128,346,109.20
LANTAI 2 144,657,790.00
PEKERJAAN LAIN-LAIN 59,770,000.00
JUMLAH SUB TOTAL 339,178,899.20
PPN 10% 33,917,889.92
JUMLAH TOTAL ANGGARAN 373,096,789.12

HARGA PERKIRAAN SENDIRI BIAYA INTERIOR GEDUNG DISHUB PARKIR BANDUNG

PEKERJAAN : PERENCANAAN INTERIOR GEDUNG DISHUB PARKIR KOTA BANDUNG


LOKASI : JL. BANDUNG

HARGA
NO URAIAN PEKERJAAN VOL SAT JUMLAH
SATUAN
BIAYA PERSIAPAN PEKERJAAN
Perlengkapan Keselamatan Kerja K3 1.00 ls 2,000,000.00 2,000,000.00
Pembersihan lokasi 1.00 ls 1,000,000.00 1,000,000.00
Penyiapan listrik 1.00 ls 700,000.00 700,000.00
Pembuatan dokumentasi awal lokasi 1.00 ls 800,000.00 800,000.00
Pek. Bongkaran Dinding Bata 15.00 m2 25,000.00 375,000.00
Pek. Bongkaran Dinding Kusen Almuinum 90.00 m2 15,000.00 1,350,000.00
Pe. Bongkaran Plafond 12.00 M2 15,000.00 180,000.00
JUMLAH BIAYA PERSIAPAN PEKERJAAN 6,405,000.00

PEKERJAAN INTERIOR LANTAI SATU


I RUANG CS dan HALL
Pengecatan dinding 61.52 m2 25,000.00 1,538,000.00
Pasang Dinding Partisi 2 muka 12.65 m2 222,000.00 2,808,388.80
Back Droff CS 8.40 m2 1,276,000.00 10,718,400.00
Pas, Pintu dan daun pintu Almunium 1.00 unit 5,400,000.00 5,400,000.00
Pas. Titik penerangan 6.00 bh 225,000.00 1,350,000.00
Pas. Stop kontak 2.00 bh 65,000.00 130,000.00
Pas. Lampu Pita droff sealing 8.00 m1 75,000.00 600,000.00
Pas. Lampu Downlight 6.00 bh 75,000.00 450,000.00
Jumlah I 22,994,788.80
II RUANG RAPAT
Pasang Dinding Partisi 2 muka 2.20 m2 222,000.00 488,400.00
Back Droff Layar Infocus 13.92 m2 1,276,000.00 17,761,920.00
Pas. Titik stop kontak 2.00 bh 225,000.00 450,000.00
Pas. Stop kontak 2.00 bh 65,000.00 130,000.00
Pasang Wall Paper 30.62 m2 208,000.00 6,369,792.00
Treatment dinding/kolom 80 cm 10.21 m2 950,000.00 9,697,600.00
Pas. Barcket Infocus 1.00 UNIT 1,650,000.00 1,650,000.00
HARGA
NO URAIAN PEKERJAAN VOL SAT JUMLAH
SATUAN
Jumlah II 36,547,712.00
III RUANG KEUANGAN
Pasangan keramik ex. Km 10.00 m2 250,000.00 2,500,000.00
Pasang Dinding Partisi 2 muka 14.46 m2 222,000.00 3,209,587.20
Pas. Titik stop kontak 2.00 bh 225,000.00 450,000.00
Pas. Stop kontak 4.00 bh 65,000.00 260,000.00
Pas, Pintu dan daun pintu Almunium 1.00 unit 2,200,000.00 2,200,000.00
Pasang Wall Paper 41.76 m2 208,000.00 8,686,080.00
Jumlah III 17,305,667.20
IV RUANG CC-ROOM
Back Drop TV. CCROOM 7.52 m2 1,276,000.00 9,595,520.00
Pengecatan dinding 33.36 m2 25,000.00 834,000.00
Pasang Perangkat CC ROOM 1.00 set 3,492,900.00 3,492,900.00
Jumlah IV 13,922,420.00
V RUANG STAFF FUNGSIONAL
Pasang Wall Paper 54.37 m2 208,000.00 11,308,211.20
Pas. Titik stop kontak 2.00 bh 225,000.00 450,000.00
Pas. Stop kontak 2.00 bh 65,000.00 130,000.00
Pas. Plafond 64.25 m2 110,000.00 7,067,500.00
Pengecatan Plafond 64.25 m2 35,000.00 2,248,750.00
Jumlah V 21,204,461.20
VI RUANG KASIR HARIAN
Pasang Wall Paper 34.32 m2 208,000.00 7,138,560.00
Pas. Titik stop kontak 2.00 bh 225,000.00 450,000.00
Pas. Stop kontak 2.00 bh 65,000.00 130,000.00
Jumlah VI 7,718,560.00
VII RUANG STAFF BELAKANG
Pengecatan dinding 24.15 m2 25,000.00 603,750.00
Jumlah VII 603,750.00
VIII MUSHOLA
Pengecatan dinding 42.40 m2 25,000.00 1,060,000.00
Pengecatan Plafond 12.00 m2 35,000.00 420,000.00
Jumlah VIII 1,480,000.00
IX KANTIN
Pasangan keramik 40x40 21.60 m2 250,000.00 5,400,000.00
Pengecatan dinding 46.75 m2 25,000.00 1,168,750.00
Jumlah IX 6,568,750.00
JUMLAH BIAYA INTERIOR LANTAI 1 128,346,109.20

