You are on page 1of 354

Name of Work : Construction of Proposed Apartment building at Moosapet ,

Hyderabad.
S.No. A- INTERNAL HYDRANT SYSTEM Quantity Rate Amount
1 Supply and fixing single headed internal / External hydrant valve with instantaneous Gunmetal/Stainless 16.00 EACH 8293.90 132702.32
Steel
coupling of 63 mm dia with cast iron wheel ISI marked conforming to IS 5290 (Type -A) with blank
Gunmetal/Stainless Steel cap and chain as required :ELEC-10.7.17
Make: Mini Max / Safex / Newage / Winco / Newtech /
Padmini.

2 Supplyand fixing of hose cabinet of size 750mm X 600mm x 250mm made of No 16 gauge SWG CRCA 16.00 EACH 3239.00 51824.00
sheet with 6mm thick glazed glass door including necessary locking arrangement suitable to accommodate
2 Nos 15 mtr long
Hose pipe, 1 No branch pipe, mounted on wall OR raised brick platform and duly painted with Post office red
externally and white internally with synthetic enamel paint complete in all respect, for external hydrant as
required.ELEC-10.7.26
Make: Mini Max / Safex / Newage / Winco / Newtech /
Padmini.

3 Supply and fixing 63mm dia, 15 mtr long RRL hose pipewith 63mm dia Male and Female Gun metal / SS 32.00 EACH 5454.00 174528.00
couplings
duly binded with GI wire, rivets etc conforming to IS 636 (Type -A) as required.ELEC-10.7.24
Make: Mini Max / Safex / Newage / Winco / Newtech /
Padmini.

4 Supply and fixing 63mm dia Gun metal branch pipe with20mm (Nominal internal diameter) size Gun metal / 16.00 EACH 2500.00 40000.00
SS nozzle conforming to IS 903, suitable for instantaneous connection to interconnect hose pipe coupling as
required.ELEC-10.7.27
Make : Mini Max / Safex / Newage / Winco / Newtech /
Padmini.

HOSPITAL BUILDING AT GACHHIBOWLI Fire - Abs 1 of 354


S.No. A- INTERNAL HYDRANT SYSTEM Quantity Rate Amount
5 Supply and fixing First -Aid Hose Reel with MS construction spray painted in Post office Red, Conforming 16.00 EACH 7613.00 121808.00
to IS 884 with upto date amendments, complete with the following as required.a) 36.6 Mtr Long 20mm
(Nominal internal) dia water hose Thermoplastic / Textile reinforced / Rubber braided /
Polypropylene Type - 2 as per IS:12585
Make: Eversafe / Newage / Newtech / SRIb) 20mm (Nominal internal) dia gun metal globe valve and
nozzle.
Make: Newage / Winco / Padmini / Newtech / Safex.c) Drum and brackets for fixing the equipments on
wall.d) Connections from riser with 25mm dia stop valve (gun
metal) & MS pipe.

6 Supply, installation, testing and commissioning of 25mm dia Ball valve 16.00 EACH 694.00 11104.00
Makes : Zoloto / Leader / Honeywell

7 Supply, Transportation, laying, testing & commissioning of'B' class heavy duty MS pipe conforming to IS
3589/IS 1239 including Welding, fittings like elbows, tees, flanges, tapers,nuts bolts, gaskets etc. and fixing
the pipe on the wall/ceiling with suitable clamp/support frame and painting with two or more coats of
synthetic enamel paint of required shade complete as required
Makes : Jindal Hissar / Tata pipes

a) 100mm dia 140.00 ONE RM 1421.00 198940.00


b)80 mm dia 40.00 ONE RM 1000.00 40000.00
d) 25mm dia 40.00 ONE RM 302.00 12080.00

HOSPITAL BUILDING AT GACHHIBOWLI Fire - Abs 2 of 354


S.No. A- INTERNAL HYDRANT SYSTEM Quantity Rate Amount
8 Supply, testing and commissioning of butterfly valve PN 1.6, with Bronze / Gun metal seat duly ISI marked
complete with Nuts, Bolts, Washers, gaskets, conforming to IS 13095 of following sizes as required.
Makes: Audco / Kirloskar / BDK / H-Shankar / Leader/
Zolotto / Intervalve / Honeywell.
c) 150mm dia 16.00 EACH 6477.00 103632.00
9 Supply and fixing ---- way fire brigade connection of cast iron body with --- Nos Gun metal Male 1.00 EACH 6817.00 6817.00
instantaneous inlet
couplings complete with cap and chain as required for 150mm dia MS pipe connection, conforming to IS 904
as
required.(2 WAY FIRE BRIGADE )
Make: Mini Max / Safex / Newage / Winco / Newtech /
Padmini.

10 Supply, installation, testing and commissioning of 25 /20mm dia Air Release Valve 16.00 EACH 1329.30 21268.73

B TERRACE FLOOR
11 Supply, Transportation, installation , testing andcommissioning of electric driven Terrace / Booster pump 1.00 EACH 69306.00 69306.00
suitable for automatic operation and consisting of following : complete in all respect as required.
Makes of Pumps : Kirloskar a) Horizontal type, multistage, centrifugal pump of cast
iron body & bronze impeller with stainless steel shaft,
mechanical seal and flow of …………. lpm at …….. Mtrb) Suitable HP SQ cage induction motor TEFC type
suitable
for operation on 415Volts, 3 phase 50 Hz. AC with IP 55
class of protection for enclosure, horizontal foot mounted
type with Class-'F' insulation, conforming to IS-325
head conforming to IS 1520c) M.S. Fabricated common base plate, coupling, coupling
guard, foundation bolts etc as required.d) Suitable cement concrete foundation duly plastered with
anti vibration pads.Makes of Pumps : Kirloskar / Mather&Platt.Makes of Motors : Siemens / ABB / Kirloskar

12 Supply, testing and commissioning of butterfly valve PN 1.6, with Bronze / Gun metal seat duly ISI marked
complete with Nuts, Bolts, Washers, gaskets, conforming to IS 13095 of following sizes as required.
Makes: Audco / Kirloskar / BDK / H-Shankar / Leader/
Zolotto / Intervalve / Honeywell.

b) 100mm dia 1.00 EACH 6477.00 6477.00


13 Supply, installation, testing and commissioning of dual plate non - return valve of following sizes confirming
to IS:
5312 complete with rubber gasket, GI bolts, nuts, washers etc as required
Makes: Audco / Kirloskar / BDK / H-Shankar / Leader/
Zolotto / Intervalve / Honeywell.

HOSPITAL BUILDING AT GACHHIBOWLI Fire - Abs 3 of 354


S.No. A- INTERNAL HYDRANT SYSTEM Quantity Rate Amount
b) 150mm dia 2.0 EACH 10180.00 20360.00
14 Supply and fixing air vessel made of 250 mm dia, 8 mm thick MS sheet, 1200mm in height with air release 2.00 EACH 17043.00 34086.00
valve on
top and flanged connection to riser, drain arrangement with 25mm dia Gun metal wheel valve, with required
accessories, pressure gauge and painting with synthetic
enamel paint of approved shade as required.

15 Supply, Transportation, laying, testing & commissioning of'B' class heavy duty MS pipe conforming to IS
3589/IS 1239 including Welding, fittings like elbows, tees, flanges, tapers,nuts bolts, gaskets etc. and fixing
the pipe on the
wall/ceiling with suitable clamp/support frame and painting with two or more coats of synthetic enamel paint
of required shade complete as required
Makes : Jindal Hissar / Tata pipesTerrace

a) 100mm dia 150.00 ONE RM 1421.00 213150.00

16 Supply, installation, testing and commissioning of Bourden type, stainless steel dial type pressure gauge 1.00 EACH 716.00 716.00
with isolation valve and pipe having calibration of 0-16 kg/cm2.
Makes : HGURU / FIEBIG

17 Supply, fabricating , installing structural steel supports for fixing all sizes of MS pipes from ceiling / wall with 150.00 ONE Kg 88.00 13200.00
MS Channels, Angles, Flats, Rods, as required at site with anchor fasteners, Clamps, threaded rods, nuts,
bolts,washers etc complete with painting..,)

HOSPITAL BUILDING AT GACHHIBOWLI Fire - Abs 4 of 354


S.No. A- INTERNAL HYDRANT SYSTEM Quantity Rate Amount

C FIRE EXTINGUISHERS
18 Supply and fixing of ABC Powder MAP 4 Kg Fire extinguisher Mono ammonium phosphate power 90, stored 16.00 EACH 6477.00 103632.00
pressure type, IS 15683 : 2006, pressure gauge gross wt. 6.9 kg, empty wt. 2.9 kg, can Ht.440mm, Diameter
140mm, Discharge time less than 13 sec, controllable discharge mechanism, range min. 4 mts applicable on
classes A,B, C & electrically started fires, A- rating 3A, B-rating 34B, can construction: Deep drawn Co2 mig
welding, wall construction: Forging & Machining, internal coating of can: Epoxy power coating, External
coating of Can:Epoxy
polyster powder coating, sheet metal thickness:1.60mm, Helium leakage detection tested, ISI & CE
approved with 5
years warranty Including transportation, all taxes and all
labour charges etc complete. (Cease Fire / Minimax)

19 Supply and fixing of ABC Powder MAP 2 Kg Fire extinguisher Mono ammonium phosphate power 90, stored 16.00 EACH 4545.00 72720.00
pressure type, IS 15683 : 2006, pressure gauge gross wt. 3.6 kg, empty wt. 1.6 kg, can Ht.344mm, Diameter
108mm, Discharge time less than 8 sec, controllable discharge mechanism, range min. 2 mts applicable on
classes A,B, C electrically started fires, A- rating 2A, B-rating 21B, can construction: Deep drawn Co2 mig
welding, wall construction: Forging & Machining, internal coating of can Epoxy power coating, External
coating of Can:Epoxy
polyster powder coating, sheet metal thickness:1.60mm, Helium leakage detection tested, insta - alert, ISI &
CE
approved with 5 years warranty Including transportation,
all taxes and all labour charges etc complete.

D MANUAL ALARAM SYSTEM


20 Supply and installation of dust and vermin proof manual call point to initiate audio visual alarm including the 16.00 EACH 580.00 9280.00
cost of mounting accessories complete as per specifications and as required.

21 Supply and installation of duel tone electronic hooter of 85dB including the cost of mounting accessories 16.00 EACH 700.00 11200.00
complete as per specifications and as required.

22 Supply of 2 Core 1.5 Sqmm Flat Copper cable as per IS 694:1990 400.00 RM 53.00 21200.00

E
SPRINKLER SYSTEM

HOSPITAL BUILDING AT GACHHIBOWLI Fire - Abs 5 of 354


S.No. A- INTERNAL HYDRANT SYSTEM Quantity Rate Amount
23 300.00 EACH 546.00 163800.00
Supply, fixing, testing and commissioning of 15mm size quartzoid bulb type sprinklers of rating 68ºC.
pendent / side wall with required accessories.
Makes: SAFEX / HD / TYCO / VIKING / NEWAGE /
Newtech / SHARP

24 Supply, Transportation, laying, testing & commissioning of'B' class heavy duty MS pipe conforming to IS
3589/IS 1239 including Welding, fittings like elbows, tees, flanges, tapers,nuts bolts, gaskets etc. and fixing
the pipe on the wall/ceiling with suitable clamp/support frame and painting with two or more coats of
synthetic enamel paint of required shade complete as required
Makes : Jindal Hissar / Tata pipes

b)100 mm dia 100.00 ONE RM 1421.00 142100.00


C) 80mm dia 50.00 ONE RM 1000.00 50000.00
d) 65mm dia 100.00 ONE RM 750.00 75000.00
e)40 mm dia 120.00 ONE RM 444.00 53280.00
f) 32mm dia 400.00 ONE RM 370.00 148000.00
g) 25mm dia 800.00 ONE RM 302.00 241600.00

25 Supply, fabricating , installing structural steel supports for fixing all sizes of MS pipes from 200.00 KG 88.00 17600.00
ceiling / wall with MS Channels, Angles, Flats, Rods, as required at site with anchor
fasteners, Clamps, threaded rods, nuts, bolts,washers etc complete with painting..,)

2381411.05

GRAND TOTAL 2381412.00

HOSPITAL BUILDING AT GACHHIBOWLI Fire - Abs 6 of 354


( No loading and unloading charges allowed for machinery loading and unloading )

(Lead)
charges for (Lead)
(Lead) trucks and charges for
(Lead)
charges for tippers for
charges for trucks and
trucks and
trucks and Cement/ tippers per (Lead) charges (Lead)
tippers for Steel/ for trucks and charges for
tippers for cu.meter for
Earth / Rubble /Size RCC PCC slabs/ tippers per trucks and
Sl No. Distance
Sand /Gravel / stones/ Cut poles/ AC Shahabad cu.meter for tippers for
Stones/ slabs/ CC & water/ 1000 Bricks /1000
Murrum/ & GI
litres nos
Coarse Laterite
Lime/ Surki/ sheets/
aggregate per blocks/
per cu.meter
cu.meter
Packed
materials/t Wood/ cum
onne

1 2 3 4 5 6 7 8
1 Lead up to 1 km 1 34.20 33.00 20.60 48.60 20.50 55.10
2 Lead up to 2 km 2 47.90 46.20 28.90 68.00 28.70 77.10
3 Lead up to 3 km 3 63.90 63.90 39.90 94.00 38.30 102.80
4 Lead up to 4 km 4 77.60 77.60 48.50 114.10 46.40 124.80
5 Lead up to 5 km 5 91.30 91.30 57.10 134.30 54.60 146.80
6 for Every km beyond 5 km up to 30 km 30 13.70 13.70 8.60 20.10 8.20 22.00
7 for Every km beyond 30 km 10000 11.40 11.40 7.10 16.80 6.80 18.40

Rubble/ size
Earth /
stone/ cut
Sand /Gravel
stone/ Coarse Cement in Steel in Bricks Rs/1000
Sl No. Description of item Murrum/ /
aggregate, Rs/Tonne Rs/Tonne Nos.
Surki/ Rs /
Lime in
cum
Rs/cum
1 Loading 22.90 45.80 75.50 90.50 62.90

2 Unloading 11.45 22.90 75.50 90.50 62.90


A Name of Work : Construction of Proposed Apartment building
at Moosapet , Hyderabad.

B Sources and Leads


Material Quarry Lead in KM
1 Cement
2 Steel
3 Sand for concrete 300.00
4 Sand for mortar, plastering 300.00
5 Sand for filling 300.00
6 Second Class Bricks Rajendranagr 30.00
7 Fly ash bricks 290 x 225 x 140 RR District 30.00
8 Fly ash bricks 290 x 100 x 140 RR District 30.00
9 Fly ash bricks 225 x 100 x 60 RR District 30.00
10 40mm HBG Metal Machine crushed 32.00
11 20mm HBG Metal Machine crushed 32.00
12 12mm HBG Metal Machine crushed 32.00
13 10mm HBG Metal Machine crushed 32.00
14 6mm HBG Metal Machine crushed 32.00
15 Rough Stone OTG 32.00
16 Rough Stone HBG 32.00
17 Gravel/Quarry Spall Local 21.00
18 Shahabad stone slabs Tandur 95.00
19 Kadapa stone slabs Tandur 95.00

For road work


20 Aggregate 13.2 - 10 mm RR District 32.00
21 Aggregate 10 - 5 mm RR District 32.00
22 Aggregate 5 mm and below RR District 32.00
23 Aggregate 9.5 mm to 4.75 mm RR District 32.00
24 Aggregate 4.75 mm to 2.36 mm RR District 32.00
25 Aggregate 2.36 mm below RR District 32.00
26 Aggregate 45 mm to 22.4 mm RR District 32.00
27 Aggregate 22.4 mm to 2.36 mm RR District 32.00
28 Aggregate 2.36 mm to 75 micron RR District 32.00
29 Aggregate 60 mm to 63 mm RR District 32.00
30 Stone crusher dust finer than 3mm with not
more than RR District
10% passing 0.075 sieve. 32.00

C Cement & Steel Rates


1 Cement 6400.00
2 Fe-500 43000.00
3 Fe-415 0.00
4 Mild Steel 43000.00
5 Structural Steel 43000.00
6 MS Flats 43000.00
D Allowances
1 Add for MA @ 40% 0.40
Overheads&Contractors Profit &Labour 0.14615
2 cess@14.615%

Water charges
Type of Habitation 2 1 for Rural
2 for Urban
Name of Work : Construction of Proposed Apartment building at Moosapet , Hyderabad.
LEAD CHART

Initial Crushing MA
S.No./ Cost charges( Convey- Seignior Unloadi
Sl. Source of Lead in Blasting Loading
Description Reference Item Code Unit excluding 25% over ance age ng Total
No. Materials KM Charges charges
No. seigniorage initial Charges Charges charges
charges cost) 40%

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)
Ordinary Portland Cement 43 /
1 53 grade (including loading 1.00 MT 6400.00 0.00 6400.00
charges)
2 Reinforcement steel Fe- 500 1.00 MT 43000.00 0.00 43000.00
3 Reinforcement steel Fe- 415 1.00 MT 0.00 0.00 0.00
4 Mild steel bars 1.00 MT 43000.00 0.00 0.00 43000.00
5 Structural steel 1.00 MT 43000.00 0.00 0.00 43000.00
6 MS flats 1.00 MT 43000.00 0.00 0.00 43000.00
Sand (un-screened for
7 0 1.00 Cum 300.00 3924.00 3060.87 6984.87
concrete items)
Sand (screened for mortar,
8 0 300.00 4512.00 3060.87 7572.87
plastering items)
9 Sand for filling 0 0 1.00 Cum 300.00 3924.00 3060.87 6984.87
Common burnt clay bricks Rajendrana
10 9 1000 Nos 30.00 10000.00 564.81 0.00 10564.81
(23x11x7cm) gr
Flyash cement / lime solid
11 blocks (50 Kgs/ sq.cm) RR District 9 1000 Nos 30.00 24000.00 2913.31 60.00 285.56 114.23 27373.10
290mmx225mmx140mm
Flyash cement / lime solid
12 blocks (50 Kgs/ sq.cm) RR District 9 1000 Nos 30.00 19000.00 2589.61 60.00 253.84 101.53 22004.98
290mmx200mmx140mm
Flyash cement / lime solid
13 blocks (50 Kgs/ sq.cm) RR District 9 1000 Nos 30.00 20000.00 1942.21 60.00 190.38 76.15 22268.74
290mmx150mmx140mm
Flyash cement / lime solid
14 blocks (50 Kgs/ sq.cm) RR District 9 1000 Nos 30.00 11000.00 1294.81 60.00 126.92 50.77 12532.49
290mmx100mmx140mm
15 Well burnt cinder RR District 0 1.00 Cum 32.00 608.00 372.84 980.84
Aggregates 40mm nominal
16 0 0 1.00 Cum 32.00 883.00 883.00
size (HBG)
Aggregates 20mm nominal
17 0 0 1.00 Cum 32.00 989.00 989.00
size (HBG)
Aggregates 13.20 / 12.50mm
18 0 0 1.00 Cum 32.00 989.00 989.00
nominal size (HBG)
Aggregates 10mm nominal
19 0 0 1.00 Cum 32.00 989.00 989.00
size (HBG)
Aggregates 6mm nominal size
20 0 0 1.00 Cum 32.00 989.00 989.00
(HBG)
21 Rough stone (HBG) 0 1.00 Cum 32.00 239.00 372.84 75.00 686.84
22 Rough stone (Revetment) Local 1.00 Cum 32.00 200.00 372.84 75.00 647.84
23 Gravel / Quarry spall Local 1.00 Cum 21.00 98.00 243.19 30.00 371.19
Polished Shahabad / Tandur
24 stone slabs 15mm to 18mm Tandur 10 10.00 Sqm 95.00 1640.00 244.02 3.33 1.33 1888.68
thick
Polished black Kadapa slabs
25 Tandur 10 10.00 Sqm 95.00 1370.00 244.02 3.33 1.33 1618.68
15mm to 18mm thick
High Polished Granite 16 to
18 mm thick up to 8'-00 (2.43
26 11 1.00 Sqm 2709.00 - 2709.00
M) other than black and
regular colours
High Polished Granite 16 to
27 18 mm thick up to 8'-00 (2.43 11 1.00 Sqm 2303.00 - 2303.00
M) black.
1) Certified that the leads mentioned in the lead statement are shortest and correct.
2) Certified that metal are to be obtained by blasting.
3) Certified that sufficient quantities & quanlity material are available in the quarries.
4) Certified that for non SSR items lowest market rates are adopted
5) Certified that 40% extra on labour towards Municipal area allowance is allowed .
Name of Work : Construction of Proposed Apartment building at Moosapet , Hyderabad.

ABSTRACT ESTIMATE FOR TWO WHEELER PARKING SHED


Sl.No. Amount
Description of work Quantity Unit Rate
(Rs.)
CIVIL WORKS:
1 Earth work excavation for foundations (Mechanical Means) 3422.00 ONE CUM 119.00 407218
for buildings in ordinary soils and depositing on bank for all lifts
and with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring, sheeting,
planking, strutting etc., and overheads & contractors profit
complete for finished item of work excluding dewatering charges
etc., as per SS 20 B(APSS 308)
2 Plain Cement Concrete (1:4:8) (cement: fine aggregate: 194.70 ONE CUM 7760.00 1510872
Coarse aggregate) for foundations and under flooring bed
using coarse aggregate 40mm size hard , machine crushed
granite from approved quarry including cost and conveyance of
all materials like cement, sand, coarse aggregate,
water,electricity etc. to site, including all taxes and seigniorage
charges except GST on all materials, all charges for machine
mixing, laying concrete in foundations and under flooring bed,
ramming in 15 cm layers finishing top surface to the required
level curing etc., and overheads & contractors profit complete for
finished item of work. (APSS No. 402)

3 Plain Cement Concrete (1:5:10) (cement: fine aggregate: 649.00 ONE CUM 7523.00 4882427
Coarse aggregate) for foundations and under flooring bed
using coarse aggregate 40mm size hard , machine crushed
granite from approved quarry including cost and conveyance of
all materials like cement, sand, coarse aggregate,
water,electricity etc. to site, including all taxes and seigniorage
charges except GST on all materials, all charges for machine
mixing, laying concrete in foundations and under flooring bed,
ramming in 15 cm layers finishing top surface to the required
level curing etc.,and overheads & contractors profit complete for
finished item of work. (APSS No. 402)

4 Filling with useful available excavated earth (excluding rock) 2714.00 ONE CUM 59.00 160126
with a lead of 50 m in trenches, sides of foundations and
basement with initial lead in layers not exceeding 15cm thick,
watering and ramming including cost and conveyance of water to
work site and all operaitonal, incidental, labour charges, hire
charges of T&P etc., excluding GST and overheads & contractors
profit complete for fnished item of work (APSS NO.309&310)

IIIT-GACHIBOWLI Abs Civil- Parking Shed 14 of 354


5 Filling with carted gravel in trenches,sides of foundations and 649.00 ONE CUM 485.00 314765
basement with initial lead in layers not exceeding 15cm
thick,watering and ramming including cost and conveyance of
water to work site, electrcity, seigniorage charges and all
operaitonal,incidental, labour charges,hire charges of T&P,
excluding GST etc., and overheads & contractors profit complete
for fnished item of work(APSS NO.309&310)

6 Supply and placing of the Design Mix Concrete M 25 grade


corresponding to IS 456 with minimum cement content of 380
kgs per 1 cum of concrete using batching and mixing plant
of 15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and
including all taxes except GST on all materials , centering using
Steel scaffolding pipes , jack props , wallers , Foot plates ,
brackets , steel centering plates etc., including all operational,
incidental and labour charges such as weigh batching, machine
mixing, laying concrete, curing etc., and overheads & contractors
profit complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)

a) Footings 348.1 ONE CUM 11096.00 3862518

b) Pedestals 94.4 1 ONE 12282.00 1159421

7 Supply and placing of the Design Mix Concrete M 25 grade


corresponding to IS 456 with minimum cement content of 380
kgs per 1 cum of concrete using batching and mixing plant
of 15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water,electricity etc., to site
and including all taxes and seigniorage charges except GST on
all materials, centering using Steel scaffolding pipes, jack
Props, Steel Centering Plates,etc., including all operational,
incidental and labour charges such as weigh batching, machine
mixing, lifting of concrete manually, laying concrete, curing ,
overheads & contractors profit etc., complete but excluding cost
of steel and its fabrication charges for finished item of work
(APSS No. 402)

a) Columns 153.4 ONE CUM 15713.00 2410374

IIIT-GACHIBOWLI Abs Civil- Parking Shed 15 of 354


8 Providing Thermo Mechanically Treated (TMT) (from Primary 51.51 ONE MT 53697.0 2765932
Producers like TATA, SAIL, VSP, JSW and Shyam Steel as
approved by Ministry of Steel) (Fe 500 grade as per IS 1786-
1979) of different diameters for RCC works , including labour
charges for straightening, cutting, bending to required sizes and
shapes, placing in position with cover blocks of approved
materials and size and tying and lap-splicing with binding wire of
18 SWG, forming grills for reinforcement work as per approved
designs and drawings, including cost and conveyance of steel
bars, including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire, cover
blocks and all incidental, operational, labour charges such as
cutting, bending, placing in position, tying including all taxes
except GST on all materials etc. ,and overheads & contractors
profit complete for finished item of work.( APSS No.126)

9 Granolithic Concrete flooring 20 mm thick with (1:1:2), using 6mm


to 12 mm size hard granite machine crushed metal and screened
sand laid over CC bed already laid or RCC roof slab, in alternate
panels of size not exceeding 1.50 m x 1.50 m, using glass strips
and finishing the top surface to required smoothness and slopes
and thread lining including cost of all materials like cement, metal
sand and water , all taxes except GST on all materials and
overheads & contractors profit complete for finished item of work.
(APSS No.701 & 710)

6407.4 ONE SQM 622.0 3985403

10 Suplying and fabricating, erecting and fixing in position tabular


trusses of approved design with M.S tube conforming to I.S
specifications including roof frame work consisting of rafters,ties
struts and purlins including cost of foundations bolts, cleats,
bearings plates,etc.,complete as per the sketch enclosed and
including cost of painting with enmel paint 2 coats over a primary
coat with red oxide paint including cost and conveyance of all
materials, labour charges for fabrication and fixing, hire charges
of all tools and plants, all incidental charges,all taxes except GST
on all materials, overheads and contractor profit etc., complete for
finished item of work as directed by the Engineer-in-Charge

118.00 ONE MT 141389.0 16683902

11 Supplying, fabricating, hoisting,erecting in position structural steel


works comprising of trusses, lattice girders, brackets, column,
bracing, rafters and other connected works with necessary joints,
channels, angles, I-section, plates, bolts and nuts, washers as
showin in the detailed approved drawings including cutting,
welding, hoisting and painting redoxide primer one coat before
erection including cost and conveyance of all materials, labour
charges for fabrication erection at site work for all heights, all
taxes except GST on all materials etc., complete as directed by
the Engineer-in-Charge

IIIT-GACHIBOWLI Abs Civil- Parking Shed 16 of 354


12.98 ONE MT 94259.0 1223482

12 Roofing With 0.5mm thick galvanized /pre painted G.I profiled


sheets fixed to the purlins With 14 size self drilling with neoprene
washer Side laps are stiched with self tapping drilling screws
.End laps are to be sealed with 25x3 mm Butyl tape .the sheets
are provided with anti capillary groove. including cost and
conveyance of all materials , labour charges , overheads and
contractors profit etc., complete for finished item of work in all
floors.

11269.0 ONE SQM 831.00 9364539

13 Painting two coats with synthetic enamel paint Grade-II VOC


(Volatile Organic Compound) content less than 50 grams/litre
over primer coat of red oxide to new iron work including cost and
conveyance of all materials to site, sales & other taxes,
incidental, operational and all labour charges, all taxes except
GST on all materials, overheads and contractors profit etc.,
complete for finished item of work in all floors. (SS No. 1201,
1212 & 1207).

7788.00 ONE SQM 235.00 1830180

Total: 50561159

IIIT-GACHIBOWLI Abs Civil- Parking Shed 17 of 354


NAME OF THE WORK :PROPOSED CONSTRUCTION OF MODERN ONION MARKET YARD AT
PATANCHERU, SANGAREDDY DISTRICT,TELANGANA

Detailed Estimate for Parking Sheds - 6 Nos(5.40 X 20.10)


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
1 Earth work excavation by Machinary up
to 3.0m
F1 7 1.750 1.750 1.500 32.156
Parking area 1 5.400 20.100 0.230 24.964
For 1 Block 57.120
For 59 Blocks Say 3422.000 Cum

2 PCC (1:4:8) for column footings


For Column Footings
F1 7 1.750 1.750 0.150 3.216
For 1 Block 3.216
For 59 Blocks Say 194.700 Cum

3 PCC (1:5:10)
Under Flooring
Granolithic flooring 1 5.400 20.100 0.100 10.854
Deductions
C1 -7 0.900 0.450 0.100 -0.284
For 1 Block 10.571
For 59 Blocks Say 649.000 Cum

4 Earth filling with available earth


Qty as per excavation 57.120 57.120
Deductions
a Qty as per PCC (1:4:8) -3.216
b Qty as per PCC (1:5:10) -10.571
c Qty as per footing -5.824
d Qty as per pedestals -1.512
e Qty as per columns upto Ground level -1.205
34.793 -22.327
For 1 Block 34.793
Say 35.000 Cum

5 Filling with Available Earth 80% 57.120 45.696


For 59 Blocks Say 2714.000 Cum

6 Filling with Carted Gravel 10.696


For 59 Blocks Say 649.000 Cum

7 VRCC M25 design mix


a) Footings
F1 7 1.600 1.600 0.325 5.824
For 1 Block 5.824
For 59 Blocks Say 348.100 Cum

b) Pedestals
F1 7 0.600 0.600 0.600 1.512

IIIT-GACHIBOWLI Detailed Estimate for Parking Shed 1818of 354


For 1 Block 1.512
For 59 Blocks Say 94.400 Cum

8 VRCC
i Pedestal top to GL
C1/F1 7 0.900 0.450 0.425 1.205
For 1 Block 1.205
For 59 Blocks Say 76.700 Cum

ii GL to Plinth top level


C1 7 0.900 0.450 0.450 1.276
For 1 Block 1.276
For 59 Blocks Say 76.700 Cum

9 Granolithic Flooring
1 5.400 20.100 108.540
For 1 Block 108.540 Sqm
For 59 Blocks Say 6407.400 Sqm

10 TMT Steel
Footings 5.824 60.000 Kg/Cum 349.440
Pedestals 1.512 100.000 Kg/Cum 151.200
Columns 2.481 150.000 Kg/Cum 372.094
For 1 Block 872.734 Kgs
For 59 Blocks 51507.000 Kgs
Say 51.51 MT

Truss
11 MS Tubular pipes
Length Weight - Total
Particulars Nos
in mts Kg/RM weight

114.30 (OD) (M) Vertical posts- (7x2=14) 14 1.89 12.100 320.17


114.30 (OD) (M) Top curved bottom -
7 5.40
(7x1=7) 12.100 457.38
88.9 (OD) (M) Top curved - (7x1=7) 7 9.41 8.480 558.58
88.9 (OD) (M) Top verticals - (7x2=14) 14 0.26 8.480 30.82
88.9 (OD) (M) Top verticals - (7x2=14) 14 0.65 8.480 77.05
88.9 (OD) (M) Top verticals - (7x1=7) 7 0.80 8.480 47.28
88.9 (OD) (M) inclined - (7x2=14) 14 1.16 8.480 137.29
48.3(OD) (M) Horizontal - (7x2=14) 14 0.28 3.610 14.31
42.40 OD -Purlins 5 20.10 3.150 316.58
For 1 Block 1959.449 Kgs
1.960 MT
For 59 Blocks Say 118.00 MT

12 Structural steel
10mm thick Base plate 14 0.09 78.5 98.91
10mm thick Gusset plate 14 0.09 78.5 98.91
12 mm dia bolts 56 0.45 0.890 22.43

IIIT-GACHIBOWLI Detailed Estimate for Parking Shed 1919of 354


12 mm dia bolts 70 0.08 0.890 4.67
For 1 Block 224.921
0.220 MT
For 59 Blocks Say 12.98 MT

13 Roofing
1 20.100 9.500 190.950
For 1 Block 190.950
For 59 Blocks Say 11269.000 Sqm

14 Painting to iron work


114.30 (OD) (M) Vertical posts- (7x2=14) 14 1.89 0.359 9.50
114.30 (OD) (M) Top curved bottom -
(7x1=7) 7 5.40
0.359 13.58
88.9 (OD) (M) Top curved - (7x1=7) 7 9.41 0.279 18.40
88.9 (OD) (M) Top verticals - (7x2=14) 14 0.26 0.279 1.02
88.9 (OD) (M) Top verticals - (7x2=14) 14 0.65 0.279 2.54
88.9 (OD) (M) Top verticals - (7x1=7) 7 0.80 0.279 1.56
88.9 (OD) (M) inclined - (7x2=14) 14 1.16 0.279 4.52
48.3(OD) (M) Horizontal - (7x2=14) 14 0.28 0.152 0.60
42.40 OD -Purlins 5 20.10 0.133 13.39
10mm thick Base plate 14 0.09 2.0 2.52
10mm thick Gusset plate 14 0.09 2.0 2.52
12 mm dia bolts 56 0.45 2.000 50.40
12 mm dia bolts 70 0.08 2.000 10.50
For 1 Block 131.04 SQM
For 59 Blocks Say 7788.000 Sqm

Parking shed 341.099


3158.720
2102.000
812.000
6413.819 Sqm
Size of each parking shed (5.40 X 20.10) 59.092

Road
left side of Buddha Nivas 1 128.000 8.000 1024.000
South west side 1 219.000 10.000 2190.000
1 241.000 10.000 2410.000
North west side 1 275.000 12.000 3300.000
Palashah nivas 1 202.000 10.000 2020.000
1 125.000 8.000 1000.000
11944.000
Say 11944.00 Sqm

EWE
left side of Buddha Nivas 1 128.000 8.000 0.300 307.200
South west side 1 219.000 10.000 0.300 657.000
1 241.000 10.000 0.300 723.000

IIIT-GACHIBOWLI Detailed Estimate for Parking Shed 2020of 354


North west side 1 275.000 12.000 0.300 990.000
Palashah nivas 1 202.000 10.000 0.300 606.000
1 125.000 8.000 0.300 300.000
3583.200
Say 3584.00 cum

GSB
left side of Buddha Nivas 1 128.000 8.000 0.150 153.600
South west side 1 219.000 10.000 0.150 328.500
1 241.000 10.000 0.150 361.500
North west side 1 275.000 12.000 0.150 495.000
Palashah nivas 1 202.000 10.000 0.150 303.000
1 125.000 8.000 0.150 150.000
1791.600
Say 1792.00 cum

WMM
left side of Buddha Nivas 1 128.000 8.000 0.150 153.600
South west side 1 219.000 10.000 0.150 328.500
1 241.000 10.000 0.150 361.500
North west side 1 275.000 12.000 0.150 495.000
Palashah nivas 1 202.000 10.000 0.150 303.000
1 125.000 8.000 0.150 150.000
1791.600
Say 1792.00 cum

Primer coat
left side of Buddha Nivas 1 128.000 8.000 1024.000
South west side 1 219.000 10.000 2190.000
1 241.000 10.000 2410.000
North west side 1 275.000 12.000 3300.000
Palashah nivas 1 202.000 10.000 2020.000
1 125.000 8.000 1000.000
11944.000
Say 11944.00 Sqm
Tack coat
left side of Buddha Nivas 1 128.000 8.000 1024.000
South west side 1 219.000 10.000 2190.000
1 241.000 10.000 2410.000
North west side 1 275.000 12.000 3300.000
Palashah nivas 1 202.000 10.000 2020.000
1 125.000 8.000 1000.000
11944.000
Say 11944.00 Sqm

SDBC
left side of Buddha Nivas 1 128.000 8.000 0.025 25.600
South west side 1 219.000 10.000 0.025 54.750
1 241.000 10.000 0.025 60.250
North west side 1 275.000 12.000 0.025 82.500
Palashah nivas 1 202.000 10.000 0.025 50.500
1 125.000 8.000 0.025 25.000

IIIT-GACHIBOWLI Detailed Estimate for Parking Shed 2121of 354


298.600
Say 299.00 cum
PCC (1:4:8)
Kerb stone
left side of Buddha Nivas 2 128.000 0.300 0.075 5.760
South west side 2 219.000 10.000 0.075 328.500
2 241.000 10.000 0.075 361.500
North west side 2 275.000 12.000 0.075 495.000
Palashah nivas 2 202.000 10.000 0.075 303.000
2 125.000 8.000 0.075 150.000
1643.760
Say 1644.00 cum

Kerb stone
Kerb stone
left side of Buddha Nivas 2 128.000 0.150 0.480 18.432
South west side 2 219.000 0.150 0.480 31.536
2 241.000 0.150 0.480 34.704
North west side 2 275.000 0.150 0.480 39.600
Palashah nivas 2 202.000 0.150 0.480 29.088
2 125.000 0.150 0.480 18.000
171.360
Say 172.00 cum

Storm water
left side of Buddha Nivas 1 128.000 128.000
South west side 1 219.000 219.000
1 241.000 241.000
North west side 1 275.000 275.000
Palashah nivas 1 202.000 202.000
1 125.000 125.000
1190.000
Say 1190.00 RM

EWE 1 1190.000 1.050 0.450 562.275


Say 563.00 cum

IIIT-GACHIBOWLI Detailed Estimate for Parking Shed 2222of 354


DATA

Name of Work : Construction of Proposed Apartment building at Moosapet ,


Hyderabad.
CEMENT MORTAR PER CUM CM (1:2) CM (1:3) CM (1:4) CM (1:5) CM (1:6) CM (1:8)
Cost of Sand for mortar & Plastering 7951.51 7951.51 7951.51 7951.51 7951.51 7951.51
( 1.05 cum )
Cost of cement 4608.00 3072.00 2304.00 1843.20 1536.00 1152.00
Mazdoor ( Unskilled ) for mixing 110.00 110.00 110.00 110.00 110.00 110.00
mortar ( 0.20 Nos.)
Add for MA @ 40% 44.00 44.00 44.00 44.00 44.00 44.00
Rate per Cum 12713.51 11177.51 10409.51 9948.71 9641.51 9257.51

20 mm HBG graded metal


Arregates 20mm nominal size 0.60 989.00 593.40
Arregates 13.20 / 12.50mm nominal 0.15 989.00 148.35
size
Arregates 10mm nominal size 0.15 989.00 148.35
Arregates 6mm nominal size 0.10 989.00 98.90
Rate per Cum 989.00

12 mm HBG graded metal


Arregates 13.20 / 12.50mm nominal 0.60 989.00 593.40
size
Arregates 10mm nominal size 0.20 989.00 197.80
Arregates 6mm nominal size 0.20 989.00 197.80
Rate per Cum 989.00

IIIT-GACHIBOWLI CIVIL DATA 23 of 354


DATA
Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)

1 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary soils and
depositing on bank for all lifts and with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., complete for
finished item of work excluding dewatering charges etc., as per SS 20 B(APSS 308)

(BLKD-CSTN-2-2)
Ordinary Soil - Mechanical Means up to 3m depth
Unit : 1 cum
Taking output : 240.00 cum
a) Labour
Mazdoor ( Unskilled) 8.32 Nos. 550.00 1 No. 4576.00
Add for MA @ 40% 0.40 4576.00 1830.40
b) Machinery
Shovel 0.85 cum 110hp 6.00 hours 2710.50 1 Hour 16263.00
Crew charges 6.00 hours 257.40 1 Hour 1544.40
Add MA on crew charges 0.40 1544.40 617.76
24831.56
c&d)
Overheads&Contractors Profit &La 0.14615 24831.56 3629.13
Cost for 240 cum ( a+b+c+d) 28460.69
Rate per 1 cum (a+b+c+d) / 240 118.59
Say 119

2 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary soils and
depositing on bank for all lifts and with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., complete for
finished item of work including dewatering charges etc., as per SS 20 B(APSS 308)

(BLKD-CSTN-2-2)
Ordinary Soil - Mechanical Means up to 3m depth
Unit : 1 cum
Taking output : 240.00 cum
a) Labour
Mazdoor ( Unskilled) 8.32 Nos. 550.00 1 No. 4576.00
Add for MA @ 40% 0.40 4576.00 1830.40
b) Machinery
Shovel 0.85 cum 110hp 6.00 hours 2710.50 1 Hour 16263.00
Crew charges 6.00 hours 257.40 1 Hour 1544.40
Add MA on crew charges 0.40 1544.40 617.76
24831.56
Add 5% for dewatering 0.05 24831.56 1241.58
26073.14
c&d)
Overheads&Contractors Profit &La 0.14615 26073.14 3810.59
Cost for 240 cum ( a+b+c+d) 29883.73
Rate per 1 cum (a+b+c+d) / 240 124.52
Say 125

3 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary soils and
conveyance of surplus excavated earth to a distance of 1 KM for disposal including all
operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc.,complete for finished
item of work excluding dewatering charges etc., as per SS 20 B(APSS 308)

IIIT-GACHIBOWLI CIVIL DATA 24 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
(BLKD-CSTN-2-2)
Ordinary Soil - Mechanical Means up to 3m depth
Unit : 1 cum
Taking output : 240.00 cum
a) Labour
Mazdoor ( Unskilled) 8.32 Nos. 550.00 1 No. 4576.00
Add for MA @ 40% 0.40 4576.00 1830.40
b) Machinery
Shovel 0.85 cum 110hp 6.00 hours 2710.50 1 Hour 16263.00
Crew charges 6.00 hours 257.40 1 Hour 1544.40
Add MA on crew charges 0.40 1544.40 617.76
24831.56
Add 5% for dewatering 0.05 24831.56 1241.58
26073.14
c&d)
Overheads&Contractors Profit &La 0.14615 26073.14 3810.59
Cost for 240 cum ( a+b+c+d) 29883.73
Rate per 1 cum (a+b+c+d) / 240 124.52
Conveyance charges-Rate as per 1 cum 34.20 1 cum 34.20
SoR
158.72
Say 159

2 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary soils and
depositing on bank for all lifts and with an initial lead of 10m and 3m to 6m depth including all
operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads &
contractors profit complete for finished item of work excluding dewatering charges etc., as per SS 20 B(APSS
308)

(BLKD-CSTN-2-3)
Ordinary Soil - Mechanical Means up to 3m to 6m depth
Unit : 1 cum
Taking output : 210.00 cum
a) Labour
Mazdoor ( Unskilled) 8.32 Nos. 550.00 1 No. 4576.00
Add for MA @ 40% 0.40 4576.00 1830.40
b) Machinery
Shovel 0.85 cum 110hp 6.00 hours 2710.50 1 Hour 16263.00
Crew charges 6.00 hours 257.40 1 Hour 1544.40
Add MA on crew charges 0.40 1544.40 617.76
24831.56
c&d)
Overheads&Contractors Profit &La 0.15 24831.56 3629.13
Cost for 210 cum ( a+b+c+d) 28460.69
Rate per 1 cum (a+b+c+d) / 240 135.53
Say 136

3 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary soils and
depositing on bank for all lifts and with an initial lead of 10m and 3m to 6m depth including all
operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and Overheads &
Contractors profit complete for finished item of work including dewatering charges etc., as per SS 20
B(APSS 308) (BLKD-CSTN-2-3)
(BLKD-CSTN-2-3)
Ordinary Soil - Mechanical Means up to 3m to 6m depth
Unit : 1 cum
Taking output : 210.00 cum
a) Labour

IIIT-GACHIBOWLI CIVIL DATA 25 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Mazdoor ( Unskilled) 8.32 Nos. 550.00 1 No. 4576.00
Add for MA @ 40% 0.40 4576.00 1830.40
b) Machinery
Shovel 0.85 cum 110hp 6.00 hours 2710.50 1 Hour 16263.00
Crew charges 6.00 hours 257.40 1 Hour 1544.40
Add MA on crew charges 0.40 1544.40 617.76
24831.56
Add 5% for dewatering 0.05 24831.56 1241.58
26073.14
c&d)
Overheads&Contractors Profit &La 0.15 26073.14 3810.59
Cost for 240 cum ( a+b+c+d) 29883.73
Rate per 1 cum (a+b+c+d) / 240 142.30
Say 142

4 Earth work excavation for foundations (Manual Means) of buildings in ordinary rock ( not requiring
blasting ) and depositing on bank with an initial lead of 10m and depth up to 3m including all
operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads &
contractors profit complete for finished item of work excluding dewatering charges etc., as per SS 20 B(APSS
308)
(BLD-CSTN-2-4)
Ordinary rock(not requiring blasting) - Manual Means up to 3m
depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
Mazdoor ( Unskilled) 5.20 Nos. 550.00 1 No. 2860.00
Add for MA @ 40% 0.40 2860.00 1144.00
4004.00
b&c)
Overheads&Contractors Profit &La 0.1462 4004.00 585.18
Cost for 10 cum ( a+b+c) 4589.18
Rate per 1 cum (a+b+c) / 10 458.92
Rate per 1 cum Say 459

2 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary rock (not
requiring blasting) and depositing on bank for all lifts and with an initial lead of 10m and up to 3m depth
including all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc.,
complete for finished item of work excluding dewatering charges etc., as per SS 20 B(APSS 308)

(BLKD-CSTN-2-5)
Ordinary rock(not requiring blasting)- Mechanical Means up to 3m depth
Unit : 1 cum
Taking output : 180.00 cum
a) Labour
Mazdoor ( Unskilled) 6.24 Nos. 550.00 1 No. 3432.00
Add for MA @ 40% 0.40 3432.00 1372.80
b) Machinery
Shovel 0.85 cum 110hp 6.00 hours 2710.50 1 Hour 16263.00
Crew charges 6.00 hours 257.40 1 Hour 1544.40
Add MA on crew charges 0.40 1544.40 617.76
23229.96
c&d)
Overheads&Contractors Profit &La 0.15 23229.96 3395.06
Cost for 180 cum ( a+b+c+d) 26625.02
Rate per 1 cum (a+b+c+d) / 180 147.92
Rate per 1 cum Say 148

