Professional Documents
Culture Documents
Excess Work & Work Not Done Div. Eng/Dist. Irrig.Eng Office……………………………….
Name of Institution: C/Agamathi Vidyalaya
Work Description : Construction chain link and fence
Contract Amount(excluiding GST) Rs. Cts.
(as per contract agreement) Quantity Amount for
BOQ Item Actually Actual Work
Short Description of Work Unit Qty. Rate In excess Not Done Excess
No Done Done
1.00 2.00 3.00 4.00 5.00 6=5-3 7=3-5 8=4x5 9=4x6
1 2" G I Post 630.00 12.50 133,875.00 7,875.00
L.ft. 200.00 126,000.00
212.50
2 1" G I horizontal bracing 245.00 192.89 113,461.95
L.ft. 656.00 160,720.00
463.11
3 2" x 2" chain link fence 80.00 383.28 100,537.60
Sq.ft. 1,640.00 131,200.00
1256.72
4 20 mm x 6 mm flat iron 135.00 64.00 18,360.00
L.ft. 200.00 27,000.00
136.00
5 Double sash gate 71,500.00 0.00 0.00 71,500.00 0.00
Item 1.00 71,500.00
1.00
6 Removing gate & handing over to 1,500.00 0.00 0.00 1,500.00 0.00
principal Item 1.00 1,500.00
1.00
Grand Total 517,920.00 439,234.55 7,875.00
discount 15%
contract am
balance 6,772.67
FINAL
…………. Approval
A
Work Not
Reasons
Done
10=4x7
126,000.00 0.00
47,258.05
160,720.00 0.00
30,662.40
131,200.00 0.00
8,640.00
27,000.00 0.00
0.00
71,500.00 0.00
0.00
1,500.00 0.00
86,560.45
517,920.00
Form - B Comparative Statement FINAL
Extra Contractual Works Div. Eng/Dist. Irrig.Eng Office………………………………. Approval
Name of Institution: C/Agamathi Vidyalaya B
Work Description : Construction chain link and fence
Contract Amount(excluiding GST) Rs. Cts.
Rate
Amount
Item No Description of Work Quantity Unit Recommende Recommended Reasons
Dept Contractor's d by the by the Engineer
Engineer
1 2 3 4 5 6 7 8=3x7 9
Ex-1 demolishing concrete 0.48 cube 18,745.00 8,997.60
Ex-2 4 1/2" bk. Work 0.32 sqr 13,670.00 4,374.40
Ex-3 excavation 0.31 cube 1,460.00 452.60
Ex-4 3" thk. screed 0.12 sqr 8,925.00 1,071.00
Ex-5 tor steel 49.24 kg 203.00 9,995.72
Ex-6 mild steel 7.44 kg 179.00 1,331.76
Ex-7 form work 0.80 sqr 10,000.00 8,000.00
Ex-8 G25 reinforced 0.26 cube 46,900.00 12,194.00
concrete
Ex-9 rough plastering 1.32 sqr 5,045.00 6,659.40
Ex-10 painting primer 1.32 sqr 1,385.00 1,828.20
Ex-11 painting weathershield 1.32 sqr 2,480.00 3,273.60
As per Guidelines on Government Tender Procedure (Revised Edition - August 1997) & Public Finance Circular No. 352(11) of 09.02.2001
Note :- The GST values for rows 2 to 8 I certified that the details given above are true and correct
should be given only if the contractor is
registered for GST
………………………………………………..
Date:-……………………… Divisional Engineer/Dist .Irrig. Engineer
FINAL Approval
Summary
ghe(SLTS 11B)
S Special Grade)
k Not Done
Total
519,849.60
517,920.00
7,875.00
73,842.38
81,717.38
86,560.45
4,843.07
513,076.93
…………………………………………..
visional Engineer/Dist .Irrig. Engineer
Variation To Contracts
Contingencies 1,929.60
Excess 7,875.00
Extra 73,842.38
574,646.16