PEKERJAAN INTERIOR LANTAI DUA


I RUANG KEPALA
Pasang Wall Paper 63.75 m2 208,000.00 13,260,000.00
Pek. Peninggian lantai kursi hadap 3.33 m2 222,000.00 738,150.00
Treatment dinding/kolom 80 cm 17.00 m2 950,000.00 16,150,000.00
Pas, Pintu dan daun pintu Almunium 1.00 unit 2,200,000.00 2,200,000.00
Pas. Plafond Droff seling gypsum rangka holo 51.60 m2 120,000.00 6,192,000.00
Pengecatan Plafond 51.60 m2 35,000.00 1,806,000.00
Jumlah I 40,346,150.00
II RUANG WAKIL KEPALA
Pasang Wall Paper 36.03 m2 208,000.00 7,493,200.00
HARGA
NO URAIAN PEKERJAAN VOL SAT JUMLAH
SATUAN
Pasang Dinding Partisi 2 muka 15.30 m2 222,000.00 3,396,600.00
Treatment dinding/kolom 80 cm 13.10 m2 950,000.00 12,445,000.00
Pas, Pintu dan daun pintu Almunium 1.00 unit 2,200,000.00 2,200,000.00
Pas. Titik stop kontak 1.00 bh 225,000.00 225,000.00
Pas. Stop kontak 1.00 bh 65,000.00 65,000.00
Jumlah II 25,824,800.00
III RUANG SATUAN PENGAWAS INTERNAL
Pasang Wall Paper 49.13 m2 208,000.00 10,218,000.00
Pasang Dinding Partisi 2 muka 15.30 m2 222,000.00 3,396,600.00
Pas, Pintu dan daun pintu Almunium 1.00 unit 2,200,000.00 2,200,000.00
Jumlah III 15,814,600.00
IV RUANG KORWIL
Pasang Wall Paper 49.13 m2 208,000.00 10,218,000.00
Pas, Pintu dan daun pintu Almunium 1.00 unit 2,200,000.00 2,200,000.00
Jumlah IV 12,418,000.00
V RUANG STAFF FUNGSIONAL
Pasang Wall Paper 121.27 m2 208,000.00 25,223,640.00
Pas. Titik stop kontak 5.00 bh 225,000.00 1,125,000.00
Pas. Stop kontak 38.00 bh 65,000.00 2,470,000.00
Pas, Pintu dan daun pintu Almunium 2 pintu 1.00 unit 4,400,000.00 4,400,000.00
Pas, Pintu dan daun pintu Almunium 1 pintu 1.00 unit 2,200,000.00 2,200,000.00
Jumlah V 35,418,640.00
VI RUANG HALL
Pengecatan dinding 71.33 m2 208,000.00 14,835,600.00
Jumlah VI 14,835,600.00
JUMLAH BIAYA INTERIOR LANTAI DUA 144,657,790.00

PEKERJAAN LAIN-LAIN
Pek. Taman Belakang 12.25 m2 1,500,000.00 18,375,000.00
Pasangan Keramik yang pecah Lantai 1 dan 2 kerusakan 20% 78.00 m2 250,000.00 19,500,000.00
Pengecatan bidang plat besi piling cabiet 39.10 m2 370,000.00 14,467,000.00
Melamik Meja-Pimpinan dan meja 160x70 27.00 m2 164,000.00 4,428,000.00
Pembersihan sisa Pekerjaan 1.00 ls 3,000,000.00 3,000,000.00
JUMLAH BIAYA LAIN-LAIN 59,770,000.00