IIIT-GACHIBOWLI CIVIL DATA 26 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
3 Earth work excavation for foundations for buildings in hard rock (requiring blasting) and depositing on
bank for all lifts and with an initial lead of 10m and up to 3m depth including all operational,incidental,
labour charges such as shoring, sheeting, planking, strutting etc., complete for finished item of work
excluding dewatering charges etc., as per SS 20 B(APSS 308)

(BLKD-CSTN-2-6)
Hard rock (requiring blasting)- up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
Driller 0.50 Nos. 800.00 1 No. 400.00
Blaster 0.25 Nos. 800.00 1 No. 200.00
Mazdoor ( Unskilled) 8.35 Nos. 550.00 1 No. 4592.50
Add for MA @ 40% 0.40 5192.50 2077.00
b) Machinery
Air compressor 7cmm (diesel) 1.00 hour 1121.60 1 Hour 1121.60
Jack hammer/Pneumatic braker 2.00 hours 19.90 1 Hour 39.80
Crew charges
Air compressor 7cmm (diesel) 1.00 hour 237.10 1 Hour 237.10
Jack hammer/Pneumatic braker 2.00 hours 370.50 1 Hour 741.00
Add MA on crew charges 0.40 978.10 391.24
c)Material
Gelatin 80% 3.50 Kgs 73.00 1 Kg 255.50
Detonator electric 14 Nos. 8.00 1 No. 112.00
10167.74
c&d)
Overheads&Contractors Profit &La 0.15 10167.74 1486.02
Cost for 10 cum ( a+b+c+d) 11653.76
Rate per 1 cum (a+b+c+d) / 10 1165.38
Rate per 1 cum Say 1165

IIIT-GACHIBOWLI CIVIL DATA 27 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
3 Earth work excavation for foundations for buildings in hard rock (blasting prohibited) and depositing on bank
for all lifts and with an initial lead of 10m and up to 3m depth including all operational,incidental, labour
charges such as shoring, sheeting, planking, strutting etc., complete for finished item of work excluding
dewatering charges etc., as per SS 20 B(APSS 308)

(BLKD-CSTN-2-7)
Hard rock (blasting prohibited)- up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
Mazdoor ( Unskilled) 5.20 Nos. 550.00 1 No. 2860.00
Add for MA @ 40% 0.40 2860.00 1144.00
b) Machinery
Air compressor 7cmm (diesel) 6.00 hour 1121.60 1 Hour 6729.60
Jack hammer/Pneumatic braker 12.00 hours 19.90 1 Hour 238.80
Crew charges
Air compressor 7cmm (diesel) 6.00 hour 237.10 1 Hour 1422.60
Jack hammer/Pneumatic braker 12.00 hours 370.50 1 Hour 4446.00
Add MA on crew charges 0.40 5868.60 2347.44
19188.44
c&d)
Overheads&Contractors Profit &La 0.15 19188.44 2804.39
Cost for 10 cum ( a+b+c+d) 21992.83
Rate per 1 cum (a+b+c+d) / 10 2199.28
Rate per 1 cum Say 2199

4 Drilling holes of 25 mm dia and 800mm deep in hard rock or sheet rock with pneumatic compressor
and placing of 20mm dia Tor steel bars and grouting the holes in CM(1:2) prop. excluding cost of steel
and its fabrication charges but including cost and conveyance of all materials and labour charges etc.,
complete for finished item of work

Unit : 1RM
Drilling holes as per item Sl No.143, 1.00 RM 144.00 1 RM 144.00
item No. 7 b II) (R&B)
Grouting charges item Sl No.146, 1.00 RM 105.00 1 RM 105.00
item No. 8 II) (R&B)
249.00
Overheads&Contractors Profit 0.14615 249.00 36.39
&Labour cess@14.615% 285.39
Rate per 1 RM Say 285
5 Pre construction Anti termite treatment is a process in which chemical toxic to subterrean tremites is
apply/ inject into soil during early stage of building Construction 2. Treatement of soil Beneath the building
and around the foundations conduct and chemical use as per BIS - IS 6313 (Part -2) 2013 code specification
& CIB RC registered termiticide which creates a continuous chemical barrier beneath the building which kills
or repels terminates & impervious to tremite entry 3. Imidacloprid 30.5% SC (IS 63131) dissolve 2.1 Ml/1 liter
of water and apply emulsion/solution @ 7.5 Litres/Square meter (Sqm) of internal, external vertical surface of
the colums, plinth beams (Back filling) walls and floor junction, external perimeters, along reatining wall @ 5.0
Liters/Sqm of the horizontal surface of basement top surface of the basement filling below flooring bed
(Plinth) & @ 2.0 Litres/ Line meter at expansion joints. The substructure of a depth of 500mm around
coulmns & 300mm deep around plinth beams, basements & floor filling area including excavation channel
along the wall & rodding etc. cost & Conveyance of all materials to the site, cost of labour for sparying,
rodding etc. complete for furnished item of work as per the approval of the Engineer-in-charge

Rate per 1 Sqm 1.00 160.00 160.00


160.00
Overheads&Contractors Profit 0.15 160.00 23.38
&Labour cess@14.615%
IIIT-GACHIBOWLI CIVIL DATA 28 of 354
Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Rate per 1 sqm 183.38

6 Filling with carted gravel in trenches,sides of foundations and basement with initial lead in layers not
exceeding 15cm thick,watering and ramming including cost and conveyance of water to work site, electrcity,
seigniorage charges and all operaitonal,incidental, labour charges,hire charges of T&P etc., complete for
fnished item of work(APSS NO.309&310)

(BLD-CSTN-2-8) & Amendment in page 12 of SoR 2014.15


Unit : 1 cum
Taking output = 6 cum
a) Labour
Mazdoor ( Unskilled ) 0.31 Nos. 550.00 1 No. 170.50
Add for MA @ 40% 0.40 170.50 68.20
b)Material :
Gravel 6.00 cum 371.19 1 cum 2227.14
Water 0.72 Kl 98.00 1 Kl 70.56
2536.40
Overheads&Contractors Profit 0.15 2536.40 370.69
&Labour cess@14.615%
Rate per 6 cum 2907.09
Rate per 1 cum 484.52
Say 485
7 Filling with useful available excavated earth (excluding rock) with a lead of 50 m in trenches, sides of
foundations and basement with initial lead in layers not exceeding 15cm thick, watering and ramming
including cost and conveyance of water to work site and all operaitonal, incidental, labour charges, hire
charges of T&P etc., complete for fnished item of work (APSS NO.309&310)

(BLD-CSTN-2-9) & Amendment in page 13 of SoR 2014.15


Unit : 1 cum
Taking output : 6.00 cum
a) Labour
Mazdoor ( Unskilled ) 0.31 Nos. 550.00 1 No. 170.50
Add for MA @ 40% 0.40 170.50 68.20
238.70
Water 0.72 Kl 98.00 1 Kl 70.56
Rate per 6 cum (a+b+c) 309.26
Overheads&Contractors Profit 0.15 309.26 45.20
&Labour cess@14.615% 354.46
Rate per 1 cum 59.08
Say 59

IIIT-GACHIBOWLI CIVIL DATA 29 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
8 Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse aggregate) for foundations and under
flooring bed using coarse aggregate 40mm size hard , machine crushed granite from approved
quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water,electricity
etc. to site, including seigniorage charges, machine mixing charges, laying concrete in foundations and
under flooring bed, ramming in 15 cm layers finishing top surface to the required level curing etc.,complete for
finished item of work. (APSS No. 402)

(BLD-CSTN-3-5)
Unit : 1 cum
A.MATERIALS :
Cement 162.00 Kgs 6400.00 1000 Kgs 1036.80
Coarse aggregate 40mm 0.90 Cum 883.00 1 Cum 794.70
Fine aggregate ( Sand ) 0.450 Cum 6984.87 1 Cum 3143.19
Water (including curing) 1.20 kl 98.00 1 kl 117.60
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8 1.00 hour 150.50 1 hour 150.50
cum)capacity
Crew charges 1.00 hour 247.00 1 hour 247.00
Add MA on crew charges 0.40 247.00 98.80
C.LABOUR :
1st class mason 0.10 Nos. 800.00 1 Each 80.00
Mazdoor (unskilled) 1.39 Nos. 550.00 1 Each 764.50
Add for MA @ 40% 0.40 844.50 337.80
6770.89
Overheads&Contractors Profit 0.15 6770.89 989.57
&Labour
Rate per cess@14.615%
1 cum 7760.46
Say 7760
9 Plain Cement Concrete (1:5:10) (cement: fine aggregate: Coarse aggregate) for foundations and under
flooring bed using coarse aggregate 40mm size hard , machine crushed granite from approved quarry
including cost and conveyance of all materials like cement, sand, coarse aggregate, water,electricity etc. to
site, including seigniorage charges , machine mixing charges, laying concrete in foundations and under
flooring bed, ramming in 15 cm layers finishing top surface to the required level curing etc., complete for
finished item of work. (APSS No. 402)

(BLD-CSTN-3-7)
Unit : 1 cum
A.MATERIALS :
Cement 129.60 Kgs 6400.00 1000 Kgs 829.44
Coarse aggregate 40mm 0.90 Cum 883.00 1 Cum 794.70
Fine aggregate ( Sand ) 0.450 Cum 6984.87 1 Cum 3143.19
Water (including curing) 1.20 kl 98.00 1 kl 117.60
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8 1.00 hour 150.50 1 hour 150.50
cum)capacity
Crew charges 1.00 hour 247.00 1 hour 247.00
Add MA on crew charges 0.40 247.00 98.80
C.LABOUR :
1st class mason 0.10 Nos. 800.00 1 Each 80.00
Mazdoor (unskilled) 1.39 Nos. 550.00 1 Each 764.50
Add for MA @ 40% 0.40 844.50 337.80
6563.53
Overheads&Contractors Profit 0.15 6563.53 959.26
&Labour
Rate per cess@14.615%
1 cum 7522.79
Say 7523

IIIT-GACHIBOWLI CIVIL DATA 30 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
10 Plain Cement Concrete M- 20 Nominal mix (Cement:fine aggregate: coarse aggregate) corresponding to
Table 9 of IS 456 using 20mm size graded machine crushed hard granite metal (coarse aggregate) from
approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site including all operational, incidental and labour charges such as machine
mixing, laying concrete, curing etc.,including steel centering, shuttering, machine mixing, lift charges, laying
concrete,curing etc., complete for finished item of work (APSS No. 402 ) for Foundation on sheet rock

(BLD-CSTN-3-13)
Unit : 1cum
A.MATERIALS :
HBG 20mm size metal 0.90 Cum 989.00 1 Cum 890.10
Sand 0.45 Cum 6984.87 1 Cum 3143.19
Cement 330.00 Kgs 6400.00 1000 Kgs 2112.00
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8 1.00 hour 150.50 1 hour 150.50
cum)capacity
Crew charges 1.00 hour 247.00 1 hour 247.00
Add MA on crew charges 0.40 247.00 98.80
B.LABOUR :
1st class Mason 0.100 Nos 800.00 1 Each 80.00
Mazdoor (both men&women) 1.390 Nos 550.00 1 Each 764.50
Add for MA @ 40% 0.40 844.50 337.80
7941.49
Overheads&Contractors Profit 0.15 7941.49 1160.65
&Labour cess@14.615%
Rate per 1cum 9102.14
Say 9102
11 Vibrated Plain Cement Concrete (1:3:6) nominal mix using 40mm size machine crushed hard granite
metal and 20mm graded machine crushed hard granite metal (coarse aggregate) in (2:1) ratio from
approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand), coarse
aggregate, water,electricity etc. to site, including seigniorage charges , mixing charges , laying concrete in
position, vibrating, curing, centering charges etc.,for finished item of work for footings and basement .

(BLD-CSTN-3-10 & 11)


Unit : 1cum
A.MATERIALS :
HBG 40mm size metal 0.60 Cum 883.00 1 Cum 529.80
HBG 20mm size graded metal 0.30 Cum 989.00 1 Cum 296.70
Sand 0.450 Cum 6984.87 1 Cum 3143.19
Cement 220.00 Kgs 6400.00 1 MT 1408.00
Water ( including for curing ) 1.20 Kl 98.00 1 Kl 117.60
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8 1.00 hour 150.50 1 hour 150.50
cum)capacity
Crew Charges 1.00 hour 247.00 1 hour 247.00
Add MA on crew charges 0.40 247.00 98.80
Needle vibrator 40mm ( petrol ) 1.00 hours 27.20 1 hour 27.20
Crew charges 1.00 hours 177.80 1 hour 177.80
Add MA on crew charges 0.40 177.80 71.12
C.LABOUR :
1st class mason 0.10 Nos. 800.00 1 Each 80.00
Mazdoor (Unskilled) 1.39 Nos. 550.00 1 Each 764.50

IIIT-GACHIBOWLI CIVIL DATA 31 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Add for MA @ 40% 0.40 844.50 337.80
Rate for 1 cum 7450.01
Centering & Scaffolding (Hire) 1.00 Cum 0.00 1 Cum 0.00
Centering & Scaffolding (Labour) 1.00 Cum 1253.00 1 Cum 1253.00
Add for MA @ 40% 0.40 1253.00 501.20
9204.21
Overheads&Contractors Profit 0.15 9204.21 1345.20
&Labour cess@14.615%
Rate per 1 cum 10549.41
Say 10549
12 Supply and placing of the VRCC of Design Mix Concrete M 25 grade corresponding to IS 456 with
minimum cement content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with
20mm size graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS
2386 Part 1 to Part 8) from approved quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water,electricity etc., to site and including seigniorage charges ,
centering using Steel scaffolding pipes , jack props , wallers , Foot plates , brackets , steel centering plates
etc., including all operational, incidental and labour charges such as weigh batching, machine mixing, laying
concrete, vibrating, curing etc., complete but excluding cost of steel and its fabrication charges for finished
item of work (APSS No. 402)

(BLD-CSTN-3-14)
FOUNDATIONS , PLINTH , PEDESTALS ( Below Plinth)
A.MATERIALS :
Cement 380.00 Kgs 6400.00 1000 Kgs 2432.00
20mm HBG graded metal 0.80 Cum 989.00 1 Cum 791.20
Sand 0.40 Cum 6984.87 1 Cum 2793.95
B.LABOUR :
1st class Mason 0.133 Nos 800.00 1 Each 106.40
2nd class Mason 0.267 Nos 650.00 1 Each 173.55
Mazdoor (both men&women) 4.60 Nos 550.00 1 Each 2530.00
Add for MA @ 40% 0.40 2809.95 1123.98
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 237.50 1 hour 316.59
Crew charges 1.333 hours 370.60 1 hour 494.01
Needle vibrator 40mm ( petrol ) 1.333 hours 27.20 1 hour 36.26
Crew charges 1.333 hours 177.80 1 hour 237.01
Add MA on crew charges 0.40 731.02 292.41
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 11444.95

IIIT-GACHIBOWLI CIVIL DATA 32 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
a Footings
Rate for Design mix M 25 1.00 Cum 11444.95 1 Cum 11444.95
Centering charges 1.00 Cum 0.00 1 Cum 0.00
Centering charges 1.00 Cum 1253.00 1 Cum 1253.00
Add for MA @ 40% 0.40 1253.00 501.20
13199.15
Overheads&Contractors Profit 0.15 13199.15 1929.06
&Labour
Rate per cess@14.615%
1 cum 15128.20
Say 15128

b Column pedestals
Rate for Design mix M 25 1.00 Cum 11444.95 1 Cum 11444.95
Centering charges 1.00 Cum 0.00 1 Cum 0.00
Centering charges 1.00 Cum 1992.00 1 Cum 1992.00
Add for MA @ 40% 0.40 1992.00 796.80
14233.75
Overheads&Contractors Profit 0.15 14233.75 2080.26
&Labour
Rate per cess@14.615%
1 cum 16314.01
Say 16314

c Tie beam/Plinth Beams


Rate for Design mix M25 1.00 Cum 11444.95 1 Cum 11444.95
Centering charges 1.00 Cum 0.00 1 Cum 0.00
Centering charges 1.00 Cum 3019.00 1 Cum 3019.00
Add for MA @ 40% 0.40 3019.00 1207.60
15671.55
Overheads&Contractors Profit 0.15 15671.55 2290.40
&Labour cess@14.615%
Rate per 1 cum 17961.94
Say 17962
13 Supply and placing of the VRCC of Design Mix Concrete M 25 grade corresponding to IS 456 with
minimum cement content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with
20mm size graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS
2386 Part 1 to Part 8) from approved quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water, electricity etc., to site and including seigniorage charges ,
centering using Steel scaffolding pipes, jack Props, Steel Centering Plates,etc., including all
operational, incidental and labour charges such as weigh batching, machine mixing, lifting of concrete
mechanically, laying concrete, vibrating, curing etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)

(BLD-CSTN-3-15)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 380.00 Kgs 6400.00 1000 Kgs 2432.00
20mm HBG graded metal 0.80 Cum 989.00 1 Cum 791.20
Sand 0.40 Cum 6984.87 1 Cum 2793.95
B.LABOUR :
1st class Mason 0.167 Nos 800.00 1 Each 133.60
2nd class Mason 0.167 Nos 650.00 1 Each 108.55
Mazdoor (both men&women) 5.60 Nos 550.00 1 Each 3080.00
Add for MA @ 40% 0.40 3322.15 1328.86
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 237.50 1 hour 316.59
Crew charges 1.333 hours 370.60 1 hour 494.01
Needle vibrator 40mm ( petrol ) 1.333 hours 27.20 1 hour 36.26
Crew charges 1.333 hours 177.80 1 hour 237.01
Add MA on crew charges 0.40 731.02 292.41

IIIT-GACHIBOWLI CIVIL DATA 33 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 12162.03

a) COLUMNS :
un supported height up to 3.66 m
Rate for other Floors FF SF TF 4F 5F 6F
Rate as above 12162.03 12162.03 12162.03 12162.03 12162.03 12162.03
Centering charges 3601.00 3601.00 3601.00 3601.00 3601.00 3601.00
Lift charges 360.10 720.20 1080.30 1440.40 1800.50 2160.60
Add for MA @ 40% 144.04 288.08 432.12 576.16 720.20 864.24
Lift charges of materials(Winch 0.00 456.29 501.91 547.54 593.17 638.80
35HP- Electric)
Crew charges 0.00 395.10 434.61 474.12 513.63 553.14
Add for MA @ 40% 0.00 158.04 173.84 189.65 205.45 221.26
Rate per 1 cum 16267.17 17780.73 18385.82 18990.90 19596.0 20201.07
Overheads&Contractors Profit 2377.45 2598.65 2687.09 2775.52 2863.95 2952.39
&Labour
Rate per cess@14.615%
1cum 18644.62 20379.38 21072.91 21766.42 22459.9 23153.46
Say 18645 20379 21073 21766 22460 23153

Rate for other Floors 7F 8F 9F 10F 11 F


Rate as above 12162.03 12162.03 12162.03 12162.03 12162.03
Centering charges 3601.00 3601.00 3601.00 3601.00 3601.00
Lift charges 2520.70 2880.80 3240.90 3601.00 3961.10
Add for MA @ 40% 1008.28 1152.32 1296.36 1440.40 1584.44
Lift charges of materials(Winch 684.43 730.06 775.69 821.31 866.94
35HP- Electric)
Crew charges 592.65 632.16 671.67 711.18 750.69
Add for MA @ 40% 237.06 252.86 268.67 284.47 300.28
Rate per 1 cum 20806.15 21411.23 22016.31 22621.40 23226.48
Overheads&Contractors Profit 3040.82 3129.25 3217.68 3306.12 3394.55
&Labour
Rate per cess@14.615%
1cum 23846.97 24540.48 25233.99 25927.52 26621.03
Say 23847 24540 25234 25928 26621

b) LINTELS :
Rate for other Floors FF SF TF 4F 5F 6F
Rate as above 12162.03 12162.03 12162.03 12162.03 12162.03 12162.03
Centering charges 2564.00 2564.00 2564.00 2564.00 2564.00 2564.00
Lift charges 256.40 512.80 769.20 1025.60 1282.00 1538.40
Add for MA @ 40% 102.56 205.12 307.68 410.24 512.80 615.36
Lift charges of materials(Winch 0.00 456.29 501.91 547.54 593.17 638.80
35HP- Electric)
Crew Charges 0.00 395.10 434.61 474.12 513.63 553.14
Add for MA @ 40% 0.00 158.04 173.84 189.65 205.45 221.26
Rate per 1 cum 15084.99 16453.37 16913.27 17373.18 17833.1 18292.99
Overheads&Contractors Profit 2204.67 2404.66 2471.87 2539.09 2606.30 2673.52
&Labour
Rate per cess@14.615%
1 cum 17289.66 18858.03 19385.14 19912.27 20439.4 20966.51
Say 17290 18858 19385 19912 20439 20967

IIIT-GACHIBOWLI CIVIL DATA 34 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Rate for other Floors 7F 8F 9F 10F 11 F
Rate as above 12162.03 12162.03 12162.03 12162.03 12162.03
Centering charges 2564.00 2564.00 2564.00 2564.00 2564.00
Lift charges 1794.80 2051.20 2307.60 2564.00 2820.40
Add for MA @ 40% 717.92 820.48 923.04 1025.60 1128.16
Lift charges of materials(Winch 684.43 730.06 775.69 821.31 866.94
35HP- Electric)
Crew Charges 592.65 632.16 671.67 711.18 750.69
Add for MA @ 40% 237.06 252.86 268.67 284.47 300.28
Rate per 1 cum 18752.89 19212.79 19672.70 20132.59 20592.50
Overheads&Contractors Profit 2740.73 2807.95 2875.16 2942.38 3009.59
&Labour cess@14.615%
Rate per 1 cum 21493.62 22020.74 22547.86 23074.97 23602.09
Say 21494 22021 22548 23075 23602
c) WATER TANKS, SUMP, LIFT :
i) 150mm thick side walls
Cost of M25design mix 0.15 cum 12162.03 1.00 cum 1824.30

Rate for other Floors FF SF 3F 4F 5F 6F


Rate as above 1824.30 1824.30 1824.30 1824.30 1824.30 1824.30
Centering charges 472.00 472.00 472.00 472.00 472.00 472.00
Lift charges 1653.00 1818.00 1983.00 2148.00 2314.00 2479.00
Add for MA @ 40% 661.20 727.20 793.20 859.20 925.60 991.60
Lift charges of materials(Winch 0.00 68.44 75.29 82.13 88.98 95.82
35HP- Electric)
Crew Charges 0.00 59.27 65.19 71.12 77.04 82.97
Add for MA @ 40% 0.00 23.71 26.08 28.45 30.82 33.19
Rate per 10 sqm 4610.50 4992.92 5239.06 5485.20 5732.74 5978.89
Overheads&Contractors Profit 673.83 729.72 765.69 801.66 837.84 873.81
&Labour
Rate per cess@14.615%
1 sqm 5284.33 5722.64 6004.75 6286.86 6570.58 6852.70
Say 5284 5723 6005 6287 6571 6853

Rate for other Floors 7F 8F 9F 10F 11 F


Rate as above 1824.30 1824.30 1824.30 1824.30 1824.30
Centering charges 472.00 472.00 472.00 472.00 472.00
Lift charges 2644.00 2810.00 2975.00 3141.00 3305.00
Add for MA @ 40% 1057.60 1124.00 1190.00 1256.40 1322.00
Lift charges of materials(Winch 102.66 109.51 116.35 123.20 130.04
35HP- Electric)
Crew Charges 88.90 94.82 100.75 106.68 112.60
Add for MA @ 40% 35.56 37.93 40.30 42.67 45.04
Rate per 10 sqm 6225.03 6472.57 6718.71 6966.25 7210.99
Overheads&Contractors Profit 909.79 945.97 981.94 1018.12 1053.89
&Labour
Rate per cess@14.615%
1 sqm 7134.82 7418.54 7700.65 7984.37 8264.88
Say 7135 7419 7701 7984 8265

IIIT-GACHIBOWLI CIVIL DATA 35 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
14 Supply and placing of the VRCC of Design Mix Concrete M 25 grade corresponding to IS 456 with
minimum cement content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with
20mm size graded machine crushed hard granite metal(coarse aggregate - as per IS 383 - 1970 and IS 2386
Part 1 to Part 8) from approved quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water,electricity etc., to site and including seigniorage charges ,
centering using steel scaffolding pipes, jack props, steel centering plates etc., including all operational,
incidental and labour charges such as weigh batching, machine mixing, lifting of concrete mechanically,
laying concrete, vibrating, curing etc., complete but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402)

(BLD-CSTN-3-16)
RCC SLABS , BEAMS :
A.MATERIALS :
Cement 380.00 Kgs 6400.00 1000 Kgs 2432.00
20mm HBG graded metal 0.80 Cum 989.00 1 Cum 791.20
Sand 0.40 Cum 6984.87 1 Cum 2793.95
B.LABOUR :
1st class Mason 0.067 Nos 800.00 1 Each 53.60
2nd class Mason 0.133 Nos 650.00 1 Each 86.45
Mazdoor (both men&women) 3.077 Nos 550.00 1 Each 1692.35
Add for MA @ 40% 0.40 1832.40 732.96
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 237.50 1 hour 73.15
Crew charges 0.308 hours 370.60 1 hour 114.14
Needle vibrator 40mm ( petrol ) 0.308 hours 27.20 1 hour 8.38
Crew charges 0.308 hours 177.80 1 hour 54.76
Add MA on crew charges 0.40 168.91 67.56
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 9018.11
A) BEAMS :
un supported height up to 3.66 m
Rate for other Floors FF SF TF 4F 5F 6F
Rate as above 9018.11 9018.11 9018.11 9018.11 9018.11 9018.11
Centering charges 3019.00 3019.00 3019.00 3019.00 3019.00 3019.00
Lift charges 301.90 603.80 905.70 1207.60 1509.50 1811.40
Add for MA @ 40% 120.76 241.52 362.28 483.04 603.80 724.56
Lift charges of materials(Winch 0.00 91.39 100.53 109.67 118.81 127.95
35HP- Electric)
Crew charges 0.00 79.14 87.05 94.97 102.88 110.79
Add for MA @ 40% 0.00 31.66 34.82 37.99 41.15 44.32
Rate for 1 cum 12459.77 13084.61 13527.49 13970.37 14413.25 14856.13
Overheads&Contractors Profit 1820.99 1912.32 1977.04 2041.77 2106.5 2171.22
&Labour
Rate per cess@14.615%
1 cum 14280.76 14996.93 15504.53 16012.14 16519.75 17027.35
Say 14281 14997 15505 16012 16520 17027

un supported height up to 3.66 m


Rate for other Floors 7F 8F 9F 10F 11 F
Rate as above 9018.11 9018.11 9018.11 9018.11 9018.11
Centering charges 3019.00 3019.00 3019.00 3019.00 3019.00
Lift charges 2113.30 2415.20 2717.10 3019.00 3320.90
Add for MA @ 40% 845.32 966.08 1086.84 1207.60 1328.36
Lift charges of materials(Winch 137.09 146.23 155.37 164.51 173.65
35HP- Electric)
Crew charges 118.71 126.62 134.54 142.45 150.36
Add for MA @ 40% 47.48 50.65 53.81 56.98 60.15
Rate for 1 cum 15299.01 15741.89 16184.77 16627.64 17070.52
Overheads&Contractors Profit 2235.95 2300.68 2365.4 2430.13 2494.86
&Labour cess@14.615%
IIIT-GACHIBOWLI CIVIL DATA 36 of 354
Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Rate per 1 cum 17534.96 18042.57 18550.17 19057.77 19565.38
Say 17535 18043 18550 19058 19565
B) RCC SLABS :
a) Roof Slabs 125mm thick :
un supported height up to 3.66 m
Rate for Design mix M25 0.125 Cum 9018.11 1 Cum 1127.26

Rate for other Floors FF SF TF 4F 5F 6F


Rate as above 1127.26 1127.26 1127.26 1127.26 1127.26 1127.26
Centering charges 339.00 339.00 339.00 339.00 339.00 339.00
Lift charges 33.90 67.80 101.70 135.60 169.50 203.40
Add for MA @ 40% 13.56 27.12 40.68 54.24 67.80 81.36
Lift charges of materials(Winch 0.00 11.42 12.57 13.71 14.85 15.99
35HP- Electric)
Crew charges 0.00 9.89 10.88 11.87 12.86 13.85
Add for MA @ 40% 0.00 3.96 4.35 4.75 5.14 5.54
Rate per 1 sqm 1513.72 1586.46 1636.44 1686.43 1736.42 1786.41
Overheads&Contractors Profit 221.23 231.86 239.17 246.47 253.78 261.08
&Labour
Rate per cess@14.615%
1 sqm 1734.95 1818.32 1875.61 1932.90 1990.20 2047.49
Say 1735 1818 1876 1933 1990 2047

Rate for other Floors 7F 8F 9F 10F 11 F


Rate as above 1127.26 1127.26 1127.26 1127.26 1127.26
Centering charges 339.00 339.00 339.00 339.00 339.00
Lift charges 237.30 271.20 305.10 339.00 372.90
Add for MA @ 40% 94.92 108.48 122.04 135.60 149.16
Lift charges of materials(Winch 17.14 18.28 19.42 20.56 21.71
35HP- Electric)
Crew charges 14.84 15.83 16.82 17.81 18.80
Add for MA @ 40% 5.94 6.33 6.73 7.12 7.52
Rate per 1 sqm 1836.39 1886.38 1936.37 1986.36 2036.34
Overheads&Contractors Profit 268.39 275.69 283 290.31 297.61
&Labour
Rate per cess@14.615%
1 sqm 2104.78 2162.07 2219.37 2276.67 2333.95
Say 2105 2162 2219 2277 2334

b) Roof Slabs 150mm thick :


un supported height up to 3.66 m
Rate for Design mix M25 0.150 Cum 9018.11 1 Cum 1352.72

Rate for other Floors FF SF TF 4F 5F 6F


Rate as above 1352.72 1352.72 1352.72 1352.72 1352.72 1352.72
Centering charges 339.00 339.00 339.00 339.00 339.00 339.00
Lift charges 33.90 67.80 101.70 135.60 169.50 203.40
Add for MA @ 40% 13.56 27.12 40.68 54.24 67.80 81.36
Lift charges of materials(Winch 0.00 13.71 15.08 16.45 17.82 19.19
35HP- Electric)
Crew charges 0.00 11.87 13.06 14.24 15.43 16.62
Add for MA @ 40% 0.00 4.75 5.22 5.70 6.17 6.65
Rate per 1 sqm 1739.18 1816.96 1867.46 1917.95 1968.44 2018.94
Overheads&Contractors Profit 254.18 265.55 272.93 280.31 287.69 295.07
&Labour
Rate per cess@14.615%
1 sqm 1993.36 2082.51 2140.39 2198.26 2256.13 2314.01
Say 1993 2083 2140 2198 2256 2314

IIIT-GACHIBOWLI CIVIL DATA 37 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Rate for other Floors 7F 8F 9F 10F 11 F
Rate as above 1352.72 1352.72 1352.72 1352.72 1352.72
Centering charges 339.00 339.00 339.00 339.00 339.00
Lift charges 237.30 271.20 305.10 339.00 372.90
Add for MA @ 40% 94.92 108.48 122.04 135.60 149.16
Lift charges of materials(Winch 20.56 21.93 23.31 24.68 26.05
35HP- Electric)
Crew charges 17.81 18.99 20.18 21.37 22.55
Add for MA @ 40% 7.12 7.60 8.07 8.55 9.02
Rate per 1 sqm 2069.43 2119.92 2170.41 2220.91 2271.40
Overheads&Contractors Profit 302.45 309.83 317.21 324.59 331.97
&Labour
Rate per cess@14.615%
1 sqm 2371.88 2429.75 2487.62 2545.50 2603.37
Say 2372 2430 2488 2545 2603

15 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum
cement content of 380 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size
graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to
Part 8) from approved quarry including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water,electricity etc., to site and including seigniorage charges , centering using
Steel scaffolding pipes, jack Props, Steel Centering Plates,etc. for 60cm wide sun-shades 7.5cm thick at
fixed end and 5cm thick at free end with an average thickness of 6.25cm including all operational, incidental
and labour charges such as weigh batching, machine mixing, lifting of concrete mechanically, laying
concrete, curing etc., but excluding cost of steel and its fabrication charges for finished item of work (APSS
No. 402, 403 & 903).

(BLD-CSTN-3-16)
A.MATERIALS :
Cement 380.00 Kgs 6400.00 1000 Kgs 2432.00
20mm HBG graded metal 0.80 Cum 989.00 1 Cum 791.20
Sand 0.40 Cum 6984.87 1 Cum 2793.95
B.LABOUR :
1st class Mason 0.067 Nos 800.00 1 Each 53.60
2nd class Mason 0.133 Nos 650.00 1 Each 86.45
Mazdoor (both men&women) 3.077 Nos 550.00 1 Each 1692.35
Add for MA @ 40% 0.40 1832.40 732.96
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 237.50 1 hour 73.15
Crew charges 0.308 hours 370.60 1 hour 114.14
Add MA on crew charges 0.40 114.14 45.66
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Rate per 1 cum 8933.06

Cost of RCC M25 design mix 0.0375 cum 8933.06 1 cum 334.99
Rate for other Floors FF SF TF 4F 5F 6F
Rate as above 334.99 334.99 334.99 334.99 334.99 334.99
Centering charges 203.40 203.40 203.40 203.40 203.40 203.40
Lift charges 20.34 40.68 61.02 81.36 101.70 122.04
Add for MA @ 40% 8.14 16.27 24.41 32.54 40.68 48.82
Lift charges of materials(Winch 0.00 3.43 3.77 4.11 4.46 4.80
35HP- Electric)
Crew charges 0.00 2.97 3.26 3.56 3.86 4.15
Add for MA @ 40% 0.00 1.19 1.31 1.42 1.54 1.66
Rate per 1 RM 566.87 602.92 632.16 661.39 690.63 719.86
Overheads&Contractors Profit 82.85 88.12 92.39 96.66 100.94 105.21
&Labour cess@14.615%
Rate per 1 RM 649.72 691.04 724.55 758.05 791.57 825.07

IIIT-GACHIBOWLI CIVIL DATA 38 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Say 650 691 725 758 792 825

IIIT-GACHIBOWLI CIVIL DATA 39 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Rate for other Floors 7F 8F 9F 10F 11 F
Rate as above 334.99 334.99 334.99 334.99 334.99
Hire charges of centering and 203.40 203.40 203.40 203.40 203.40
scaffolding
Labour , lift charges for scaffolding 142.38 162.72 183.06 203.40 223.74
Add for MA @ 40% 56.95 65.09 73.22 81.36 89.50
Lift charges of materials(Winch 5.14 5.48 5.83 6.17 6.51
35HP- Electric)
Crew charges 4.45 4.75 5.05 5.34 5.64
Add for MA @ 40% 1.78 1.90 2.02 2.14 2.26
Rate per 1 RM 749.09 778.33 807.56 836.80 866.03
Overheads&Contractors Profit 109.48 113.75 118.03 122.3 126.57
&Labour cess@14.615%
Rate per 1 RM 858.57 892.08 925.59 959.10 992.60
Say 859 892 926 959 993
16 Brick masonry for panel walls in superstructure with CM (1:8) prop: (Cement : Screened sand) using light
weight common burnt clay bricks of class as per Table- I of IS:1077-1992, Non- Modular or traditional size 23
x 11 x 7 cms from approved source having minimum crushing strength of 50 Kg/Sqcm. including cost and
conveyance of all materials like cement, screened sand, bricks, water,electricity etc., to site, including
seigniorage charges , labour charges for mixing cement mortar, scaffolding charges, constructing masonry,
lift charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).

(BLD-CSTN-5-5)
Unit : 1cum
A.MATERIALS :
Cement 36.00 Kgs 6400.00 1000 Kgs 230.40
light weight Common burnt clay 512 Nos 10564.81 1000 Nos 5409.18
bricks 23x11x7cms
Fine aggregate ( Sand ) 0.20 cu.m. 7572.87 1 cu.m. 1514.57
B.LABOUR :
1st class mason 0.24 Nos. 800.00 1 Each 192.00
2nd class mason 0.56 Nos. 650.00 1 Each 364.00
Mazdoor (Unskilled) 1.89 Nos. 550.00 1 Each 1039.50
Add for MA @ 40% 0.40 1595.50 638.20
water charges @ 1% 0.01 9387.86 93.88
Rate per 1 cum 9481.74

a Up to basement
Rate as worked out above 1.00 Cum 9481.74 1 Cum 9481.74
Overheads&Contractors Profit 0.15 9481.74 1385.76
&Labour cess@14.615%
Rate per 1 cum 10867.49
Say 10867
a) Superstructure :
Rate for other Floors FF SF TF 4F 5F 6F
Rate as worked out above 9481.74 9481.74 9481.74 9481.74 9481.74 9481.74
Hire charges for Access Scaffolding 44.87 44.87 44.87 44.87 44.87 44.87
Labour charges for scaffolding 345.48 494.70 643.87 793.09 942.26 1091.43
Add for MA @ 40% 138.19 197.88 257.55 317.24 376.90 436.57
Lift charges ( Page 131 of Std. Data ) 0.00 159.55 319.10 478.65 638.20 797.75

Add for MA @ 40% 0.00 63.82 127.64 191.46 255.28 319.10


Rate per 1 cum 10010.28 10442.55 10874.76 11307.04 11739.25 12171.46
Overheads&Contractors Profit 1463 1526.18 1589.35 1652.52 1715.69 1778.86
&Labour
Rate per cess@14.615%
1 cum 11473.28 11968.73 12464.11 12959.56 13454.94 13950.32

IIIT-GACHIBOWLI CIVIL DATA 40 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Say 11473 11969 12464 12960 13455 13950

Rate for other Floors 7F


Rate as worked out above 9481.74
Hire charges for Access Scaffolding 44.87
Labour charges for scaffolding 1240.57
Add for MA @ 40% 496.23
Lift charges ( Page 131 of Std. Data ) 957.30

Add for MA @ 40% 382.92


Rate per 1 cum 12603.62
Overheads&Contractors Profit 1842.02
&Labour cess@14.615%
Rate per 1 cum 14445.64
Say 14446

17 Reinforced Brick Masonry for partition walls (11.0 cm thick) in CM (1:4) prop. (Cement : Screened sand)
using light weight common burnt clay bricks of class as per Table- I of IS:1077-1992, Non- Modular or
traditional size 23 x 11 x 7 cms from approved source having minimum crushing strength of 50 Kg/Sq.cm
and placing 2 Nos. of 6mm M.S plain rods in every third layer with free ends of the reinforcement pegged into
mortar joints of main brick walls where applicable including cost and conveyance of all materials like cement,
steel, sand, bricks, water,electricity etc., to site, including seigniorage charges , all operational, incidental
charges such as labour charges for mixing cement mortar, scaffolding charges, constructing masonry, lift
charges, curing, etc., but excluding cost of steel and its fabrication charges complete for finished item of
work. (APSS No. of 501 & 509)

(BLD-CSTN-5-12)
Unit - 10sqm
A.MATERIALS :
light weight Common burnt clay 565 Nos. 10564.81 1000 Nos. 5969.12
bricks 23x11x7cms
Cement 79.20 Kgs 6400.00 1000 Kgs 506.88
Fine aggregate ( Sand ) 0.22 cu.m. 7572.87 1 cu.m. 1666.03
B.LABOUR :
1st class mason 0.60 Nos. 800.00 1 Each 480.00
2nd class mason 0.60 Nos. 650.00 1 Each 390.00
Mazdoor (Unskilled) 2.75 Nos. 550.00 1 Each 1512.50
Add for MA @ 40% 0.40 2382.50 953.00
water charges @ 1% 0.01 11477.53 114.78
Rate per 1 cum 11592.30
Rate per 1 sqm 1159.23

Internal walls :
Rate for other Floors FF SF TF 4F 5F 6F
Rate as worked out above 1159.23 1159.23 1159.23 1159.23 1159.23 1159.23
Hire charges for Access Scaffolding 10.32 10.32 10.32 10.32 10.32 10.32
Labour charges for scaffolding 79.46 113.78 148.09 182.41 216.72 251.03
Add for MA @ 40% 31.78 45.51 59.24 72.96 86.69 100.41
Lift charges ( Page 131 of Std. Data ) 0.00 23.83 47.65 71.48 95.30 119.13

Add for MA @ 40% 0.00 9.53 19.06 28.59 38.12 47.65


Rate per 1 sqm 1280.79 1362.20 1443.59 1525.00 1606.38 1687.77
Overheads&Contractors Profit 187.19 199.09 210.98 222.88 234.77 246.67
&Labour
Rate per cess@14.615%
1 sqm 1467.98 1561.29 1654.57 1747.88 1841.15 1934.44
Say 1468 1561 1655 1748 1841 1934

IIIT-GACHIBOWLI CIVIL DATA 41 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
19 Plain Cement Concrete (1:3:6) nominal mix using 20mm size graded machine crushed hard granite metal
(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate(sand), coarse aggregate, water, electricity etc.,
to site, including seigniorage charges, mixing charges, laying concrete in position, curing etc., & lift
chargesfor Bed Blocks & Hold Fasts for finished item of work. (APSS No. 402)

(BLD-CSTN-3-10 & 11)


Unit : 1cum
A.MATERIALS :
HBG 20mm size metal 0.90 Cum 989.00 1 Cum 890.10
Sand 0.450 Cum 6984.87 1 Cum 3143.19
Cement 220.00 Kgs 6400.00 1 MT 1408.00
Water ( including for curing ) 1.20 Kl 98.00 1 Kl 117.60
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8 1.00 hour 150.50 1 hour 150.50
cum)capacity
Crew Charges 1.00 hour 247.00 1 hour 247.00
Add MA on crew charges 0.40 247.00 98.80
C.LABOUR :
1st class mason 0.10 Nos. 800.00 1 Each 80.00
Mazdoor (Unskilled) 1.39 Nos. 550.00 1 Each 764.50
Add for MA @ 40% 0.40 844.50 337.80
Rate per 1 cum 7237.49

Rate for other Floors FF SF TF 4F 5F 6F


Rate as worked out above 7237.49 7237.49 7237.49 7237.49 7237.49 7237.49
Hire charges of centering and 0.00 0.00 0.00 0.00 0.00 0.00
scaffolding
Lift charges for scaffolding 1253.00 1290.60 1328.20 1365.80 1403.40 1441.00
Add for MA @ 40% 501.20 516.24 531.28 546.32 561.36 576.40
Lift charges ( Page 131 of Std. Data ) 0.00 84.45 168.90 253.35 337.80 422.25

Add for MA @ 40% 0.00 33.78 67.56 101.34 135.12 168.90


Rate per 1 cum 8991.69 9162.56 9333.43 9504.30 9675.17 9846.04
Overheads&Contractors Profit 1314.14 1339.11 1364.08 1389.05 1414.03 1439.00
&Labour
Rate per cess@14.615%
1 cum 10305.83 10501.67 10697.51 10893.35 11089.20 11285.04
say 10306 10502 10698 10893 11089 11285

Rate for other Floors 7F 8F


Rate as worked out above 7237.49 7237.49
Hire charges of centering and 0.00 0.00
scaffolding
Lift charges for scaffolding 1478.50 1516.10
Add for MA @ 40% 591.40 606.44
Lift charges ( Page 131 of Std. Data ) 506.70 591.15

Add for MA @ 40% 202.68 236.46


Rate per 1 cum 10016.77 10187.64
Overheads&Contractors Profit 1463.95 1488.92
&Labour
Rate per cess@14.615%
1 cum 11480.72 11676.56
say 11481 11677

IIIT-GACHIBOWLI CIVIL DATA 42 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
20 Plain Cement Concrete M 20 design mix using WEIGH BATCHER / MIXER, 20mm size hard granite
machine crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concrete including cost and
conveyance of all materials, water, electricity etc., and seigniorage charges including steel centering,
shuttering, machine mixing, lift charges, laying concrete,vibrating, curing etc., complete for finished item of
work (APSS No. 402 & 403) for steps

(BLD-CSTN-3-16)
Unit : 1cum
A.MATERIALS :
HBG 20mm size metal 0.80 Cum 989.00 1 Cum 791.20
Sand 0.40 Cum 6984.87 1 Cum 2793.95
Cement 330.00 Kgs 6400.00 1000 Kgs 2112.00
Water ( including for curing ) 1.20 Kl 98.00 1 Kl 117.60
B.MACHINERY :
Batching plant 0.50 cum 0.308 hour 237.50 1 hour 73.15
Crew charges 0.308 hour 370.60 1 hour 114.14
Needle vibrator 40mm ( petrol ) 0.308 hours 27.20 1 hour 8.38
Crew charges 0.308 hours 177.80 1 hour 54.76
Add MA on crew charges 0.40 168.91 67.56
C.LABOUR :
1st class mason 0.067 Nos. 800.00 1 Each 53.60
2nd class mason 0.067 Nos. 650.00 1 Each 43.55
Mazdoor (Unskilled) 3.077 Nos. 550.00 1 Each 1692.35
Add for MA @ 40% 0.40 1789.50 715.80
Rate per 1 cum 8638.05
Rate for other Floors Stilt/FF SF TF 4F 5F 6F
Cost of M 20 design mix 8638.05 8638.05 8638.05 8638.05 8638.05 8638.05
Hire charges of centering and 0.00 0.00 0.00 0.00 0.00 0.00
scaffolding
Lift charges for scaffolding 1253.00 1290.60 1328.20 1365.80 1403.40 1441.00
Add for MA @ 40% 501.20 516.24 531.28 546.32 561.36 576.40
Lift charges ( Page 131 of Std. Data ) 0.00 178.95 357.90 536.85 715.80 894.75

Add for MA @ 40% 0.00 71.58 143.16 214.74 286.32 357.90


Rate per 1 cum 10392.25 10695.42 10998.59 11301.76 11604.93 11908.10
Overheads&Contractors Profit 1518.83 1563.14 1607.44 1651.75 1696.06 1740.37
&Labour
Rate per cess@14.615%
1 cum 11911.07 12258.55 12606.03 12953.51 13300.99 13648.46
Say 11911 12259 12606 12954 13301 13648

IIIT-GACHIBOWLI CIVIL DATA 43 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
21 Reinforced Cement Concrete M 20 design mix using 12mm size hard granite machine crushed
graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry,
using a minimum quantity of 350 kgs. of cement per 1 cum of concrete using WEIGH BATCHER / MIXER
including cost and conveyance of all materials , water,electricity etc., to site and including seigniorage
charges including steel centering, shuttering, machine mixing, laying concrete, lift charges, curing etc., but
excluding cost of steel and its fabrication charges complete for finished item of work (APSS No. 402 & 403)
for sill slabs.

