9500
5. Exact floor pattern and setting out to
DE2 be confirmed on site with Architect.
FE
6. Provide screeding as necessary to
CCTV Room
RF1 RF1 RF1 F2a ensure same FFL for all site areas.
F3a F2b F2b RF1 7. Screeding and finishes at the toilets
D11 RF1 F4
F3b are to lay to fall to floor drains typical.
AV
D3
F4
EXIT 8. All material to be as per the latest
F2a F2a cabinet F2a F2b D2 HR provisions required in Building
F
MCB RF2 New
HR D12 FE
D5 D4 D4 RF1 Regulations / Lingnan / M+
D10 F2a 12/F STAIR requirements.
F2a
F2a F1 F4 LOBBY
RF1 RF1 RF1
1:100