CEMENT
1 CEMENT GR 43 OPC BAG 1,996.000 2,100.000 2,100.000 70,835.000 470.000 470.000 67,209.000 3,626.000 111060.000 40,225.000
PLANT PRODUCTION
SL NO PRODUCT NAME UOM TODAY THIS MONTH COMMULITIVE
1 GSB MT - - -
2 WMM MT 383.740 383.740 124,472.920
3 CTSB MT - - -
4 CTB MT - - -
5 DBM MT - - 19,566.430
6 OGPS MT - - 205.740
7 BC MT - - -
8 RMC M-15 PCC M3 15.500 15.500 3,046.300
9 RMC M-20 RCC M3 - - 34.000
10 RMC M-25 RCC M3 19.500 19.500 2,588.500
11 RMC M-30 RCC M3 - - 202.000
12 RMC M-35 RCC M3 - - -
13 DLC M3 - - 1,682.000
14 PQC M3 32.000 32.000 2,443.000
APCO INFRATECH PVT LTD
HALIYAPUR-KUDEBHAR ROAD PROJECT,PKG:II
DAILY MATERIALS REPORT (SUMMARY) - AS ON DATE : 02/01/2019
RECEIVED ISSUED
OPENING CLOSING BALANCE TO
SL NO ITEM DESCRIPTION UOM
BALANCE TODAY THIS MONTH CUMMULITIVE TODAY THIS MONTH CUMMULITIVE BALANCE BOQ BE RECEIVE
CEMENT
1 CEMENT GR 43 OPC BAG 3,626.000 2,792.000 4,892.000 73,627.000 282.000 752.000 67,491.000 6,136.000 111060.000 37,433.000
PLANT PRODUCTION
SL NO PRODUCT NAME UOM TODAY THIS MONTH COMMULITIVE
1 GSB MT - - -
2 WMM MT - 383.740 124,472.920
3 CTSB MT - - -
4 CTB MT - - -
5 DBM MT 375.190 375.190 19,941.620
6 OGPS MT - - 205.740
7 BC MT - - -
8 RMC M-15 PCC M3 25.500 41.000 3,071.800
9 RMC M-20 RCC M3 - - 34.000
10 RMC M-25 RCC M3 24.500 44.000 2,613.000
11 RMC M-30 RCC M3 - - 202.000
12 RMC M-35 RCC M3 - - -
13 DLC M3 3.000 3.000 1,685.000
14 PQC M3 - 32.000 2,443.000