(BLD-CSTN-3-13 - A)
A.MATERIALS :
Cement 350.00 Kgs 6400.00 1000 Kgs 2240.00
12mm HBG graded metal 0.80 Cum 989.00 1 Cum 791.20
Sand 0.40 Cum 6984.87 1 Cum 2793.95
B.LABOUR :
1st class Mason 0.133 Nos 800.00 1 Each 106.40
2nd class Mason 0.267 Nos 650.00 1 Each 173.55
Mazdoor (both men&women) 3.60 Nos 550.00 1 Each 1980.00
Add for MA @ 40% 0.40 2259.95 903.98
C.MACHINERY :
Batching plant 0.50 cum 0.308 hour 237.50 1 hour 73.15
Crew charges 0.308 hour 370.60 1 hour 114.14
Add MA on crew charges 0.40 114.14 45.66
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Basic cost per 1cum 9339.63

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 9339.63 9339.63 9339.63 9339.63 9339.63 9339.63
Hire charges of centering and 0.00 0.00 0.00 0.00 0.00 0.00
scaffolding
Lift charges for scaffolding 1253.00 1290.60 1328.20 1365.80 1403.40 1441.00
Add for MA @ 40% 501.20 516.24 531.28 546.32 561.36 576.40
Lift charges ( Page 131 of Std. Data ) 0.00 226.00 451.99 677.99 903.98 1129.98

Add for MA @ 40% 0.00 90.40 180.80 271.20 361.59 451.99


Rate per 1 cum 11093.83 11462.87 11831.90 12200.94 12569.96 12939.00
Overheads&Contractors Profit 1621.36 1675.30 1729.23 1783.17 1837.10 1891.04
&Labour cess@14.615%
Rate per 1 cum 12715.19 13138.17 13561.13 13984.10 14407.06 14830.04
Say 12715 13138 13561 13984 14407 14830

Rate for other Floors 7F 8F


Rate as worked out above 9339.63 9339.63
Hire charges of centering and 0.00 0.00
scaffolding
Lift charges for scaffolding 1478.50 1516.10
Add for MA @ 40% 591.40 606.44
Lift charges ( Page 131 of Std. Data ) 1355.97 1581.97

Add for MA @ 40% 542.39 632.79


Rate per 1 cum 13307.89 13676.93
Overheads&Contractors Profit 1944.95 1998.88
&Labour cess@14.615%
Rate per 1 cum 15252.84 15675.81
Say 15253 15676

IIIT-GACHIBOWLI CIVIL DATA 44 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
22 Reinforced Cement Concrete M 20 design mix using 12mm size hard granite machine crushed graded
metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry, using a
minimum quantity of 350 kgs. of cement per 1 cum of concrete using WEIGH BATCHER / MIXER including
cost and conveyance of all materials, water,electricity etc., to site and seigniorage charges including steel
centering, shuttering, labour charges such as weigh batching, machine mixing, laying concrete, lift charges,
curing etc., but excluding cost of steel and its fabrication charges complete for finished item of work (APSS
No. 402 & 403) for platforms and shelves.

(BLD-CSTN-3-16)
A.MATERIALS :
Cement 350.00 Kgs 6400.00 1000 Kgs 2240.00
12mm HBG graded metal 0.80 Cum 989.00 1 Cum 791.20
Sand 0.40 Cum 6984.87 1 Cum 2793.95
B.LABOUR :
1st class Mason 0.067 Nos 800.00 1 Each 53.60
2nd class Mason 0.133 Nos 650.00 1 Each 86.45
Mazdoor (both men&women) 3.077 Nos 550.00 1 Each 1692.35
Add for MA @ 40% 0.40 1832.40 732.96
C.MACHINERY :
Batching plant 0.50 cum 0.308 hour 237.50 1 hour 73.15
Crew charges 0.308 hour 370.60 1 hour 114.14
Add MA on crew charges 0.40 114.14 45.66
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
Basic cost per 1cum 8741.06
a) 50mm thick platforms :
Cost of M 20 design mix 0.05 cum 8741.06 1 cum 437.05

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 437.05 437.05 437.05 437.05 437.05 437.05
Hire charges of centering and 79.00 79.00 79.00 79.00 79.00 79.00
scaffolding (50% of roof slab)
Lift charges for scaffolding 83.50 92.00 100.50 108.50 117.00 125.50
Add for MA @ 40% 33.40 36.80 40.20 43.40 46.80 50.20
Lift charges ( Page 131 of Std. Data ) 0.00 9.16 18.32 27.49 36.65 45.81

Add for MA @ 40% 0.00 3.66 7.33 10.99 14.66 18.32


Rate per 1 sqm 632.95 657.68 682.41 706.43 731.16 755.89
Overheads&Contractors Profit 92.51 96.12 99.73 103.25 106.86 110.47
&Labour
Rate per cess@14.615%
1 sqm 725.46 753.80 782.14 809.68 838.02 866.36
Say 725 754 782 810 838 866

b) 25mm thick shelves :


Cost of M 20 design mix 0.025 cum 8741.06 1 cum 218.53
Rate per 1sqm 218.53

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 218.53 218.53 218.53 218.53 218.53 218.53
Hire charges of centering and 39.50 39.50 39.50 39.50 39.50 39.50
scaffolding
Lift charges for scaffolding 41.75 46.00 50.25 54.25 58.50 62.75
Add for MA @ 40% 16.70 18.40 20.10 21.70 23.40 25.10
Lift charges ( Page 131 of Std. Data ) 0.00 4.58 9.16 13.74 18.32 22.91
Add for MA @ 40% 0.00 1.83 3.66 5.50 7.33 9.16
Rate per 1 sqm 316.48 328.84 341.20 353.22 365.58 377.94
Overheads&Contractors Profit 46.25 48.06 49.87 51.62 53.43 55.24
&Labour cess@14.615%
IIIT-GACHIBOWLI CIVIL DATA 45 of 354
Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Rate per 1 sqm 362.73 376.90 391.07 404.84 419.01 433.18
Say 363 377 391 405 419 433
23 Providing Thermo Mechanically Treated (TMT) (from Primary Producers like TATA, SAIL, VSP, JSW
and Shyam Steel as approved by Ministry of Steel) (Fe 500 grade as per IS 1786-1979) of different
diameters for RCC works , including labour charges for straightening, cutting, bending to required sizes and
shapes, placing in position with cover blocks of approved materials and size and tying and lap-splicing with
binding wire of 18 SWG, forming grills for reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire, cover blocks and all incidental, operational,
labour charges such as cutting, bending, placing in position, tying etc. ,complete for finished item of work.
( APSS No.126)

(BLD-CSTN-4.2)& Amendment in SoR 2011-12 page No. 392


Unit - 1 MT
a) Material
TMT bars including 5% for overlaps 1.05 MT 43000.00 1 MT 45150.00
and wastage
Binding wire 6.00 Kgs 50.00 1 Kgs 300.00
carriage of steel 1.00 MT 1000.00 1 MT 1000.00
Add for MA @ 40% 0.40 1000.00 400.00
46850.00
Rate for other Floors Stilt/FF SF TF 4F 5F 6F
Rate as worked out above 46850.00 46850.00 46850.00 46850.00 46850.00 46850.00
Lift charges ( Page 131 of Std. Data ) 0.00 100.00 200.00 300.00 400.00 500.00

Add for MA @ 40% 0.00 40.00 80.00 120.00 160.00 200.00


Rate per MT 46850.00 46990.00 47130.00 47270.00 47410.00 47550.00
Overheads&Contractors Profit 6847.13 6867.59 6888.05 6908.51 6928.97 6949.43
&Labour cess@14.615%
Rate per 1 MT 53697.13 53857.59 54018.05 54178.51 54338.97 54499.43
Say 53697 53858 54018 54179 54339 54499

Rate for other Floors 7F 8F


Rate as worked out above 46850.00 46850.00
Lift charges ( Page 131 of Std. Data ) 600.00 700.00

Add for MA @ 40% 240.00 280.00


Rate per MT 47690.00 47830.00
Overheads&Contractors Profit 6969.89 6990.35
&Labour cess@14.615%
Rate per 1 MT 54659.89 54820.35
Say 54660 54820

IIIT-GACHIBOWLI CIVIL DATA 46 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
24 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS 432) of different diameters including labour
charges for straightening, cutting, bending to required sizes and shapes, placing in position with cover blocks
of approved materials and size and tying and lap-splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings, chairs, spacer bars including cost and conveyance of
binding wire, cover blocks and all incidental, operational, labour charges such as cutting, bending, placing in
position, tying etc. , complete for finished item of work.( APSS No.126)

(BLD-CSTN-4.2)& Amendment in SoR 2011-12 page No. 392


Unit - 1 MT
a) Material
Mild steel bars including 5% for 1.05 MT 43000.00 1 MT 45150.00
overlaps and wastage
Binding wire 6.00 Kgs 50.00 1 Kgs 300.00
carriage of steel 1.00 MT 1000.00 1 MT 1000.00
Add for MA @ 40% 0.40 1000.00 400.00
46850.00

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 46850.00 46850.00 46850.00 46850.00 46850.00 46850.00
Lift charges ( Page 131 of Std. Data ) 0.00 100.00 200.00 300.00 400.00 500.00

Add for MA @ 40% 0.00 40.00 80.00 120.00 160.00 200.00


Rate per MT 46850.00 46990.00 47130.00 47270.00 47410.00 47550.00
Overheads&Contractors Profit 6847.13 6867.59 6888.05 6908.51 6928.97 6949.43
&Labour
Rate per cess@14.615%
1 MT 53697.13 53857.59 54018.05 54178.51 54338.97 54499.43
Say 53697 53858 54018 54179 54339 54499

Rate for other Floors 7F 8F


Rate as worked out above 46850.00 46850.00
Lift charges ( Page 131 of Std. Data ) 600.00 700.00

Add for MA @ 40% 240.00 280.00


Rate per MT 47690.00 47830.00
Overheads&Contractors Profit 6969.89 6990.35
&Labour
Rate per cess@14.615%
1 MT 54659.89 54820.35
Say 54660 54820

IIIT-GACHIBOWLI CIVIL DATA 47 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
25 Ornamental ceiling plastering 12mm thick in two coats using screened sand) with base coat of 8mm
thick in CM (1:6) and top coat of 4mm thick in CM (1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water,electricity etc., to site, including seigniorage charges
and all operational, incidental charges on materials and including cost of all labour charges for mixing mortar,
finishing, scaffolding, lift charges, curing, including cutting grooves as directed by Engineer - in - charge etc.,
complete for finished item of work. (SS 901,903 & 904)

(BLD-CSTN-8-3)
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6) , 8mm thick
Cement 26.40 Kgs 6400.00 1000 Kgs 168.96
Fine aggregate (Sand) 0.110 cu.m. 7572.87 1 cu.m. 833.02
Top coat in CM(1:4) , 4mm thick
Cement 14.40 Kgs 6400.00 1000 Kgs 92.16
Fine aggregate (Sand) 0.040 cu.m. 7572.87 1 cu.m. 302.91
B.LABOUR :
1st Class Mason 0.63 Nos. 800.00 1 Each 504.00
2nd Class Mason 1.47 Nos. 650.00 1 Each 955.50
Mazdoor (Unskilled) 3.90 Nos. 550.00 1 Each 2145.00
Add for MA @ 40% 0.40 3604.50 1441.80
water charges @ 1% 0.01 6443.35 64.43
Rate per 10 Sqm 6507.78
Rate per 1 Sqm 650.78

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 650.78 650.78 650.78 650.78 650.78 650.78
Hire charges for Access Scaffolding 2.46 2.46 2.46 2.46 2.46 2.46
Labour charges for scaffolding 15.91 22.57 29.23 35.90 42.56 49.22
Add for MA @ 40% 6.36 9.03 11.69 14.36 17.02 19.69
Lift charges ( Page 131 of Std. Data ) 0.00 36.05 72.09 108.14 144.18 180.23

Add for MA @ 40% 0.00 14.42 28.84 43.26 57.67 72.09


Rate per 1 Sqm 675.51 735.31 795.09 854.90 914.67 974.47
Overheads&Contractors Profit 98.73 107.47 116.20 124.94 133.68 142.42
&Labour
Rate per cess@14.615%
1 Sqm 774.24 842.78 911.29 979.84 1048.35 1116.89
Say 774 843 911 980 1048 1117

Rate for other Floors 7F 8F


Rate as worked out above 650.78 650.78
Hire charges for Access Scaffolding 2.46 2.46
Labour charges for scaffolding 55.89 62.55
Add for MA @ 40% 22.36 25.02
Lift charges ( Page 131 of Std. Data ) 216.27 252.32

Add for MA @ 40% 86.51 100.93


Rate per 1 Sqm 1034.27 1094.06
Overheads&Contractors Profit 151.16 159.90
&Labour
Rate per cess@14.615%
1 Sqm 1185.43 1253.96
Say 1185 1254

IIIT-GACHIBOWLI CIVIL DATA 48 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
26 Plastering 12mm thick in two coats using screened sand with base coat of 8mm thick in CM (1:6) and top
coat of 4mm thick in CM (1:4) with dubara sponge finishing including cost and conveyance of all materials like
cement, sand, water,electricity etc., to site, including seigniorage charges and all operational, incidental
charges on materials and including cost of all labour charges for mixing mortar, finishing, scaffolding, lift
charges, curing, including cutting grooves as directed by Engineer - in - charge etc., complete for finished
item of work. (SS 901,903 & 904)

( BLD-CSTN-8-10)
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6) , 8mm thick
Cement 26.40 Kgs 6400.00 1000 Kgs 168.96
Fine aggregate (Sand) 0.110 Cum 7572.87 1 Cum 833.02
Top coat in CM(1:4) , 4mm thick
Cement 14.40 Kgs 6400.00 1000 Kgs 92.16
Fine aggregate (Sand) 0.04 Cum 7572.87 1 Cum 302.91
B.LABOUR :
1st Class Mason 0.63 Nos. 800.00 1 Each 504.00
2nd Class Mason 1.47 Nos. 650.00 1 Each 955.50
Mazdoor (Unskilled) 3.90 Nos. 550.00 1 Each 2145.00
Add for MA @ 40% 0.40 3604.50 1441.80
water charges @ 1% 0.01 6443.35 64.43
Rate per 10 Sqm 6507.78
Rate per 1 Sqm 650.78

Walls in superstructure :
Rate for other Floors Stilt/FF SF TF 4F 5F 6F
Rate as worked out above 650.78 650.78 650.78 650.78 650.78 650.78
Hire charges for Access Scaffolding 1.03 1.03 1.03 1.03 1.03 1.03
Labour charges for scaffolding 7.95 11.38 14.80 18.24 21.67 25.11
Add for MA @ 40% 3.18 4.55 5.92 7.30 8.67 10.04
Lift charges ( Page 131 of Std. Data ) 0.00 36.05 72.09 108.14 144.18 180.23

Add for MA @ 40% 0.00 14.42 28.84 43.26 57.67 72.09


Rate per 1 Sqm 662.94 718.21 773.46 828.75 884.00 939.28
Overheads&Contractors Profit 96.89 104.97 113.04 121.12 129.20 137.28
&Labour cess@14.615% 759.83 823.18 886.50 949.87 1013.20 1076.56
Say 760 823 886 950 1013 1077

Rate for other Floors 7F 8F


Rate as worked out above 650.78 650.78
Hire charges for Access Scaffolding 1.03 1.03
Labour charges for scaffolding 28.54 31.96
Add for MA @ 40% 11.42 12.78
Lift charges ( Page 131 of Std. Data ) 216.27 252.32

Add for MA @ 40% 86.51 100.93


Rate per 1 Sqm 994.55 1049.80
Overheads&Contractors Profit 145.35 153.43
&Labour cess@14.615% 1139.90 1203.23
Say 1140 1203

IIIT-GACHIBOWLI CIVIL DATA 49 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
27 Plastering 20mm thick in two coats for weather exposed exterior walls using screened sand with base
coat of 16mm thick in CM(1:6) and top coat of 4mm thick in CM(1:4) with dubara sponge finishing including
cost and conveyance of all materials like cement, sand, water,electricity etc., to site, including seigniorage
charges and all operational, incidental charges on materials and including cost of all labour charges for
mixing mortar, finishing, scaffolding, lift charges, curing, including cutting grooves as directed by Engineer-in-
charge etc., complete for finished item of work .(SS 901,903 & 904)

(BLD-CSTN-8-9)
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6) , 16mm thick
Cement 43.20 Kgs 6400.00 1000 Kgs 276.48
Fine aggregate (Sand) 0.18 Cum 7572.87 1 Cum 1363.12
Top coat in CM(1:4) , 4mm thick
Cement 14.40 Kgs 6400.00 1000 Kgs 92.16
Fine aggregate (Sand) 0.04 Cum 7572.87 1 Cum 302.91
B.LABOUR :
1st Class Mason 0.63 Nos. 800.00 1 Each 504.00
2nd Class Mason 1.47 Nos. 650.00 1 Each 955.50
Mazdoor (Unskilled) 3.90 Nos. 550.00 1 Each 2145.00
Add for MA @ 40% 0.40 3604.50 1441.80
water charges @ 1% 0.01 7080.97 70.81
Rate per 10 Sqm 7151.78
Rate per 1 Sqm 715.18
Walls in superstructure :
Rate for other Floors FF SF TF 4F 5F 6F
Rate as worked out above 715.18 715.18 715.18 715.18 715.18 715.18
Hire charges for Access Scaffolding 1.03 1.03 1.03 1.03 1.03 1.03
Labour charges for scaffolding 7.95 11.38 14.80 18.24 21.67 25.11
Add for MA @ 40% 3.18 4.55 5.92 7.30 8.67 10.04
Lift charges ( Page 131 of Std. Data ) 0.00 36.05 72.09 108.14 144.18 180.23

Add for MA @ 40% 0.00 14.42 28.84 43.26 57.67 72.09


727.34 782.61 837.86 893.15 948.40 1003.68
Overheads&Contractors Profit 106.30 114.38 122.45 130.53 138.61 146.69
&Labour
Rate per cess@14.615%
1 Sqm 833.64 896.99 960.31 1023.68 1087.01 1150.37
Say 834 897 960 1024 1087 1150

Rate for other Floors 7F


Rate as worked out above 715.18
Hire charges for Access Scaffolding 1.03
Labour charges for scaffolding 28.54
Add for MA @ 40% 11.42
Lift charges ( Page 131 of Std. Data ) 216.27

Add for MA @ 40% 86.51


1058.95
Overheads&Contractors Profit 154.77
&Labour cess@14.615%
Rate per 1 Sqm 1213.72
Say 1214

IIIT-GACHIBOWLI CIVIL DATA 50 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
28 Plastering 12mm thick single coat in CM(1:5) using screened sand including cost and conveyance of all
materials like cement, sand, water,electricity etc., to site, including seigniorage charges and all operational,
incidental charges on materials and including cost of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., complete for finished item of work .(SS 901,903 & 904)

(BLD-CSTN-8-8)
Unit : 10 sqm
A.MATERIALS :
Cement 43.20 Kgs 6400.00 1000 Kgs 276.48
Fine aggregate (Sand) 0.150 Cum 7572.87 1 Cum 1135.93
B.LABOUR :
1st Class Mason 0.60 Nos. 800.00 1 Each 480.00
Mazdoor (Unskilled) 0.96 Nos. 550.00 1 Each 528.00
Add for MA @ 40% 0.40 1008.00 403.20
water charges @ 1% 0.01 2823.61 28.24
Rate per 10 Sqm 2851.85
Rate per 1 Sqm 285.18
285
a) for basement :
Rate per 1 Sqm 1.00 sqm 285.18 1 sqm 285.18
Overheads&Contractors Profit 0.15 285.18 41.68
&Labour
Rate per cess@14.615%
1 Sqm 326.86
Say Say 327

29 Providing impervious coat to exposed RCC roof slab surfaces to required slopes with CM (1:3) prop.
using screened sand 20mm thick (average) mixed with integral cement water proofing liquid confirming to
IS: 2645-2003 manufactured by reputed manufacturers as approved by Engineer-in-charge at 200ml per one
bag of cement, laid over roof slab when it is green, finished smooth with a floating coat of neat cement and
thread lining at regular intervals of 45cmx45cm including cost and conveyance of all materials like cement,
sand, water proofing compound, water,electricity etc., to site, including seigniorage charges and operational,
incidental, and labour charges for mixing mortar, laying, lift charges, rendering smooth and thread lining,
curing including rounding off junctions of wall and slab etc., complete for finished item of work. (APSS No.
901 & 903).

(BLD-CSTN-10-25)
Unit : 10 sqm
A.MATERIALS :
Cement 100.80 Kgs 6400.00 1000 Kgs 645.12
Fine aggregate (Sand) 0.21 Cum 7572.87 1 Cum 1590.30
Integral water proofing liquid 0.40 Lts 191.00 1.00 Lts 76.40
B.LABOUR :
1st Class Mason 0.66 Nos. 800.00 1 Each 528.00
2nd Class Mason 1.54 Nos. 650.00 1 Each 1001.00
Mazdoor (Unskilled) 3.70 Nos. 550.00 1 Each 2035.00
Add for MA @ 40% 0.40 3564.00 1425.60
water charges @ 1% 0.01 7301.42 73.01
Rate per 10 Sqm 7374.44
Rate for other Floors 7F 8F
Rate as worked out above 7374.44 7374.44
Lift charges ( Page 131 of Std. Data ) 2138.40 2494.80

Add for MA @ 40% 855.36 997.92


10368.20 10867.16
Overheads&Contractors Profit 1515.31 1588.23
&Labour cess@14.615% 11883.51 12455.39

IIIT-GACHIBOWLI CIVIL DATA 51 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Rate per 1 Sqm 1188.35 1245.54
Say 1188 1246
30 Providing impervious coat to exposed RCC roof slab surfaces of sump , sump side wall,sump bottom
slab,in side of septic tank , in sunken slabs etc. to required slopes with CM (1:3) prop. using screened
sand 12mm thick mixed with integral cement water proofing liquid confirming to IS: 2645-2003
manufactured by reputed manufacturers as approved by Engineer-in-charge at 200ml per one bag of
cement, laid over roof slab when it is green, finished smooth with a floating coat of neat cement and thread
lining at regular intervals of 45cmx45cm where ever necessary including cost and conveyance of all materials
like cement, sand, water proofing compound, water,electricity etc., to site, including seigniorage charges and
operational, incidental, and labour charges for mixing mortar, laying, lift charges, rendering smooth and
thread lining, curing including rounding off junctions of wall and slab etc., complete for finished item of work.
(APSS No. 901 & 903).

(BLD-CSTN-8-2)
A.MATERIALS :
Cement 72.00 Kgs 6400.00 1000 Kgs 460.80
Fine aggregate (Sand) 0.15 Cum 7572.87 1 Cum 1135.93
Integral water proofing liquid 0.29 Lts 191.00 1.00 Lts 55.39
B.LABOUR :
1st Class Mason 0.60 Nos. 800.00 1 Each 480.00
Mazdoor (Unskilled) 0.96 Nos. 550.00 1 Each 528.00
Add for MA @ 40% 0.40 1008.00 403.20
water charges @ 1% 0.01 3063.32 30.63
Rate per 10 Sqm 3093.95

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 3093.95 3093.95 3093.95 3093.95 3093.95 3093.95
Lift charges ( Page 131 of Std. Data ) 0.00 100.80 201.60 302.40 403.20 504.00

Add for MA @ 40% 0.00 40.32 80.64 120.96 161.28 201.60


3093.95 3235.07 3376.19 3517.31 3658.43 3799.55
Overheads&Contractors Profit 452.18 472.81 493.43 514.06 534.68 555.30
&Labour
Rate per cess@14.615%
10 Sqm 3546.13 3707.88 3869.62 4031.37 4193.11 4354.85
Rate per 1 Sqm 354.61 370.79 386.96 403.14 419.31 435.49
Say 355 371 387 403 419 435

Rate for other Floors 7F 8F


Rate as worked out above 3093.95 3093.95
Lift charges ( Page 131 of Std. Data ) 604.80 705.60

Add for MA @ 40% 241.92 282.24


3940.67 4081.79
Overheads&Contractors Profit 575.93 596.55
&Labour
Rate per cess@14.615%
10 Sqm 4516.60 4678.34
Rate per 1 Sqm 451.66 467.83
Say 452 468

IIIT-GACHIBOWLI CIVIL DATA 52 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
31 RCM facia 50mm thick using screened sand for drop walls, fins with rabbit wire mesh & nomianl
reinforcement as directred by Engineer - In - Charge with dubara sponge finishing,including cost and
conveyance of all materials to site,water,electricity and seigniorage charges ,operationals & incidental,cost
and conveyance of cement,wire mesh,water to work site,centering,scaffolding and form work,lift charges etc.,
complete for finished item of work but excluding cost of steel and its fabrication charges for finished item of
work(APSS NO.403&903)

(BLD-CSTN-8-11)
Unit : 10 sqm
A.MATERIALS :
Rabbit wire mesh 13.30 sqm 19.00 1 sqm 252.70
Cement for base coat and plastering 240.00 Kgs 6400.00 1000 Kgs 1536.00

Cement for lumps 50.00 Kgs 6400.00 1000 Kgs 320.00


Fine aggregate (Sand) 0.50 Cum 7572.87 1 Cum 3786.44
Excluding HYSD steel/mild steel &
binding wire
B.LABOUR :
1st Class Mason 8.00 Nos. 800.00 1 Each 6400.00
Operator concrete mixer 1.00 Nos. 800.00 1 Each 800.00
Mazdoor (Unskilled) 10.00 Nos. 550.00 1 Each 5500.00
Add for MA @ 40% 0.40 12700.00 5080.00
C.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8 2.00 hour 150.50 1 hour 301.00
cum)capacity
Crew Charges 2.00 hour 247.00 1 hour 494.00
Add MA on crew charges 0.40 494.00 197.60
water charges @ 1% 0.01 24667.74 246.68
Rate per 10 Sqm 24914.41
Rate per 1 Sqm 2491.44

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 2491.44 2491.44 2491.44 2491.44 2491.44 2491.44
Hire charges for Access Scaffolding 1.03 2.06 3.09 4.12 5.15 6.18
Labour charges for scaffolding 7.95 11.38 14.80 18.24 21.67 25.11
Add for MA @ 40% 3.18 4.55 5.92 7.30 8.67 10.04
Lift charges ( Page 131 of Std. Data ) 0.00 127.00 254.00 381.00 508.00 635.00

Add for MA @ 40% 0.00 50.80 101.60 152.40 203.20 254.00


2503.60 2687.23 2870.85 3054.50 3238.13 3421.78
Overheads&Contractors Profit 365.90 392.74 419.57 446.41 473.25 500.09
&Labour
Rate per cess@14.615%
1 Sqm 2869.50 3079.97 3290.42 3500.91 3711.38 3921.87
Say 2870 3080 3290 3501 3711 3922

Rate for other Floors 7F


Rate as worked out above 2491.44
Hire charges for Access Scaffolding 7.21
Labour charges for scaffolding 28.54
Add for MA @ 40% 11.42
Lift charges ( Page 131 of Std. Data ) 762.00

Add for MA @ 40% 304.80


3605.41
Overheads&Contractors Profit 526.93
&Labour cess@14.615%

IIIT-GACHIBOWLI CIVIL DATA 53 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Rate per 1 Sqm 4132.34
Say 4132
32 Flooring with non-skid full body ceramic floor tiles of size 300mm x 300mm and thickness between 7 -
8mm 1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Part 1 to 15) of any colour and finish in all
shades and designs as approved by Engineer-in-charge, set over base coat of cement mortar (1:8), 12mm
thick using screened sand over CC bed already laid or RCC roof slab, including neat cement slurry of honey
like consistency spread @ 3.3 Kgs per Sqm & jointed neatly with white cement paste to full depth mixed with
pigment of matching shade, including cost of all materials like cement, screened sand , water,electricity and
tiles, seigniorage charges etc., complete for finished item of work.( In toilets) (APSS No.701 & 707)

(BLD-CSTN-9-6)
Unit = 10 sqm.
A. MATERIALS:
Ceramic tiles between 7-8 mm thick 10.50 Sqm 300.00 1 Sqm 3150.00
Cement for CM(1:8) proportion for 21.60 Kgs 6400.00 1000 Kgs 138.24
base coat
Cement for slurry 33.00 Kgs 6400.00 1000 Kgs 211.20
White Cement 2.00 Kgs 29.00 1 Kg 58.00
Sand for CM(1:8) 0.12 Cum 7572.87 1 Cum 908.74
B .LABOUR
Mason 1st class 0.96 Nos 800.00 1 Each 768.00
Mason 2nd class 2.24 Nos 650.00 1 Each 1456.00
Mazdoor(un skilled) 3.30 Nos 550.00 1 Each 1815.00
Add for MA @ 40% 0.40 4039.00 1615.60
Add water charges 1% 0.01 10120.78 101.21
Rate for 10sqm 10221.99

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 10221.99 10221.99 10221.99 10221.99 10221.99 10221.99
Lift charges ( Page 131 of Std. Data ) 0.00 403.90 807.80 1211.70 1615.60 2019.50

Add for MA @ 40% 0.00 161.56 323.12 484.68 646.24 807.80


10221.99 10787.45 11352.91 11918.37 12483.83 13049.29
Overheads&Contractors Profit 1493.94 1576.59 1659.23 1741.87 1824.51 1907.15
&Labour
Rate per cess@14.615%
10 Sqm 11715.93 12364.04 13012.14 13660.24 14308.34 14956.44
Rate per 1 Sqm 1171.59 1236.40 1301.21 1366.02 1430.83 1495.64
Say 1172 1236 1301 1366 1431 1496

IIIT-GACHIBOWLI CIVIL DATA 54 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
33 Flooring with Double charged / multi charged stain free full body porcelain vitrified tiles with double
layer pigment of size 600 x 600 mm and thickness between 8-10 mm 1st quality conforming to IS:13711,
IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and design as per the approved
flooring pattern as directed by the Engineer-In -Charge, laying tiles using spacers of 2mm thick, set over a
base coat of CM (1:8) prop. 12mm thick using screened sand over CC bed already laid or RCC roof slab ,
including neat cement slurry of honey like consistancy spread @ 3.3 kgs per Sqm. and jointed neately with
white cement paste to full depth mixed with pigment of matching shade including cost and conveyance of
all materials like cement, sand, water,electricity, tiles, white cement etc., to site (excluding cost of C.C.
bed) including cost of base coat and all labour charges for mixing of cement mortar, laying tiles to
required slope as directed by the Engineer- in-charge including seigniorage charges etc., complete for
finished item of work. (APSS No.701 & 707)

(BLD-CSTN-9-5)
Unit = 10 sqm.
A. MATERIALS:
Double charged / multi charged stain 10.50 Sqm 550.00 1 Sqm 5775.00
free full body porcelain vitrified tiles
with double layer pigment of size 600
x 600 mm TBSC-C.II-05
Cement for CM(1:8)proportion for 21.60 Kgs 6400.00 1000 Kgs 138.24
base coat
Cement for slurry 33.00 Kgs 6400.00 1000 Kgs 211.20
White Cement 6.00 Kgs 29.00 1 Kg 174.00
Sand for CM(1:8) 0.12 Cum 7572.87 1 Cum 908.74
B .LABOUR
Mason 1st class 0.96 Nos 800.00 1 Each 768.00
Mason 2nd class 2.24 Nos 650.00 1 Each 1456.00
Mazdoor(un skilled) 3.30 Nos 550.00 1 Each 1815.00
Add for MA @ 40% 0.40 4039.00 1615.60
Add water charges 1% 0.01 12861.78 128.62
Rate for 10sqm 12990.40

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 12990.40 12990.40 12990.40 12990.40 12990.40 12990.40
Lift charges ( Page 131 of Std. Data ) 0.00 403.90 807.80 1211.70 1615.60 2019.50

Add for MA @ 40% 0.00 161.56 323.12 484.68 646.24 807.80


12990.40 13555.86 14121.32 14686.78 15252.24 15817.70
Overheads&Contractors Profit 1898.55 1981.19 2063.83 2146.47 2229.12 2311.76
&Labour
Rate per cess@14.615%
10 Sqm 14888.95 15537.05 16185.15 16833.25 17481.36 18129.46
Rate per 1 Sqm 1488.90 1553.71 1618.52 1683.33 1748.14 1812.95
Say 1489 1554 1619 1683 1748 1813

IIIT-GACHIBOWLI CIVIL DATA 55 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
34 Flooring with 16 to 18mm thick High Polished granite stone slabs other than black and regular
colours (i.e. of shades like paradiso / bala flower / copper silk / laka red / lavender blue) with borders and
design as per the pattern approved by the Engineer-in-Charge of length not less than 2.43 mts set over base
coat of cement mortar (1:8) , 20mm thick using screened sand over CC bed already laid or RCC roof slab
including neat grey cement slurry of honey like consistency spread @ 3.3 Kg per sqm and jointed neatly with
white cement paste mixed with pigment of matching shade to full depth including cost and conveyance of all
materials like cement , sand , water , electricity, granite slabs etc., to work site and all operational, incidental
labour & lift charges, polishing charges , seigniorage charges , cost of base coat etc., complete for finished
item of work (S.S.701 & special) for Staircase MIdlanding

(BLD-CSTN-9-7)
Unit = 10 sqm.
A. MATERIALS:
High polished granite slabs other 10.50 Sqm 2709.00 1 Sqm 28444.50
than black 16 to 18mm thick
Cement for CM(1:8) for base coat 36.00 Kgs 6400.00 1000 Kgs 230.40
Cement for slurry 33.00 Kgs 6400.00 1000 Kgs 211.20
White cement for jointing 6.00 Kgs 29.00 1 Kg 174.00
Sand for CM(1:8) 0.20 Cum 7572.87 1 Cum 1514.57
B .LABOUR
Mason 1st class 3.00 Nos 800.00 1 Each 2400.00
Mason 2nd class 1.00 Nos 650.00 1 Each 650.00
Mazdoor(un skilled) 8.00 Nos 550.00 1 Each 4400.00
Add for MA @ 40% 0.40 7450.00 2980.00
Add water charges 1% 0.01 41004.67 410.05
Rate for 10sqm 41414.72
Rate for other Floors Stilt/FF SF TF 4F 5F 6F
Rate as worked out above 41414.72 41414.72 41414.72 41414.72 41414.72 41414.72
Lift charges ( Page 131 of Std. Data ) 0.00 745.00 1490.00 2235.00 2980.00 3725.00

Add for MA @ 40% 0.00 298.00 596.00 894.00 1192.00 1490.00


41414.72 42457.72 43500.72 44543.72 45586.72 46629.72
Overheads&Contractors Profit 6052.76 6205.20 6357.63 6510.06 6662.50 6814.93
&Labour
Rate per cess@14.615%
10 Sqm 47467.48 48662.92 49858.35 51053.78 52249.22 53444.65
Rate per 1 Sqm 4746.75 4866.29 4985.84 5105.38 5224.92 5344.47
Say 4747 4866 4986 5105 5225 5344

IIIT-GACHIBOWLI CIVIL DATA 56 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
35 Flooring with 16 to 18 mm thick High Polished Granite stone slabs black colour as approved by the
Engineer-in-Charge of length not less than 2.43 mts set over base coat of cement mortar (1:8) , 20mm thick
using screened sand over CC bed already laid or RCC roof slab including neat grey cement slurry of honey
like consistency spread @ 3.3 Kg per sqm and jointed neatly with white cement paste mixed with pigment of
matching shade to full depth including cost and conveyance of all materials like cement , sand , water ,
electricty, granite slabs etc., to work site and all operational, incidental labour & lift charges, half rounding the
edge , polishing charges, seigniorage charges , cost of base coat etc., complete for finished item of work for
Sill slabs (S.S.701 & special)

(BLD-CSTN-9-7)
Unit = 10 sqm.
A. MATERIALS:
High polished granite slabs black 16 10.50 Sqm 2303.00 1 Sqm 24181.50
to 18mm thick
Cement for CM(1:8) for base coat 36.00 Kgs 6400.00 1000 Kgs 230.40
Cement for slurry 33.00 Kgs 6400.00 1000 Kgs 211.20
White cement for jointing 6.00 Kgs 29.00 1 Kg 174.00
Sand for CM(1:8) 0.20 Cum 7572.87 1 Cum 1514.57
B .LABOUR
Mason 1st class 3.00 Nos 800.00 1 Each 2400.00
Mason 2nd class 1.00 Nos 650.00 1 Each 650.00
Mazdoor(un skilled) 8.00 Nos 550.00 1 Each 4400.00
Add for MA @ 40% 0.40 7450.00 2980.00
Machine cutting charges 16.67 RM 18.00 1 RM 300.06
Half rounding the edges 16.67 RM 353.00 1 RM 5884.51
Add for MA @ 40% 0.40 2473.83 989.53
Add water charges 1% 0.01 43915.78 439.16
Rate for 10 sqm 44354.93

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 44354.93 44354.93 44354.93 44354.93 44354.93 44354.93
Lift charges ( Page 131 of Std. Data ) 0.00 745.00 1490.00 2235.00 2980.00 3725.00

Add for MA @ 40% 0.00 298.00 596.00 894.00 1192.00 1490.00


44354.93 45397.93 46440.93 47483.93 48526.93 49569.93
Overheads&Contractors Profit 6482.47 6634.91 6787.34 6939.78 7092.21 7244.65
&Labour cess@14.615%
Rate per 10 Sqm 50837.40 52032.84 53228.27 54423.71 55619.14 56814.58
Rate per 1 Sqm 5083.74 5203.28 5322.83 5442.37 5561.91 5681.46
Say 5084 5203 5323 5442 5562 5681

Rate for other Floors 7F 8F


Rate as worked out above 44354.93 44354.93
Lift charges ( Page 131 of Std. Data ) 4470.00 5215.00

Add for MA @ 40% 1788.00 2086.00


50612.93 51655.93
Overheads&Contractors Profit 7397.08 7549.51
&Labour cess@14.615%
Rate per 10 Sqm 58010.01 59205.44
Rate per 1 Sqm 5801.00 5920.54
Say 5801 5921

IIIT-GACHIBOWLI CIVIL DATA 57 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
36 Granolithic Concrete flooring 20 mm thick with (1:1:2), using 6mm to 12 mm size hard granite machine
crushed metal and screened sand laid over CC bed already laid or RCC roof slab, in alternate panels of size
not exceeding 1.50 m x 1.50 m, using glass strips and finishing the top surface to required smoothness and
slopes and thread lining including cost of all materials like cement, metal, sand and water , electricity,
seigniorage charges etc., complete for finished item of work. (APSS No.701 & 710)

(BLD-CSTN-9-13)
Unit : 10sqm
A.MATERIALS :
6mm to 12mm HBG Metal 0.17 Cum 989.00 1 Cum 168.13
Cement 120.00 Kgs 6400.00 1000 Kgs 768.00
Sand 0.0850 Cum 6984.87 1 Cum 593.71
Add for glass strips 10.00 Sqm 8.00 1 Sqm 80.00
B. LABOUR
Mason 1st class 1.25 Nos. 800.00 1 Each 1000.00
Mason 2nd class 0.06 Nos. 650.00 1 Each 39.00
Mazdoor (unskiled) 3.00 Nos. 550.00 1 Each 1650.00
Add for MA @ 40% 0.40 2689.00 1075.60
Add water charges 1% 0.01 5374.44 53.74
Rate per 10 Sqm 5428.19

Rate for other Floors 7F 8F


Rate as worked out above 5428.19 5428.19
Lift charges ( Page 131 of Std. Data ) 1613.40 1882.30

Add for MA @ 40% 645.36 752.92


7686.95 8063.41
Overheads&Contractors Profit 1123.45 1178.47
&Labour cess@14.615%
Rate per 10 Sqm 8810.40 9241.88
Rate per 1 Sqm 881.04 924.19
Say 881 924
37 Flooring with chequered cement concrete heavy duty tiles confirming to IS:13801 using aggregates,
cement, pigments of size 300mm x 300mm and thickness 25mm of any shade as approved by Engineer -
In - Charge set over base coat of cement mortar (1:6), 12 mm thick using screened sand over CC bed alredy
laid or RCC roof slab including neat cement slurry of honey like consistency spread @ 3.3 kgs per sqm and
jointed with neat white cement to full depth mixed with pigment of matching shade including cost and
conveyance of all materials like cement, sand, water , electricity and tiles, seigniorage charges etc.,
complete for finished item of work.

(BLD-CSTN-9-4)
Unit : 10sqm
A.MATERIALS :
Chequrred cement concrete heavy 10.50 sqm 274.00 1 sqm 2877.00
duty tiles, 25mm thick
Cement for CM(1:6) proportion for 28.80 Kgs 6400.00 1000 Kgs 184.32
base coat
Cement for slurry 33.00 Kgs 6400.00 1000 Kgs 211.20
White cement for jointing & pointing 2.00 Kgs 29.00 1.00 Kgs 58.00
Sand for CM(1:6) proportion 0.12 Cum 7572.87 1 Cum 908.74
B. LABOUR
Mason 1st class 0.96 Nos. 800.00 1 Each 768.00
Mason 2nd class 2.24 Nos. 650.00 1 Each 1456.00
Mazdoor (unskiled) 3.30 Nos. 550.00 1 Each 1815.00
Add for MA @ 40% 0.40 4039.00 1615.60

IIIT-GACHIBOWLI CIVIL DATA 58 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Add water charges 1% 0.01 9893.86 98.94
Rate per 10 Sqm 9992.80

IIIT-GACHIBOWLI CIVIL DATA 59 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 9992.80 9992.80 9992.80 9992.80 9992.80 9992.80
Lift charges ( Page 131 of Std. Data ) 0.00 403.90 807.80 1211.70 1615.60 2019.50

Add for MA @ 40% 0.00 161.56 323.12 484.68 646.24 807.80


9992.80 10558.26 11123.72 11689.18 12254.64 12820.10
Overheads&Contractors Profit 1460.45 1543.09 1625.73 1708.37 1791.02 1873.66
&Labour cess@14.615%
Rate per 10 Sqm 11453.25 12101.35 12749.45 13397.55 14045.66 14693.76
Rate per 1 Sqm 1145.33 1210.14 1274.95 1339.76 1404.57 1469.38
Say 1145 1210 1275 1340 1405 1469

38 Providing 16 to 18mm thick high polished granite stone slabs other than black and regular colours
(i.e. of shades like paradiso / bala flower / copper silk / laka red / lavender blue) with borders and design as
per the pattern approved by the Engineer-in-Charge of length not less than 2.43 mts set over base coat of
cement mortar (1:5) , 12mm thick using screened sand over CC bed already laid or RCC roof slab including
neat grey cement slurry of honey like consistency spread @ 3.3 Kg per sqm and jointed neatly with white
cement paste mixed with pigment of matching shade to full depth including cost and conveyance of all
materials like cement , sand , water ,electricity, granite slabs etc., to work site and all operational, incidental
labour & lift charges, half rounding the edges of treads , polishing charges , seigniorage charges , cost of
base coat etc., complete for finished item of work for treads and risers (S.S.701 & special)

a) Treads of 0.30m wide :


(BLD-CSTN-9-7)
Unit = 10 sqm.
A. MATERIALS:
High polished granite slabs other 10.50 Sqm 2709.00 1 Sqm 28444.50
than black 16 to 18mm thick
Cement for CM(1:5) for base coat 34.56 Kgs 6400.00 1000 Kgs 221.18
Cement for slurry 33.00 Kgs 6400.00 1000 Kgs 211.20
White cement for jointing 6.00 Kgs 29.00 1 Kg 174.00
Sand for CM(1:5) 0.12 Cum 7572.87 1 Cum 908.74
B .LABOUR
Mason 1st class 3.00 Nos 800.00 1 Each 2400.00
Mason 2nd class 1.00 Nos 650.00 1 Each 650.00
Mazdoor(un skilled) 8.00 Nos 550.00 1 Each 4400.00
Add for MA @ 40% 0.40 7450.00 2980.00
Machine cutting charges 33.33 RM 18.00 1 RM 599.94
Half rounding the edges 33.33 RM 353.00 1 RM 11765.49
Add for MA @ 40% 0.40 4946.17 1978.47
Add water charges 1% 0.01 54733.53 547.34
Rate for 10sqm 55280.86

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 55280.86 55280.86 55280.86 55280.86 55280.86 55280.86
Lift charges ( Page 131 of Std. Data ) 0.00 745.00 1490.00 2235.00 2980.00 3725.00

Add for MA @ 40% 0.00 298.00 596.00 894.00 1192.00 1490.00


55280.86 56323.86 57366.86 58409.86 59452.86 60495.86
Overheads&Contractors Profit 8079.30 8231.73 8384.17 8536.60 8689.04 8841.47
&Labour
Rate per cess@14.615%
10 Sqm 63360.16 64555.59 65751.03 66946.46 68141.90 69337.33
Rate per 1 Sqm 6336.02 6455.56 6575.10 6694.65 6814.19 6933.73
Say 6336 6456 6575 6695 6814 6934

IIIT-GACHIBOWLI CIVIL DATA 60 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)

IIIT-GACHIBOWLI CIVIL DATA 61 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
b) Risers of 0.15m height :
(BLD-CSTN-9-19)
Unit = 10 sqm
A.MATERIALS :
Cost of high polished granite 10.50 sqm 2709.00 1 sqm 28444.50
Sand for CM(1:5) base coat 0.12 cum 7572.87 1 cum 908.74
Cement for CM(1:5) base coat 34.56 Kgs 6400.00 1000 Kgs 221.18
Cement for slurry 33.00 Kgs 6400.00 1000 Kgs 211.20
White cement for jointing & pointing 5.00 Kgs 29.00 1 Kg 145.00
Machine cutting charges 66.67 RM 18.00 1 RM 1200.06
Add for MA @ 40% 0.40 480.02 192.01
B.LABOUR
Mason 1st class 2.10 Nos. 800.00 1 Each 1680.00
Man Mazdoor(Beldar) 4.90 Nos. 550.00 1 Each 2695.00
Add for MA @ 40% 0.40 4375.00 1750.00
Add water charges 1% 0.01 37447.70 374.48
Rate for 10 sqm 37822.17

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 37822.17 37822.17 37822.17 37822.17 37822.17 37822.17
Lift charges ( Page 131 of Std. Data ) 0.00 437.50 875.00 1312.50 1750.00 2187.50

Add for MA @ 40% 0.00 175.00 350.00 525.00 700.00 875.00


37822.17 38434.67 39047.17 39659.67 40272.17 40884.67
Overheads&Contractors Profit 5527.71 5617.23 5706.74 5796.26 5885.78 5975.30
&Labour cess@14.615%
Rate per 10 Sqm 43349.88 44051.90 44753.91 45455.93 46157.95 46859.97
Rate per 1 Sqm 4334.99 4405.19 4475.39 4545.59 4615.80 4686.00
Say 4335 4405 4475 4546 4616 4686
39 Providing skirting to internal walls to 10 cm height with Double charged / multi charged stain free full
body porcelain vitrified tiles with double layer pigment of size 600 x 600 mm and thickness between 8-
10 mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all
shades and design , length equal to flooring tiles, set over base coat of CM(1:5) 12 mm thick using screened
sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with
white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like
tiles, cement, sand, water,electricity, all operational, incidental , labour and lift charges, seigniorage charges
etc. complete for finished item of work.(APSS No.701 &707)

(BLD-CSTN-9-20)
Unit = 10 sqm
Double charged / multi charged stain 10.50 sqm 550.00 1 sqm 5775.00
free full body porcelain vitrified tiles
with double layer pigment of size 600
x 600 mm TBSC-C.II-05
Sand for CM(1:5) base coat 0.12 cum 7572.87 1 cum 908.74
Cement for CM(1:5) base coat 34.56 Kgs 6400.00 1000 Kgs 221.18
Cement for slurry 33.00 Kgs 6400.00 1000 Kgs 211.20
White cement for jointing & pointing 2.00 Kgs 29.00 1 Kg 58.00

B.LABOUR
Mason 1st class 0.96 Nos. 800.00 1 Each 768.00
Mason 2nd class 2.24 Nos. 650.00 1 Each 1456.00
Mazdoor(unskilled) 3.30 Nos. 550.00 1 Each 1815.00
Add for MA @ 40% 0.40 4039.00 1615.60
Add water charges 1% 0.01 12828.73 128.29
Rate for 10 sqm 12957.02

IIIT-GACHIBOWLI CIVIL DATA 62 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)

IIIT-GACHIBOWLI CIVIL DATA 63 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Rate for other Floors Stilt/FF SF TF 4F 5F 6F
Rate as worked out above 12957.02 12957.02 12957.02 12957.02 12957.02 12957.02
Lift charges ( Page 131 of Std. Data ) 0.00 403.90 807.80 1211.70 1615.60 2019.50

Add for MA @ 40% 0.00 161.56 323.12 484.68 646.24 807.80


12957.02 13522.48 14087.94 14653.40 15218.86 15784.32
Overheads&Contractors Profit 1893.67 1976.31 2058.95 2141.59 2224.24 2306.88
&Labour
Rate per cess@14.615%
10 Sqm 14850.69 15498.79 16146.89 16794.99 17443.10 18091.20
Rate per 1 RM 148.51 154.99 161.47 167.95 174.43 180.91
Say 149 155 161 168 174 181
40 Providing skirting to internal walls 10cm height with High Polished Granite 16 to 18 mm thick up to 8'-
00 (2.43 M) other than black and regular colours, length equal to flooring slabs set over base coat of CM(1:5)
12 mm thick using screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs
per sqm and jointing with white cement paste mixed with pigment of matching shade to full depth, including
cost of all materials like tiles, cement, sand , water , electricity, all operational, incidental , labour and lift
charges, seigniorage charges etc., complete for finished item of work.

