Progress Report for - SRDP Package - II - LB Nagar Up to 31-03-2023.

SL Work Done
Location Items Qty % of Work For IPC 53 Remarks
No Amount
IPC - 53
Foundations - P21 & A3 02 nos 45,17,784 0.128% 45,17,784 Completed
Piers Vertical Stressing 04 nos 14,47,103 0.041% 14,47,103 Completed
Casting done Stressing
PSC Girders Casting & Stressing 15 nos 87,17,912 0.247% 87,17,912
Pending
Fixing of Bearings P24,25,26 & 27 12 nos 3,52,952 0.010% 3,52,952 Completed
Foundations - 05 05 nos 99,88,539 0.283% 99,88,539 Work to be done

Bairamalguda Steel Girders - SAW Welding 07 Nos 1,81,41,728 0.514% 1,81,41,728 RKV- 07 Nos Work to be done
1
2nd Level Flyover Completed-of Steel Girders
Steel Girders - SAW Welding Placeboo- 02 Nos Work to be
02 Nos 51,88,393 0.147% 51,88,393
Completed-of Steel Girders done
Fabrication of structural steel
10 nos 1,03,41,491 0.293% 1,03,41,491 RKV - Work to be done
girder
PSC Girders Casting & Stressing
05 nos 28,94,206 0.082% 28,94,206 Work to be done
Balance 05 nos
Deck Slabs A2 to P28 05 Spans 73,76,695 0.209% 73,76,695 Work to be done
Total 6,89,66,801 1.954% 6,89,66,801
2 Fixing of Bearings - P11,12,13 10 nos 4,94,133 0.014% 4,94,133 Work to be done
Loop -LHS
Deck Slabs 01 spnas 01 Nos 19,41,235 0.055% 19,41,235 Work to be done
Deck Slabs 3 spnas 03 Nos 42,70,718 0.121% 42,70,718 Work to be done
RCC Girders 4 nos 9,88,265 0.028% 9,88,265 Completed
3 RHS Loop
Casting of RCC Girders Balance 08 Nos 19,76,531 0.056% 19,76,531 Work to be done
Fixing of Bearings-P4,7,8,9 14 nos 14,47,103 0.041% 14,47,103 Work to be done
Total 1,11,17,985 0.315% 1,11,17,985
4 G.Total for IPC - 53 8,00,84,786 2.269% 8,00,84,786
5 Till Date Work done amount 1,60,24,016 0.454% 1,60,24,016
6 To be Work done amount 6,40,60,770 1.815% 6,40,60,770