Status of Pile Caps & Girders 16-Apr-23

Piles Caps Girders


Pile Caps - Scope Pile Caps - Status Girders - Scope Girders - Status
Remarks
Service/ Upto Total As 1.90m 1.70m 1.40m 1.20m Upto Total As
S.No Chainage Type of Structure MCW Total Today Total Today Balance
Slip Road Today on Date (PSC) (PSC) (PSC) (RCC) Today on Date
1 4+285 Major Bridge 14 7 21 21 21 66 66 33 33 33

2 8+482 Major Bridge 10 5 15 15 15 44 44 4 1 5 39

3 8+932 Minor Bridge 6 3 9 - 0 22 22 0 22

4 15+433 Minor Bridge 6 6 12 8 8 14 14 28 0 28

5 0+560 Flyover 6 - 6 6 6 16 16 16 16 0

6 7+452 Flyover 6 - 6 6 6 16 16 0 16

7 15+885 Flyover 6 - 6 4 4 16 16 2 2 14

Total 54 21 75 60 0 60 142 14 38 14 208 55 1 56 152