(BLD-CSTN-9-19)
Unit = 10 sqm
A.MATERIALS :
Cost of high polished granite 10.50 sqm 2709.00 1 sqm 28444.50
Sand for CM(1:5) base coat 0.12 cum 7572.87 1 cum 908.74
Cement for CM(1:5) base coat 34.56 Kgs 6400.00 1000 Kgs 221.18
Cement for slurry 33.00 Kgs 6400.00 1000 Kgs 211.20
White cement for jointing & pointing 5.00 Kgs 29.00 1 Kg 145.00
Machine cutting charges 66.67 RM 18.00 1 RM 1200.06
Add for MA @ 40% 0.40 480.02 192.01
B.LABOUR
Mason 1st class 2.10 Nos. 800.00 1 Each 1680.00
Man Mazdoor(Beldar) 4.90 Nos. 550.00 1 Each 2695.00
Add for MA @ 40% 0.40 4375.00 1750.00
Add water charges 1% 0.01 37447.70 374.48
Rate for 10 sqm 37822.17

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 37822.17 37822.17 37822.17 37822.17 37822.17 37822.17
Lift charges ( Page 131 of Std. Data ) 0.00 437.50 875.00 1312.50 1750.00 2187.50

Add for MA @ 40% 0.00 175.00 350.00 525.00 700.00 875.00


37822.17 38434.67 39047.17 39659.67 40272.17 40884.67
Overheads&Contractors Profit 5527.71 5617.23 5706.74 5796.26 5885.78 5975.30
&Labour cess@14.615%
Rate per 10 Sqm 43349.88 44051.90 44753.91 45455.93 46157.95 46859.97
Rate per 1 RM 433.50 440.52 447.54 454.56 461.58 468.60
PVC 433 441 448 455 462 469

IIIT-GACHIBOWLI CIVIL DATA 64 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
41 Providing cladding to walls with High Polished Granite 16 to 18 mm thick up to 8'-00 (2.43 M) other
than black and regular colours, length equal to flooring slabs set over base coat of CM(1:5) 12 mm thick
using screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and
jointing with white cement paste mixed with pigment of matching shade to full depth, including cost of all
materials like tiles, cement, sand , water, electricity etc., to site, cost of base coat, all operational charges,
incidental , labour and lift charges, seigniorage charges etc., complete for finished item of work

Rate for other Floors Stilt/FF SF TF 4F 5F 6F


Rate as worked out above 37822.17 37822.17 37822.17 37822.17 37822.17 37822.17
Lift charges ( Page 131 of Std. Data ) 0.00 437.50 875.00 1312.50 1750.00 2187.50

Add for MA @ 40% 0.00 175.00 350.00 525.00 700.00 875.00


37822.17 38434.67 39047.17 39659.67 40272.17 40884.67
Overheads&Contractors Profit 5527.71 5617.23 5706.74 5796.26 5885.78 5975.30
&Labour
Rate per cess@14.615%
10 Sqm 43349.88 44051.90 44753.91 45455.93 46157.95 46859.97
Rate per 1 Sqm 4334.99 4405.19 4475.39 4545.59 4615.80 4686.00
Say 4335 4405 4475 4546 4616 4686
42 Providing dadooing to walls with glazed full body ceramic tiles of any size and thickness between 5 to
7mm 1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Parts 1 to 15) of any colour and finish in all
shades and designs with borders as approved by Engineer-in-Charge set over base coat of CM(1:5) 12 mm
thick using screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per
sqm and jointing with white cement paste mixed with pigment of matching shade to full depth, including cost
and conveyance of all materials like tiles, cement, sand , water , electricity etc., to site, cost of base coat,all
operational charges, incidental , labour and lift charges, seigniorage charges etc., complete for finished item
of work.

(BLD-CSTN-9-18)
Unit = 10 sqm
A.MATERIALS :
Cost of glazed red or white full body 10.50 sqm 480.00 1 sqm 5040.00
ceramic wall tiles
Sand for CM(1:5) base coat 0.12 cum 7572.87 1 cum 908.74
Cement for CM(1:5) base coat 34.56 Kgs 6400.00 1000 Kgs 221.18
Cement for slurry 33.00 Kgs 6400.00 1000 Kgs 211.20
White cement for jointing & pointing 6.00 Kgs 29.00 1 Kg 174.00
B.LABOUR
Mason 1st class 0.77 Nos. 800.00 1 Each 616.00
Mazdoor(unskilled) 0.80 Nos. 550.00 1 Each 440.00
Add for MA @ 40% 0.40 1056.00 422.40
Add water charges 1% 0.01 8033.53 80.34
Rate for 10 sqm 8113.86
Rate for other Floors Stilt/FF SF TF 4F 5F 6F
Rate as worked out above 8113.86 8113.86 8113.86 8113.86 8113.86 8113.86
Lift charges ( Page 131 of Std. Data ) 0.00 105.60 211.20 316.80 422.40 528.00

Add for MA @ 40% 0.00 42.24 84.48 126.72 168.96 211.20


8113.86 8261.70 8409.54 8557.38 8705.22 8853.06
Overheads&Contractors Profit 1185.84 1207.45 1229.05 1250.66 1272.27 1293.88
&Labour
Rate per cess@14.615%
10 Sqm 9299.70 9469.15 9638.59 9808.04 9977.49 10146.94
Rate per 1 Sqm 929.97 946.92 963.86 980.80 997.75 1014.69
Say 930 947 964 981 998 1015

IIIT-GACHIBOWLI CIVIL DATA 65 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
43 Filling with light weight concrete in Cement Concrete (1:5:10) proportion using brick jelly for low roofs
including cost and conveyance of all materials like cement, sand, brick bats, water, electricty etc., to site
including cost of all labour charges for laying concrete, ramming, curing ,all incidental charges and
seigniorage charges etc., complete for finished item of work. (APSS. No. 402)

(BLD-CSTN-3-7)
Unit: 1 Cum
A. Materials :-
Cement 129.60 Kgs 6400.00 1000 Kgs 829.44
Cost of brick jelly 20mm size(1/3rd 460 Nos. 10564.81 1000 Nos. 1619.94
rate)
Fine aggregate ( Sand ) 0.450 Cum 6984.87 1 Cum 3143.19
Water (including curing) 1.20 kl 98.00 1 kl 117.60
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8 1.00 hour 150.50 1 hour 150.50
cum)capacity
Crew Charges 1.00 hour 247.00 1 hour 247.00
Add MA on crew charges 0.40 247.00 98.80
C.LABOUR :
1st class mason 0.10 Nos. 800.00 1 Each 80.00
Mazdoor (unskilled) 1.39 Nos. 550.00 1 Each 764.50
Add for MA @ 40% 0.40 844.50 337.80
7388.77
Rate for other Floors Stilt/FF SF TF 4F 5F 6F
Rate as above 7388.77 7388.77 7388.77 7388.77 7388.77 7388.77
Lift charges ( Page 131 of Std. Data ) 0.00 84.45 168.90 253.35 337.80 422.25

Add for MA @ 40% 0.00 33.78 67.56 101.34 135.12 168.90


Rate per 1 cum 7388.77 7507.00 7625.23 7743.46 7861.69 7979.92
Overheads&Contractors Profit 1079.87 1097.15 1114.43 1131.71 1148.99 1166.27
&Labour
Rate per cess@14.615%
1 cum 8468.64 8604.15 8739.66 8875.17 9010.68 9146.19
Say 8469 8604 8740 8875 9011 9146

44 Reinforced cement concrete (1:5:10) proportion (Cement: fine aggregates: coarse aggregate) using
40mm size (SS5) hard granite metal (coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand), coarse aggregate, water,elecricity etc., to site
including centering using Steel scaffolding pipes, jack Props, Steel Centering Plates,etc., shuttering,
machine mixing, laying concrete, lifting concrete manually , curing,all incidental charges, seigniorage
charges etc., complete as per drawings but excluding cost of steel and it's fabrication charges for finished
item of work (APSS NO. 402 & 403) for Dummy columns.

(BLDS-CSTN-3-13)
Unit: 1 Cum
A. Materials :-
Cement 129.60 Kgs 6400.00 1000 Kgs 829.44
40mm HBG metal 0.90 Cum 883.00 1 Cum 794.70
Fine aggregate ( Sand ) 0.450 Cum 6984.87 1 Cum 3143.19
B.LABOUR :
1st class mason 0.17 Nos. 800.00 1 Each 133.60
2nd class Mason 0.167 Nos 650.00 1 Each 108.55
Mazdoor (unskilled) 4.70 Nos. 550.00 1 Each 2585.00
Add for MA @ 40% 0.40 2827.15 1130.86

IIIT-GACHIBOWLI CIVIL DATA 66 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
C.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8 1.00 hour 150.50 1 hour 150.50
cum)capacity
Crew Charges 1.00 hour 247.00 1 hour 247.00
Needle vibrator 40mm ( petrol ) 1.00 hour 27.20 1 hour 27.20
Crew charges 1.00 hour 177.80 1 hour 177.80
Add MA on crew charges 0.40 424.80 169.92
Water(including for curing) 1.20 kl 98.00 1 kl 117.60
9615.36
Rate for other Floors 7F 8F
Rate as above 9615.36 9615.36
Hire charges of centering and 3601.00 3601.00
scaffolding
Labour , lift charges for scaffolding 2520.70 2880.80
Add for MA @ 40% 1008.28 1152.32
Lift charges ( Page 131 of Std. Data ) 1696.29 1979.01

Add for MA @ 40% 678.52 791.60


Rate per 1 cum 19120.15 20020.10
Overheads&Contractors Profit 2794.41 2925.94
&Labour cess@14.615%
Rate per 1 cum 21914.56 22946.04
Say 21915 22946
45 Supplying and fixing of stainless steel ( grade 304 ) hand railing as per approved drawing with top rail of
50mm dia pipe and 2mm thick medium class and vertical posts of 25mm dia and 1.6mm thick medium class
2 Nos for each step fixed with base plate of 75mm dia using bonding agent and anchor fastner and welding,
drilling of 25mm dia holes with pneumatic compressor for fixing railing, buffing, polishing all members of the
railing thouroughly , lacquer finishing to present seamless finish including cost and conveyance of all
materials, electrodes, welding charges, cost of all consumables, labour charges etc., complete for finished
item of work.

For a flight length of 4.60 M. 4.60 RM


Cost of 50mm dia SS pipe (1x4.60) 4.60 RM
Cost of 25mm dia SS pipe (26x0.90) 23.40 RM
50.00mm pipe (4.60 x 2.39 Kgs/RM) 10.99 Kgs

25mm pipe (23.40x 0.89 Kgs/RM) 20.83 Kgs


Cost of stainless steel pipes 31.82 Kgs 387.00 1 Kg 12314.34
Labour charges for fabrication 31.82 Kgs 146.00 1 Kg 4645.72
Drilling of 25mm dia hole(13 x 0.10) 1.30 RM 144.00 1 RM 187.20
Base Plate 75mm dia. 13 Nos. 100.00 1 Each 1300.00
Add for anchor bars 13 Nos. 40.00 1 No 520.00
Add for bonding 13 Nos. 20.00 1 No 260.00
19227.26
Rate per 1 RM 4179.84
Rate per 1 Sqm 4644.27
Overheads&Contractors Profit &La 0.15 4644.27 678.76
5323.03
say 5323

IIIT-GACHIBOWLI CIVIL DATA 67 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
46 Providing 110 mm Dia ISI marked PVC down water take pipes with socket , 2.5mm thick 4.0 kg/sq.cm
pressure of ISI marked including cost of necessary PVC Bends, shoes, iron / PVC clamps and all other
accessories and fixing in position including cost and conveyance of all materials, operational & incidental
charges including all labour charges for fixing at site etc., complete for finished item of work. (APSS No.
1328)

PVC pipe 110mm dia 6.00 RM 164.00 1 RM 984.00


MS Clamps 3 Nos. 18.00 1 Each 54.00
Labour charges for fixing pipes 6.00 RM 76.00 1 RM 456.00
Rate per 6 RM 1494.00
249.00
Overheads&Contractors Profit 0.15 249.00 36.39
&Labour
Rate per cess@14.615%
1 RM 285.39
Say 285
47 Providing and applying Wall putty of White Cement or Polymer or Cement based of average 1 to 2 mm
thickness over plastered surface to prepare the surface even and smooth after thoroughly brushing the
surface to remove all dirt and remains of loose powdered materials, applying emery paper, Sand the surface,
clean & wipe off loose dust, applying knifing paste filler by putty knife / muslin pad, air dry for 2 - 3 hrs, sand
with 180 and 320 No., emery paper for the surface preparation including cost and conveyance of all materials
to work site and all operational, incidental, labour charges etc., complete for finished item of work in all floors
for Internal walls

(As per Amendment in SoR 2011-12)


Unit = 10 Sqm
wall putty 23.00 Kgs 41.00 1 Kg 943.00
Painter 1st class 0.273 Nos. 800.00 1 Each 218.40
Painter 2nd class 0.637 Nos. 650.00 1 Each 414.05
Mazdoor 0.91 Nos. 550.00 1 Each 500.50
Add for MA @ 40% 0.40 1132.95 453.18
Sundries for emery papers, fillers, 0 2529.13 0.00
knife etc., @ 1%
2529.13
Overheads&Contractors Profit 0.15 2529.13 369.63
&Labour cess@14.615%
Rate per 10 sqm 2898.76
Rate per 1 sqm 289.88
Say 290
48 Supply & application of one coat water based cement primer of interior grade I and two coats of
acrylic emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/litre for
internal walls including cost and conveyance of all materials to site, incidental, operational and all labour
charges etc., complete for finished item of work in all floors

(BLD-CSTN-12-2& Amendment in SoR 2011-


12)
Unit 10 Sqm.
A. Materials:-
Cost of cement primer interior grade I 1.00 Kg 150.00 1 Kg 150.00
Painter 1st class 0.21 Nos. 800.00 1 Each 168.00
Painter 2nd class 0.49 Nos. 650.00 1 Each 318.50
Acrylic emulsion paint 0.80 Ltrs 195.00 1 Ltrs 156.00
Painter 1st class 0.36 Nos. 800.00 1 Each 288.00
Painter 2nd class 0.84 Nos. 650.00 1 Each 546.00
Add for MA @ 40% 0.40 1320.50 528.20
Sundries including brushes , ladders 0 2154.70 0.00
etc., @ 1%
2154.70
Overheads&Contractors Profit 0.15 2154.70 314.91
&Labour
Rate per cess@14.615%
10 sqm 2469.61

IIIT-GACHIBOWLI CIVIL DATA 68 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Rate per 1 sqm 246.96
Say 247

49 Providing and applying Exterior grade Texture ready mixed plaster made with natural minerals -
granite flakes/ marble flakes/ powder, sand and other carefully selected and sieved minerals in an
acrylic binding medium of average 2 to 3 mm thickness over plastered surface to prepare the surface even
and smooth after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials,
applying emery paper, Sand the surface, clean & wipe off loose dust, applying putty/ texture paint filler by
putty knife / muslin pad, air dry for 2 - 3 hrs for the surface preparation including cost and conveyance of
all materials to work site and all operational, incidental, labour charges, scaffolding charges etc., complete for
finished item of work in all floors for external walls

(As per Amendment in SoR 2011-12)


Unit 10 Sqm.
A. Materials:-
exterior texture 34.50 Kgs 47.00 1 Kgs 1621.50
Painter 1st class 0.273 Nos. 800.00 1 Each 218.40
Painter 2nd class 0.637 Nos. 650.00 1 Each 414.05
Mazdoor 0.91 Nos. 550.00 1 Each 500.50
Add for MA @ 40% 0.40 1132.95 453.18
Sundries for emery papers, fillers, 0 3207.63 0.00
knife etc., @ 1%
Hire charges for Access Scaffolding 10 sqm 1.03 1 sqm 10.30
Labour charges for scaffolding 10 sqm 18.24 1 sqm 182.40
Add for MA @ 40% 0.40 182.40 72.96
3473.29
Overheads&Contractors Profit 0.15 3473.29 507.62
&Labour cess@14.615%
Rate per 10 sqm 3980.91
Rate per 1 sqm 398.09
Say 398
51 Painting two coats with synthetic enamel paint Grade-II VOC (Volatile Organic Compound) content less
than 50 grams/litre over primer coat of red oxide to new iron work including cost and conveyance of all
materials to site, incidental, operational and all labour charges etc., complete for finished item of work in all
floors. (SS No. 1201, 1212 & 1207).

(BLD-CSTN-12-7 & 12-12-197)


Unit : 10 sqm
A.MATERIALS :
Red oxide primer 0.70 Ltr 129.00 1 Ltr 90.30
Cost of Synthetic Enamel Paint 1.10 Ltr 191.00 1 Ltr 210.10
B.LABOUR :
for primer coat
1st Class Painter 0.21 Nos. 800.00 1 Each 168.00
2nd Class Painter 0.49 Nos. 650.00 1 Each 318.50
for enamel painting
1st Class Painter 0.33 Nos. 800.00 1 Each 264.00
2nd Class Painter 0.77 Nos. 650.00 1 Each 500.50
Add for MA @ 40% 0.40 1251.00 500.40
Sundries including brushes , ladders 0 2051.80 0.00
etc., @ 1%
2051.80
Overheads&Contractors Profit 0.14615 2051.80 299.87
&Labour cess@14.615%
Rate per 10 sqm 2351.67

IIIT-GACHIBOWLI CIVIL DATA 69 of 354


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit
(Rs.)
Rate per 1 sqm 235.17
Say 235

52 Providing specialized polysulphide sealant treatment to the expansion joints (Size : 25mm x 12mm) duly
a].Chipping and removing of existing covering on expansion joints b]. Cleaning of the surface from dirt, dust
and other contaminations c].Application of one coat of - High performance specially designed SBR latex
polymer based bonding agent d]. Providing and application of Acrylic Polymer modified reinstatement
concrete /mortar to the damaged edges of joint and making the groove. e]. Providing and fixing of masking
tape on top of the joint both sides f]. Providing and fixing of Back up support material of Backer rod to leave
the depth of 12mm on the joint g]. Providing and application of one coat of polysulphide primer on inner
edges of Joint. h]. Providing and application of Two part Polysulphide sealant to a width of 25mm and 12mm
depth with putty knife and neat finish i]. Removing of masking tape and providing and application of two coats
of Acrylic elastomeric cementitious coating of approved make including cost and conveyance of all materials
to site, all incidental, operational, labour charges etc., complete for finished item of work as per approved
drawing (for all floors on top of slab i.e in the flooring and for internal vertical joints of grooves in dadooing
surface).

Rate as per SSR 1.00 RM 675.00 1 RM 675.00


Overheads&Contractors Profit 0.14615 675.00 98.65
&Labour cess@14.615%
738.50
Rate per 1 RM Say 738
53 Providing and fixing of Expansion joint filler board for buildings, columns, beams and slabs 25 mm thick
including cost and conveyance of all materials to site, all incidental, operational, labour charges etc. complete
for finished item of work as per approved drawing for all floors

Rate as per SSR 1.00 Sqm 366.00 1 Sqm 366.00


Overheads&Contractors Profit 0.15 366.00 53.49
&Labour
Rate per cess@14.615%
1 sqm 419.49
Say 419
54 Providing and fixing of 24 gauge alluminium sheet over expansion joint groove of width 15cm fixed to walls /
columns at one edge and resting over the other block walls/columns concealing expansion joint with slotted
holes for free edge of aluminium sheet to facilitate free movement of aluminium sheet over the finished
surface of expansion joint and wall face using sheet metal screws with nylon receiver complete including cost
and conveyance of all materials to site, all incidental, operational, labour charges etc., complete for finished
item of work as per approved drawing (for all floors for vertical joints and bottom of slab)

Cost of aluminium sheet 24 gauge 1.00 Sqm 274.00 1 Sqm 274.00


Add for labour charges including cost 6.60 RM 25.00 1 RM 165.00
of nails, making holes to wall and in
aluminium sheet etc.
Rate per 1 sqm 439.00
Rate per 1 RM 67.00
Overheads&Contractors Profit 0.14615 67.00 9.79
&Labour cess@14.615%
76.79
Say 77

IIIT-GACHIBOWLI CIVIL DATA 70 of 354


JOINERY DATA
MARKET RATES
1 Supply & Fixing of Powder Coated Mild Steel doors, frames & shutters made of Skin pass galvanized Iron
sheet conforming to Base Steel as per IS 513 “D” Quality, Galvanized as per IS 277 with Hot Zinc Coating
of 120 grams / Sq.Mtr with powder coating of thickness 60-65 Microns, frame with 1.2mm thick Skin pass
Galvanized Iron sheet formed to single rebate profile of size 100 mm X 58 mm and filled with in-fill
Polyurethane foam, the Door Shutters are with 0.80 mm thick Skin pass Galvanized Iron Sheet formed to
provide a 46 mm thick fully flush, double skin door shell with Lock Seam joints at stile edges, fitted with in-
fill of Honeycomb Kraft Paper and coated with polyester powders of Pure polyester/ epoxy polyester or
polyurethane powder for powder coating of thickness 60 – 65 microns and are coated with Zinc Phosphate
Primer to receive any paint on site or finished with Thermosetting Polyurethane paint of Aliphatic Grade
providing high levels of scratch resistance and durability, the Shutter provided with 6 MM clear float vision
glass in Circular, Square or Rectangular shapes, Stainless Steel Ball Bearing Butt Hinges 3 mm thick fixed
flush to the frame and shutter (Profile 102x76x3mm thick).Mortise Sash Lock with Lever Handles, Mortise
Dead Bolt, etc for industrial, commercial, residential, clean room applications etc., including cost and
conveyance of all materials and labour charges etc., complete for finished item of work

Rate as per SoR TBSC-L.III-18 1.00 Sqm 11110.00 1 Sqm 11110.00


Rate for 1 sqm 12733.7

2 Providing and fixing factory made solid Wood Polymer Composite (WPC) single extruded Door
Frame section of 100*65 MM with encapsulation of 6 MM rigid layer on all external surfaces. The door
frame will have a rebate of 32MM/ 37 MM. The two Vertical members are to be joined together with the
horizontal member using 8x75 MM long MS Star full thread screws to be used with reverse forward speed
control hand drilling machine. The ready/assembled door frame is fixed to wall using Z Hand fast 300 MM
long hold fast including cost and conveyance of all materials, labour charges for fixing etc., complete for
finished item of work.

Rate as per SoR TBSC-L.I-21 1.00 RM 660.00 1 RM 660.00


Overheads&Contractors Profit &Labour
cess@14.615% 0.15 660.00 96.46
Rate per 1 RM 756.46
Say 756
3 Providing and fixing 28 -30 MM thick solid Wood Polymer Composite(WPC) single extruded door shutter
with 3MM top and bottom rigid layer with an overall density of 750kg/Cum.It will be fixed to the frame using
3 inch /4 inch hinges. A minimum of 4 hinges will be required for fixing the door with the frame including
ISI marked Stainless steel fixtures 3 Nos. butt hinges (IS:12817) of 150mm long, 1 No. aldrop (IS:15834)
250 mm long, 1 No. Tower Bolt-10 mm Bolt (IS:15833) 50 mm Long , 2 Nos. 125mm long handles ,1 No.
Rubber / Nylon door stop bushes including labour charges for fixing the shutter to frame etc., including
cost and conveyance of all materials and labour charges etc., complete for finished item of work

Quantity analysis for door of size : 0.75m x 2.10m


Rate as per SoR BMT-N.88 1.333 Sqm 3030.00 1 Sqm 4038.99
Cost of Stainless steel tower bolt 150mm
long 1 No. 147.00 Each 147.00
Cost of Stainless steel butt hinges 150mm
long 3 Nos. 148.00 Each 444.00
Cost of Stainless steel aldrop 250mm long 1 No. 279.00 Each 279.00
Cost of stainless steel handle 125mm long 1 No. 114.00 Each 114.00
Cost of Rubber / Nylon door stop bushes 1 No. 9.00 Each 9.00
Add for nails & screws etc. 0.55
Rate for 1.575 sqm 5032.54
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 5032.54 735.51
5768.05
Rate for 1 sqm 4327.12

IIIT-GACHIBOWLI Joinery Data 1 of 354


Say 4327
4 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) 3 track sliding doors with mesh shutter
– (2-glass shutters and 1-mesh shutter)- 95 - Series duly manufactured using UPVC reinforced profiles
(Composition of profile shall consists a minimum of 5.5 PHR of TiO2 and not more than 12 PHR of CaCo3
for every 100 parts of PVC resin) of (108 mm x 45 mm)/(95.50 mm x 60 mm) x 2.20 mm for outer frames,
(75 mm x 39 mm)/(66 mm x 42 mm) x 2.20 mm for sliding door shutter frames capable of mounting single
glazing system, structurally reinforced with hot dip galvanized up to 50 microns of minimum thickness of
1.2 mm prefabricated & welded through fusion welding the door sash shall be fitted with 6 mm thick clear
float glass of reputed make duly fixed with Grey colour TPV Gasket for sash & Glazing bead shall be
coextruded with Grey colour soft PVC. Mesh shutter shall be made of (48 mm x 30 mm))/(50 mm x 26.5
mm) x 2.0 mm uPVC profile section and fitted with Vinyl Coated Fibre mesh and rollers/pulley duly fixed
with TPV Gaskets weathering seal resistant Door shall be provided with standard hardware & multi point
locking system of Patio/Roto espagulate and the system is to be installed at the site using anchor
fasteners, silicon rubber sealant, easy glazing/ deglazing at site etc., including cost and conveyance of all
materials and labour charges etc., complete for finished item of work

Rate as per SoR TBSC-L.III-10 1.00 Sqm 5598.00 1 Sqm 5598.00


Overheads&Contractors Profit &Labour
cess@14.615% 0.15 5598.00 818.15
Rate per 1 Sqm: 6416.15
Say 6416
5 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) 3 track sliding windows with
mesh shutter – (2-glass shutters and 1-mesh shutter) duly manufactured using UPVC reinforced profiles
(Composition of profile shall consists a minimum of 5.5 PHR of TiO2 and not more than 12 PHR of CaCo3
for every 100 parts of PVC resin) of (94 mm x 45 mm)/(80 mm x 52 mm) x 2.20 mm for outer frames, (58
mm x 39 mm)/(54 mm x 38 mm) x 2.20 mm for sliding shutter frames capable of mounting single glazing
system structurally reinforced with hot dip galvanized up to 50 microns of minimum thickness of 1.0/1.2
mm prefabricated & welded through fusion welding. The window sash shall be fitted with 5 mm thick clear
float glass of reputed make and mesh shutter frame shall be (42 mm x 25 mm)/(52 mm x 21.5 mm) x 2.0
mm fitted with Vinyl Coated Fiber mesh- on rollers/ pulley duly fixed with Grey colour TPV Gasket for sash
& Glazing bead shall be co-extruded with Grey colour soft PVC. System shall have single point locking
with Touch Lock and the system is to be installed at the site using anchor fasteners, silicon rubber sealant,
easy glazing/ deglazing at site etc., including cost and conveyance of all materials, accessories, labour
charges for transportation, erection at site etc., including cost and conveyance of all materials,
accessories, labour charges for transportation, erection at site etc., complete for finished item of work

Rate as per SoR 1.00 Sqm 5113.00 1.00 Sqm 5113.00


Overheads&Contractors Profit &Labour 5113.00
cess@14.615% 0.15 5113.00 747.26
Rate for 1 Sqm 5860.26
Say 5860
6 Providing, supplying & fixing of Fixed Louvered Ventilator made out of multi chambered uPVC
sections with Glazing bead shall be co-extruded with Grey colour soft PVC. having isolated drainage and
reinforced with Galvanized Iron profiles throughout the window. The outer frame having an overall size of
60 mm x 55 mm x 2.40 with reinforcement of 1 mm thickness and Mullion with overall size of 74 mm x 60
mm x 2.40 mm with reinforcement of 1 mm thickness. (Composition of profile shall consists a minimum of
5.5 PHR of TiO2 and not more than 12 PHR of CaCo3 for every 100 parts of PVC resin).Ventilator shall be
provided with 4.5 mm Pin Head glass, standard hardware. Wall thickness of frame & Mullion shall be 2.4
mm.,including cost and conveyance of all materials, accessories, labour charges for transportation,
erection at site etc., complete for finished item of work

Rate as per SoR


Overheads&Contractors Profit &Labour 1.00 Sqm 4844.00 1.00 Sqm 4844.00
cess@14.615% 0.15 4844.00 707.95
Rate for 1 Sqm 5551.95
Say 5552

IIIT-GACHIBOWLI Joinery Data 2 of 354


7 Supplying and fixing of MS Grill to windows using 25mm x 6mm MS flat alround and 10mm MS
square bars horizontally at 125mm centre to centre and vertically at 30cm centre to centre including fixing
with 4 Nos of MS Z holdfasts (2 on each side) duly making cutting brick masonry, fixing and making to
original surface neatly and painting grill with one coat of red oxide primer including cost and conveyance of
all materials including cutting, bending, welding including all operational charges and all labour charges
etc., complete for finished item of work.

For1.80mx1.70m size 3.06 Sqm


Quantity Anailysis
Cost of 25mm x 6mm MS flat alround 2 ( 1.80+ 1.70 ) 7.00 RM
7.00 RM @ 1.20 Kgs/RM 8.40 Kgs

Cost of 10mm M.S square bars @0.785 kg /RM


Vertical bars 5 5 x 1.70 8.50
Horizontal bars 13 x 1.80 23.40
31.90 RM 25.04 Kgs
33.44 Kgs
Cost Analysis
Cost of 10mm MS squre bars 25.04 Kgs 43000.00 1000 Kgs1076.78
Cost of 25X 6mm MS Flat 8.40 Kgs 43000.00 1000 Kgs 361.20
Labour charges for fabrication of steel 33.44 Kgs 29.00 1 Kg 969.80
Labour charges for fixing 33.44 4.00 133.77
Add for MA @ 40% 0.40 521.69 208.67
Rate per 3.06 Sqm 2750.23
898.77
Overheads&Contractors Profit @14% 0.14 898.77 125.83
1024.60
Rate per 1 Sqm Say 1025
8 Supplying and fixing of two shutter cupboards as per drawing with medium teak wood frames of size
75mm x 40mm and MDF Board Interior grade both sides laminated 18mm thick for shutters with 18mm x
12mm teak wood beading alround and supplying and fixing powder coated MS fixtures 3 Nos. butt
hinges of size 100mm long(for each shutter), tower bolt 2 Nos. of 100mm x 10mm, 2 Nos of handles
100mm long and standard locking arrangements for shutters including cost and conveyance of all
materials to site, labour charges, etc., complete for finished item of work.

For Cup board of size 1.20m x 1.80m 2.16 sqm


Cost of medium teak wood frame 0.0180 Cum 72620.00 1 Cum 1307.16
MDF Board Interior - BSL 18mm thick 2.16 Sqm 1100.00 1 Sqm 2376.00
Powder coated butt hinges 100mm long 6 Nos 21.00 1 Each 126.00
Powder coated tower bolts 100mm long 2 Nos 24.00 1 Each 48.00
Powder coated handles 100mm long 2 Nos 30.00 1 Each 60.00
Teak wood beading 18mm x 12mm 7.20 RM 30.00 1 RM 216.00
Cupboard locks 1 No 100.00 1 Each 100.00
Labour charges for frame work 0.0144 Cum 17141.50 1 Cum 246.84
Labour charges for shutters and fixing
fixtures 2.16 Sqm 800.00 1 Sqm 1728.00
Add for MA @ 40% 0.40 1974.84 789.94
Add LS for Screws, Nails etc. 2.48
7000.41
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 7000.41 1023.11
Rate per 2.16 Sqm 8023.52
Rate per 1 Sqm 3714.59
Say 3715

IIIT-GACHIBOWLI Joinery Data 3 of 354


Electrical Datas

S.N
SSR No Description Qty Unit Rate
o
CONDUIT PIPE
1 Supply and Laying of ISI 25mm outer dia heavy grade with IS:9537 part 3 regid PVC
concealed in Roof Slabs with all required PVC / Metallic Deep Boxes including mason
work and labour charges etc., complete. Makes : Sudhakar / GM / Modi / Million Pla

a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 540.00
2 Lineman Electric / Telephone 2.00 day 1 day 450.00
3 Helper (Electrical). 2.00 day 1 day 450.00
Labour Rate Per 100 Rm
Labour Rate for 1 Mtr
b) Material
ELEC- Supply of PVC Junction Boxes 12.00 Nos 1 Nos 24.00
1.2.9 Deep size 25mm.
ELEC- Supply of 25mm dia 1.5mm thick 12.00 Nos 1 Nos 7.00
1.2.10 PVC Bends.
ELEC- Supply of ISI 25mm outer dia 100.00 Mtr 1 Mtr 30.00
1.2.1 heavy grade FRLS with IS:9537
part 3 regid PVC pipe.

Material Rate for 100 Mtrs


Material Rate for 1 Mtr
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

2 Supply and laying of ISI 25mm outer dia medium grade with IS:9537 part 3 regid PVC
concealed in wall with all required PVC / Metallic Junction Boxes including masonary
and labour charges etc., Makes : Sudhakar / GM / Modi / Million Plast.

a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 540.00
2 Lineman Electric / Telephone 2.00 day 1 day 450.00
3 Helper (Electrical). 2.00 day 1 day 450.00
4 Mason Cl- I / Brick layer Cl- I 2.00 day 1 day 470.00
Labour Rate Per 100 Rm
Labour Rate for 1 Mtr
b) Material
ELEC- Cement. 50.00 kg 1 Kg 8.00
9.4.11
ELEC- U Nails. 200.00 Nos 100 Nos 30.00
9.1.4
ELEC- Supply of 25mm PVC Junction 12.00 Nos 1 Nos 18.00
1.2.8 Boxes Normal.

IIIT-HYD ELEC-Data 4 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC- Supply of 25mm dia 1.5mm thick 12.00 Nos 1 Nos 7
1.2.10 PVC Bends.
ELEC- Supply of ISI 25mm outer dia 100.00 Mtr 1 Mtr 24.00
1.2.2 medium grade FRLS with
Material Rate3for
IS:9537 part 100PVC
regid Mtrspipe.
Material Rate for 1 Mtr
Total Cost of Material +
Add Contractors Profit ###
Labour Charges

Rate per Meter 79.00

IIIT-HYD ELEC-Data 5 of 354


S.N
SSR No Description Qty Unit Rate
o
3 Supply and erecting PVC / GI / MS Galvanished fan hook box with hook in RCC slab
including all Labour charges etc., complete.
a) Material
ELEC- PVC/ MS with hook in RCC Fan each 1 1 Nos 98.00
9.1.22 hook ELEC-9.1.21
ELEC- Supply of PVC Junction Boxes each 1 -1 Nos 24
1.2.9 Deep size 25mm.
Rate
Add Contractors Profit ###
Rate per Each

Wiring
Point wiring in Non Residential Building
4 Wiring with run of 2 of 22/0.3mm (1.5 Sqmm) FRLS / HFFR PVC insulated flexible IS
copper cable Makes : Finolex/ RR Cable/ Havells/ Polycab/ HPL/ RPG/ Power flex / G
Million / Gold Medal in existing PVC conduit pipe including Supply and fixing of Jumb
Ceiling rose and 6A/10A ISI Mark 1way Modular switch with required modular box an
cover frame Makes : GM Four-Five / Legrand Arteor / Schneider Zen celo /Honeywell
Blenge Plus/ Cabtree Verna/ Million logus / Gold Medal Curve in existing Surface or
Concealed pipe wiring including cost and conveyance of all material and all labour ch
etc., complete for light, Fan, Exhaust fan and bell points in N.R.B.
a) Labour charges :
1 Skilled Electrician. 0.60 day 1 day 540.00
2 Lineman Electric / Telephone 1.20 day 1 day 450.00
3 Helper (Electrical). 0.60 day 1 day 450.00
Labour for 6 Points
Labour for 1 Point
b) Material
ELEC- 100 Supply of 3 Module box. 2 Nos 1 No 76.00
1.3.1
ELEC- 106 Supply of 3 Modular Cover 2 Nos 1 No 72.00
1.3.2
ELEC- 277 Frame.
Supply of 6A / 10A 1 Way 1 6 Nos 1 No 86.00
1.9.1 Module Modular Switch.
ELEC- 247 Supply of 3 Plate Jumbo Ceiling 6 Nos 1 No 19.00
1.7.1 Rose.
ELEC- 149 Supply of 22/0.3mm (1.5 Sqmm) 100.00 Mtrs 100 Mtrs 1482.00
1.5.1 FRLS / HFFR PVC insulated
1100V grade as perIS:694/1990
specification for Copper cable.

Cost of Material for 6 Points


Cost of Material Rate per 1 Point

Total Cost of Material +


Labour Charges
Add Contractors Profit ###

Rate per Each


Stair case point wiring Point wiring in Non Residential Building

IIIT-HYD ELEC-Data 6 of 354


S.N
SSR No Description Qty Unit Rate
o

IIIT-HYD ELEC-Data 7 of 354


S.N
SSR No Description Qty Unit Rate
o
5 Wiring with run of 2 of 22/0.3mm (1.5 Sqmm) FRLS / HFFR PVC insulated flexible IS
copper cable Makes : Finolex/ RR Cable/ Havells/ Polycab/ HPL/ RPG/ Power flex / G
Million / Gold Medal in existing PVC conduit pipe including Supply and fixing of Jumb
Ceiling rose and 6A/10A ISI Mark 1way Modular switch with required modular box an
cover frame Makes : GM Four-Five / Legrand Arteor / Schneider Zen celo /Honeywell
Blenge Plus/ Cabtree Verna/ Million logus / Gold Medal Curve in existing Surface or
Concealed pipe wiring including cost and conveyance of all material and all labour ch
etc., complete for staircase light points in N.R.B.
1.5 times of normal (Total 603 Nos 1 No 1.50
Cost of Material + Labour
Charges) of Item number 4

Rate per Each

Point wiring in Residential Building


6 Wiring with 2 runs of 22/0.3mm ( 1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible
cable (ISI MARK) in existing pipe with 6A Modular switch, Ceiling rose/BH/SBH Modu
switches with cover plate and GI switch box including all labour charges etc., comple
(for Non-Residential Building)
Makes of wires : Finolex/ RR Cable/ Havells/ Polycab/ HPL/ RPG/ Power flex / GM /
Million / Gold Medal.
Makes of switches:-
a) Labour charges : GM Four-Five / Legrand Arteor / Schneider Zen celo /Honeywell
1 Blenge Plus/ Cabtree Verna/ Million 0.70
Skilled Electrician. logusday
/ Gold Medal
1 Curve.
day 540.00
2 Lineman Electric / Telephone 1.40 day 1 day 450.00
3 Helper (Electrical). 0.70 day 1 day 450.00
Labour for 6 Points
Labour for 1 Point
b) Material
ELEC- 100 Supply of 3 Module box. 1 Nos 1 No 76.00
1.3.1
ELEC- 101 Supply of 4 Module box. 1 Nos 1 No 90.00
1.3.1
ELEC- 106 Supply of 3 Modular Cover 1 Nos 1 No 72.00
1.3.2 Frame.
ELEC- 107 Supply of 4 Modular Cover 1 Nos 1 No 84.00
1.3.2 Frame.
ELEC- 277 Supply of 6A / 10A 1 Way 1 7 Nos 1 No 86.00
1.9.1 Module Modular Switch.
ELEC- 247 Supply of 3 Plate Jumbo Ceiling 7 Nos 1 No 19.00
1.7.1 Rose.
ELEC- 149 Supply of 22/0.3mm (1.5 Sqmm) 100.00 Mtrs 100 Mtrs 1482.00
1.5.1 FRLS / HFFR PVC insulated
1100V grade as perIS:694/1990
specification for Copper cable.

Cost of Material for 7 Points


Cost of Material Rate per 1 Point

IIIT-HYD ELEC-Data 8 of 354


S.N
SSR No Description Qty Unit Rate
o
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Each

IIIT-HYD ELEC-Data 9 of 354


S.N
SSR No Description Qty Unit Rate
o
7 Wiring with run of 2 of 22/0.3mm (1.5 Sqmm) FRLS / HFFR PVC insulated flexible IS
copper cable Makes : Finolex/ RR Cable/ Havells/ Polycab/ HPL/ RPG/ Power flex / G
Million / Gold Medal in existing PVC conduit pipe including Supply and fixing of Jumb
Ceiling rose and 6A/10A ISI Mark 1way Modular switch with required modular box an
cover frame Makes : GM Four-Five / Legrand Arteor / Schneider Zen celo /Honeywell
Blenge Plus/ Cabtree Verna/ Million logus / Gold Medal Curve in existing Surface or
Concealed pipe wiring including cost and conveyance of all material and all labour ch
etc., complete for staircase light points in R.B.
1.5 times of normal (Total 626 Nos 1 No 1.50
Cost of Material + Labour
Charges) of Item number 4

Rate per Each

Common Socket
8 Supply and fixing of 6A/10A ISI Mark 3/2 pin Modular socket with 6A/10A 1way Modu
switch, 3 Module box with cover frame Makes : GM Four-Five / Legrand Arteor / Sch
Zen celo /Honeywell Blenge Plus/ Cabtree Verna/ Million logus / Gold Medal Curve o
Common switch board including cost and conveyance of all materials and all labour
charges etc., complete in N.R.B. / R.B.
a) Labour charges :
1 Skilled Electrician. 0.067 day 1 day 540.00
2 Helper (Electrical). 0.067 day 1 day 450.00
Labour for 1 Point
b) Material
ELEC- 100 Supply of 3 Module box. 1 No 1 No 76.00
1.3.1
ELEC- 106 Supply of 3 Modular Cover 1 No 1 No 72.00
1.3.2 Frame.
ELEC- 277 Supply of 6A / 10A 1 Way 1 1 No 1 No 86.00
1.9.1 Module Modular Switch.
ELEC- 280 Supply of 6A / 10A 3/2 Pin 2 1 No 1 No 132.00
1.9.1 Module Modular Socket with
shutter.
Cost of Material Rate per 1 Point

Total Cost of Material +


Labour Charges
Add Contractors Profit ###

Rate per Each

IIIT-HYD ELEC-Data 10 of 354


S.N
SSR No Description Qty Unit Rate
o
Separate Socket
9 Wiring with 3 of 22/0.3mm ( 1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copp
cable (ISI MARK) in existing pipe with 6A switch and 6A, 3/2 pin socket Modular typ
6A switch control and MS boxes with cover plate and GI switch box fixing on separa
board including all labour charges etc., complete.
Makes of wires : Finolex/ RR Cable/ Havells/ Polycab/ HPL/ RPG/ Power flex / GM /
Million / Gold Medal.
Makes of switches:-
a) Labour charges : GM Four-Five / Legrand Arteor / Schneider Zen celo /Honeywell
1 Blenge Plus/ Cabtree Verna/ Million 1.50
Skilled Electrician. logusday
/ Gold Medal
1 Curve.
day 540.00
2 Lineman Electric / Telephone 1.50 day 1 day 450.00
3 Helper (Electrical). 1.50 day 1 day 450.00
Labour for 15 Points
Labour for 1 Point
b) Material
ELEC- 100 Supply of 3 Module box. 15 Nos 1 No 76.00
1.3.1
ELEC- 106 Supply of 3 Modular Cover 15 No 1 No 72.00
1.3.2 Frame.
ELEC- 277 Supply of 6A / 10A 1 Way 1 15 No 1 No 86.00
1.9.1 Module Modular Switch.
ELEC- 280 Supply of 6A / 10A 3/2 Pin 2 15 No 1 No 132.00
1.9.1 Module Modular Socket with
shutter.
ELEC- 149 Supply of 22/0.3mm (1.5 Sqmm) 150.00 Mtrs 100 Mtrs 1482.00
1.5.1 FRLS / HFFR PVC insulated
1100V grade as perIS:694/1990
specification for Copper cable.

Cost of Material for 15 Points


Cost of Material Rate per 1 Point

Total Cost of Material +


Labour Charges
Add Contractors Profit ###

Rate per Each

6A Switches - 3 Nos & 6A Sockets - 3 Nos


10 Supply and fixing of 3 Nos 6A ISI mark Modular type switch with 3 Nos 6A 3/2 pin wa
socket on suitable size Modular box with required cover frame Makes : GM Four-Five
Legrand Arteor / Schneider Zen celo /Honeywell Blenge Plus/ Cabtree Verna/ Million
/ Gold Medal Curve including cost and coveyance of all material and all labour charge
complete for Computers in N.R.B. / R.B.
a) Labour charges :
1 Skilled Electrician. 0.20 day 1 day 540.00
2 Helper (Electrical). 0.13 day 1 day 450.00
Labour for 1 No
b) Material

IIIT-HYD ELEC-Data 11 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC- 103 Supply of 9 Module box 1 No 1 No 160.00
1.3.1
ELEC- 109 Supply of 9 Modular Cover 1 Nos 1 No 161.00
1.3.2
ELEC- Frame. of 6A / 10A 1 Way 1
277 Supply 3 Nos 1 No 86.00
1.9.1 Module Modular Switch.
ELEC- 280 Supply of 6A / 10A 3/2 Pin 2 3 Nos 1 No 132.00
1.9.1 Module Modular Socket with
shutter.
Cost of Material for 1 No
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Each

16 A Socket
11 Supply and fixing of ISI mark 16A 3pin / 6A 3 Pin Modular combi socket with 16 Amps
Modular switch fixed on suitable size Modular box with required cover frame Makes :
Four-Five / Legrand Arteor / Schneider Zen celo /Honeywell Blenge Plus/ Cabtree Ve
Million logus / Gold Medal Curve including with connections, cost and conveyance of
material and all labour charges etc., complete in N.R.B. / R.B.
a) Labour charges :
1 Skilled Electrician. 0.10 day 1 day 540.00
2 Lineman Electric / Telephone 0.10 day 1 day 450.00
3 Helper (Electrical). 0.10 day 1 day 450.00
Labour for 1 No
b) Material
ELEC- 100 Supply of 3 Module box. 1 No 1 No 76.00
1.3.1
ELEC- 106 Supply of 3 Modular Cover 1 No 1 No 72.00
1.3.2 Frame.
ELEC- 281 Supply of 16A / 20A 1 Way 1 1 No 1 No 118.00
1.9.1 Module Modular Switch.
ELEC- 284 Supply of 16A/6A 1 way Combi 1 No 1 No 184.00
1.9.1 Socket Modular Socket with
shutter.
Cost of Material for 1 No
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Each

Run of Mains
12 Supply and Run of 1 of 22/0.3mm (1.5 Sq.mm) FRLS / HFFR PVC insulated flexible
mark copper of Makes : Finolex/ RR Cable/ Havells/ Polycab/ HPL/ RPG/ Power flex
Million / Gold Medal cable in existing pipe for earth continuity inlcuding all labour char
etc., complete.
a) Labour charges :

IIIT-HYD ELEC-Data 12 of 354


S.N
SSR No Description Qty Unit Rate
o
1 Skilled Electrician. 0.34 day 1 day 540.00
2 Lineman Electric / Telephone 0.70 day 1 day 450.00
3 Helper (Electrical). 0.34 day 1 day 450.00
Labour for 100 Mtr
Labour for 1 Mtr
b) Material
ELEC- 149 Supply of 22/0.3mm (1.5 Sqmm) 100.00 Mtrs 100 Mtrs 1482.00
1.5.1 FRLS / HFFR PVC insulated
1100V grade as perIS:694/1990
specification for Copper
Cost of Material cable.
for 100 Metres
Cost of Material Rate per Mtr=
C/100
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

13 Supply and Run of 3 of 22/0.3mm (1.5 Sq.mm) FRLS / HFFR PVC insulated flexible
mark copper of Makes : Finolex/ RR Cable/ Havells/ Polycab/ HPL/ RPG/ Power flex
Million / Gold Medal cable in existing pipe for earth continuity inlcuding all labour char
etc., complete.
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 540.00
2 Lineman Electric / Telephone 2.50 day 1 day 450.00
3 Helper (Electrical). 1.00 day 1 day 450.00
Labour for 100 Mtr
Labour for 1 Mtr
b) Material
ELEC- 149 Supply of 22/0.3mm (1.5 Sqmm) 300.00 Mtrs 100 Mtrs 1095.00
1.5.1 FRLS / HFFR PVC insulated
1100V grade as perIS:694/1990
specification for Copper
Cost of Material cable.
for 100 Metres
Cost of Material Rate per Mtr=
C/100
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

IIIT-HYD ELEC-Data 13 of 354


S.N
SSR No Description Qty Unit Rate
o
14 Supply and Run of 3 of 36/0.3mm (2.50 Sq.mm) FRLS / HFFR PVC insulated flexible
mark copper cable of Makes : Finolex/ RR Cable/ Havells/ Polycab/ HPL/ RPG/ Powe
GM / Million / Gold Medal in existing pipe for run of mains inlcuding all labour charge
complete.
Makes of wires : Finolex/ RR Kabel/ Havells/ Polycab / HPL / RPG / Anchor / GM /
/ Gold Medal / Power Flex.
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 540.00
2 Lineman Electric / Telephone 2.50 day 1 day 450.00
3 Helper (Electrical). 1.00 day 1 day 450.00
Labour for 100 Mtr
Labour for 1 Mtr
b) Material
ELEC- 150 Supply of 36/0.3mm (2.5 Sqmm) 300.00 Mtrs 100 Mtrs 2391.00
1.5.1 FRLS / HFFR PVC insulated
1100V grade as perIS:694/1990
specification for Copper cable.

Cost of Material for 100 Metres

Cost of Material Rate per Mtr=


C/100
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

15 Supply and Run of 3 of 56/0.3mm (4.00 Sq.mm) FRLS / HFFR PVC insulated flexible
mark copper cable of Makes : Finolex/ RR Cable/ Havells/ Polycab/ HPL/ RPG/ Powe
GM / Million / Gold Medal in existing pipe for run of mains inlcuding all labour charge
complete.
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 540.00
2 Lineman Electric / Telephone 3.00 day 1 day 450.00
3 Helper (Electrical). 1.00 day 1 day 450.00
Labour for 100 Mtr
Labour for 1 Mtr
b) Material
ELEC- 151 Supply of 56/0.3mm (4.0 Sqmm) 300.00 Mtrs 100 Mtrs 3650.00
1.5.1 FRLS / HFFR PVC insulated
1100V grade as perIS:694/1990
specification for Copper cable.

Cost of Material for 100 Metres

Cost of Material Rate per Mtr=


C/100

IIIT-HYD ELEC-Data 14 of 354


S.N
SSR No Description Qty Unit Rate
o
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

IIIT-HYD ELEC-Data 15 of 354


S.N
SSR No Description Qty Unit Rate
o
16 Supply and Run of 3 of 84/0.3mm (6.00 Sq.mm) FRLS / HFFR PVC insulated flexible
mark copper cable of Makes : Finolex/ RR Cable/ Havells/ HPL/ RPG/ Power flex / G
Million / Gold Medal in existing pipe for run of mains inlcuding all labour charges etc.,
complete.

a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 540.00
2 Lineman Electric / Telephone 3.00 day 1 day 450.00
3 Helper (Electrical). 1.00 day 1 day 450.00
Labour for 100 Mtr
Labour for 1 Mtr
b) Material
ELEC- 152 Supply of 84/0.3mm (64.0 300.00 Mtrs 100 Mtrs 5549.00
1.5.1 Sqmm) FRLS / HFFR PVC
insulated 1100V grade as
perIS:694/1990 specification for
Copper cable.
Cost of Material for 100 Metres

Cost of Material Rate per Mtr=


C/100
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

17 Supply and Run of 5 of 84/0.3mm (6.0 Sq.mm) FRLS / HFFR PVC insulated flexible
mark copper cable of Makes : Finolex/ RR Cable/ Havells/ Polycab/ HPL/ RPG/ Powe
GM / Million / Gold Medal in existing pipe for run of mains inlcuding all labour charge
complete.
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 540.00
2 Lineman Electric / Telephone 5.50 day 1 day 450.00
3 Helper (Electrical). 2.00 day 1 day 450.00
Labour for 100 Mtr
Labour for 1 Mtr
b) Material
ELEC- 152 Supply of 84/0.3mm (6.0 Sqmm) 500.00 Mtrs 100 Mtrs 5549.00
1.5.1 FRLS / HFFR PVC insulated
1100V grade as perIS:694/1990
specification for Copper cable.

Cost of Material for 100 Metres

Cost of Material Rate per Mtr=


C/100

IIIT-HYD ELEC-Data 16 of 354


S.N
SSR No Description Qty Unit Rate
o
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

IIIT-HYD ELEC-Data 17 of 354


S.N
SSR No Description Qty Unit Rate
o
18 Supply and Run of 5 of 140/0.3mm (10.0 Sq.mm) FRLS / HFFR PVC insulated flexib
mark copper cable of Makes : Finolex/ RR Cable/ Havells/ Polycab/ HPL/ RPG/ Powe
GM / Million / Gold Medal in existing pipe for run of mains inlcuding all labour charge
complete.
a) Labour charges :
1 Skilled Electrician. 2.34 day 1 day 540.00
2 Lineman Electric / Telephone 6.50 day 1 day 450.00
3 Helper (Electrical). 2.34 day 1 day 450.00
Labour for 100 Mtr
Labour for 1 Mtr
b) Material
ELEC- 153 Supply of 140/0.3mm (10.0 500.00 Mtrs 100 Mtrs 8597.00
1.5.1 Sqmm) PVC FRLS / HFFR
insulated flexible Copper cable.

Cost of Material for 100 Metres

Cost of Material Rate per Mtr=


C/100
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

Distribution Boards
19 Supply and fixing of DP Metal Enclosure with IP 20 Protection DB Make Makes : Legr
Schneider/ Siemens / GE / ABB / GM / Havells / HPL / Hager / Indo Asian (Gold Plus
C&S / L&T with 1 No 20A - 32 A, 10 KA DP MCB Make: Legrand-DX3 / Schneider-Ac
including internal connection and labour charges for Flush Mounting etc., complete.
LABOUR
1 Skilled Electrician. 0.25 day 1 day 540.00
2 Lineman Electric / Telephone 0.25 day 1 day 450.00
4 Mason Cl- I / Brick layer Cl- I 0.15 day 1 day 470.00
COST OF LABOUR FOR
FULSH MOUNTING
MATERIAL
ELEC- 556 Supply of DP/TP/FP Metal 1 Nos 1 No 330.00
2.16.13 Enclosure with IP 20 Protection.
ELEC-2.13460 Supply of 6-32A 10KA DP MCB, 1 Nos 1 No 567.00
C/D Curve ISI Mark.
ELEC- ### Cement. 5.00 Kg 1 Kg 8.00
9.4.11 COST OF MATERIAL FOR
FULSH MOUNTING
TOTAL COST OF MATERIAL + 1255.00
LABOUR FOR FULSH
MOUNTING
Add Contractors Profit ### 170.87
1425.87

IIIT-HYD ELEC-Data 18 of 354


S.N
SSR No Description Qty Unit Rate
o
Hence Rate allowed 1426.00

IIIT-HYD ELEC-Data 19 of 354


S.N
SSR No Description Qty Unit Rate
o
8 Way SPNDB
20 Supply and fixing of 8 Way SPN DB with IP 43 Protection as per IS:13032 and suitab
8Nos S.P out goings and for 1 No DP Incommer, concealing in wall etc complete.
Makes : Legrand / Shneider.
LABOUR
1 Skilled Electrician. 0.50 day 1 day 540.00
2 Lineman Electric / Telephone 0.50 day 1 day 450.00
4 Mason Cl- I / Brick layer Cl- I 0.50 day 1 day 470.00

MATERIAL
2.15.1 507 Supply of 8 Way SPN DB 1 Nos 1 No 1298.00
ELEC- 1 No 1 No 917.00
461 Supply of 40A DP Isolator .
2.13.1
ELEC- Supply of 20A 10KA SP MCB, 6 Nos 1 No 193.00
458
2.13.1 C/D Curve ISI Mark.
ELEC- 12.50 Kg 1 Kg 8.00
### Cement.
9.4.11

TOTAL COST OF MATERIAL + FLUSH


LABOUR FOR FLUSH
MOUNTING
Add Contractors Profit ###

Rate per Each

21 Supply and fixing of 4 Way TPN DB Horizontal with IP 43 Protection as per IS:13032
: Legrand / Shneider and Supply and Fixing of 1 No., of 40A FP Isolator as incomer a
Nos 6-32 A 10kA SP MCBs Makes : Legrand-DX3 / Schneider-Acti9 as out goings
including internal connections and labour charges for FLUSH Mounting etc., complete
Lighting DBs)
MATERIAL
ELEC- 523 Supply of 4 Way TPN DB 1 Nos 1 No 2598.00
2.16.1 Horizontal with IP 243 Protection
as per IS:13032 and suitable for
12 Nos S.P. out goings and for 1
No 4 pole Incommer etc
complete.
ELEC-
487 Supply of 40A FP Isolator . 1 No 1 No 776.00
2.14.1
ELEC- Supply of 6-32A 10KA SP MCB,
458 12 Nos 1 No 193.00
2.13.1
ELEC- C/D Curve ISI Mark.
### Cement. 12.50 Kg 1 Kg 8.00
9.4.11
LABOUR
1 Skilled Electrician. 0.70 day 1 day 540.00
2 Lineman Electric / Telephone 1.00 day 1 day 450.00
3 Helper (Electrical). 1.00 day 1 day 450.00
4 Mason Cl- I / Brick layer Cl- I 0.50 day 1 day 470.00

IIIT-HYD ELEC-Data 20 of 354


S.N
SSR No Description Qty Unit Rate
o
TOTAL COST OF MATERIAL + FLUSH
LABOUR FOR FLUSH
MOUNTING
Add Contractors Profit ###

Rate per Each

IIIT-HYD ELEC-Data 21 of 354


S.N
SSR No Description Qty Unit Rate
o
22 Supply and fixing of 4 Way TPN DB Horizontal with IP 43 Protection as per IS:13032
: Legrand / Shneider and Supply and Fixing of 1 No., of 63A FP Isolator as incomer a
Nos 6-32 A 10kA SP MCBs Makes : Legrand-DX3 / Schneider-Acti9 as out goings
including internal connections and labour charges for FLUSH Mounting etc., complete
DBs.
LABOUR
1 Skilled Electrician. 0.70 day 1 day 540.00
2 Lineman Electric / Telephone 1.00 day 1 day 450.00
3 Helper (Electrical). 1.00 day 1 day 450.00
4 Mason Cl- I / Brick layer Cl- I 0.50 day 1 day 470.00

MATERIAL
ELEC- 523 Supply of 4 Way TPN DB 1 Nos 1 No 2598.00
2.16.1 Horizontal with IP 243 Protection
as per IS:13032 and suitable for
12 Nos S.P. out goings and for 1
No 4 pole Incommer etc
complete.

ELEC- Supply of 63A FP Isolator . 1 No 1 No 563.00


2.14.1 486
ELEC- Supply of 6-32A 10KA SP MCB, 12 Nos 1 No 193.00
2.13.1 458 C/D Curve ISI Mark.
ELEC- Cement. 12.50 Kg 1 Kg 8.00
9.4.11 ###

TOTAL COST OF MATERIAL + FLUSH


LABOUR FOR FLUSH
MOUNTING
Add Contractors Profit ###

Rate per Each

8 Way VTPN DB
23 Supply and fixing of 8 Way VTPN DB with IP 43 Protection as per IS:13032 Makes :
Legrand / Shneider and Supply and Fixing of 1 No., of 125A TPN MCCB, Adjustable,
Confirms to IS/IEC 60947-2 having Breaking Capacity 25 KA with thermal magnetic re
Panel Mounted Makes : L&T / Schneider / Siemens / Legrand / Hager as incomer wit
Nos of 63A, 10KA, TP MCBs C Curve ISI Mark Makes : Legrand-DX3 / Schneider-Ac
Out goings including internal connections and labour charges for FLUSH Mounting e
LABOUR
complete.
1 Skilled Electrician. 1.25 day 1 day 540.00
2 Lineman Electric / Telephone 1.50 day 1 day 450.00
3 Helper (Electrical). 1.50 day 1 day 450.00
COST OF LABOUR FOR
SURFACE MOUNTING
MATERIAL
ELEC- 527 Supply of 8 Way VTPN DB 1 Nos 1 No 8103.00
2.16.2

IIIT-HYD ELEC-Data 22 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC- 463 Supply of 40-63A 10KA TP 8 Nos 1 No 1407.00
2.13.1 MCB,
ELEC- 373 Supply of 125A TPN MCCB,
2.8.1
Makes : L&T / Schneider / 1 Nos 1 No 8526.00
Siemens / Legrand / Hager /
ABB.
COST OF MATERIAL FOR
SURFACE MOUNTING
TOTAL COST OF MATERIAL + SURFACE 29910.00
LABOUR FOR SURFACE
MOUNTING
Add Contractors Profit ### 4072.25
33982.25
Rate per Each 33982.00

24 AR Supply and fixing of cable 1 No 1 No 600.00


adopteres box with cover for
DBs including, massanory work
etc., complete.,
Makes : Legrand / Schneider.

Approved in Vemulawada
BOQ
Earthings
25 Providing independent earthing by exacavating a pit to a depth of 2.25Mtr in all soils a
size specified in the data for Important equipment with 2.5Mtr length 40mm dia 'B' cla
pipe and 18" dia 3" thick hume pipe ring with R.C.C. Slab cover duly providing stagge
holes filling with 20Kg Salt and 40Kg Charcoal or 40Kg bentonite powder from the bo
the pipe giving earth connection from electrode through G.I strip of 25 x 6mm x 200m
length to be bolted with nut bolts including supply and termination of No.8 G.I.wire fro
bottm of the pipe with all accessories and labour charges complete, as per IS specific
732/1982 (Part II)
b) labour charges for fixing pipe

1 Skilled Electrician. 1.00 No 1 No 540.00


Sub Total
a) Material
ELEC- 1479 40mm Nominal Bore Medium 2.50 Mtr 1 Mtr 350.00
9.4.15 grade G.I.Pipe.
ELEC- ### G.I. Strip / Plate / Wire (per K. 0.24 Kgs 1 Kg 65.00
9.3.6 G).
ELEC- ### G.I. Strip / Plate / Wire (per K. 0.83 Kgs 1 kg 65.00
9.3.6 G).
ELEC- ### Drilling of through holes of 16.00 Nos 1 No 6.00
9.4.18 12mm dia to G.I pipe.

IIIT-HYD ELEC-Data 23 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC- ### G.I Nuts, Bolts an Washers each 4.00 Sets 1 Set 12.00
9.4.19 set.
ELEC- ### 18" dia 3" hume pipe ring. 1.00 No 1 No 300.00
9.4.21
ELEC- ### Hard Coke. 40.00 Kg 1 Kg 20.00
9.1.10
ELEC- ### Salt. 20.00 Kg 1 Kg 15.00
9.1.11
ELEC- ### Earth work excacvation 1.27 cum 1 cum 250.00
9.4.17 including all soils for trench,
Pole Pit and Earth Pit. of Hard
ELEC- ### gravel
Earth Soil work
with smallexcacvation
boulder for 1.87 cum 1 cum 250.00
9.4.17 trench
including all soils for1.2trench,
1st step of size x 0.6
xPole
0.9 m
Pit(4'x2'x3')
and Earth Pit. of Hard
disteggrated
25% extra for rocks and trench
narrow boulders& 25% 785.00
for
pit trench
and back2nd Step
filling ofwith
sizeSand,
0.9 x
0.6
Coke,x 1.2
Saltmetc.,
(CivilandSSR) (3'x2'x4')
leveling
Sundries such as Lugs and
Saddles
Rate per each
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Each

26 Providing independent earthing by exacavating a pit to a depth of 2.25Mtr in all soils a


size specified in the data for Sophisticated Electronic equipment with 600mm x 600m
3.15mm thick copper plate rigidly fixed to 40mm dia 'B' Class G.I Pipe of 2.5Mtr length
per National Electric Code and earth connection from electrode Copper strip of 25mm
5mm x 200mm length to be bolted with nut bolts to G.I.pipe including 25mm x 3mm c
strip of 6Mtrs length connected from plate to Copper strip including filling with 20Kg S
40Kg Charcoal or 40Kg bentonite powder and providing 18" dia 18" height 3" thick hu
pipe ring covered with R.C.C. Slab including all accessories and labour charges etc
b) labour charges
complete as per ISfor fixing pipe 732/1982 (Part II).
specification

1 Skilled Electrician. 1.00 No 1 No 540.00


Sub Total
a) Material
ELEC- 1479 40mm Nominal Bore Medium 2.50 Mtr 1 Mtr 350.00
9.4.15 grade G.I.Pipe.
ELEC- ### 600mm x600mm x 3.15mm thick 10.00 kg 1 kg 590.00
9.3.1 copper plate (Per K.G).
ELEC- ### 25mm x 3mm x 6Mtrs Length 3.98 Kgs 1 Kg 65.00
9.3.6 Copper Strip (Per K.G).
ELEC- ### Copper plate / Copper strip (Per 0.22 Kgs 1 Kg 590.00
9.3.1 K.G).
ELEC- ### Drilling of through holes of 16.00 Nos 1 No 6.00
9.4.18 12mm dia to G.I pipe.

IIIT-HYD ELEC-Data 24 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC- ### G.I Nuts, Bolts an Washers each 4.00 Set 1 Set 12.00
9.4.19 set.
ELEC- ### Hard Coke. 40.00 kg 1 kg 20.00
9.4.21
ELEC- ### Salt. 20.00 kg 1 kg 15.00
9.1.10
ELEC- ### 18" dia 3" hume pipe ring. 1.00 No 1 No 300.00
9.1.11
ELEC- ### Earth work excacvation 1.27 cum 1 cum 250.00
9.4.17 including all soils for trench,
Pole Pit and Earth Pit. of Hard
ELEC- gravel Soil work
### Earth with smallexcacvation
boulder for 1.87 cum 1 cum 250.00
9.4.17 trench
including all soils for1.2trench,
1st step of size x 0.6
x 0.9 m
Pole Pit(4'x2'x3')
and Earth Pit of Hard
gravel Soil work
Earth with smallexcacvation
boulder for 25% 785.00
trench
including all soils for1.2trench,
1st step of size x 0.6
xPole
0.9 m (4'x2'x3')
Pit and Earth Pit of Hard
disteggrated rocks and boulders
for trench 2nd
Sundries suchStepas ofLugs
size 0.9
andx
0.6 x
Saddles1.2 m (Civil SSR) (3'x2'x4')
Rate per each
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Each

IIIT-HYD ELEC-Data 25 of 354


S.N
SSR No Description Qty Unit Rate
o
27 Supply and Run of 25mm x 6mm G.I Strip including cost of all accessories and labou
charges etc., complete. (1.18Kgs/1Mtr)
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 540.00
3 Helper (Electrical). 1.00 day 1 day 450.00
Labour for 100 Mtrs
Labour for 1 Mtr
b) Material
ELEC- ### G.I. Strip / Plate / Wire (per K.
9.3.6 G). 118.00 Kgs 1 Kg 65.00
Sundries.
Cost of Material for 100 Metres

Cost of Material Rate per Mtr=


C/100
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

28 Supply and Run of 50mm x 6mm G.I Strip including cost of all accessories and labou
charges etc., complete. (2.36 Kg / Mtr)
a) Labour charges :
1 Skilled Electrician. 2.00 day 1 day 540.00
3 Helper (Electrical). 2.00 day 1 day 450.00
Labour for 100 Mtrs
Labour for 1 Mtr
b) Material
ELEC- ### G.I. Strip / Plate / Wire (per K.
9.3.6 G). 236.00 Kgs 1 Kg 65.00
Sundries.
Cost of Material for 100 Metres

Cost of Material Rate per Mtr=


C/100
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

29 Supply and Run of 25mm x 3mm copper strip (Cuurrent Carrying Capacity 270A) inc
cost of all accessories and labour charges etc., complete. (0.663Kgs/1Mtr)
a) Labour charges :
1 Skilled Electrician. 1.00 day 1 day 540.00
3 Helper (Electrical). 1.50 day 1 day 450.00

IIIT-HYD ELEC-Data 26 of 354


S.N
SSR No Description Qty Unit Rate
o
Labour for 100 Mtrs
Labour for 1 Mtr
b) Material
ELEC- Copper plate / Copper strip (Per
### K.G). 66.30 Kgs 1 Kg 590.00
9.3.1
Sundries.
Cost of Material for 100 Metres

Cost of Material Rate per Mtr=


C/100
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

IIIT-HYD ELEC-Data 27 of 354


S.N
SSR No Description Qty Unit Rate
o
30 Supply and Run of No.8 SWG G.I wire including cost of all accessories and labour ch
etc., complete. (0.104Kgs/1Mtr)
a) Labour charges :
3 Helper (Electrical). 2.00 day 1 day 450.00
Labour for 100 Mtrs
Labour for 1 Mtr
b) Material
ELEC- ### G.I. Strip / Plate / Wire (per K.
9.3.6 G). 10.40 Kgs 1 Kg 65.00

ELEC- U Nails.
### 150.00 Nos 100 Nos 30.00
9.1.4
Sundries.
Cost of Material for 100 Metres

Cost of Material Rate per Mtr=


C/100
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

FIXTURES
31 Supply, transportation and fixing of 20W, 2000 lumens, T8,1200mm length LED
light (Industrial Application) input voltage AC 220 - 260Volts with PF≥0.9, Surge
protection: 2KV,THD<10%, with inbuilt driver and frosted cover CCT: 3000K - 5
minimum CRI≥80,.etc., complete Manufacture has to submit LM79,LM80 & Photobio
Safety Report. Luminaire Performance Complies to IS10322 (Part 5/Sec 3) & IEC 605
1,IEC 60529 ISO certified company.
MAKE: Phillips / OSRAM / GE / Crompton / VIN / Bajaj / Havells / HPL/Surya/Syska.
a) Labour charges
1 Skilled Electrician. 0.10 day 1 day 540.00
2 Lineman Electric / Telephone 0.10 day 1 day 450.00
Labour for 1 No
b) Material
ELEC- 169 Supply of 23 / 0060 twin core
1.5.4 twisted / flat heavy Copper wire.

Makes : Finolex / RR Kabel / 1.00 Mtr 100 Mtrs 953.00


Havells / Polycab / GM /
Million / V- Guard / Gold
Medal / Kundancab / HPL / RPG
/ Nandicab / Nakoda / Payal /
Finecab / Gemini / Vimal /
Suncab

ELEC- Supply of No.8 Screws of 2 Nos 100 Nos 101.00


145 35/38mm.
1.4.4

IIIT-HYD ELEC-Data 28 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC- ### Rawl Plugs. 2.00 Nos 100 Nos 31.00
9.1.2
Fixing arrangements on wall 2 Nos 1 Nos 5.00
with required support on wall
Cost of Material for fixing
luminaire
ELEC- 689 20W, 1800 lumens, 1 Nos 1 Nos 922.00
3.9.10 T8,1200mm length LED tube
light
Cost of Material
Total Cost of Material + 1043.00
Labour Charges
Add Contractors Profit ### 142.00
1185.00
Rate per Each 1185.00

IIIT-HYD ELEC-Data 29 of 354


S.N
SSR No Description Qty Unit Rate
o
36W, 2' x2' (600mm x 600mm) Recessed / Surface mounted LED luminaire
32 Supply and Transportation of 36W, 2' x2' (600mm x 600mm) slim panel LED luminair
Square Housing Made of Aluminum alloy with corrosion resistant powder coat, with
diffuser, Constant current out put of Driver operating voltage range of 150 to 265 Volt
Power factor ≥ 0.9 high power LEDs having efficacy of ≥ 100 lumens/watt, junction
temperature less than 85 degrees centigrade and THD is less than 12% etc.,
complete. MAKE: Phillips / OSRAM / GE / Crompton / VIN / Bajaj / Havells / HPL/ Sur
a) Labour charges
Syska.
1 Skilled Electrician. 0.050 day 1 day 540.00
3 Helper (Electrical). 0.125 day 1 day 450.00
Labour for 1 No
b) Material
ELEC- 169 Supply of 23 / 0060 twin core 2.00 Mtr 100 Mtrs 953.00
1.5.4 twisted / flat heavy Copper wire.

Alluminium Flat (As per


requirement)
Cost of Material for fixing
luminaire
ELEC- 693 Supply and Transportation of 1 Nos 1 Nos 4259.00
3.9.14 36W , 2' x 2' (600mm x 600mm)
slim panel LED luminaire

Cost of Material
Total Cost of Material + 4411.00
Labour Charges
Add Contractors Profit ### 600.56
5011.56
Rate per Each 5012.00
12W Down lighter Recessed / Surface Mounting
33 Supply and Transportation of 12W Down lighter with system lumens of 1000lm, suit
for Recessed / Surface mounting made of pressure die cast aluminum body with
powder coating, acrylic diffuser with Driver, operating voltage range of 150 to 265 Vol
P.F ≥ 0.9, Surge protection: 2KV, THD<15%, with high power LED's having efficacy o
100 lumens/watt,CCT: 3000K - 5700K, minimum CRI≥70,.etc., complete with 3
warranty.
a) Labour charges
MAKE: Phillips / OSRAM / GE / Crompton / VIN / Bajaj / Havells / Halonix /
1 Skilled Electrician.
HPL/Surya/Syska. 0.066 day 1 day 540.00
2 Lineman Electric / Telephone 0.000 day 1 day 450.00
3 Helper (Electrical). 0.100 day 1 day 450.00
Labour for 1 No
b) Material
ELEC- 169 Supply of 23 / 0060 twin core 1.00 Mtr 100 Mtrs 953.00
1.5.4 twisted / flat heavy Copper wire.

ELEC- 145 Supply of No.8 Screws of 2 Nos 100 Nos 101.00


1.4.4 35/38mm.
ELEC- ### Rawl Plugs. 2.00 Nos 100 Nos 31.00
9.1.2

IIIT-HYD ELEC-Data 30 of 354


S.N
SSR No Description Qty Unit Rate
o
Fixing arrangements on wall 0 Nos 1 Nos 5.00
with required support on wall
ELEC- 681 12W Down lighter with system 1 Nos 1 Nos 933.00
3.9.6 lumens of 1000lm, suitable for
Recessed / Surface

Cost of Material
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Each

18W Down lighter Recessed / Surface Mounting


34 Supply and Transportation of 18W Down lighter with system lumens of 1000lm, suit
for Recessed / Surface mounting made of pressure die cast aluminum body with
powder coating, acrylic diffuser with Driver, operating voltage range of 150 to 265 Vol
P.F ≥ 0.9, Surge protection: 2KV, THD<15%, with high power LED's having efficacy o
100 lumens/watt,CCT: 3000K - 5700K, minimum CRI≥70,.etc., complete with 3
warranty.
a) Labour charges
MAKE: Phillips / OSRAM / GE / Crompton / VIN / Bajaj / Havells / Halonix /
1 Skilled Electrician.
HPL/Surya/Syska. 0.066 day 1 day 540.00
2 Lineman Electric / Telephone 0.000 day 1 day 450.00
3 Helper (Electrical). 0.100 day 1 day 450.00
Labour for 1 No
b) Material
ELEC- 169 Supply of 23 / 0060 twin core 1.00 Mtr 100 Mtrs 953.00
1.5.4 twisted / flat heavy Copper wire.

ELEC- 145 Supply of No.8 Screws of 2 Nos 100 Nos 101.00


1.4.4 35/38mm.
ELEC- ### Rawl Plugs. 2.00 Nos 100 Nos 31.00
9.1.2
Fixing arrangements on wall 0 Nos 1 Nos 5.00
with required support on wall
ELEC- 682 18W Down lighter with system 1 Nos 1 Nos 1282.00
3.9.6 lumens of 1000lm, suitable for
Recessed / Surface

Cost of Material
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Each

IIIT-HYD ELEC-Data 31 of 354


S.N
SSR No Description Qty Unit Rate
o
BH/SBH
35 Supply and fixing of ISI mark batten holder / slanting holder Makes : Anchor / Gold Me
Olive / Million Zoom in lieu of ceiling rose of light point complete with all connections a
labour charges with 0.5W LED Lamp Make:Phillips / OSRAM / GE / Crompton / VIN
Bajaj / Havells /HPL/Surya.
a) Labour charges :
1 Skilled Electrician. 0.05 day 1 day 540.00
3 Helper (Electrical). 0.05 day 1 day 450.00
Labour for 1 No
b) Material
ELEC- 248 Supply of BH / SBH ofMakes : 1 No 1 No 18.00
1.7.1 Anchor / Gold Medal Olive /
ELEC- 704 Million
Supply Zoom.
of 0.5 W LED Lamp 1 No 1 No 57.00
3.10.1
ELEC- 703 Less Cost of 3 Plate Jumbo 1 No -1 No 19.00
3.10.1 Ceiling Rose Makes : Anchor /
Gold Medal
Cost of Olive / Million Zoom.
Material
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Each 119.00


Ceiling Fans
36 ELEC- 931 Supply of 48" (1200mm) Sweep Each 1 1 Nos 1995.00
5.1.1 ISI mark Ceiling Fan as per IS
374 - 1979 and, with double ball
bearings but without
RegulatorMakes : Crompton
High speed/ Bajaj Regal star /
Havells Fusion / Orient Summer
Crown / Usha technix
decorative

Transportation 2%
Sub total
Add Contractors Profit ###

Rate per Each

37 ELEC- 934 Supply of 56" (1400mm) Sweep Each 1 1 Nos 1976.00


5.1.4 Ceiling Fan as per IS 374 - 1979
and, with double ball bearings
but without Regulator.Makes :
Crompton High speed/ Bajaj
Regal star / Havells Fusion /
s Transportation
Orient Summer Crown / Usha 2%
technix decorative Sub total
Add Contractors Profit ###

Rate per Each

IIIT-HYD ELEC-Data 32 of 354


S.N
SSR No Description Qty Unit Rate
o
38 Supply and fixing of Modular type Stepped electronic regulator Makes : GM Four-Fiv
Legrand Arteor / Schneider Zen celo /Honeywell Blenge Plus/ Cabtree Verna/ Million
/ Gold Medal Curve for sweep AC ceiling fans of 1200mm / 1400mm complete with
connections.
a) Labour charges
2 Lineman Electric / Telephone 0.05 Nos 1 Nos 450.00
Labour for 1 No
b) Material
ELEC- 290 stepped type Electronic 1 Nos 1 Nos 442.00
1.9.2 Regulator
Cost of Material for 1 No
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Each


39 Labour charges for fixing of ceiling fan and regulator including transportation and givin
connections with twin core wire etc., complete. Makes : Finolex / RR Kabel / Havells /
Polycab / GM / Million / V-Guard / Gold Medal / Kundancab / HPL / RPG

a) Labour charges
1 Skilled Electrician. 0.125 day 1 day 540.00
3 Helper (Electrical). 0.125 day 1 day 450.00
Labour for 1 No
b) Material
ELEC- 169 Supply of 23 / 0060 twin core 1.00 Mtrs 100 Mtrs 953.00
1.5.4 twisted / flat heavy Copper wire.

Cost of Material for fixing fan


Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Each

40 Supply and erecting 19/20mm steel tube down rod of one meter length with bolts & nu
duly painted with matching colour of fan complete
a) Labour charges
3 Helper (Electrical). 0.100 day 1 day 450.00
Labour for 1 No
b) Material
ELEC- ### 19/20mm steel tube down rod 1.00 Mtrs 1 Mtrs 83.00
9.1.21 with bolts & nuts for fan with
maching colour.
Cost of Material for fixing fan
Total Cost of Material + 128.00
Labour Charges

IIIT-HYD ELEC-Data 33 of 354


S.N
SSR No Description Qty Unit Rate
o
Less cost of fan down rod 0.23 Mtrs 1 Mtrs 80.00
supplied with new fan of about
9" in length equal to 0.23 Metre
at above rate

Add Contractors Profit ###


Rate per Each

IIIT-HYD ELEC-Data 34 of 354


S.N
SSR No Description Qty Unit Rate
o
41 ELEC- Supply,Transportation of light Each 1 1 Nos 1368.00
5.1.9 duty exhaust fan 12"(300 mm)
size 900 rpm with metal blades
wiremesh with all accessories
etc complete Makes :
Crompton / Bajaj Transportation
Bahar WG / 2%
Sub total
Havells Ventil Air-DB / Orient hill
air. Add Contractors Profit ###

Rate per Each


42 Supply,Transportation of 12" (300mm) ISI, 900 RPM Heavy duty exhaust fan with me
blades wiremesh with all accessories etc complete Makes : Crompton / Almounard
ELEC- Havells Turbo
Supply of Force. ISI, 900 Each
12" (300mm) 1 1 Nos 2829.00
5.1.10 RPM Heavy duty exhaust fan
Transportation 0.02

Add Contractors Profit ###

Rate per Each

43 Labour charges for fixing the Light duty exhaust fan in wall with necessary connection
masonary work of making hole, finishing etc., complete. Makes : Finolex / RR Kabel /
Havells / Polycab / GM / Million / V-Guard / Gold Medal / Kundancab / HPL / RPG
a) Labour charges
1 Skilled Electrician. 0.250 day 1 day 540.00
2 Lineman Electric / Telephone 0.250 day 1 day 450.00
4 Mason Cl- I / Brick layer Cl- I 0.250 day 1 day 470.00
Labour for 1 No
ELEC- 169 Supply of 23 / 0060 twin core 1.00 Mtrs 100 Mtrs 953.00
1.5.4 twisted / flat heavy Copper wire.

ELEC- ### Cement. 25 Kg 1 Kg 8.00


9.4.11
Sundries such as Sand, Bolt, 1 Job 1 Job 15.00
Nuts etc.
Cost of Material for fixing fan
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Each

44 Supply, Transportation and Fixing of Louver shutter suitable for 12" (300mm) Exhaus
of Best quality and makes as directed with fixing arrangments and all labour charges
a) Labour charges
complete.
1 Skilled Electrician. 0.050 day 1 day 540.00
2 Lineman Electric / Telephone 0.050 day 1 day 450.00
Labour for 1 No

IIIT-HYD ELEC-Data 35 of 354


S.N
SSR No Description Qty Unit Rate
o
3 Sundries such as Sand, Bolt, 1 Job 1 Job 15.00
Nuts etc.
Cost of Material for fixing fan
b) Material
Louver shutter suitable for 12" 1 No 1 No 210.00
(300mm) Exhaust fan (MR)
Cost of Material for 1 No
Total Cost of Material + 289.00
Labour Charges
Add Contractors Profit ### 39.35
328.35
Rate per Each 328.00

45 Supply and fixing of buzzer Makes : GM / Million / Gold Medal on 4"x4" decolam block
including giving connections, cost of all accessories and labour charges etc., complet
1 Skilled Electrician. 0.05 day 1 day 540.00
3 Helper (Electrical). 0.05 day 1 day 450.00
Labour for 1 No
b) Material
ELEC- 130 Supply of Decolam Board of Nos 1 No 14.00
1.4.2 Size 4" x 4".
Supply of Buzzer.
ELEC- 255 Makes : GM / Million / Gold 1 Nos 1 No 41.00
1.7.2 Medal / Anchor / Great white.
Cost of Material
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Hence Rate allowed 103.00


46 Supply and fixing of Calling Bell of Makes : GM / Million / Gold Medal on 4"x7" decola
block including giving connections, cost of all accessories and labour charges etc.,
complete.
a) Labour charges :
1 Skilled Electrician. 0.05 day 1 day 540.00
3 Helper (Electrical). 0.05 day 1 day 450.00
Labour for 1 No
b) Material
ELEC-1.4.131 Supply of Decolam Board of 1 Nos 1 No 25.00
Size 4" x 7".
Supply of Calling Bell.
ELEC-1.7.254 Makes : GM / Million / Gold 1 Nos 1 No 46.00
Medal / Anchor / Great white.
Cost of Material
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

IIIT-HYD ELEC-Data 36 of 354


S.N
SSR No Description Qty Unit Rate
o
Hence Rate allowed 137.00

47 Supply and fixing of Ding Dong Bell Makes : GM / Million / Gold Medal on 4"x7" decol
block including giving connections, cost of all accessories and labour charges etc.,
complete.
a) Labour charges :
1 Skilled Electrician. 0.05 day 1 day 540.00
3 Helper (Electrical). 0.05 day 1 day 450.00
Labour for 1 No
b) Material
ELEC-1.4.131 Supply of Decolam Board of 1 Nos 1 No 25.00
Size 4" x 7".
ELEC-1.7.256 Supply of Ding Dong Bell.
Makes : GM / Million / Gold 1 Nos 1 No 93.00
Medal / Anchor / Great white.
Cost of Material
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Hence Rate allowed 190.00

48 Supply and fixing of Electronic Musical bell Makes : GM / Million / Gold Medal on 4"x7
decolam block including giving connections, cost of all accessories and labour charge
complete.
a) Labour charges :
1 Skilled Electrician. 0.05 day 1 day 540.00
3 Helper (Electrical). 0.06 day 1 day 450.00
Labour for 1 No
b) Material
ELEC-1.4.131 Supply of Decolam Board of 1 Nos 1 No 25.00
Size 4" x 7"
Supply of Electronic Musical
Bell.
ELEC- 257 Makes : GM / Million / Gold 1 Nos 1 No 218.00
1.7.2 Medal / Anchor / Great white.
Cost of Material
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Hence Rate allowed 335.00

IIIT-HYD ELEC-Data 37 of 354


S.N
SSR No Description Qty Unit Rate
o
49 Supply and fixing of Modular telephone Jack with connector on modular box with cove
frame Makes : GM Four-Five / Legrand Arteor / Schneider Zen celo /Honeywell Bleng
Plus/ Cabtree Verna/ Million logus / Gold Medal Curve in existing consealed pipe w
including cost and coveyance of all material and all labour charges etc., complete in
a) Labour charges :
N.R.B. / R.B.
2 Lineman Electric / Telephone 0.06 day 1 day 450.00
Labour for 1 No
b) Material
1.3.1 Supply of 1 or 2 Module box. 1.00 Nos 1 No 57.00
1.9.17 Supply of 1 or 2 Modular Cover
Frame
Makes : Legrand Myrius / 1.00 Nos 1 No 56.00
Cabtree Verona / Million / Logus
/ Gold Medal Curve / Anchor
Roma viola / CPL / Great White /
Vimal.
ELEC- 291 Supply of Modular socket type
1.9.1 Telephone jack with Connector.

Makes : Legrand Myrius / 1.00 Nos 1 No 93.00


Cabtree Verona / Million / Logus
/ Gold Medal Curve / Anchor
Roma viola / CPL / Great White /
Vimal.
Cost of Material
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Hence Rate allowed 261.00

50 Supply, Transportation and Run of 1 of 2 Pair, 0.5mm telephone copper wire Makes
Finolex / Delton / Surabi / Polycab in the existing cable tray/ conduit pipe and labour
b) Labouretc.,
charges charges
complete.
1 Skilled Electrician. 0.50 day 1 day 540.00
2 Lineman Electric / Telephone 1.00 day 1 day 450.00
3 Helper (Electrical). 0.50 day 1 day 450.00
Labour for 100 Mtrs
Labour for 1 Mtr
a) Material
Supply of 2 Pair, 0.5mm
telephone copper
ELEC- ### Makes : Finolex / Delton / Surabi 100.00 Mtrs 100 Mtrs 910.00
8.1.1 / Polycab
Cost of Material for 100 Mtrs
Cost of Material for 1 Mtrs
Total Cost of Material + 18.50
Labour Charges

IIIT-HYD ELEC-Data 38 of 354


S.N
SSR No Description Qty Unit Rate
o
Add Contractors Profit ### 2.52
21.02
Hence Rate allowed 22.00
51 Supply, Transportation and Run of 5 Pair telephone copper wire Makes : Finolex / De
Surabi / Polycab in the existing cable tray/ conduit pipe and labour charges etc., com
b) Labour charges
1 Skilled Electrician. 0.50 day 1 day 540.00
2 Lineman Electric / Telephone 1.00 day 1 day 450.00
3 Helper (Electrical). 0.50 day 1 day 450.00
Labour for 100 Mtrs
Labour for 1 Mtr
a) Material
ELEC- ### Supply of 5 Pair telephone
8.1.1 copper wire.ELEC-8.1.2
Makes : Finolex / Delton / Surabi 100.00 Mtrs 100 Mtrs 2540.00
/ Polycab
Cost of Material for 100 Mtrs
Cost of Material for 1 Mtrs
Total Cost of Material + 34.80
Labour Charges
Add Contractors Profit ### 4.74
39.54
Hence Rate allowed 40.00

52 Supply, Transportation and Run of 1 of 10 Pair, 0.5mm telephone copper wire Makes
Finolex / Delton / Surabi / Polycab in the existing cable tray/ conduit pipe and labour
charges
b) Labouretc., complete.
charges
1 Skilled Electrician. 0.50 day 1 day 540.00
2 Lineman Electric / Telephone 1.00 day 1 day 450.00
3 Helper (Electrical). 1.00 day 1 day 450.00
Labour for 100 Mtrs
Labour for 1 Mtr
a) Material
ELEC- ### Supply of 10 Pair telephone
8.1.1 Copper wire. (ELEC.-8.1.15)
Makes : Finolex / Delton / Surabi 1.00 Mtrs 1 Mtrs 36.00
/ Polycab.
Cost of Material for 1 Mtrs
Total Cost of Material + 47.70
Labour Charges
Add Contractors Profit ### 6.49
54.19
Hence Rate allowed 55.00
53 Supply, Transportation and Run of 1 of 20 Pair, 0.5mm telephone copper wire Makes
Finolex / Delton / Surabi / Polycab in the existing cable tray/ conduit pipe and labour
charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.70 day 1 day 540.00

IIIT-HYD ELEC-Data 39 of 354


S.N
SSR No Description Qty Unit Rate
o
2 Lineman Electric / Telephone 1.00 day 1 day 450.00
3 Helper (Electrical). 1.00 day 1 day 450.00
Labour for 100 Mtrs
Labour for 1 Mtr
a) Material
ELEC- ### Supply of 20 Pair telephone
8.1.1 Copper wire .(ELEC-8.1.16)
Makes : Finolex / Delton / Surabi 1.00 Mtrs 1 Mtrs 70.00
/ Polycab.
Cost of Material for 1 Mtrs
Total Cost of Material + 82.70
Labour Charges
Add Contractors Profit ### 11.26
93.96
Hence Rate allowed 94.00

54 Supply, Transportation and Run of 1 of 50 Pair, 0.5mm telephone copper wire Makes
Finolex / Delton / Surabi / Polycab in the existing cable tray/ conduit pipe and labour
charges
b) Labouretc., complete.
charges
1 Skilled Electrician. 1.00 day 1 day 540.00
2 Lineman Electric / Telephone 1.00 day 1 day 450.00
3 Helper (Electrical). 1.00 day 1 day 450.00
Labour for 100 Mtrs
Labour for 1 Mtr
a) Material
ELEC- ### Supply of 50 Pair telephone
8.1.1 Copper wire .(ELEC- 8.1.17)
5 Makes : Finolex / Delton / Surabi 1.00 Mtrs 1 Mtrs 175.00
/ Polycab.
Cost of Material for 1 Mtrs
Total Cost of Material + 189.40
Labour Charges
Add Contractors Profit ### 25.79
215.19
Hence Rate allowed 215.00

55 Supply, Transportation and Run of 1 of 100 Pair, 0.5mm telephone copper wire Make
Finolex / Delton / Surabi / Polycab in the existing cable tray/ conduit pipe and labour
charges
b) Labouretc., complete.
charges
1 Skilled Electrician. 1.20 day 1 day 540.00
2 Lineman Electric / Telephone 1.00 day 1 day 450.00
3 Helper (Electrical). 1.00 day 1 day 450.00
Labour for 100 Mtrs
Labour for 1 Mtr
a) Material

IIIT-HYD ELEC-Data 40 of 354


S.N
SSR No Description Qty Unit Rate
o
8.1.14 Supply of 100 Pair raiser cable 1.00 Mtrs 1 Mtrs 387.00
for telephone of Makes :
Finolex / Delton / Surabi /
Polycab.(ELEC-8.1.14)
Cost of Material for 1 Mtrs
Total Cost of Material + 402.40
Labour Charges
Add Contractors Profit ### 54.79
457.19
Hence Rate allowed 458.00

56 Supply, Transportation and Fixing of 10 pair MDF/ Telephone distribution box with ba
mount frame, krone connector, powder coated metal body of best quality and make a
directed with lock and key arrangement including all accessories and labour charges
complete.
b) Labour charges
1 Skilled Electrician. 0.10 day 1 day 540.00
2 Lineman Electric / Telephone 0.12 day 1 day 450.00
3 Helper (Electrical). day 1 day 450.00
Labour for 1 Mtr
a) Material
ELEC- ### Supply of 10 pair Telephone 1.00 Nos 1 Nos 580.00
8.1.2 distribution box with back mount
frame, krone connector, powder
coated metal body with lock and
key arrangement. (ELEC.-
8.1.18)

Cost of Material for 1 Mtrs


Total Cost of Material + 685.70
Labour Charges
Add Contractors Profit ### 93.36
779.06
Hence Rate allowed 780.00

IIIT-HYD ELEC-Data 41 of 354


S.N
SSR No Description Qty Unit Rate
o
57 Supply, Transportation and Fixing of 20 pair Telephone distribution box with back mo
frame, krone connector, powder coated metal body with lock and key arrangement in
all accessories
b) Labour and labour charges etc., complete.
charges
1 Skilled Electrician. 0.10 day 1 day 540.00
2 Lineman Electric / Telephone 0.12 day 1 day 450.00
Labour for 1 Mtr
a) Material
ELEC- ### Supply of 20 pair Telephone 1 Nos 1 Nos 880.00
8.1.2 distribution box with back mount
frame, krone connector, powder
coated metal body with lock and
key arrangement. (ELEC.-
8.1.19)

Cost of Material for 1 Mtrs


Total Cost of Material + 988.40
Labour Charges
Add Contractors Profit ### 134.57
1122.97
Hence Rate allowed 1123.00

58 Supply, Transportation and Fixing of 100 pair Telephone distribution box with back m
frame, krone connector, powder coated metal body with lock and key arrangement in
all accessories and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.150 day 1 day 540.00
2 Lineman Electric / Telephone 0.150 day 1 day 450.00
Labour for 1 Mtr
a) Material
ELEC- Supply of 100 pair MDF loaded
8.1.9 with 2/10 Modular. (ELEC.-
8.1.13)
Makes : Krone make or its 1 Nos 1 Nos 3680.00
equivalent.
sundries
Cost of Material for 1 Mtrs
Total Cost of Material + 3858.50
Labour Charges
Add Contractors Profit ### 525.33
4383.83
Hence Rate allowed 4384.00

59 Supply, Transportation and Fixing of 200 pair Telephone distribution box with back m
frame, krone connector, powder coated metal body with lock and key arrangement in
all accessories and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.300 day 1 day 540.00
2 Lineman Electric / Telephone 0.400 day 1 day 450.00
Labour for 1 Mtr

IIIT-HYD ELEC-Data 42 of 354


S.N
SSR No Description Qty Unit Rate
o
a) Material
ELEC- ### Supply of 200 pair Telephone 1 Nos 1 Nos 7000.00
8.1.2 distribution box with back mount
frame, krone connector, powder
coated metal body with lock and
key arrangement. (ELEC.-
8.1.21)

sundries
Cost of Material for 1 Mtrs
Total Cost of Material + 7365.00
Labour Charges
Add Contractors Profit ### 1002.74
8367.74
Hence Rate allowed 8368.00

IIIT-HYD ELEC-Data 43 of 354


S.N
SSR No Description Qty Unit Rate
o
60 Supply, Installation, Testing
and commissioning of IP
Based digtal Telephone
(EPABX) system complied with
following specifications:
> IP @ Core, PCM/TDM, Non
blocking,
> Must Support PRI, E1, Analog
Junctions
> Must Support PC Console,
> Must support Mobile SIP
(Android and Ios)
> Must support Voice Mail
> Must support Card based
GSM
> Inbuilt 8 Channel Auto
Attendant
> Inbuilt Call Details Software
> 8 Analog
with searchTrunks
engine software
> 8 Digital Extensions
>------------------------
> 96 Analog Extensions
>------------------------
ELEC-8.3.a 1 No 1 Each ###
> Expandable
>------------------------
to
> 6220 Ports
Digital wired or more at
Extensions
extra
> 1 costDigital Key Phone with
minimum 16 Keys (Must work
61 only
Supplyon 2installation
wires) testing and
>
commissioning ofto Push
Expandable 64 Analog
Button
Extensions or more
type Telephone Instruments of
Approved
makes: Brands: Panasonic:
NEC /
Alcatel / Karel
Mofel:TS500. / Unify

(as per Quotation from M/sRGP


Electronics India Pvt Ltd., 1 No 1 Each 500.00
Hyderabad-38 )
Excise Duty Including 0.00%

Add VAT 5.00%

Installation and commissioning c 5%


Transportation charges @ 2 % on 2%
TOTAL:
Rs.560.00/-

62 Supply installation testing and 1 Nos 1.00 Each 43219.00


commissioning of ISDN PRI
Card of makes: KAREL, Mofel:
EX 200(IS2/0)
(as per Quotation from M/sRGP
Electronics India Pvt Ltd., 1 No 1 Each 38588.00
Hyderabad-38 )
Excise Duty Including 0.00%

IIIT-HYD ELEC-Data 44 of 354


S.N
SSR No Description Qty Unit Rate
o

Add VAT 5.00%

Installation and commissioning c 5%


Transportation charges @ 2 % on 2%
TOTAL:
Or say Rs.
63 MR Supply, Transportation and 1 Rms 1.00 One 122.00
Fixing of 10 pair 0.5mm UG RM
Telephone copper cable in the
existing trench with connection
etc., complete.
64 MR Supply, Transportation and 1 Rms 1.00 One 403.00
Fixing of 50 pair 0.5mm UG RM
Telephone copper cable in the
existing trench with connection
etc., complete.
65 MR Supply, Transportation and 1 Rms 1.00 One 729.00
Fixing of 100 pair 0.5mm UG RM
Telephone copper cable in the
existing trench with connection
etc., complete.

IIIT-HYD ELEC-Data 45 of 354


S.N
SSR No Description Qty Unit Rate
o
66 Supply, Transportation and Fixing of Cat 6 RJ-45 information outlets Makes : D Link /
Molex / Legrand / Krone including duel face plate including all accessories and lab
b) Labour charges charges etc., complete.
1 Skilled Electrician. 0.067 day 1 day 540.00
2 Lineman Electric / Telephone 0.067 day 1 day 450.00
3 Helper (Electrical). 0.067 day 1 day 450.00
Labour for 1 Mtr
a) Material
ELEC- ### Supply of Cat 6 RJ-45
8.1.4 information outlets including
duel face plate.
Makes : D Link / AMP / Molex / 1 Nos 1 Nos 305.00
Legrand / Krone.
Cost of Material for 1 Mtrs
Total Cost of Material + 401.40
Labour Charges
Add Contractors Profit ### 54.65
456.05
Hence Rate allowed 457.00

67 Supply, Transportation and Run of 1 of LAN Cable cat - 6 UTP cable Makes : D Link
/ Molex / Legrand / Krone in the existing cable tray/ conduit pipe and labour charges
complete.
b) Labour charges
1 Skilled Electrician. 0.50 day 1 day 540.00
2 Lineman Electric / Telephone 1.00 day 1 day 450.00
3 Helper (Electrical). 0.75 day 1 day 450.00
Labour for 100 Mtrs
Labour for 1 Mtr
a) Material
ELEC- ### Supply of LAN Cable cat - 6
8.1.3 UTP cable.(ELEC.-8.1.3)
Makes : D Link / AMP / Molex / 100.00 Mtrs 100 Mtrs 2100.00
Legrand / Krone.
Cost of Material for 100 Mtrs
Cost of Material for 1 Mtrs
Total Cost of Material + 31.50
Labour Charges
Add Contractors Profit ### 4.29
35.79
Hence Rate allowed 36.00

68 Supply of 7 feet length moulded patch cord Makes : D Link / AMP / Molex / Legrand /
Krone.
Makes : D Link / AMP / Molex / 1 Nos 1 Nos 200.00
ELEC-8.1.### Legrand / Krone.

IIIT-HYD ELEC-Data 46 of 354


S.N
SSR No Description Qty Unit Rate
o
Cost of Material for 1
Total Cost of Material + 200.00
Labour Charges
Add Contractors Profit ### 27.23
229.23
Hence Rate allowed 230.00
69 Supply of 3 feet length moulded patch cord Makes : D Link / AMP / Molex / Legrand /
Krone. 1 Nos 1 Nos 180.00
ELEC- Cost of Material for 1
8.1.7 ###
Total Cost of Material + 180.00
Labour Charges
Add Contractors Profit ### 24.51
205.51
Hence Rate allowed 206.00

70 Supply, Transportation and Fixing of 24 Port manageble switches Makes : CISCO / N


Gear / HP / D link including all accessories and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.400 day 1 day 540.00
2 Lineman Electric / Telephone 0.307 day 1 day 450.00
Labour for 1 Mtr
a) Material
ELEC- ### Supply of 24 Port manageble
8.1.5 switches. (ELEC.-8.1.7)
Makes : CISCO / Net Gear / 1 Nos 1 Nos 6000.00
HP / D link.
Cost of Material for 1
Total Cost of Material + 6354.10
Labour Charges
Add Contractors Profit ### 865.11
7219.21
Hence Rate allowed 7220.00

IIIT-HYD ELEC-Data 47 of 354


S.N
SSR No Description Qty Unit Rate
o
71 Supply, Transportation and Fixing of 24 port patch panels Makes : D Link / AMP / Mo
Legrand / Krone including all accessories and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.300 day 1 day 540.00
2 Lineman Electric / Telephone 0.400 day 1 day 450.00
Labour for 1 Mtr
a) Material
ELEC- ### Supply of 24 port patch panels.
8.1.5
Makes : D Link / AMP / Molex / 1 Nos 1 Nos 6000.00
Legrand / Krone.
sundries
Cost of Material for 1 Mtrs
Total Cost of Material + Labour 6354.50
Charges
Add Contractors Profit ### 865.17
7219.67
Hence Rate allowed 7220.00

72 Supply, Transportation and Fixing of 19" 6U floor / Wall mounting net work rack Make
HCL / Vall with power spike including all accessories and labour charges etc., comple
b) Labour charges
1 Skilled Electrician. 0.30 day 1 day 540.00
2 Lineman Electric / Telephone 0.40 day 1 day 450.00
Labour for 1 Mtr
a) Material
ELEC- ### Supply of 6U floor / Wall
8.1.11 mounting net work rack with
power spike including all
accessories. (ELEC.-8.1.22)
Makes : HCL / Vall. 1 Nos 1 Nos 4200.00
Cost of Material for 1
Total Cost of Material + 4540.20
Labour Charges
Add Contractors Profit ### 618.15
5158.35
Hence Rate allowed 5159.00

73 Supply, Transportation and Fixing of 19" 12U floor / Wall mounting net work rack Mak
HCL / Vall with power spike including all accessories and labour charges etc., comple
b) Labour charges
1 Skilled Electrician. 0.30 day 1 day 540.00
2 Lineman Electric / Telephone 0.43 day 1 day 450.00

IIIT-HYD ELEC-Data 48 of 354


S.N
SSR No Description Qty Unit Rate
o
Labour for 1 Mtr
a) Material
ELEC- ### Supply of 12U floor / Wall
8.1.11 mounting net work rack with
power spike including all
accessories. (ELEC.-8.1.24)
Makes : HCL / Vall. 1 Nos 1 Nos 5800.00
Cost of Material for 1
Total Cost of Material + 6156.40
Labour Charges
Add Contractors Profit ### 838.19
6994.59
Hence Rate allowed 6995.00

IIIT-HYD ELEC-Data 49 of 354


S.N
SSR No Description Qty Unit Rate
o
74 Supply, Transportation and Fixing of 19" 42U floor / Wall mounting net work rack Mak
HCL / Vall with power spike including all accessories and labour charges etc., comple
b) Labour charges
1 Skilled Electrician. 0.400 day 1 day 540.00
2 Lineman Electric / Telephone 0.450 day 1 day 450.00
Labour for 1 Mtr
a) Material
ELEC- Supply of 42U floor / Wall
8.1.11 mounting net work rack with
power spike including all
accessories. (ELEC.-8.1.27)
Makes : HCL / Vall. 1 Nos 1 Nos 32000.00
Cost of Material for 1
Total Cost of Material + 32418.50
Labour Charges
Add Contractors Profit ### 4413.78
36832.28
Hence Rate allowed 36833.00

75 Certificate, Testing and


Documentation etc., of each
LAN Point complete.
(as per Quotation from M/sRGP
Electronics India Pvt Ltd., 1 No 1 Each 125.00
Hyderabad-38 )

76 Supply, Transportation and Run of 1 of RG6 Co-axial Cable Makes : Finolex / Delton
Surabi / Polycab for TVs in the existing cable tray/ conduit pipe and labour charges e
complete.
b) Labour charges
1 Skilled Electrician. 0.50 day 1 day 540.00
2 Lineman Electric / Telephone 1.00 day 1 day 450.00
3 Helper (Electrical). 1.00 day 1 day 450.00
Labour for 100 Mtrs
Labour for 1 Mtr
a) Material
Supply of RG6 Co-axial Cable
for TVs . (MR)
5 Makes : Finolex / Delton / Surabi 1.00 Mtrs 1 Mtrs 17.00
/ Polycab.
Cost of Material for 1 Mtrs
Total Cost of Material + 28.70
Labour Charges
Add Contractors Profit ### 3.91
32.61
Hence Rate allowed 33.00

IIIT-HYD ELEC-Data 50 of 354


S.N
SSR No Description Qty Unit Rate
o
Main Power panel
77 Supply installation testing and commissioning of 3 phase and neutral 415V free stand
floor mounted indoor LT panel made out of No.16/14 gauge CRCA sheet steel after
process and painting with powder coating. The panel shall consists of suitable rating
Alluminium busbar ( with rating of 0.8A/ Sqmm)supported with DMC /SMC barriers a
colour coaded with heat shrinkable sleeves, flexibiltioy to accept the up four out going
cables and necessary cable chamber . The panel shall have comprised of following s
gear . Including supply and fixing the same and painting with powder coating includin
internal connections cost and conveyance
Fabrication: L of all
H materials
D & labour charges.
Size of panel : in Mtr 4.00 2.18 1.00
Front and back faces 4.00 1.65 13.20
Top and bottom faces 4.00 1.00 12.00
Side faces 2.18 1.00 4.35
Vertical sheets 2.18 1.00 10.88
Horizontal sheets 0.70 0.60 4.62
Horizontal sheets 0.60 0.60 5.40
Sub total 50.45
Add extra 10 % for wastage 5.04
a Total 55.49
ELEC-7.12### Fabrication and erection of 14 / 55.49 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
ELEC-2.11428 Supply of 800A 4 Pole, 50kA Air 3 Nos 1 No ###
powder coating including cost
Circuit Breaker electrically
and conveyance of all materials
drawout Confirms to IS 13947-
and labour charges.(ELEC-
2, IEC 60947-2 and BS-EN
7.12.1)
60947 with Micro processer
based having over load, shot
circuit and earth fault protection
Elec.-2.8. 380 Supply
of Makes of 630A 3 Pole/ MCCB,
: Siemens L&T / 2 Nos 1 No 30620.00
Adjustable,
Schneider asConfirms
incomer to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic release Panel
Mounted.Makes : L&T /
Elec.-2.8. 378 Supply of 400A 3 Pole
Schneider / Siemens / Legrand.MCCB, 10 Nos 1 No 21257.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic release Panel
Mounted.Makes : L&T /
Elec.-2.8. 376 Supply of 250A 3 Pole
Schneider / Siemens / Legrand.MCCB, 5 Nos 1 No 15706.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic release Panel
Mounted.Makes : L&T /
Schneider / Siemens / Legrand.

IIIT-HYD ELEC-Data 51 of 354


S.N
SSR No Description Qty Unit Rate
o
Elec.-2.8. 372 Supply of 125A 3 Pole MCCB, 0 Nos 1 No 7051.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 25 KA with thermal
magnetic release Panel
Mounted.Makes : L&T /
Elec.-2.8. 370 Supply of 63A 3 Pole
Schneider / Siemens / Legrand. MCCB, 2 Nos 1 No 5939.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic release Panel
ELEC-7.13### Supply and
Mounted.Makes erection: of 0-415V
L&T / 2 No 1 No 2,000.00
volt Digital
Schneider meter / Legrand.
/ Siemens of size
96x96mm on exisiting box /
panel board including
connections etc., complete of
ELEC-7.13### Supply
CONZERVE and erection of 0-100 //
/ ELMEASURE 2 No 1 No 2,000.00
200 / 400 /
MECO / HPL MAKE. 600 /1000 - 5A CT
Digital Ammeter of size
96x96mm on existing box /
panel board including
connections etc., complete of
ELEC-7.13### Supply
CONZERVE and erection of Analog/
/ ELMEASURE 4 No 1 No 172.00
selector switch
MECO / HPL MAKE. for voltmeter /
Ammeter on the existing box /
panel including connections etc.,
complete. L&T / C&S /
ELEC-7.13### Supply
SALZARand / HPL erection
MAKE.of Analog 9 No 1 No 132.00
LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.
ELEC-7.13### Supply and erection of Analog 9 No 1 No 440.00
LT current transformer with bar
primary 100/5A to 1000 / 5A
ratio in the existing box / panel
including connections etc.,
complete. KAPPA MAKE.
Bus bar arrangement with 5%
insulators
Hard ware such as base 2%
channel etc.
Transportation 2%
Control wiring with flexible wires 5%
and MCBs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR
Or say

IIIT-HYD ELEC-Data 52 of 354


S.N
SSR No Description Qty Unit Rate
o
Main Lighting Panel
78 Supply installation testing and commissioning of 3 phase and neutral 415V free stand
floor mounted indoor LT panel made out of No.16/14 gauge CRCA sheet steel after
process and painting with powder coating. The panel shall consists of suitable rating
Alluminium busbar ( with rating of 0.8A/ Sqmm)supported with DMC /SMC barriers a
colour coaded with heat shrinkable sleeves, flexibiltioy to accept the up four out going
cables and necessary cable chamber . The panel shall have comprised of following s
gear . Including supply and fixing the same and painting with powder coating includin
internal connections cost and conveyance
Fabrication: L of all
H materials
D & labour charges.
Size of panel : in Mtr 2.10 2.23 0.60
Front and back faces 2.10 1.65 6.93
Top and bottom faces 2.10 0.60 3.78
Side faces 2.23 0.60 2.67
Vertical sheets 2.23 0.60 4.01
Horizontal sheets 0.70 0.40 0.84
Horizontal sheets 0.55 0.30 1.98
extra of ACB chamber 3.62
(0.2x0.7x2.225)
Sub total 23.83
Add extra 10 % for wastage 2.38
a Total 26.21
ELEC-7.12### Fabrication and erection of 14 / 26.21 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
Elec.-2.8. 381 Supply of 630A Adjustable, 1 Nos 1 No 37900.00
powder coating including cost
Confirms to IS/IEC 60947-2
and conveyance of all materials
having Breaking Capacity 50 KA
and labour charges.
with thermal magnetic release
Panel Mounted.
Makes : L&T / Schneider /
Siemens / Legrand / Hager /
Elec.-2.8. 376 ABB.
Supply of 400A 3 Pole MCCB, 4 Nos 1 No 21257.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic release Panel
Elec.-2.8. 376 Supply of 250A 3 Pole MCCB,/
Mounted.Makes : L&T 4 Nos 1 No 15706.00
Schneider / Siemens
Adjustable, Confirms/ Legrand.
to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic release Panel
Elec.-2.8. 372 Mounted.Makes
Supply of 125A 3 :PoleL&T MCCB,/ 4 Nos 1 No 7051.00
Schneider / Siemens / Legrand.
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 25 KA with thermal
magnetic release Panel
Mounted.Makes : L&T /
Schneider / Siemens / Legrand.
IIIT-HYD ELEC-Data 53 of 354
S.N
SSR No Description Qty Unit Rate
o
Elec.-2.8. 370 Supply of 63A 3 Pole MCCB, 0 Nos 1 No 5939.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic release Panel
ELEC-7.13### Supply and erection
Mounted.Makes : ofL&T
0-415V/ 1 No 1 No 2,000.00
volt Digital
Schneider meter / Legrand.
/ Siemens of size
96x96mm on exisiting box /
panel board including
connections etc., complete of
ELEC-7.13### Supply
CONZERVE and erection of 0-100 //
/ ELMEASURE 1 No 1 No 2,000.00
200
MECO / 400
/ HPL/ 600 /1000 - 5A CT
MAKE.
Digital Ammeter of size
96x96mm on existing box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
MECO / HPL MAKE.

IIIT-HYD ELEC-Data 54 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC-7.13### Supply and erection of Analog 2 No 1 No 172.00
selector switch for voltmeter /
Ammeter on the existing box /
panel including connections etc.,
complete. L&T / C&S /
ELEC-7.13### Supply
SALZARand erection
/ HPL MAKE.of Analog 3 No 1 No 132.00
LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.
ELEC-7.13### Supply and erection of Analog 2 No 1 No 440.00
LT current transformer with bar
primary 100/5A to 1000 / 5A
ratio in the existing box / panel
including connections etc.,
complete. KAPPA MAKE.
Bus bar arrangement with 5%
insulators
Hard ware such as base 2%
channel etc.
Transportation 2%
Control wiring with flexible wires 5%
and MCBs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR
Or say
APFC Panel
79 Supply installation testing and commissioning of 3 phase and neutral 415V free st
floor mounted Out door Type MV panel made out of No.16/14 gauge CRCA shee
after 7 tank process and painting with powder coating. The panel shall consists of s
rating TPN Alluminium busbar ( with rating of 0.8A/ Sqmm)supported with DMC
barriers and colour coaded with heat shrinkable sleeves, flexibiltioy to accept the u
out going cables and necessary cable chamber . The panel shall have compr
following switch gear . Including supply
Fabrication: L andHfixing the
D same and painting with p
coating including internal
Size of panel : in Mtr connections cost
1.20 1.68 and conveyance
0.90 of all materials &
charges.
Front and back faces + Mid 3.00 1.20 1.68 6.03
particion
Top and bottom faces 3.00 1.20 0.90 3.24
Side faces 2.00 1.68 0.90 3.02
Vertical sheets 1.00 1.68 0.90 1.51
Horizontal sheets 2.00 0.60 0.90 1.08
Horizontal sheets 3.00 0.55 0.90 1.49
Additional Front Cover for out 0.00 1.20 1.68 0.00
door panel
Sub total 16.36
Add extra 10 % for wastage 1.64
Total 17.99

IIIT-HYD ELEC-Data 55 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC-7.12### Fabrication and erection of 14 / 17.99 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
powder coating including cost
and conveyance of all materials
and labour charges.

Elec.-2.8. 376 Supply of 250A 3 Pole MCCB, 1 Nos 1 No 15706.00


Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic release Panel
Mounted.Makes : L&T /
Schneider / Siemens / Legrand.

Elec.-2.8. 372 Supply of 125A 3 Pole MCCB, 1 Nos 1 No 7051.00


Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 25 KA with thermal
magnetic release Panel
Mounted.

Elec.-2.13462 Supply of 63A 10KA TP MCB, 6 Nos 1 No 1407.00


C/D Curve ISI Mark Makes :
Legrand-DX3 / Shneider-Acti9.

Elec.-7.13### Supply and fixing of 50.0 KVAR 1 Nos 1 No 9800.00


Rating capacitor duty contactor

Elec.-7.13### Supply and fixing of 25.0 KVAR 1 Nos 1 No 3543.00


Rating capacitor duty contactor

Elec.-7.13### Supply and fixing of 20.0 KVAR 5 Nos 1 No 3160.00


Rating capacitor duty contactor

IIIT-HYD ELEC-Data 56 of 354


S.N
SSR No Description Qty Unit Rate
o
Elec.-7.14### Supply of MPP type heavy duty 165 KVAR 1 KVAR 327.00
capacitor of operating voltage
not less than 480V and losses
not more than 0.35W per KVAR
and inrush current withstand
capability 300 times the rated
current
Makes:L&T/Siemens/Schneider/
Epcos..

ELEC-7.13### Supply and erection of 0-415V 1 No 1 No 2000.00


volt Digital meter of size
96x96mm on exisiting box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
MECO / HPL MAKE.

ELEC-7.13### Supply and erection of 0-100 / 1 No 1 No 2000.00


200 / 400 / 600 /1000 - 5A CT
Digital Ammeter of size
96x96mm on existing box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
MECO / HPL MAKE.

ELEC-7.13### Supply and erection of Analog 2 No 1 No 172.00


selector switch for voltmeter /
Ammeter on the existing box /
panel including connections etc.,
complete. L&T / C&S /
SALZAR / HPL MAKE.

ELEC-7.13### Supply and erection of push 28 No 1 No 74.00


buttons on the existing panel
board.
ELEC-7.13### Supply and erection of Analog 35 No 1 No 132.00
LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.

ELEC-7.13### Supply and erection of Analog 3 No 1 No 440.00


LT current transformer with bar
primary 100/5A to 1000 / 5A
ratio in the existing box / panel
including connections etc.,
complete. KAPPA MAKE.

IIIT-HYD ELEC-Data 57 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC-7.13### Supply and erection of Digital 1 No 1 No 2500.00
power factor meter, 3 phase,
4 wire balanced or
unabalanced load 5A, 415V of
size 96x96mm on existing
box / panel board including
connections etc., complete.
MAKES : CONZERVE /
ELMEASURE / L&T / SEIMENS.

ELEC-7.13### Supply and fixing of 8Stage 1 No 1 No 12331.00


APFC Relay with connection
etc complete.
Makes : L&T / Siemens /
EPCOS / Schneider /
Elmeasure.

q Bus bar arrangement with 5%


insulators
r Hard ware such as base 5%
channel etc.
s Transportation 2%
t Control wiring with flexible wires 15%
and MCBs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR
Or say

Main panel for Power in


College
80 Supply installation testing and commissioning of 3 phase and neutral 415V free stand
floor mounted indoor LT panel made out of No.16/14 gauge CRCA sheet steel after
process and painting with powder coating. The panel shall consists of suitable rating
Aluminium bus bar ( with rating of 0.8A/ Sqmm)supported with DMC /SMC barriers a
colour coaded with heat shrinkable sleeves, flexibility to accept the up four out going
and necessary cable chamber . The panel shall have comprised of following switch g
Including supply and fixing the same and painting with powder coating including inte
connections
Fabrication: cost and conveyance of Lall materials
H & labour D charges.
Size of panel : in Mtr 2.15 2.22 0.90
Front and back faces 2.15 2.22 14.29
Top and bottom faces 2.15 0.90 3.87
Side faces 2.22 0.90 3.99

IIIT-HYD ELEC-Data 58 of 354


S.N
SSR No Description Qty Unit Rate
o
Vertical sheets 2.22 0.90 1.99
Vertical sheets 1.80 0.90 4.86
Horizontal sheets 0.60 0.90 0.54
Horizontal sheets 0.45 0.40 2.16
Horizontal sheets 0.55 0.40 0.66
Sub total 32.36
Add extra 10 % for wastage 3.24
Total 35.59
ELEC-7.12### Fabrication and erection of 14 / 35.59 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
Incomer.
powder coating including cost
Elec.-2.11424 Supply of 630A EDO
and conveyance of allAir Circuit
materials 1 Nos 1 No ###
Breaker
and Confirms to IS
labour charges.
13947-2, IEC 60947-2 and
BS-EN 60947 with Micro
processer
Out goingsbased having over
Elec.-2.8. 379 load,
Supplyshotof circuit
400A 3and Poleearth fault
MCCB, 6 Nos 1 No 21257.00
Protection
Adjustable, Makes
Confirms : Siemens
to IS/IEC/
L&T
60947-2/ Schneider /
havingABB Breaking
Capacity 36/35 KA with thermal
magneticof 250A
Elec.-2.8. 376 Supply release Panel
3Pole MCCB, 3 Nos 1 No 15706.00
Mounted. Confirms to IS/IEC
Adjustable,
60947-2 having Breaking
Capacity 35 KA with thermal
Elec.-2.8. 372 magnetic
Supply of 125A release Panel
3Pole MCCB, 4 Nos 1 No 7051.00
Mounted.
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 25 KA with thermal
Elec.-2.8. 370 magnetic release
Supply of 63A / 60A 3 Panel
Pole 2 Nos 1 No 5939.00
Mounted.
MCCB, Adjustable, Confirms to
IS/IEC 60947-2 having Breaking
Capacity 25 KA with thermal
magnetic release Panel
ELEC-7.13### Supply
Mounted. and erection of 0-415V 1 No 1 No 2,000.00
volt Digital meter of size
96x96mm on existing box /
panel board including
connections etc., complete of
ELEC-7.13### Supply
CONZERVE and erection of 0-100 /
/ ELMEASURE 1 No 1 No 2,000.00
200 / 400 / 600
MECO / HPL MAKE. /1000 - 5A CT
Digital Ammeter of size
96x96mm on existing box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
MECO / HPL MAKE.

IIIT-HYD ELEC-Data 59 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC-7.13### Supply and erection of Analog 2 No 1 No 172.00
selector switch for voltmeter /
Ammeter on the existing box /
panel including connections etc.,
complete. L&T / C&S /
ELEC-7.13### Supply
SALZARand erection
/ HPL MAKE.of Analog 3 No 1 No 132.00
LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.
ELEC-7.13### Supply and erection of Analog 3 No 1 No 440.00
LT current transformer with bar
primary 100/5A to 1000 / 5A
ratio in the existing box / panel
including connections etc.,
complete. KAPPA MAKE.
Bus bar arrangement with 5%
insulators
Hard ware such as base 2%
channel etc.
Transportation 2%
Control wiring with flexible wires 5%
and MCBs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR
Or say
Sub-Panel for Power in
College
81 Supply installation testing and commissioning of 3 phase and neutral 415V free stand
floor mounted indoor LT panel made out of No.16/14 gauge CRCA sheet steel after
process and painting with powder coating. The panel shall consists of suitable rating
Aluminium bus bar ( with rating of 0.8A/ Sqmm)supported with DMC /SMC barriers a
colour coaded with heat shrinkable sleeves, flexibility to accept the up four out going
and necessary cable chamber . The panel shall have comprised of following switch g
Including supply and fixing the same and painting with powder coating including inte
connections cost and conveyance of all materials & labour charges.
Fabrication: L H D
Size of panel : in Mtr 1.35 1.98 0.60
Front and back faces 1.35 1.98 5.33
Top and bottom faces 1.35 0.60 1.62
Side faces 1.98 0.60 2.37
Vertical sheets 1.50 0.60 2.70
Vertical sheets 1.20 0.45 0.54
Horizontal sheets 1.50 0.45 0.68
Horizontal sheets 0.30 0.45 1.35
Horizontal sheets 0.60 0.45 0.27
Sub total 14.86
Add extra 10 % for wastage 1.49
Total 16.34

IIIT-HYD ELEC-Data 60 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC-7.12### Fabrication and erection of 14 / 16.34 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
Incomer.
powder coating including cost
Elec.-2.8. 379 Supply of 400A 4of Pole
and conveyance MCCB,
all materials 1 Nos 1 No 25685.00
Adjustable, Confirms
and labour charges. to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic
Out goings release Panel
Mounted.
Elec.-2.8. 376 Supply of 250A 3Pole MCCB, 0 Nos 1 No 15706.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 36 KA with thermal
Elec.-2.8. 372 magnetic
Supply of 125A release Panel
3Pole MCCB, 8 Nos 1 No 7051.00
Mounted.
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 25 KA with thermal
Elec.-2.8. 370 magnetic release
Supply of 63A / 60A 3 Panel
Pole 4 Nos 1 No 5939.00
Mounted.
MCCB, Adjustable, Confirms to
IS/IEC 60947-2 having Breaking
Capacity 25 KA with thermal
magnetic release Panel
ELEC-7.13### Supply
Mounted. and erection of 0-415V 1 No 1 No 2,000.00
volt Digital meter of size
96x96mm on existing box /
panel board including
connections etc., complete of
ELEC-7.13### Supply
CONZERVE and erection of 0-100 /
/ ELMEASURE 1 No 1 No 2,000.00
200
MECO / 400 / 600
/ HPL /1000 - 5A CT
MAKE.
Digital Ammeter of size
96x96mm on existing box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
ELEC-7.13### Supply
MECO / andHPL erection
MAKE. of Analog 2 No 1 No 172.00
selector switch for voltmeter /
Ammeter on the existing box /
panel including connections etc.,
complete. L&T / C&S /
ELEC-7.13### Supply
SALZARand / HPLerection
MAKE.of Analog 3 No 1 No 132.00
LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.
ELEC-7.13### Supply and erection of Analog 3 No 1 No 440.00
LT current transformer with bar
primary 100/5A to 1000 / 5A
ratio in the existing box / panel
including connections etc.,
complete. KAPPA MAKE.

IIIT-HYD ELEC-Data 61 of 354


S.N
SSR No Description Qty Unit Rate
o

Bus bar arrangement with 5%


insulators
Hard ware such as base 2%
channel etc.
Transportation 2%
Control wiring with flexible wires 5%
and MCBs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR
Or say

Main panel for Lighting in


College
82 Supply installation testing and commissioning of 3 phase and neutral 415V free stand
floor mounted indoor LT panel made out of No.16/14 gauge CRCA sheet steel after
process and painting with powder coating. The panel shall consists of suitable rating
Aluminium bus bar ( with rating of 0.8A/ Sqmm)supported with DMC /SMC barriers a
colour coaded with heat shrinkable sleeves, flexibility to accept the up four out going
and necessary cable chamber . The panel shall have comprised of following switch g
Including supply and fixing the same and painting with powder coating including inte
connections
Fabrication: cost and conveyance of Lall materials
H & labour D charges.
Size of panel : in Mtr 2.00 2.10 0.90
Front and back faces 3.00 2.00 2.10 12.60
Top and bottom faces 2.00 2.00 0.90 3.60
Side faces 2.00 2.10 0.90 3.78
Vertical sheets 1.00 2.10 0.90 1.89
Vertical sheets 3.00 1.80 0.90 4.86
Horizontal sheets 1.00 0.60 0.90 0.54
Horizontal sheets 12.00 0.45 0.40 2.16
Horizontal sheets 3.00 0.55 0.40 0.66
Sub total 30.09
Add extra 10 % for wastage 3.01
Total 33.10
ELEC-7.12### Fabrication and erection of 14 / 33.10 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
Incomer.
powder coating including cost
Elec.-2.8. 379 Supply of 400A 4of Pole
and conveyance MCCB,
all materials 1 Nos 1 No 25685.00
Adjustable, Confirms
and labour charges. to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic release Panel
Mounted.
IIIT-HYD ELEC-Data 62 of 354
S.N
SSR No Description Qty Unit Rate
o
Out goings
Elec.-2.8. 376 Supply of 250A 3Pole MCCB, 4 Nos 1 No 15706.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 35 KA with thermal
Elec.-2.8. 372 magnetic release
Supply of 125A Panel
3Pole MCCB, 8 Nos 1 No 7051.00
Mounted.
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 25 KA with thermal
Elec.-2.8. 370 magnetic release
Supply of 63A / 60A 3 Panel
Pole 4 Nos 1 No 5939.00
Mounted.
MCCB, Adjustable, Confirms to
IS/IEC 60947-2 having Breaking
Capacity 25 KA with thermal
magnetic release Panel
ELEC-7.13### Supply
Mounted. and erection of 0-415V 1 No 1 No 2,000.00
volt Digital meter of size
96x96mm on existing box /
panel board including
connections etc., complete of
ELEC-7.13### Supply
CONZERVE and erection of 0-100 /
/ ELMEASURE 1 No 1 No 2,000.00
200 / 400 / 600
MECO / HPL MAKE. /1000 - 5A CT
Digital Ammeter of size
96x96mm on existing box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
ELEC-7.13### Supply
MECO / andHPL erection
MAKE. of Analog 2 No 1 No 172.00
selector switch for voltmeter /
Ammeter on the existing box /
panel including connections etc.,
complete. L&T / C&S /
ELEC-7.13### Supply
SALZARand / HPL erection
MAKE.of Analog 3 No 1 No 132.00
LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.
ELEC-7.13### Supply and erection of Analog 3 No 1 No 440.00
LT current transformer with bar
primary 100/5A to 1000 / 5A
ratio in the existing box / panel
including connections etc.,
complete. KAPPA MAKE.
Bus bar arrangement with 5%
insulators
Hard ware such as base 2%
channel etc.
Transportation 2%
Control wiring with flexible wires 5%
and MCBs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR

IIIT-HYD ELEC-Data 63 of 354


S.N
SSR No Description Qty Unit Rate
o
Or say

Sub-Panel for Lighting in


College
83 Supply installation testing and commissioning of 3 phase and neutral 415V free stand
floor mounted indoor LT panel made out of No.16/14 gauge CRCA sheet steel after
process and painting with powder coating. The panel shall consists of suitable rating
Aluminium bus bar ( with rating of 0.8A/ Sqmm)supported with DMC /SMC barriers a
colour coaded with heat shrinkable sleeves, flexibility to accept the up four out going
and necessary cable chamber . The panel shall have comprised of following switch g
Including supply and fixing the same and painting with powder coating including inte
connections
Fabrication: cost and conveyance of all materials
L & labour H charges.
D
Size of panel : in Mtr 1.35 1.98 0.60
Front and back faces 1.35 2.70
Top and bottom faces 1.35 0.60 1.62
Side faces 1.98 0.60 2.37
Vertical sheets 1.50 0.60 2.70
Vertical sheets 1.20 0.45 0.54
Horizontal sheets 1.50 0.45 0.68
Horizontal sheets 0.30 0.45 1.35
Horizontal sheets 0.60 0.45 0.27
Sub total 12.23
Add extra 10 % for wastage 1.22
Total 13.45
ELEC-7.12### Fabrication and erection of 14 / 13.45 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
Incomer.
powder coating including cost
Elec.-2.8. 377 Supply of 250A 4of Pole
and conveyance MCCB,
all materials 1 Nos 1 No 20403.00
Adjustable, Confirms
and labour charges. to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic
Out goings release Panel
Mounted.
Elec.-2.8. 372 Supply of 125A 3Pole MCCB, 8 Nos 1 No 7051.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 25 KA with thermal
Elec.-2.8. 370 magnetic
Supply of 63A release
/ 60A 3 Panel
Pole 4 Nos 1 No 5939.00
Mounted.
MCCB, Adjustable, Confirms to
IS/IEC 60947-2 having Breaking
Capacity 25 KA with thermal
magnetic release Panel
Mounted.

IIIT-HYD ELEC-Data 64 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC-7.13### Supply and erection of 0-415V 1 No 1 No 2,000.00
volt Digital meter of size
96x96mm on existing box /
panel board including
connections etc., complete of
ELEC-7.13### Supply
CONZERVE and erection of 0-100 /
/ ELMEASURE 1 No 1 No 2,000.00
200 / 400 / 600
MECO / HPL MAKE. /1000 - 5A CT
Digital Ammeter of size
96x96mm on existing box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
ELEC-7.13### Supply
MECO / andHPL erection
MAKE. of Analog 2 No 1 No 172.00
selector switch for voltmeter /
Ammeter on the existing box /
panel including connections etc.,
complete. L&T / C&S /
ELEC-7.13### Supply
SALZARand / HPLerection
MAKE.of Analog 3 No 1 No 132.00
LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.
ELEC-7.13### Supply and erection of Analog 3 No 1 No 440.00
LT current transformer with bar
primary 100/5A to 1000 / 5A
ratio in the existing box / panel
including connections etc.,
complete. KAPPA MAKE.
Bus bar arrangement with 5%
insulators
Hard ware such as base 2%
channel etc.
Transportation 2%
Control wiring with flexible wires 5%
and MCBs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR
Or say

B&G Hostel Power PANEL


84 Supply installation testing and commissioning of 3 phase and neutral 415V free stand
floor mounted indoor LT panel made out of No.16/14 gauge CRCA sheet steel after
process and painting with powder coating. The panel shall consists of suitable rating
Aluminium bus bar ( with rating of 0.8A/ Sqmm)supported with DMC /SMC barriers a
colour coaded with heat shrinkable sleeves, flexibility to accept the up four out going
and necessary cable chamber . The panel shall have comprised of following switch g
Including supply and fixing the same and painting with powder coating including inte
connections
Fabrication: cost and conveyance of all materials
L & labour H charges.
D
Size of panel : in Mtr 1.35 1.78 0.60
Front and back faces 1.35 1.78 4.79

IIIT-HYD ELEC-Data 65 of 354


S.N
SSR No Description Qty Unit Rate
o
Top and bottom faces 1.35 0.60 1.62
Side faces 1.78 0.60 2.13
Vertical sheets 1.50 0.60 2.70
Vertical sheets 1.20 0.45 0.54
Horizontal sheets 1.50 0.45 0.68
Horizontal sheets 0.30 0.45 1.35
Horizontal sheets 0.60 0.45 0.27
Sub total 14.08
Add extra 10 % for wastage 1.41
Total 15.49
ELEC-7.12### Fabrication and erection of 14 / 15.49 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
Incomer.
powder coating including cost
Elec.-2.8. 379 Supply of 400A 4of Pole
and conveyance MCCB,
all materials 1 Nos 1 No 25685.00
Adjustable, Confirms to IS/IEC
and labour charges.
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic
Out goings release Panel
Mounted.
Elec.-2.8. 372 Supply of 125A 3Pole MCCB, 6 Nos 1 No 7051.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 25 KA with thermal
Elec.-2.8. 370 magnetic
Supply of 63A release
/ 60A 3 Panel
Pole 2 Nos 1 No 5939.00
Mounted.
MCCB, Adjustable, Confirms to
IS/IEC 60947-2 having Breaking
Capacity 25 KA with thermal
magnetic release Panel
Elec.-2.13465 Supply
Mounted. of 63A 4P Pole MCB, 4 Nos 1 No 1808.00
10KA
ELEC-7.13### Supply and erection of 0-415V 1 No 1 No 2,000.00
volt Digital meter of size
96x96mm on existing box /
panel board including
connections etc., complete of
ELEC-7.13### Supply
CONZERVE and erection of 0-100 /
/ ELMEASURE 1 No 1 No 2,000.00
200
MECO / 400 / 600
/ HPL /1000 - 5A CT
MAKE.
Digital Ammeter of size
96x96mm on existing box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
ELEC-7.13### Supply
MECO / andHPL erection
MAKE. of Analog 2 No 1 No 172.00
selector switch for voltmeter /
Ammeter on the existing box /
panel including connections etc.,
complete. L&T / C&S /
SALZAR / HPL MAKE.

IIIT-HYD ELEC-Data 66 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC-7.13### Supply and erection of Analog 3 No 1 No 132.00
LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.
ELEC-7.13### Supply and erection of Analog 3 No 1 No 440.00
LT current transformer with bar
primary 100/5A to 1000 / 5A
ratio in the existing box / panel
including connections etc.,
complete. KAPPA MAKE.
Bus bar arrangement with 5%
insulators
Hard ware such as base 2%
channel etc.
Transportation 2%
Control wiring with flexible wires 5%
and MCBs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR
Or say
B&G Hostel Lighting PANEL

85 Supply installation testing and commissioning of 3 phase and neutral 415V free stand
floor mounted indoor LT panel made out of No.16/14 gauge CRCA sheet steel after
process and painting with powder coating. The panel shall consists of suitable rating
Aluminium bus bar ( with rating of 0.8A/ Sqmm)supported with DMC /SMC barriers a
colour coaded with heat shrinkable sleeves, flexibility to accept the up four out going
and necessary cable chamber . The panel shall have comprised of following switch g
Including supply and fixing the same and painting with powder coating including inte
connections
Fabrication: cost and conveyance of all materials
L & labour H charges.
D
Size of panel : in Mtr 1.35 1.78 0.60
Front and back faces 1.35 1.78 4.79
Top and bottom faces 1.35 0.60 1.62
Side faces 1.78 0.60 2.13
Vertical sheets 1.50 0.60 2.70
Vertical sheets 1.20 0.45 0.54
Horizontal sheets 1.50 0.45 0.68
Horizontal sheets 0.30 0.45 1.35
Horizontal sheets 0.60 0.45 0.27
Sub total 14.08
Add extra 10 % for wastage 1.41
Total 15.49

IIIT-HYD ELEC-Data 67 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC-7.12### Fabrication and erection of 14 / 15.49 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
Incomer.
powder coating including cost
Elec.-2.8. 377 Supply of 250A 4of Pole
and conveyance MCCB,
all materials 1 Nos 1 No 20403.00
Adjustable, Confirms
and labour charges. to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic
Out goings release Panel
Mounted.
Elec.-2.8. 372 Supply of 125A 3Pole MCCB, 6 Nos 1 No 7051.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 25 KA with thermal
Elec.-2.8. 370 magnetic
Supply of 63A release
/ 60A 3 Panel
Pole 2 Nos 1 No 5939.00
Mounted.
MCCB, Adjustable, Confirms to
IS/IEC 60947-2 having Breaking
Capacity 25 KA with thermal
magnetic release Panel
Elec.-2.13465 Supply
Mounted. of 63A 4P Pole MCB, 4 Nos 1 No 1808.00
10KA
ELEC-7.13### Supply and erection of 0-415V 1 No 1 No 2,000.00
volt Digital meter of size
96x96mm on existing box /
panel board including
connections etc., complete of
ELEC-7.13### Supply
CONZERVE and erection of 0-100 /
/ ELMEASURE 1 No 1 No 2,000.00
200
MECO / 400
/ HPL/ 600 /1000 - 5A CT
MAKE.
Digital Ammeter of size
96x96mm on existing box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
ELEC-7.13### Supply
MECO / andHPL erection
MAKE. of Analog 2 No 1 No 172.00
selector switch for voltmeter /
Ammeter on the existing box /
panel including connections etc.,
complete. L&T / C&S /
ELEC-7.13### Supply
SALZARand / HPL erection
MAKE.of Analog 3 No 1 No 132.00
LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.
ELEC-7.13### Supply and erection of Analog 3 No 1 No 440.00
LT current transformer with bar
primary 100/5A to 1000 / 5A
ratio in the existing box / panel
including connections etc.,
complete. KAPPA MAKE.

IIIT-HYD ELEC-Data 68 of 354


S.N
SSR No Description Qty Unit Rate
o
Bus bar arrangement with 5%
insulators
Hard ware such as base 2%
channel etc.
Transportation 2%
Control wiring with flexible wires 5%
and MCBs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR
Or say
TSQ Meter Panel
86 Supply installation testing and commissioning of 3 phase and neutral 415V free stand
floor mounted indoor LT panel made out of No.16/14 gauge CRCA sheet steel after
process and painting with powder coating. The panel shall consists of suitable rating
Aluminium bus bar ( with rating of 0.8A/ Sqmm)supported with DMC /SMC barriers a
colour coaded with heat shrinkable sleeves, flexibility to accept the up four out going
and necessary cable chamber . The panel shall have comprised of following switch g
Including supply and fixing the same and painting with powder coating including inte
connections
Fabrication: cost and conveyance of all materials
L & labour H charges.
D
Size of panel : in Mtr 2.60 2.25 0.25
Front and back faces 2.60 2.25 11.70
Top and bottom faces 2.60 0.25 1.30
Side faces 2.25 0.25 1.13
Vertical sheets 1.93 0.25 2.90
Vertical sheets 1.27 0.25 0.00
Horizontal sheets 2.60 0.25 0.65
Horizontal sheets 1.50 0.25 1.13
Horizontal sheets 0.75 0.25 0.56
Sub total 19.36
Add extra 10 % for wastage 1.94
Total 21.29
ELEC-7.12### Fabrication and erection of 14 / 21.29 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
Incomer.
powder coating including cost
Elec.-2.8. 377 Supply of 250A 4of Pole
and conveyance MCCB,
all materials 1 Nos 1 No 20403.00
Adjustable, Confirms to IS/IEC
and labour charges.
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic
Out goings release Panel
Mounted.

IIIT-HYD ELEC-Data 69 of 354


S.N
SSR No Description Qty Unit Rate
o
Elec.-2.8. 372 Supply of 125A 3Pole MCCB, 0 Nos 1 No 7051.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 25 KA with thermal
Elec.-2.8. 370 magnetic
Supply of 63Arelease
/ 60A 3 Panel
Pole 0 Nos 1 No 5939.00
Mounted.
MCCB, Adjustable, Confirms to
IS/IEC 60947-2 having Breaking
Capacity 25 KA with thermal
magnetic release Panel
Elec.-2.13459 40A 10KA SP MCB, C/D Curve
Mounted. 30 Nos 1 No 403.00
ISI Mark of Makes : Legrand-
DX3 / Schneider-Acti9. (30 Nos.,
for quarters )
ELEC-7.13### Supply and erection of 0-415V 1 No 1 No 2,000.00
volt Digital meter of size
96x96mm on existing box /
panel board including
connections etc., complete of
ELEC-7.13### Supply
CONZERVE and erection of 0-100 //
/ ELMEASURE 1 No 1 No 2,000.00
200
MECO / 400 / 600
/ HPL /1000 - 5A CT
MAKE.
Digital Ammeter of size
96x96mm on existing box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
ELEC-7.13### Supply
MECO / andHPL erection
MAKE. of Analog 2 No 1 No 172.00
selector switch for voltmeter /
Ammeter on the existing box /
panel including connections etc.,
complete. L&T / C&S /
ELEC-7.13### Supply
SALZARand / HPLerection
MAKE.of Analog 3 No 1 No 132.00
LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.
ELEC-7.13### Supply and erection of Analog 3 No 1 No 440.00
LT current transformer with bar
primary 100/5A to 1000 / 5A
ratio in the existing box / panel
including connections etc.,
complete. KAPPA MAKE.
Bus bar arrangement with 5%
insulators
Hard ware such as base 2%
channel etc.
Transportation 2%
Control wiring with flexible wires 5%
and MCBs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR
Or say

IIIT-HYD ELEC-Data 70 of 354


S.N
SSR No Description Qty Unit Rate
o

NSQ Meter Panel


87 Supply installation testing and commissioning of 3 phase and neutral 415V free stand
floor mounted indoor LT panel made out of No.16/14 gauge CRCA sheet steel after
process and painting with powder coating. The panel shall consists of suitable rating
Aluminium bus bar ( with rating of 0.8A/ Sqmm)supported with DMC /SMC barriers a
colour coaded with heat shrinkable sleeves, flexibility to accept the up four out going
and necessary cable chamber . The panel shall have comprised of following switch g
Including supply and fixing the same and painting with powder coating including inte
connections
Fabrication: cost and conveyance of all materials
L & labour H charges.
D
Size of panel : in Mtr 2.59 1.85 0.25
Front and back faces 2.59 1.85 9.58
Top and bottom faces 2.59 0.25 1.30
Side faces 1.85 0.25 0.93
Vertical sheets 1.50 0.25 1.88
Vertical sheets 1.20 0.25 0.00
Horizontal sheets 2.59 0.25 0.65
Horizontal sheets 0.39 0.25 0.96
Horizontal sheets 0.60 0.25 0.00
Sub total 15.29
Add extra 10 % for wastage 1.53
Total 16.82
ELEC-7.12### Fabrication and erection of 14 / 16.82 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
Incomer.
powder coating including cost
Elec.-2.8. 377 Supply of 250A 4of Pole
and conveyance MCCB,
all materials 1 Nos 1 No 20403.00
Adjustable, Confirms to IS/IEC
and labour charges.
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic
Out goings release Panel
Mounted.
Elec.-2.8. 372 Supply of 125A 3Pole MCCB, 1 Nos 1 No 7051.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 25 KA with thermal
Elec.-2.13463 magnetic
40-63A 10KArelease TP MCB,PanelC/D 18 Nos 1 No 1407.00
Mounted. (HOSTELS)
Curve ISI Mark of Makes :
Legrand-DX3 / Schneider-Acti9.
(17 Nos., for quarters +
ELEC-7.13### Supply
COMMON and) erection of 0-415V 1 No 1 No 2,000.00
volt Digital meter of size
96x96mm on existing box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
MECO / HPL MAKE.

IIIT-HYD ELEC-Data 71 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC-7.13### Supply and erection of 0-100 / 1 No 1 No 2,000.00
200 / 400 / 600 /1000 - 5A CT
Digital Ammeter of size
96x96mm on existing box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
ELEC-7.13### Supply
MECO / and
HPL erection
MAKE. of Analog 2 No 1 No 172.00
selector switch for voltmeter /
Ammeter on the existing box /
panel including connections etc.,
complete. L&T / C&S /
ELEC-7.13### Supply
SALZARand erection
/ HPL MAKE.of Analog 3 No 1 No 132.00
LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.
ELEC-7.13### Supply and erection of Analog 3 No 1 No 440.00
LT current transformer with bar
primary 100/5A to 1000 / 5A
ratio in the existing box / panel
including connections etc.,
complete. KAPPA MAKE.
Bus bar arrangement with 5%
insulators
Hard ware such as base 2%
channel etc.
Transportation 2%
Control wiring with flexible wires 5%
and MCBs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR
Or say

NTSQ Meter Panel-1


88 Supply installation testing and commissioning of 3 phase and neutral 415V free stand
floor mounted indoor LT panel made out of No.16/14 gauge CRCA sheet steel after
process and painting with powder coating. The panel shall consists of suitable rating
Aluminium bus bar ( with rating of 0.8A/ Sqmm)supported with DMC /SMC barriers a
colour coaded with heat shrinkable sleeves, flexibility to accept the up four out going
and necessary cable chamber . The panel shall have comprised of following switch g
Including supply and fixing the same and painting with powder coating including inte
connections
Fabrication: cost and conveyance of all materials
L & labour H charges.
D
Size of panel : in Mtr 2.17 1.86 0.25
Front and back faces 2.17 1.86 8.03
Top and bottom faces 2.17 0.25 1.08
Side faces 1.86 0.25 0.93
Vertical sheets 1.56 0.25 1.56
Vertical sheets 1.27 0.25 0.32

IIIT-HYD ELEC-Data 72 of 354


S.N
SSR No Description Qty Unit Rate
o
Horizontal sheets 1.50 0.25 0.00
Horizontal sheets 1.27 0.25 0.95
Horizontal sheets 0.45 0.25 0.34
Sub total 13.21
Add extra 10 % for wastage 1.32
Total 14.53
ELEC-7.12### Fabrication and erection of 14 / 14.53 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
Incomer.
powder coating including cost
Elec.-2.8. 377 Supply of 250A 4of Pole
and conveyance MCCB,
all materials 1 Nos 1 No 20403.00
Adjustable, Confirms
and labour charges. to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic
Out goings release Panel
Elec.-2.8. 374 Mounted.
Supply of 160A 3Pole MCCB, 0 Nos 1 No 9350.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 25 KA with thermal
Elec.-2.8. 370 magnetic
Supply of 63A release
/ 60A 3 Panel
Pole 0 Nos 1 No 5939.00
Mounted.
MCCB, Adjustable, Confirms to
IS/IEC 60947-2 having Breaking
Capacity 25 KA with thermal
magnetic release Panel
Elec.-2.13463 40-63A
Mounted.10KA TP MCB, C/D 15 Nos 1 No 1407.00
Curve ISI Mark of Makes :
Legrand-DX3 / Schneider-Acti9.
(15 Nos., for quarters + 1 No.,
ELEC-7.13### Supply and meter-16)
for common erection of 0-415V 1 No 1 No 2,000.00
volt Digital meter of size
96x96mm on existing box /
panel board including
connections etc., complete of
ELEC-7.13### Supply
CONZERVE and erection of 0-100 /
/ ELMEASURE 1 No 1 No 2,000.00
200
MECO / 400 / 600
/ HPL /1000 - 5A CT
MAKE.
Digital Ammeter of size
96x96mm on existing box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
ELEC-7.13### Supply
MECO / andHPL erection
MAKE. of Analog 2 No 1 No 172.00
selector switch for voltmeter /
Ammeter on the existing box /
panel including connections etc.,
complete. L&T / C&S /
ELEC-7.13### Supply
SALZARand / HPLerection
MAKE.of Analog 3 No 1 No 132.00
LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.

IIIT-HYD ELEC-Data 73 of 354


S.N
SSR No Description Qty Unit Rate
o
ELEC-7.13### Supply and erection of Analog 3 No 1 No 440.00
LT current transformer with bar
primary 100/5A to 1000 / 5A
ratio in the existing box / panel
including connections etc.,
complete. KAPPA MAKE.
Bus bar arrangement with 5%
insulators
Hard ware such as base 2%
channel etc.
Transportation 2%
Control wiring with flexible wires 5%
and MCBs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR
Or say

NTSQ Meter Panel-2


89 Supply installation testing and commissioning of 3 phase and neutral 415V free stand
floor mounted indoor LT panel made out of No.16/14 gauge CRCA sheet steel after
process and painting with powder coating. The panel shall consists of suitable rating
Aluminium bus bar ( with rating of 0.8A/ Sqmm)supported with DMC /SMC barriers a
colour coaded with heat shrinkable sleeves, flexibility to accept the up four out going
and necessary cable chamber . The panel shall have comprised of following switch g
Including supply and fixing the same and painting with powder coating including inte
connections
Fabrication: cost and conveyance of all materials
L & labour H charges.
D
Size of panel : in Mtr 2.17 1.86 0.25
Front and back faces 2.17 1.86 8.03
Top and bottom faces 2.17 0.25 1.08
Side faces 1.86 0.25 0.93
Vertical sheets 1.56 0.25 1.56
Vertical sheets 1.27 0.25 0.32
Horizontal sheets 1.50 0.25 0.00
Horizontal sheets 1.27 0.25 0.95
Horizontal sheets 0.45 0.25 0.34
Sub total 13.21
Add extra 10 % for wastage 1.32
Total 14.53
ELEC-7.12### Fabrication and erection of 14 / 14.53 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
Incomer.
powder coating including cost
and conveyance of all materials
and labour charges.
IIIT-HYD ELEC-Data 74 of 354
S.N
SSR No Description Qty Unit Rate
o
Elec.-2.8. 375 Supply of 160A 4 Pole MCCB, 1 Nos 1 No 12210.00
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 36/35 KA with thermal
magnetic
Out goings release Panel
Mounted.
Elec.-2.13463 40-63A 10KA TP MCB, C/D 16 Nos 1 No 1407.00
Curve ISI Mark of Makes :
Legrand-DX3 / Schneider-Acti9.
(15 Nos., for quarters)
ELEC-7.13### Supply and erection of 0-415V 1 No 1 No 2,000.00
volt Digital meter of size
96x96mm on existing box /
panel board including
connections etc., complete of
ELEC-7.13### Supply
CONZERVE and erection of 0-100 /
/ ELMEASURE 1 No 1 No 2,000.00
200 / 400 / 600
MECO / HPL MAKE. /1000 - 5A CT
Digital Ammeter of size
96x96mm on existing box /
panel board including
connections etc., complete of
CONZERVE / ELMEASURE /
ELEC-7.13### Supply
MECO / andHPL erection
MAKE. of Analog 2 No 1 No 172.00
selector switch for voltmeter /
Ammeter on the existing box /
panel including connections etc.,
complete. L&T / C&S /
ELEC-7.13### Supply
SALZARand / HPLerection
MAKE.of Analog 3 No 1 No 132.00
LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.
ELEC-7.13### Supply and erection of Analog 3 No 1 No 440.00
LT current transformer with bar
primary 100/5A to 1000 / 5A
ratio in the existing box / panel
including connections etc.,
complete. KAPPA MAKE.
Bus bar arrangement with 5%
insulators
Hard ware such as base 2%
channel etc.
Transportation 2%
Control wiring with flexible wires 5%
and MCBs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR
Or say

63A MCCB Switches

IIIT-HYD ELEC-Data 75 of 354


S.N
SSR No Description Qty Unit Rate
o
90 Supply installation testing and commissioning of 3 phase and neutral 415V free m
indoor LT panel made out of No.16/14 gauge CRCA sheet steel after 7 tank proce
painting with powder coating. The panel shall consists of suitable rating TPN. The
shall have comprised of following switch gear . Including supply and fixing the sam
painting with powder coating including internal connections cost and conveyance
materials & labour charges.
Fabrication: L H D Nos
Size of panel : in Mtr 0.30 0.30 0.30
Front and back faces 0.30 0.60 2
Top and bottom faces 0.30 0.30 0.18 2
Side faces 0.30 0.30 0.18 2
Sub total 0.96
Add extra 10 % for wastage 0.10
Total 1.06
ELEC-7.12### Fabrication and erection of 14 / 1.06 Sqmtr 1 Sqmtr 3941.00
16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process
Incomer & Outand painting with
goings
powder coating including cost
b Elec.-2.8. 371 Supply of 63A / 60A 4 Pole 1 Nos 1 No 6678.00
and conveyance of all materials
MCCB, Adjustable, Confirms to
and labour charges.
IS/IEC 60947-2 having Breaking
Capacity 25 KA with thermal
magnetic release Panel
c Mounted.
Bus bar arrangement with 0%
insulators
d Hard ware such as base 0%
channel etc.
e Transportation 1%
f Control wiring with flexible wires 0.50%
and connections to MCBs with
required lugs including
commissioning
TOTAL COST OF andMATERIAL
testing etc
AND LABOUR
Or say

91 Supply, Transportation, Erection and Comissioning of 500 KVA 3 Phase, 50 Hz, oil
immersed and naturally cooled, outdoor type copper wound transformer designed and
manufactured as per IS 1180 (Part 1):2014 and 1st filling of oil, connected delta on pr
side and Star on secondary side with additional neutral brought out on load side, 110
(433V / 415V) with HV tapping + or - 2.5% contineously rated for full load and tempor
rise not exceeding 50°C in oil and 55°C rise by the resistance of the winding after
contineous run onWound
500 KVA Copper full load rating complete with the following
1 No 1 standard mountings.
Each ###
Transformer ELEC-7.15.1 (F)

Or say

IIIT-HYD ELEC-Data 76 of 354


S.N
SSR No Description Qty Unit Rate
o

92 HT Cable
a) 4.2.6 Supply of 3 Core 11 KV RMS 1 1 One 907.00
95Sqmm HT XLPE (E) Rmt
armoured Cable, as per IS
specification confirming to IS
7098/II/85 with latest
ammendments of makes
Makes : Torrent /Rate per Meter
Universal /
Unicab / Polycab / Havells /
93 KEI / RPG
Supply and/ fixing
Gloster. (ELEC- Box type RS Joist pole joined
of 175X85
4.2.1) with 2 Nos 9 mtrs length pole including excavation of pit,
together
coil earthing, hire charges of special T&P painting of Pole CC
1:3:6 upto ground and 1:2:4 for Couping work, including labour
and transportation charges etc., complete.
ELEC- 19.6 Kg/mt X 9 = 176.4 Kgs Kg 352.8 50.00
7.16.10 For 2 Poles 176.40 X 2 = 352.80
Kgs
13.4.2(a) Erection charges for 9 mtrs to 11
mtrs long swaged pole
a) Material
Pit excavation 156 Cmx
60Cmx60cm
ELEC- Earth work excacvation 250.00
9.4.17 including all soils for trench, cum 1.72
Pole Pit and Earth Pit.
AR C.C.work for pit Plain Cement Con cum 0.72 3804.00
AR Couping Vibrated Plain Cement Cocum 0.054 5177.00
AR Painting with red oxid and 78.00
enamel paint. M 8.35
ELEC- 74.00
9.1.24 each 1
Coil earthing
b) Labour charges
1 Skilled Electrician 0.660 day 1 day 540.00
3 Helper day 5.34 400.00 450.00
4 Mason day 0.66 445.00 470.00
Hire charges for Spl.T&P 40%
2786.1
on labour cost
Rate per Each
Total cost of pole with erection

Transportation of pole 2%
Sundries such as nut bolts etc.,

TOTAL:
Or say Rs.

IIIT-HYD ELEC-Data 77 of 354


S.N
SSR No Description Qty Unit Rate
o
94 Supply, transportation and fixing of 11 KV 400 amps capacity air
break switch(tilting), loop earthing, locking arrangement including
base channels with all accessories etc., complete as required.
ELEC- Approved made 11KV, 400A Each 1 6500.00
7.16.4 A.B switch with all standard
accessories etc.,
(Tilting.)complete with cost and
conveyance of all materials.

b) Labour charges
1 Skilled Electrician 1.000 day 1 day 540.00
2 Semi Skilled Electrician 1.000 day 1 day 450.00
3 Helper day 1 400.00 450.00
Sundries such as nut bolts etc.,

Rate per each Rs 7300/-


95 Supply, Transportation, Fixing of 11KV, Horn Gap (HG) fuse set
and MS channel base with bolts and nuts etc., with metal parts
etc., as reqired
ELEC- Cost of 11V, HG fuse set with Each 1 3600.00
7.16.5 all standard acessories
b) Labour charges
1 Skilled Electrician 1.000 day 1 day 540.00
2 Semi Skilled Electrician 1.000 day 1 day 450.00
3 Helper day 1 400.00 450.00
Sundries such as nut bolts etc.,

96 Supply and erecting porcelain disc type insulator suitable for 11KV
line with suitable hardware on existing cross arms.

a) Material
ELEC- Cost of porcelain disc type each 1 530.00
7.16.2 insulator suitable for 11 KV

Rate per Each

97 ELEC- Supply and erecting porcelain Each 1 1 Each 600.00


7.16.2 post type insulator suitable for
11KV line with suitable
hardware on existing cross
arms. Rate per Meter

98 ELEC- Supply and erecting approved Each 1 1 Each 1400.00


7.16.1 make 11KV, 5KA metal oxide
lightning arrestors suitable for 11
KV supply with necessary
Ratecross
materials on existing per Meter
arm.

IIIT-HYD ELEC-Data 78 of 354


S.N
SSR No Description Qty Unit Rate
o

99 ELEC- Providing and errecting heat Each 1 1 Each 8029.00


4.7.1 shrinkable indoor termination kit
for 11 KV XLPE HT cable 3 core
95 Sqmm with necessary
materials etc., complete of
Makes : Transeal Rate
- Hong shang
per Each/
Raychem / M Seal / Multy.
100 ELEC- Providing and errecting heat Each 1 1 Each 12176.00
4.7.1 shrinkable outdoor termination
kit for 11 KV XLPE HT cable 3
core 150-185 Sqmm with
necessary materials etc.,
complete with anti tracking red
colour material asRate
per IEC
per/Each
IS
specs only of
HT PANELS & DTRSMakes : Transeal -
Hong shang / Raychem / M Seal
101 Supply, Installation, Testing and commissioning of indoor type floor mounted metal cl
/ Multy.
VCB 3 Panel l with totally enclosed and fully inter locked horizantaldraw out , horizant
isolated type breaker with the folwing accessories etc complete.
1). Vaccum Circuit Breakers of
CG, ABB, SIEMENS,
SCHNEIDER OR their
Authorized / Certified Dealers of
OEM.(Authorization / Dealership
Certificate to be enclosed) .

a. 11 KV,800A, 20KA VCB with


horizontal Isolation - 3 Nos

b. 230V AC Motorised
Mechanism
c. Degree of protection - IP4X

d. Shunt Trip & Closing Coils -


24V DC
2). EPOXY RESIN CAST 11KV
PT of makes: VIDYUT or its
equalant
a. 3 Phase Draw out Potential
Transformer - 11KV/ 110V,
Class-1, Burden-100VA - 1 No.

3). EPOXY RESIN CAST, 1-Ph


CT (STR-20KA/1 Sec). Of
makes HUPHEN or its equalant

a. 100/5A,cl-5P10/1, Burden -
15VA - 9 Nos.

IIIT-HYD ELEC-Data 79 of 354


S.N
SSR No Description Qty Unit Rate
o
4). METERS of makes Conzerv
or its equalant
a. Digital Ammeter - 3 Nos
b. Digital Voltmeter
c. Digital Multi Funtion Meter
5). POWER PACK 24V DC - 3
Nos.
6). RELAYS
a. Microprocessed based IDMTL
Relay (3 O/C & 1 E/F) CG1 14N
of CG, ABB, SIEMENS,
SCHNEIDER make. - 3 Nos.

b). Transformer Aux. Relay (3-


Element) of Makes Ashida or its
equvalant. - 4 Nos.
c. Master trip Relay of Makes
Ashida or its equvalant. - 2 Nos.

d. 8 Window Annunciator +
Hooter of MINILEC or its
equalant make. - 2 Nos.
7). Wiring - LS
8). 800A Copper Bus-Bar with
PVC Sleeves (at C.D-1)
Manufactured by:- CGL, ABB,
SIEMENS, SCHNEIDER OR
their Authorized / Certified
Dealers of OEM.(Authorization /
Dealership Certificate to be
enclosed) .

(as per Quotation from M/s DN


power systems., Secunderabad- 1 No 1 Each ###
03 )
Installation and commissioning c 5%
Transportation charges @ 2 % on 2%
TOTAL:
Or say

IIIT-HYD ELEC-Data 80 of 354


S.N
SSR No Description Qty Unit Rate
o
102 Elec- Supply, Transportation, erection
10.1.8 and commissioning (Excluding
Foundation) of 320KVA, 3
Phase, 415, 50Hz, 380BHP,
water cooled multi cylinder
diesel generator set with
alternator of 320 KVA out put
continous rating at 0.8 p.f, and
Batteries with alternator of
320KVA/ 256 KW out put
continuous rating directly
coupled Engine and Alternator
with guard and mounted on a
common base plate of Robust
construction and complete with
AMF panel having IP-52
320 KVA DG
protection, Set (ELEC-11.1.5)
Acoustic Enclosure Nos 1 1 Each ###
as per CPCB norms , sound
103 AR absorbing
Providing material
of CC tofoundations
restrict 1 No 1 No 20000.00
sound
suitable for the 320KVAupDG
level up to 75 dB to 1se
Mtr distance and as per CPCB
complete as directed and as per
norms etc as
the norms perallfollowing
with required hard
specifications
ware materialsmentioned
complete. below.

IIIT-HYD ELEC-Data 81 of 354


S.N
SSR No Description Qty Unit Rate
o
104 U.G Cables
a) ELEC- 781 Supply of 16 Sqmm 4 Core RMS 1 1 One 154.00
4.1.1 XLPE insulated, 1100V grade Rmt
armoured alluminium cable as
per specification confirming to
IS:7098 Rate per Meter
Makes : Torrent
b) ELEC-4.1.8 Supply of 35 Sqmm / Universal
3.5 Core/ RMS 1 1 One 235.00
Unicab / Polycab1100V
XLPE insulated, / Havells /
grade Rmt
Gloster / KEI.
armoured alluminium cable as
per specification confirming to
IS:7098
Makes : Torrent / Universal /
Unicab / Polycab Rate per Meter
/ Havells /
c) ELEC-4.1.9 Supply
Gloster of 50 Sqmm 3.5 Core
/ KEI. RMS 1 1 One 310.00
XLPE insulated, 1100V grade Rmt
armoured alluminium cable as
per specification confirming to
IS:7098
Makes : Torrent / Universal /
Unicab / Polycab Rate per Meter
/ Havells /
d) ELEC-4.1.10 Supply of 70
Gloster / KEI.Sqmm 3.5 Core RMS 1 1 One 401.00
XLPE insulated, 1100V grade Rmt
armoured alluminium cable as
per specification confirming to
IS:7098
Makes : Torrent / Universal /
Unicab / Polycab / Havells /
Gloster / KEI.

Rate per Meter


e) ELEC-4.1.12 Supply of 120 Sqmm 3.5 Core RMS 1 1 One 637.00
XLPE insulated, 1100V grade Rmt
armoured alluminium cable as
per specification confirming to
IS:7098
Makes : Torrent / Universal /
Unicab / Polycab Rate per Meter
/ Havells /
f) ELEC-4.1.14 Supply
Gloster of 185 Sqmm 3.5 Core
/ KEI. RMS 1 1 One 889.00
XLPE insulated, 1100V grade Rmt
armoured alluminium cable as
per specification confirming to
IS:7098
Makes : Torrent / Universal /
Unicab / Polycab Rate per Meter
/ Havells /
g) ELEC-4.1.15 Supply of 240
Gloster / KEI. Sqmm 3.5 Core RMS 1 1 One 1128.00
XLPE insulated, 1100V grade Rmt
armoured alluminium cable as
per specification confirming to
IS:7098
Makes : Torrent / Universal /
Unicab / Polycab Rate
/ Havells /
per Meter
Gloster / KEI.

IIIT-HYD ELEC-Data 82 of 354


S.N
SSR No Description Qty Unit Rate
o
h) ELEC-4.1.16 Supply of 300 Sqmm 3.5 Core RMS 1 1 One 1378.00
XLPE insulated, 1100V grade Rmt
armoured alluminium cable as
per specification confirming to
IS:7098
Makes : Torrent /Rate
Universal /
per Meter
Unicab / Polycab / Havells /
Gloster / KEI.
105 Earth work excavation of Trench in hard ground soil and Sand filling shall be provided
bottom of trench before laying the cable and laying of U.G cables from 95 Sqmm up t
sqmm covering the cable with bricks and back filling of Trench duly providing route in
at every 8 Mtrs distance embedded in C.C including cost and conveyance of materia
b) Labour
labour charges
charges etc., complete.
1 Skilled Electrician. 1.60 day 1 day 540.00
3 Helper (Electrical). 3.30 day 1 day 450.00
5 Man Mazdoor for spreading the 2.50 day 1 day 425.00
sand and back filling of the
exacavated soils.
5 Man Mazdoor for concreating 2.10 day 1 day 425.00
and embedding of cable route
indicators.
Labour Charges for 100 Mtrs
Labour Charges for 1 Mtr
a) Material
ELEC- Earth work excacvation 36.00 Cum 1 Cum 250.00
9.1.50
ELEC- Cost of Sand. 4.00 Cum 1 Cum 600.00
9.1.51
ELEC- Cost of Bricks. 1000.00 Nos 952 Nos 4000.00
9.1.52
ELEC- Cement. 25.00 Kg 1 Kg 8.00
9.1.48
ELEC- Cable root Indicators. 12.00 Nos 1 Nos 88.00
9.1.23
Cost of Material for laying of 100.00 Mtrs
cable in trench for
Cost of Material for laying of 1.00 Mtrs
cable in trench for
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

106 Earth work excavation of Trench in hard ground soil and Sand filling shall be provided
bottom of trench before laying the cable and laying of U.G cables up to 70 sqmm cov
the cable with back filling of Trench duly providing route indicator embedded in C.C
including cost and conveyance of materials and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 1.00 day 1 day 540.00

IIIT-HYD ELEC-Data 83 of 354


S.N
SSR No Description Qty Unit Rate
o
3 Helper (Electrical). 2.00 day 1 day 450.00
5 Man Mazdoor for spreading the 2.50 day 1 day 425.00
sand and back filling of the
exacavated soils.
5 Man Mazdoor for concreating 2.10 day 1 day 425.00
and embedding of cable route
indicators.
Labour Charges for 100 Mtrs
Labour Charges for 1 Mtr

IIIT-HYD ELEC-Data 84 of 354


S.N
SSR No Description Qty Unit Rate
o
a) Material
ELEC- Earth work excacvation 36.00 Cum 1 Cum 250.00
9.1.50 including all soils for trench,
ELEC- Cost of Sand. 4.00 Cum 1 Cum 600.00
9.1.51
ELEC- Cost of Bricks. 1000.00 Nos 952 Nos 4000.00
9.1.52
ELEC- Cement. 25.00 Kg 1 Kg 8.00
9.1.48
ELEC- Cable root Indicators. 12.00 Nos 1 Nos 88.00
9.1.23
Cost of Material for laying of 100.00 Mtrs
cable in trench for
Cost of Material for laying of 1.00 Mtrs
cable in trench for
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

107 Laying of PVC armoured under ground cable from 95 Sq.mm to 400 Sqmm fixing on
chromium plated metallic base saddles on wall as per IS 1255 and as directed by the
department including cost and conveyance of all materials and labour charges etc.,
complete.
b) Labour charges
1 Skilled Electrician. 1.50 day 1 day 540.00
3 Helper (Electrical). 2.30 day 1 day 450.00
Labour Charges for 100 Mtrs
Labour Charges for 1 Mtr
a) Material
ELEC- Rawl Plugs. 4.00 Nos 100 Nos 31.00
9.1.2
ELEC- 147 Supply of No.8 Screws of 4.00 Nos 100 Nos 138.00
1.4.4 63/75mm.
ELEC- Supply of Saddle / Clamps 2.00 Nos 100 Nos 534.00
9.1.67 suitable for fixing 3.5 Core 70 &
95 Sqmm Cable.

Total Cost of Material +


Labour Charges
Add Contractors Profit ###

Rate per Meter

IIIT-HYD ELEC-Data 85 of 354


S.N
SSR No Description Qty Unit Rate
o
108 Laying of PVC armoured under ground cable up to 70 Sqmm fixing on chromium plat
metallic base saddles on wall as per IS 1255 and as directed by the department inclu
cost and conveyance of all materials and labour charges etc., complete.

b) Labour charges
1 Skilled Electrician. 1.50 day 1 day 540.00
3 Helper (Electrical). 2.30 day 1 day 450.00
Labour Charges for 100 Mtrs
Labour Charges for 1 Mtr
a) Material
ELEC- Rawl Plugs. 4.00 Nos 100 Nos 31.00
9.1.2
ELEC- Supply of No.8 Screws of 4.00 Nos 100 Nos 101.00
1.4.23 35/38mm.
ELEC- Supply of Saddle / Clamps 2.00 Nos 100 Nos 534.00
9.1.66 suitable for fixing 3.5 Core 50
Sqmm Cable.
Cost of Material for Laying on 1.00 Mtr
wall for
Total Cost of Material +
Labour Charges
Add Contractors Profit ###

Rate per Meter

109 Cable Terminations:


a) Termination of UG cables of 4 core 10 sq.mm & 4 core 16 sq.mm including with requi
cable glands, Lugs complete with all required accessories as directed by the departm
including cost and conveyance of all materials and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.027 day 1 day 540.00
2 Lineman Electric / Telephone 0.020 day 1 day 450.00
3 Helper (Electrical). 0.020 day 1 day 450.00
Labour Charges for each
a) Material
ELEC- Glands for 4 core XLPE 1.00 Nos 1 Nos 94.00
4.3.5 armoured cable up to 16.0
Sq.mm
ELEC- aluminium lugs for cable upto 4.00 Nos 1 Nos 12.00
4.4.13 16 Sq.mm

Total Cost of Material +


Labour Charges
Add Contractors Profit ###

Rate per Each

IIIT-HYD ELEC-Data 86 of 354


S.N
SSR No Description Qty Unit Rate
o
b) Termination of UG cables of 3.5 core 35 Sq.mm including with required cable glands,
complete with all required accessories as directed by the department including cost a
conveyance of all materials and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.027 day 1 day 540.00
2 Lineman Electric / Telephone 0.020 day 1 day 450.00
3 Helper (Electrical). 0.020 day 1 day 450.00
Labour Charges for each
a) Material
ELEC- glands for 3.5 core XLPE 1.00 Nos 1 Nos 138.00
4.3.6 armoured cable from 25 Sqmm
to 50.0 Sq.mm
ELEC- aluminium lugs for cable upto 1.00 Nos 1 Nos 12.00
4.4.13 16 Sq.mm
ELEC- aluminium lugs for cable of 35 3.00 Nos 1 Nos 17.00
4.4.15 Sq.mm

Total Cost of Material +


Labour Charges
Add Contractors Profit ###

Rate per Each

c) Termination of UG cables of 3.5 core 50 Sq.mm including with required cable glands,
complete with all required accessories as directed by the department including cost a
conveyance of all materials and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.020 day 1 day 540.00
2 Lineman Electric / Telephone 0.020 day 1 day 450.00
3 Helper (Electrical). 0.028 day 1 day 450.00
Labour Charges for each
a) Material
ELEC- glands for 3.5 core XLPE 1.00 Nos 1 Nos 138.00
4.3.6 armoured cable from 25 Sqmm
to 50.0 Sq.mm
ELEC- aluminium lugs for cable of 25 1.00 Nos 1 Nos 14.00
4.4.14 Sq.mm
ELEC- aluminium lugs for cable of 50 3.00 Nos 1 Nos 20.00
4.4.16 Sq.mm

Total Cost of Material +


Labour Charges
Add Contractors Profit ###

Rate per Each

IIIT-HYD ELEC-Data 87 of 354


S.N
SSR No Description Qty Unit Rate
o
d) Termination of UG cables of 3.5 core 70 Sq.mm including with required cable glands,
complete with all required accessories as directed by the department including cost a
conveyance of all materials and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.020 day 1 day 540.00
2 Lineman Electric / Telephone 0.020 day 1 day 450.00
3 Helper (Electrical). 0.030 day 1 day 450.00
Labour Charges for each
a) Material
ELEC- glands for 3.5 core XLPE 1.00 Nos 1 Nos 264.00
4.3.7 armoured cable from 70 Sqmm
to 150.0 Sq.mm
ELEC- aluminium lugs for cable of 35 1.00 Nos 1 Nos 17.00
4.4.15 Sq.mm
ELEC- aluminium lugs confirming to I.S 3.00 Nos 1 Nos 25.00
4.4.17 specifications for cable of 70
Sq.mm

Total Cost of Material +


Labour Charges
Add Contractors Profit ###

Rate per Each

e) Termination of UG cables of 3.5 core 120 Sq.mm including with required cable glands
complete with all required accessories as directed by the department including cost a
conveyance of all materials and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.030 day 1 day 540.00
2 Lineman Electric / Telephone 0.030 day 1 day 450.00
3 Helper (Electrical). 0.040 day 1 day 450.00
Labour Charges for each
a) Material
ELEC- glands for 3.5 core XLPE 1.00 Nos 1 Nos 264.00
4.3.7 armoured cable from 70 Sqmm
to 150.0 Sq.mm
ELEC- aluminium lugs for cable of 70 1.00 Nos 1 Nos 25.00
4.4.17 Sq.mm
ELEC- aluminium lugs for cable of 120 3.00 Nos 1 Nos 35.00
4.4.19 Sq.mm

Total Cost of Material +


Labour Charges
Add Contractors Profit ###

Rate per Each

IIIT-HYD ELEC-Data 88 of 354


S.N
SSR No Description Qty Unit Rate
o
g) Termination of UG cables of 3.5 core 185 Sq.mm including with required cable glands
complete with all required accessories as directed by the department including cost a
conveyance of all materials and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.060 day 1 day 540.00
2 Lineman Electric / Telephone 0.060 day 1 day 450.00
3 Helper (Electrical). 0.072 day 1 day 450.00
Labour Charges for each
a) Material
ELEC- glands for 3.5 core XLPE 1.00 Nos 1 Nos 491.00
4.3.2 armoured cable for 240Sqmm

4.4.18EL aluminium lugs confirming to I.S 1.00 Nos 1 Nos 27.00


EC- specifications for cable of 95
Sq.mm.
ELEC- aluminium lugs confirming to I.S 3.00 Nos 1 Nos 46.00
4.4.21 specifications for cable of 185
Sq.mm

Total Cost of Material +


Labour Charges
Add Contractors Profit ###

Rate per Each

f) Termination of UG cables of 3.5 core 240 Sq.mm including with required cable glands
complete with all required accessories as directed by the department including cost a
conveyance of all materials and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.11 day 1 day 540.00
2 Lineman Electric / Telephone 0.10 day 1 day 450.00
3 Helper (Electrical). 0.10 day 1 day 450.00
Labour Charges for each
a) Material
ELEC- glands for 3.5 core XLPE 1.00 Nos 1 Nos 491.00
4.3.2 armoured cable for 240Sqmm

ELEC- aluminium lugs for cable of 120 1.00 Nos 1 Nos 35.00
4.4.19 Sq.mm
ELEC- aluminium lugs for cable of 240 3.00 Nos 1 Nos 71.00
4.4.22 Sq.mm

Total Cost of Material +


Labour Charges
Add Contractors Profit ###

Rate per Each

IIIT-HYD ELEC-Data 89 of 354


S.N
SSR No Description Qty Unit Rate
o

IIIT-HYD ELEC-Data 90 of 354


S.N
SSR No Description Qty Unit Rate
o
h) Termination of UG cables of 3.5 core 300 Sq.mm including with required cable glands
complete with all required accessories as directed by the department including cost a
conveyance of all materials and labour charges etc., complete.
b) Labour charges
1 Skilled Electrician. 0.12 day 1 day 540.00
2 Lineman Electric / Telephone 0.10 day 1 day 450.00
3 Helper (Electrical). 0.10 day 1 day 450.00
Labour Charges for each
a) Material
ELEC- glands for 3.5 core XLPE 1.00 Nos 1 Nos 578.00
4.3.3 armoured cable for 300Sqmm

ELEC- aluminium lugs for cable of 150 1.00 Nos 1 Nos 40.00
4.4.20 Sq.mm
ELEC- aluminium lugs for cable of 300 3.00 Nos 1 Nos 92.00
4.4.23 Sq.mm

Total Cost of Material +


Labour Charges
Add Contractors Profit ###

Rate per Each

110 ELEC- Supply and Installation of 1.00 Mtr 1 Mtr 725.00


4.9.4 300mm x 50mm x 2mm thick GI
perforated cable tray with out
cover along with required angle
supports, with coupler plates,
Anchor bolts and nuts etc
complete and the tray should be
fitted on the wall / Ceiling etc.
complete.

Deduct towards less for cover at 30%


30 % on original cost
507.50
Add Contractors Profit ### 69.10
576.60
Sundries 4.00
Hence Rate allowed 581.00

111 ELEC - Supply , fabrication and transportation of MS channel iron/ angle iron /flats includin
9.1.25 coats of alluminium paint and one coat of red oxide paint including all labour charges
Mild Steel Items
complete. 1.00 Kg 1 Kg 61.00
Labour charges for fabricating
steel works TBSC-T.I-16 1.00 Kg 1 Kg 24.00

IIIT-HYD ELEC-Data 91 of 354


S.N
SSR No Description Qty Unit Rate
o
TOTAL
Add Contractors Profit 0.000% 0.00
85.00
Hence Rate allowed 85.00

112 8.1.31 Supply of Rubber hand gloves Nos 1 1 EACH 154.00


suitable for 11 KV.
113 ELEC- Supply and fixing of PVC Nos 1 1 EACH 4200.00
9.1.73 synthetic elastomer electrically
insulated mat with Class B
insulation conforming to IS:
15652-2006 having 2.5mm
114 ELEC- thickness &
Providing upto 11KV.
Fixing of Shock Nos 1 1 EACH 500.00
9.1.33 instrution chart in English / Hindi
/ Telugu duly framed with front
glass.
115 ELEC- Providing & Fixing of Danger Nos 1 1 EACH 250.00
9.1.32 Notice Plates of size
250x200mm, shall comply with
IS:2551-1982.
116 (ELEC- Providing floor mounting stand Nos 1 1 EACH 1200.00
9.1.76) for keeping 4No of fire bucket
1500mm length, 900mm height
made out of 40x40x6mm angle
iron welded with 4 hooks and
duly painted with one coat of red
117 (ELEC- Providing & Supply
lead and two of enamel
coats of round Nos 1 1 EACH 300.00
9.1.75) bottom
paint. G.I sheet bucket of 9
Ltrs. Capacity as per IS:2546
made out of 24 gauge GI sheet
with extra handle at bottom duly
painted inside and red out side
with printed with FIRE Mark for
stand and hook and filled with
118 (ELEC- First Aid box 18" x 12" x 8" Nos 1 1 EACH 1100.00
sand and arranged to existing
9.1.30) containing material as
stand or hook.
prescribed by St. John
Ambulance brigade OR Indian
119 AR Red Cross complete
Preparation of Drawingsas of Nos 1 1 EACH 40000.00
required.
existing or new installations and
obtaining approval from the
CEIG complete as per the
120 requirement
Supply at site.(AR) of Outer dia 63mm and Inner dia 51mm double walled
and Transportation
corrugated HDPE duct made as per specification BSEN - 500 86/IS 14930 Part-II etc.
complete by making trench in all soils up to 0.90Mtr deep and back filling the exacava
earth without stones and making the surface proper with 15cm crown on the top and
directed by the department including cost and conveyance of all materials and labour
Makes:DURA
charges LINE (Dura Guard) or its equivalent
etc., complete.
b) Labour charges
1 Skilled Electrician. 1.00 No 1 No 540.00
3 Helper (Electrical). 3.30 day 1 day 450.00

IIIT-HYD ELEC-Data 92 of 354


S.N
SSR No Description Qty Unit Rate
o
5 Man Mazdoor for spreading the 2.50 day 1 day 425.00
sand and back filling of the
exacavated soils.
Labour Charges for 60 Mtrs
Labour Charges for 1 Mtr
a) Material
4 Earth work excacvation 41.50 Cum 1 Cum 220.00
including all soils for trench,
Pole Pit and Earth Pit. (SOR-
2015-16-TBSE-8.1.51)
Cost of Material for 100 Mtrs
Cost of Material for 1 Mtr
Supply and Transportation of
Outer dia 63mm and Inner dia
51mm double walled corrugated
HDPE duct made as per
specification BSEN - 500 86/IS
14930 Part-II with all
accessories like couplers,
bends, end caps, Ts etc.,
complete.(ELEC-4.8.2)

5 Makes:DURA LINE (Dura 1.00 Mtr 1 Mtrs 124.00


Guard) or its equivalent make.
Cost of Material for 1 Mtr
Total Cost of Material + 266.00
Labour Charges
Add Contractors Profit 13.62%

Hence Rate allowed


121 9.1.56 40mm Nominal Bore Medium RMS 1 1 One 381.00
grade G.I.pipe (ELEC-9.1.56) Rm
122 Supply and fixing of 8 Way VTPN DB of Makes : Legrand / Shneider suitable for
accomodating 125A / 160A 4 Pole MCCB as incomer with IP 43 Protection as per IS:
with 1 No 125A 3 Pole MCCB, Adjustable, Confirms to IS/IEC 60947-2 having Break
Capacity 25 KA with thermal magnetic release Panel Mounted of Makes : L&T / Schn
Siemens / Legrand as incomer and 8 Nos 63A TP MCB C/D Curve 10KA ISI Mark of
: Legrand-DX3 / Shneider-Acti9 as out goings including internal connections and labo
charges
MATERIALfor SURFACE / FLUSH Mounting etc., complete.
Supply of 8 Way VTPN DB
suitable for accomodating
125A / 160A 4 Pole MCCB as
incomer and 8 Nos TP MCBs as
outgoing and with IP 43
Makes : Legrand / Shneider. 1 Nos 1 No 9823.00
Protection . (SOR-2015-16-
Supply of 40-63A 10KA TP
TBSE-2.12.13)
MCB, C/D Curve ISI Mark.
(SOR-2015-16-TBSE-2.9.6)
Makes : Legrand-DX3 / 8 Nos 1 No 1477.00
Shneider-Acti9.

IIIT-HYD ELEC-Data 93 of 354


S.N
SSR No Description Qty Unit Rate
o
Supply of 125A 4 Pole MCCB,
Adjustable, Confirms to IS/IEC
60947-2 having Breaking
Capacity 25 KA with thermal
magnetic: L&T
Makes release Panel/
/ Schneider 1 Nos 1 No 8700.00
Mounted.
Siemens (SOR-2015-16-TBSE-
COST OF/ Legrand.
MATERIAL
2.8.4)
LABOUR
1 Skilled Electrician. 1.75 day 1 day 500.00
3 Helper (Electrical). 1.50 day 1 day 400.00
2 Lineman Electric / Telephone 1.50 day 1 day 400.00
COST OF LABOUR FOR
SURFACE MOUNTING
4 Mason Cl- I / Brick layer Cl- I 1.20 day 1 day 415.00
COST OF LABOUR FOR
FULSH MOUNTING
TOTAL COST OF MATERIAL + SURFACE 32414.00
LABOUR FOR SURFACE
MOUNTING
Add Contractors Profit 13.62%

Hence Rate allowed


Airconditioners
123 Supply, transportation and installation of split AC unit with high wall mounted indoor u
and outdoor condencing unit Hermetically sealed compressor suitable for operation o
230V, 50Hz, 1Phase AC supply capable of performing cooling dehumidifying air circu
and filtering with cooling and condensing units with 3.5 mts of copper piping, insulatio
and 4 mts of 3 core copper flexible chord , built-in stabilizer (Voltage range 160- 264 v
( 1.5 TR
and cordless 3 STAR)
remote control
a) a) 1.5 Ton ( 3 STAR)
Make: Daikin FTE-M or N
Sereis / Carrier Novello / Blue
Star 3HW18VB1 / Hitachi
(Kazi+) / Voltas 183 PX-R.

6.1.1 b) 1.5 Ton ( 3 star rates) 1 Nos 1 Each 39600


6.6.28 Installation charges
Transportation @ 2%
LS for Hard ware etc.,
Rate per each
Add Contractors Profit ###

Hence Rate allowed


( 2.0 TR 3 STAR)
b) a) 2.0 Ton ( 3 STAR)
Make: Daikin FTC60QRV16 or
its equivalent make of
Carrier / Blue Star

IIIT-HYD ELEC-Data 94 of 354


S.N
SSR No Description Qty Unit Rate
o
6.1.1 e) 2.0 Ton ( 3 star rates) 1 Nos 1 Each 50250
6.6.28 Installation charges
Transportation @ 2%
LS for Hard ware etc.,
Rate per each
Add Contractors Profit ###

Hence Rate allowed


Rate per Each

Ductable AC Units
124 MR Supply , testing , errection and
commisioning of 11.00 TR
Ductable Split Air conditioner
unit Make : Blue Star / Diakin /
Hitachi including intial gas filling
with R-22 including
transportation and shifting of
machines to fourth floor etc
complete.

(as per Carrier make Quotation 1 No 1 Each ###


from M/s I-Cool air conditioning
india Pvt Ltd,, Hyderabad,
dated: 08.12.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

Or say
125 MR Supply , fabrication and
installation of GI sheet ducting
24 Guage with proper supports
fromper
(as slabCarrier make Quotation 1 SQM 1 One 682.00
from M/s I-Cool air conditioning SQM
india Pvt Ltd,, Hyderabad,
dated: 08.12.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

Or say

IIIT-HYD ELEC-Data 95 of 354


S.N
SSR No Description Qty Unit Rate
o
126 MR Supply , fabrication and
installation of GI sheet ducting
22 Guage with proper supports
from slab
(as per Carrier make Quotation 1 SQM 1 One 907.50
from M/s I-Cool air conditioning SQM
india Pvt Ltd,, Hyderabad,
dated: 08.12.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

Or say

127 MR Supply and installation of


canvass connection at the out
let
(asofper
theCarrier
indoor units.
make Quotation 1 Nos 1 EACH 4180.00
from M/s I-Cool air conditioning
india Pvt Ltd,, Hyderabad,
dated: 08.12.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

Or say

128 MR Supply and fixing of Alluminium


power coated Air grills ( Supply
and return ) with volume control
dampers including all labour
chrages etc complete.
(as per Carrier make Quotation 1 Sqmtr 1 Sqmtr 11275.00
from M/s I-Cool air conditioning
india Pvt Ltd,, Hyderabad,
dated: 08.12.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

Or say

129 MR Acoustic insulation with 12mm


rigid board with RP tissue paper
coverd with alluiminuem
perforated sheet.
IIIT-HYD ELEC-Data 96 of 354
S.N
SSR No Description Qty Unit Rate
o
(as per Carrier make Quotation 1 SqMtrs 1 1 Sqm 655.00
from M/s I-Cool air conditioning
india Pvt Ltd,, Hyderabad,
dated: 08.12.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

Or say

130 MR Supply and fixing of Thermal


insulation with 25mm thick fibre
glass covered with Alluminimu
foil.
(as per Carrier make Quotation 1 SqMtrs 1 1 Sqm 538.00
from M/s I-Cool air conditioning
india Pvt Ltd,, Hyderabad,
dated: 08.12.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

Or say

131 MR Supply and  installation  of


copper refrigerant piping of size
5/8" as per the manufacurer
directions. and thickness duly
insulated with nitrile insulation
suitable
(as per above
Carrierductable Split AC 1
make Quotation Rms 1 1 RM 682.00
unit (AR)
from M/s I-Cool air conditioning
india Pvt Ltd,, Hyderabad,
dated: 08.12.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

Or say

132 MR Supply and  installation  of


copper refrigerant piping of size
7/8" as per the manufacurer
directions. and thickness duly
insulated with nitrile insulation
suitable above ductable Split AC
IIIT-HYD unit (AR) ELEC-Data 97 of 354
S.N
SSR No Description Qty Unit Rate
o
(as per Carrier make Quotation 1 Rms 1 1 RM 864.00
from M/s I-Cool air conditioning
india Pvt Ltd,, Hyderabad,
dated: 08.12.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

Or say

133 MR Supply   & installation of PVC


drain piping with suitable
supports as required & insulated
with 6mm thick nitrile rubber
insulation (AR)
(as per Carrier make Quotation 1 Rms 1 1 RM 98.00
from M/s I-Cool air conditioning
india Pvt Ltd,, Hyderabad,
dated: 08.12.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

Or say
134 a) Supply and run of one of 3 Core 1.5 Sqmm Flat Copper cable as per IS 694:1990 for
Submersible Motors of makes Polycab / GM / Million / V-Guard / Gold Medal /RPG /H
Finolex/
a) LabourRR cable
charges
1 Skilled Electrician. 0.34 day 1 day 515.00
2 Lineman Electric / Telephone 1.00 day 1 day 400.00
3 Helper (Electrical). 0.50 day 1 day 400.00
Labour for 100 Mtr
Labour for 1 Mtr
Supply of 3 Core 1.5 Sqmm Flat 1.00 Mtrs 100 Mtrs 5430.00
Copper cable as per IS
694:1990 for Submersible
Motors of makes Polycab / GM /
Million / V-Guard / Gold
Medal /RPG /Havells/ Finolex/
RR cable. (SoR-2016-17-ELEC-
1.6.9)

Cost of Material for fixing


luminaire
Cost of Material for 1 No

IIIT-HYD ELEC-Data 98 of 354


S.N
SSR No Description Qty Unit Rate
o
Total Cost of Material + 62.05
Labour Charges
Add Contractors Profit 13.62%

Hence Rate allowed

b) Supply and run of one of 3 Core 4.0 Sqmm Flat Copper cable as per IS 694:1990 for
Submersible Motors of makes Polycab / GM / Million / V-Guard / Gold Medal /RPG /H
Finolex/
a) LabourRR cable
charges
1 Skilled Electrician. 0.34 day 1 day 515.00
2 Lineman Electric / Telephone 1.00 day 1 day 400.00
3 Helper (Electrical). 0.60 day 1 day 400.00
Labour for 100 Mtr
Labour for 1 Mtr
Supply of 3 Core 4.00 Sqmm 1.00 Mtrs 100 Mtrs 12510.00
Flat Copper cable as per IS
694:1990 for Submersible
Motors of makes Polycab / GM /
Million / V-Guard / Gold
Medal
Cost of /RPG /Havells/forFinolex/
Material fixing
RR cable.
luminaire (SoR-2016-17-ELEC-
1.6.11)
Cost of Material for 1 No
Total Cost of Material +
Labour Charges
Add Contractors Profit 13.62%

Hence Rate allowed Or say

135 Supply , fabrication and transportation of MS channel iron/ angle iron /flats includin
coats of alluminium paint and one coat of red oxide paint including all labour charges
Mild Steel Items
complete. 1.00 Kg 1 Kg 61.00
Labour charges for fabricating
steel works TBSC-T.I-16 1.00 Kg 1 Kg 24.00

TOTAL
Add Contractors Profit ### 11.57
96.57
Hence Rate allowed 97.00

IIIT-HYD ELEC-Data 99 of 354


S.N
SSR No Description Qty Unit Rate
o
136 MR Supply and fixing of fresh air
duct provision with wire mesh
and volume control.
(as per Quotation from M/s I- 1 No 1 Each 2057.00
Cool air conditioning india Pvt
Ltd,, Hyderabad, dated:
27.11.2016)
Add Excise Duty (The above 0.00%
price is Inclusive)

Add VAT 14.50%

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

OR SAY

137 MR Provding of scaffolding up to 4th


floor for errection of out door
units.3
(as per Quotation from M/s I- 1 No 1 Each 9345.00
Cool air conditioning india Pvt
Ltd,, Hyderabad, dated:
27.11.2016)

Labor and commissioning 5%


charges @ 5 % on basic price
Transportation charges @ 2 % on 2%

OR SAY

138 Supply and fixing of IRDome


20mtr range 2.0 megapixel IP
Cameras as per detailed
specification in the annexure.
(MR)
Make:CP pluse

(as per Quotation from 1 No 1 Each 2657.00


M/sEYECATCH
TECHNOLOGIES, Hyderabad,
dated:09.11.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

IIIT-HYD ELEC-Data 100 of 354


S.N
SSR No Description Qty Unit Rate
o
Transportation charges @ 2 % on 2%

OR SAY

139 Supply and fixing of IR BULLET


20mtr range 2.0 megapixel IP
Cameras as per detailed
specification in the annexure.
(MR)
Make:CP pluse

(as per Quotation from 1 No 1 Each 3795.00


M/sEYECATCH
TECHNOLOGIES, Hyderabad,
dated:09.11.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

OR SAY

140 Supply and fixing of 8 Channel


DVR 1080P IP cameras inputs
as per detailed specification in
the annexure. Make:CP pluse

(as per Quotation from 1 No 1 Each 8300.00


M/sEYECATCH
TECHNOLOGIES, Hyderabad,
dated:09.11.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

OR SAY

141 Supply and fixing of 16 Channel


DVR 1080P IP cameras inputs
as per detailed specification in
the annexure. Make:CP pluse

IIIT-HYD ELEC-Data 101 of 354


S.N
SSR No Description Qty Unit Rate
o
(as per Quotation from 1 No 1 Each 14750.00
M/sEYECATCH
TECHNOLOGIES, Hyderabad,
dated:09.11.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

OR SAY
142 Supply and fixing of 4-TB
Surveillance Disk as per detailed
specification in the annexure.
(MR) Make: Toshiba

(as per Quotation from 1 No 1 Each 15500.00


M/sEYECATCH
TECHNOLOGIES, Hyderabad,
dated:09.11.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

OR SAY

143 Supply and fixing of 32" LED


Monitor, as per detailed
specification in the annexure.
(MR) Make: DELL/LG.

(as per Quotation from 1 No 1 Each 16095.00


M/sEYECATCH
TECHNOLOGIES, Hyderabad,
dated:09.11.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

OR SAY

IIIT-HYD ELEC-Data 102 of 354


S.N
SSR No Description Qty Unit Rate
o
144 Supply and fixing of 8 Port
Switch as per detailed
specification in the annexure.
(MR) Make:Netgear
(as per Quotation from 1 No 1 Each 6300.00
M/sEYECATCH
TECHNOLOGIES, Hyderabad,
dated:09.11.2018)

5%
Installation and commissioning
charges @ 5 % on basic price

Transportation charges @ 2 % on 2%

OR SAY

145 (ELEC- Fabrication, Transportation and Nos 1 1 EACH 10647.00


7.2.1) supply of hot-dip galvanized
Octagonal Pole with BSEN -
10025 grade S 355 JO steel
plate for shaft, IS 2062 for base
plate with door opening
arrangement, including the
supply of suitable boards with
Bakelite sheet and MCB's as per
IS specification suitable to
withstand the wind speed of 180
KMPH for 7.50 Mtrs height Pole
146 (ELEC- having dimensions
Fabrication, Bottom and
transportation 130 Nos 1 1 EACH ###
7.4.1) mm,. Top
supply 70mm
of 12 Mtrswith 3mmHigh
Polygon thick,
base plate
Mast 220 x section
with single 220 x 12mm
of 3mm
and 4ofNos
thick of M20
Bottom x 700 and
360mm longTop
'J'
bolts along
150mm dia with
with template of
BSEN - 10025
Makes:SBajaj
grade 355 JO / Valmont / for
steel plate
TRANSRAIL.
shaft, IS 2062 for base plate,
having a base plate of size
520mm dia 16mm thick with its
accessories. Mast shall be in
single section for 12 Mtrs and 2
sections for 16 and 20 Mtrs.
Mast shall be hot dip galvanized
and suiatble for wind velocity of
180 KMPH as per IS 875 part 3
including head frame, 2 point
suspension system with steel
rope 6mm dia (7/19)
construction double drum
winch / power tool operating
speed of 900 RPM, and
necessary cable trailer
connections and single speed
motor with M 24 x 800 mm
foundation bolts of required
IIIT-HYD quantity, suitable for 6 ELEC-Data 103 of 354
S.N
SSR No Description Qty Unit Rate
o
147 (ELEC- Fabrication, Transportation and Nos 1 1 EACH 4500.00
7.3.4) supply of of 1.5mtrs sword type
decorative Single arm bracket
with dooms complete with all
accessories with MS galvanized
50mm dia Pipe.
148 (ELEC- Fabrication, Transportation and Nos 1 1 EACH 4950.00
7.3.7) supply of of 1.5mtrs sword type
decorative double arm bracket
with dooms either sides
complete with all accessories
with MS galvanized 50mm dia
149 (ELEC- Foundation
Pipe. and erection Nos 1 1 EACH 4500.00
7.9.2) charges with special T&P, for
7.50 Mtrs long Octagonal /
Conical pole duly erecting on
base plate duly providing 4 Nos
foundation bolts with nuts with
providing of 0.45Mtr x0.45 Mtrs
x 1.20 Mtr size M20 cc work
vibrated concreting mixing with
necessary steel (10kgs)
reinforcement as directed by the
field engineers during execution
including all labour charges and
150 (ELEC- cost and exacavation
Earth work conveyancewith ofa Nos 1 1 EACH 28073.00
7.6.1) materials etc. complete.
approximate quantity of 4.0 Cum
for errection of 12 Mtrs high
mast and refilling with a quantity
of 0.53 Cum of PCC 1:4:8, 1.50
Cum M 20 grade concrete and
(80 Kgs) reinforced steel of
12mm / 10mm / 8mm, Soil
bearing capacity of 10 T/Sqm,
Anchor plate with cost and
conveyance of all above
materials including labour
151 (ELEC- Supply
charges and fixing of of
for errection suitable
High Nos 1 1 EACH 28884.00
7.5.1) feeder
Mast andpillar box made
Carraige with 14
etc complete.
SWG CRCA sheet including S &
F of Legrand / Schnieder /
Siemens / ABB / L&T make 40A
TP MCB, 6 Nos SP MCB's, din
channel, 6 Sqmm 3 core copper
cable for individual light control,
contactor, connectors and
provision for energy meter etc.,
complete for finished item of
work.(for High mast light control)

IIIT-HYD ELEC-Data 104 of 354


S.N
SSR No Description Qty Unit Rate
o
152 Supply and fixing of suitable out
door feeder piller box of size 3'
x 2' x 1' made with 14 SWG
CRCA sheet with double door
arrangement, making powder
coating after processing of 7
Tank process, lock and key,
hinges, rubber gasket, danger
board,suitable angle iron stand
for mounting the feeder pillar
with cement concrete, including
Supply and fixing of Legrand /
Schnieder make 63A, 4 Pole
isolator as incomer, 6 Nos 6-
32A SP MCBs as out goings.
indication lamps, din channel, 6
Sqmm 3 core copper cable for
invidual light control,
connectors, gland plates and
provision for 3 phase energy
meter etc., complete for finished
Fabrication: L H D Nos
item
Size of of panel
work and suitable wiring
: in Mtr 0.90 0.60 0.30
provision for connecting the
Front
natureand backwith
switch facesfollowing.(for 0.90 1.80 2
Top
streetand bottom
light faces
control) (ELEC-7.5.1 0.90 0.30 0.54 2
Side
b (ii))faces 0.60 0.30 0.36 2
Sub total 2.70
Add extra 10 % for wastage 0.27
Total 2.97
a ELEC- Fabrication and erection of 14 / 2.97 Sqmtr 1 Sqmtr 4030.00
7.11.2 16 SWG CRCA sheet steel
enclosure for power control
cubicle panel / boxes etc.,
including cutting, bending
drilling, welding and reveting
etc., complete with cleaning with
7 tank process and painting with
powder coating including cost
and conveyance of all materials
and labour charges.

Incomer.
b ELEC- Supply of 63A 4 Pole 1 Nos 1 No 962.00
2.10.7 IsolatorPanel Mounted of makes
L&T / Schneider / Siemens /
Hager
Out goings
c ELEC- 6A 10KA SP MCB, C/D Curve 6 Nos 1 No 201.00
2.9.1 ISI Mark of Makes : Legrand-
DX3 / Schneider-Acti9.

IIIT-HYD ELEC-Data 105 of 354


S.N
SSR No Description Qty Unit Rate
o
g ELEC- Supply and erection of Analog 3 No 1 No 135.00
7.12.19 LED indicator lamps on the
existing box / panel board.L&T /
C&S / SALZAR / HPL MAKE.

i Bus bar arrangement with 5%


insulators
j Hard ware such as base 8%
channel etc.
k Transportation 1%
l Control wiring with flexible wires 5%
and connections to MCBs with
required lugs including
commissioning and testing etc

TOTAL COST OF MATERIAL


AND LABOUR
Or say

153 (ELEC- Supply of Automatic Street Light Nos 1 1 EACH 13100.00


3.5.3) Control System with Optical
Sensor, Low volatage / High
voltage trip and reset, operating
voltage 150 - 280V AC, 50 HZ
with suitable SMC enclousure of
IP 54 protection, MCBs and
contactor suitable to control the
load of 8 KW of single phase
load with necessary clamping
arrangements of Makes :
154 Supply and transportation & Fixing of 65W LED Street light Body made of high grade
Swadeep Nature Switch / Light
pressure die – cast Aluminum alloy with corrosion resistant powder coat, having prote
Mate. (ELEC-3.5.3)
toughened glass cover, Less Glare, IP 66 (Silicon gasket ensures Optical & Electrical
compartments are IP 66) protected, universal Voltage 100 - 270 V AC, P.F, ≥ 0.90, h
power LED's having efficacy ≥120 lumens/watt, and junction temperature < 75°C, with
Ingress protection IP66, Driver surge protection 4KV, with optics distribution Type II
medium, THD<10% at 110 Volts AC, driver efficiency ≥90%, CCT: 5600K, minimum
CRI≥80, Inbuilt Electrical protections like Over voltage, short circuit, Over load, Open
Circuit, Miswiring, Intelligent pole mounting option provides flexibility of vertical or hor
pole mounting option complete, with Top Openable Maintenance and Manufacture ha
submit LM79,LM80 & Photobiological Safety Report. Luminaire Performance Complie
IS10322 (Part 5/Sec 3) & IEC 60598-1,IEC 60529 and ISO certified company fixed on
bracket of the pole complete with required 3 runs 2.50 Sq.mm round/flat copper cable
a) Labour
leads charges
complete with connections as directed.
1 Skilled Electrician.
MAKE: 0.25 day
Phillips / OSRAM / GE / Crompton / VIN / Bajaj1/ Havells
day / HPL/Surya/Syska.
515.00
2 Lineman Electric / Telephone 0.25 day 1 day 400.00
3 Helper (Electrical). 0.25 day 1 day 400.00
Labour for 1 No
b) Material

IIIT-HYD ELEC-Data 106 of 354


S.N
SSR No Description Qty Unit Rate
o
4 Supply of 3 Core 2.5 Sqmm Flat 10.00 Mtrs 100 Mtrs 8340.00
Copper cable as per IS
694:1990 for Submersible
Motors of makes Polycab / GM /
Million / V-Guard / Gold
Medal /RPG /Havells/ Finolex/
RR cable. (SoR-2016-17-ELEC-
1.6.10)

Cost of Material for fixing


luminaire
5 Supply and transportation of 1 Nos 1 Nos 8900.00
65W LED Street light . (SoR-
2016-17-ELEC-3.9.21)
Luminaire Make : PHILIPS
(ROAD STAR) / OSRAM /
SCHREDER (VOLTANA /
TECEO) / GE / VIN (PTX /
MATRIX) / CROMPTON
(OLYMPUS+) / BAJAJ (EDGE+)
/ HALONIX (MODULAR /
LUMOS-SUPER)

Cost of Material for 1 No


Total Cost of Material + 10062.75
Labour Charges
Add 14.50%
Contra
ctors
Profit

Hence Rate allowed


155 Supply and transportation & Fixing of 120W LED Flood light Luminaire made of press
die cast aluminum housing with powder coated, having toughened glass cover,IP 65/
(Silicon gasket ensures Optical & Electrical compartments are IP 66 )protected, input
voltage range of 100 to 270 volts AC,power factor ≥ 0.90, high power LED's having ef
120 lumens/watt and junction temperature < 85 degree centigrade of IP65 with optics
harmonic distortion less than 10% at 110 Volts AC, driver efficiency ≥90% etc comple
5 years warranty fixed on the existing bracket complete with required 3 runs 2.50 Sq.
round/flat copper cable wire leads complete with connections as directed.
AKE: Phillips / OSRAM / GE / Crompton / VIN / Bajaj / Havells / HPL/Surya/Syska.
a) Labour charges
1 Skilled Electrician. 0.50 day 1 day 515.00
2 Lineman Electric / Telephone 0.50 day 1 day 400.00
3 Helper (Electrical). 0.50 day 1 day 400.00
Labour for 1 No
b) Material

IIIT-HYD ELEC-Data 107 of 354


S.N
SSR No Description Qty Unit Rate
o
4 Supply of 3 Core 2.5 Sqmm Flat 25.00 Mtrs 100 Mtrs 8340.00
Copper cable as per IS
694:1990 for Submersible
Motors of makes Polycab / GM /
Million / V-Guard / Gold
Medal /RPG /Havells/ Finolex/
RR cable. (SoR-2016-17-ELEC-
1.6.10)

Cost of Material for fixing


luminaire
5 Supply and transportation of 1 Nos 1 Nos 19970.00
120W LED Flood light Luminaire
(ELEC-3.11.4d)
Luminaire Make : PHILIPS /
GE / VIN / CROMPTON / BAJAJ
/ HALONIX
Cost of Material for 1 No
Total Cost of Material + 22712.00
Labour Charges
Add Contractors Profit 14.50%

Hence Rate allowed


(As per Quotation of Johnson)

156 (ELEC- Supply and installation of 1.00 No 1 Each 29400.00


12.1.4) 2.0KVA true on line UPS
system IGBT technology pure
sine wave out put, double
conversion with auto and
manual static by pass switch
single phase input / Single
phase output of Makes:
Servomax / Top Power / Amar
157 (ELEC- Supply and providing
Raja / Samhitha of UPS
/ Microtech / 1.00 No 1 Each 1500.00
12.2.1) cum
Excidebattery
/ Sucom.rack up to 4
batteries
158 (ELEC- Supply and fixing of 12V 100 AH 1.00 No 1 Each 9900.00
12.1.7) SMF battery including wire leads
of Makes : Quanta / Racket /
Exide.

IIIT-HYD ELEC-Data 108 of 354


Amount

art 3 regid PVC pipe


cluding masonary
di / Million Plast.

1080.00
900.00
900.00
2880.00
28.80

288.00

84.00

3000.00

3372.00
33.72
62.50

8.51
71.01
71.00

art 3 regid PVC pipe


ng masonary work

1080.00
900.00
900.00
940.00
3820.00
38.20

400.00

60.00

216.00

IIIT-HYD ELEC-Data 109 of 354


Amount
84.00

2400.00

3160.00
31.60
69.80
9.50
79.30

IIIT-HYD ELEC-Data 110 of 354


Amount
in RCC slab

98.00

24.00

74.00
10.08
84.00

ted flexible ISI mark


Power flex / GM /
fixing of Jumbo
odular box and
lo /Honeywell
ng Surface or
d all labour charges

324.00
540.00
270.00
1134.00
189.00

152.00
144.00
516.00

114.00

1482.00

2408.00
401.33

590.00

80.33
670.33
670.00

IIIT-HYD ELEC-Data 111 of 354


Amount

IIIT-HYD ELEC-Data 112 of 354


Amount
ted flexible ISI mark
Power flex / GM /
fixing of Jumbo
odular box and
lo /Honeywell
ng Surface or
d all labour charges

904.50

905.00

lated flexible copper


BH/SBH Modular
s etc., complete.

er flex / GM /

o /Honeywell
378.00
630.00
315.00
1323.00
189.00

76.00

90.00

72.00

84.00

602.00

133.00

1482.00

2539.00
362.71

IIIT-HYD ELEC-Data 113 of 354


Amount
551.00

75.02
626.02
626.00

IIIT-HYD ELEC-Data 114 of 354


Amount
ted flexible ISI mark
Power flex / GM /
fixing of Jumbo
odular box and
lo /Honeywell
ng Surface or
d all labour charges

939.00

939.00

A 1way Modular
d Arteor / Schneider
Medal Curve on a
nd all labour

36.18
30.15
66.33

76.00

72.00

86.00

132.00

366.00

432.00

58.82
490.82
491.00

IIIT-HYD ELEC-Data 115 of 354


Amount

flexible copper
et Modular type with
ing on separate

er flex / GM /

o /Honeywell
810.00
675.00
675.00
2160.00
144.00

1140.00

1080.00

1290.00

1980.00

2223.00

7713.00
514.20

658.00

0.00
658.00
658.00

6A 3/2 pin wall plug


GM Four-Five /
Verna/ Million logus
labour charges etc.,

108.00
60.30
168.30

IIIT-HYD ELEC-Data 116 of 354


Amount
160.00
161.00
258.00

396.00

975.00
1143.00

155.62
1298.62
1298.00

with 16 Amps
ame Makes : GM
s/ Cabtree Verna/
onveyance of all

54.00
45.00
45.00
144.00

76.00

72.00

118.00

184.00

450.00
594.00

80.87
674.87
675.00

lated flexible ISI


G/ Power flex / GM /
all labour charges

IIIT-HYD ELEC-Data 117 of 354


Amount
183.60
315.00
153.00
651.60
6.52

1482.00

1482.00
14.82

21.30

2.90
24.20
24.00

lated flexible ISI


G/ Power flex / GM /
all labour charges

540.00
1125.00
450.00
2115.00
21.15

3285.00

3285.00
32.85

54.00

7.35
61.35
61.00

IIIT-HYD ELEC-Data 118 of 354


Amount
ulated flexible ISI
L/ RPG/ Power flex /
abour charges etc.,

nchor / GM / Million

540.00
1125.00
450.00
2115.00
21.15

7173.00

7173.00

71.73

92.80

12.63
105.43
105.00

ulated flexible ISI


L/ RPG/ Power flex /
abour charges etc.,

540.00
1350.00
450.00
2340.00
23.40

10950.00

10950.00

109.50

IIIT-HYD ELEC-Data 119 of 354


Amount
132.90

18.09
150.99
151.00

IIIT-HYD ELEC-Data 120 of 354


Amount
ulated flexible ISI
Power flex / GM /
charges etc.,

540.00
1350.00
450.00
2340.00
23.40

16647.00

16647.00

166.47

189.80

25.84
215.64
216.00

lated flexible ISI


L/ RPG/ Power flex /
abour charges etc.,

1080.00
2475.00
900.00
4455.00
44.55

27745.00

27745.00

277.45

IIIT-HYD ELEC-Data 121 of 354


Amount
322.00

43.84
365.84
366.00

IIIT-HYD ELEC-Data 122 of 354


Amount
nsulated flexible ISI
L/ RPG/ Power flex /
labour charges etc.,

1263.60
2925.00
1053.00
5241.60
52.42

42985.00

42985.00

429.85

482.20

65.65
547.85
548.00

Makes : Legrand /
an (Gold Plus) /
Schneider-Acti9.
., complete.

135.00
112.50
70.50
318.00

330.00

567.00

40.00
937.00

IIIT-HYD ELEC-Data 123 of 354


Amount

IIIT-HYD ELEC-Data 124 of 354


Amount

32 and suitable for


complete.

270.00
225.00
235.00
730.00

1298.00
917.00

1158.00

100.00

3473.00
4203.00

572.24
4775.24
4775.00

per IS:13032 Makes


as incomer and 12
out goings
etc., complete. (For

2598.00

776.00
2316.00
100.00
5790.00

378.00
450.00
450.00
235.00
1513.00

IIIT-HYD ELEC-Data 125 of 354


Amount
7303.00

994.30
8297.30
8297.00

IIIT-HYD ELEC-Data 126 of 354


Amount
per IS:13032 Makes
as incomer and 12
out goings
etc., complete for

378.00
450.00
450.00
235.00
1513.00

2598.00

563.00

2316.00

100.00

5577.00

7090.00

965.30
8055.30
8055.00

032 Makes :
B, Adjustable,
al magnetic release
as incomer with 8
Schneider-Acti9 as
H Mounting etc.,
675.00
675.00
675.00
2025.00

8103.00

IIIT-HYD ELEC-Data 127 of 354


Amount
11256.00

8526.00

27885.00

600

Mtr in all soils as per


mm dia 'B' class G.I
oviding staggered
er from the bottom of
x 6mm x 200mm
o.8 G.I.wire from
per IS specifications

540.00
540.00

875.00

15.60

53.95

96.00

IIIT-HYD ELEC-Data 128 of 354


Amount
48.00

300.00

800.00

300.00

317.50

467.50

196.25

43.00

3512.80
4052.00

551.68
4603.68
4603.00

Mtr in all soils as per


0mm x 600mm x
f 2.5Mtr length as
strip of 25mm x
mm x 3mm copper
g with 20Kg Salt and
ght 3" thick hume
charges etc

540.00
540.00

875.00

5900.00

258.70

129.80

96.00

IIIT-HYD ELEC-Data 129 of 354


Amount
48.00

800.00

300.00

300.00

317.50

467.50

196.25

9688.75
79.50

9768.25
10308.00

1403.43
11711.43
11711.00

IIIT-HYD ELEC-Data 130 of 354


Amount
ies and labour

540.00
450.00
990.00
9.90

7670.00

7670.00

76.70
86.60

11.79
98.39
98.00

ies and labour

1080.00
900.00
1980.00
19.80

15340.00
200.00
15540.00

155.40
175.20

23.85
199.05
199.00

city 270A) including


Mtr)

540.00
675.00

IIIT-HYD ELEC-Data 131 of 354


Amount
1215.00
12.15

39117.00

39117.00

391.17
403.30

54.91
458.21
459.00

IIIT-HYD ELEC-Data 132 of 354


Amount
and labour charges

900.00
900.00
9.00

676.00

45.00

721.00

7.21
16.20

2.21
18.41
19.00

mm length LED tube


≥0.9, Surge
T: 3000K - 5700K,
80 & Photobiological
c 3) & IEC 60598-

/Surya/Syska.

54.00
45.00
99.00

9.53

2.02

IIIT-HYD ELEC-Data 133 of 354


Amount
0.62

10.00

22.17

922.00

944.17

IIIT-HYD ELEC-Data 134 of 354


Amount
uminaire
LED luminaire
der coat, with acrylic
50 to 265 Volts AC,
att, junction
12% etc.,
ells / HPL/ Surya/
27.00
56.25
83.25

19.06

50.00

69.06

4259.00

4328.06

1000lm, suitable
num body with
50 to 265 Volts AC,
ving efficacy of ≥
mplete with 3 years

onix /
35.64
0.00
45.00
80.64

9.53

2.02

0.62

IIIT-HYD ELEC-Data 135 of 354


Amount
0.00

933.00

945.17
1025.81

139.66
1165.47
1165.00

1000lm, suitable
num body with
50 to 265 Volts AC,
ving efficacy of ≥
mplete with 3 years

onix /
35.64
0.00
45.00
80.64

9.53

2.02

0.62

0.00

1282.00

1294.17
1374.81

187.18
1561.99
1562.00

IIIT-HYD ELEC-Data 136 of 354


Amount

chor / Gold Medal


connections and all
mpton / VIN /

27.00
22.50
49.50
18.00

57.00

-19.00

56.00
105.00
14.30
119.30

1995.00

39.90
2034.90
277.05
2311.95
2312.00

1976.00

39.52
2015.52
274.41
2289.93
2130.00

IIIT-HYD ELEC-Data 137 of 354


Amount
: GM Four-Five /
Verna/ Million logus
mplete with

22.50
22.50

442.00

442.00
464.00

63.17
527.17
527.00
ation and giving
bel / Havells /
G

67.50
56.25
123.75

9.53

9.53
133.00

18.11
151.11
151.00

with bolts & nuts

45.00
45.00

83.00

83.00

IIIT-HYD ELEC-Data 138 of 354


Amount
18.40

109.60
17.43
117.00

IIIT-HYD ELEC-Data 139 of 354


Amount
1368.00

27.36
1395.36
189.98
1585.34
1585.00
st fan with metallic
n / Almounard /
2829.00
56.58
2885.58
392.87
3278.45
3278.00

ary connections and


x / RR Kabel /
PL / RPG

135.00
112.50
117.50
365.00
9.53

200.00

15.00

224.53
589.00

80.19
669.19
669.00

0mm) Exhaust fan


bour charges etc.,

27.00
22.50
49.50

IIIT-HYD ELEC-Data 140 of 354


Amount
15.00

15.00

210.00

225.00

decolam block
etc., complete.
27.00
22.50
49.50

0.00

41.00

41.00
90.00

12.25
102.25

n 4"x7" decolam
arges etc.,

27.00
22.50
49.50

25.00

46.00

71.00
120.00

16.34
136.34

IIIT-HYD ELEC-Data 141 of 354


Amount

n 4"x7" decolam
arges etc.,

27.00
22.95
49.95

25.00

93.00

118.00
167.00

22.74
189.74

Medal on 4"x7"
labour charges etc.,

27.00
24.75
51.75

25.00

218.00

243.00
294.00

40.03
334.03

IIIT-HYD ELEC-Data 142 of 354


Amount
box with cover
neywell Blenge
sealed pipe wiring
complete in
24.75
24.75

57.00

56.00

93.00

206.00
230.00

31.31
261.31

r wire Makes :
pe and labour

270.00
450.00
225.00
945.00
9.45

910.00

910.00
9.10

IIIT-HYD ELEC-Data 143 of 354


Amount

: Finolex / Delton /
rges etc., complete.

270.00
450.00
225.00
945.00
9.45

2540.00

2540.00
25.40

er wire Makes :
e and labour

270.00
450.00
450.00
1170.00
11.70

36.00

36.00

er wire Makes :
e and labour

378.00

IIIT-HYD ELEC-Data 144 of 354


Amount
450.00
450.00
1278.00
12.78

70.00

70.00

er wire Makes :
e and labour

540.00
450.00
450.00
1440.00
14.40

175.00

175.00

per wire Makes :


e and labour

648.00
450.00
450.00
1548.00
15.48

IIIT-HYD ELEC-Data 145 of 354


Amount
387.00

387.00

n box with back


y and make as
bour charges etc.,

54.00
51.75
0.00
105.75

580.00

580.00

IIIT-HYD ELEC-Data 146 of 354


Amount
with back mount
rangement including

54.00
54.45
108.45

880.00

880.00

x with back mount


rangement including

81.00
67.50
148.50

3680.00

30.00
3710.00

x with back mount


rangement including

162.00
180.00
342.00

IIIT-HYD ELEC-Data 147 of 354


Amount

7000.00

23.00
7023.00

IIIT-HYD ELEC-Data 148 of 354


Amount

227300.00

500.00

0.00
500.00
25.00
525.00
25.00
10.00
560.00
560.00/-

43219.00

38588.00

0.00

IIIT-HYD ELEC-Data 149 of 354


Amount
38588.00
1929.40
40517.40
1929.40
771.76
43218.56
43219
122.00

403.00

729.00

IIIT-HYD ELEC-Data 150 of 354


Amount
akes : D Link / AMP /
sories and labour

36.18
30.15
30.15
96.48

305.00

305.00

akes : D Link / AMP


bour charges etc.,

270.00
450.00
337.50
1057.50
10.58

2100.00

2100.00
21.00

ex / Legrand /
200.00

IIIT-HYD ELEC-Data 151 of 354


Amount
200.00

ex / Legrand /
180.00
180.00

s : CISCO / Net
mplete.

216.00
138.15
354.15

6000.00

6000.00

IIIT-HYD ELEC-Data 152 of 354


Amount
nk / AMP / Molex /
plete.

162.00
180.00
342.00

6000.00

12.50
6012.50

ork rack Makes :


s etc., complete.

162.00
178.20
340.20

4200.00
4200.00

work rack Makes :


s etc., complete.

162.00
194.40

IIIT-HYD ELEC-Data 153 of 354


Amount
356.40

5800.00
5800.00

IIIT-HYD ELEC-Data 154 of 354


Amount
work rack Makes :
s etc., complete.

216.00
202.50
418.50

32000.00
32000.00

125.00

nolex / Delton /
bour charges etc.,

270.00
450.00
450.00
1170.00
11.70

17.00

17.00

IIIT-HYD ELEC-Data 155 of 354


Amount

5V free standing
eet steel after 7 tank
uitable rating TPN
MC barriers and
four out going
of following switch
oating including
ges.

2.00
3.00
2.00
5.00
11.00
15.00

218684.12

537270.00

61240.00

212570.00

78530.00

IIIT-HYD ELEC-Data 156 of 354


Amount
0.00

11878.00

4000.00

4000.00

688.00

1188.00

3960.00

1134008.12
56700.41

22680.16
22680.16

56700.41

1292769.26
1292800.00

IIIT-HYD ELEC-Data 157 of 354


Amount

5V free standing
eet steel after 7 tank
uitable rating TPN
MC barriers and
four out going
of following switch
oating including
ges.

2.00
3.00
2.00
3.00
3.00
12.00

103283.76

37900.00

85028.00

62824.00

28204.00

IIIT-HYD ELEC-Data 158 of 354


Amount
0.00

2000.00

2000.00

IIIT-HYD ELEC-Data 159 of 354


Amount
344.00

396.00

880.00

322859.76
16142.99

6457.20
6457.20

16142.99

368060.12

368100.00

415V free standing


e CRCA sheet steel
l consists of suitable
ed with DMC /SMC
o accept the up four
have comprised of
inting with powder
materials & labour

IIIT-HYD ELEC-Data 160 of 354


Amount
70911.40

15706.00

7051.00

8442.00

9800.00

3543.00

15800.00

IIIT-HYD ELEC-Data 161 of 354


Amount
53955.00

2000.00

2000.00

344.00

2072.00

4620.00

1320.00

IIIT-HYD ELEC-Data 162 of 354


Amount
2500.00

12331.00

212395.40
10619.77

10619.77

4247.91
31859.31

269742.16

269800.00

5V free standing
eet steel after 7 tank
uitable rating TPN
MC barriers and
our out going cables
owing switch gear .
including internal
Nos

3.00
2.00
2.00

IIIT-HYD ELEC-Data 163 of 354


Amount
1.00
3.00
1.00
12.00
3.00

140271.91

136998.00

127542.00

47118.00

28204.00

11878.00

2000.00

2000.00

IIIT-HYD ELEC-Data 164 of 354


Amount
344.00

396.00

1320.00

498071.91
24903.60

9961.44
9961.44

24903.60

567801.98
567900.00

5V free standing
eet steel after 7 tank
uitable rating TPN
MC barriers and
our out going cables
owing switch gear .
including internal
Nos

2
2
2
3
1
1
10
1

IIIT-HYD ELEC-Data 165 of 354


Amount
64408.75

25685.00

0.00

56408.00

23756.00

2000.00

2000.00

344.00

396.00

1320.00

IIIT-HYD ELEC-Data 166 of 354


Amount
176317.75
8815.89

3526.35
3526.35

8815.89

201002.23
201100.00

5V free standing
eet steel after 7 tank
uitable rating TPN
MC barriers and
our out going cables
owing switch gear .
including internal
Nos

130443.16

25685.00

IIIT-HYD ELEC-Data 167 of 354


Amount

62824.00

56408.00

23756.00

2000.00

2000.00

344.00

396.00

1320.00

305176.16
15258.81

6103.52
6103.52

15258.81

347900.82

IIIT-HYD ELEC-Data 168 of 354


Amount
348000.00

5V free standing
eet steel after 7 tank
uitable rating TPN
MC barriers and
our out going cables
owing switch gear .
including internal
Nos

2
2
2
3
1
1
10
1

52996.60

20403.00

56408.00

23756.00

IIIT-HYD ELEC-Data 169 of 354


Amount
2000.00

2000.00

344.00

396.00

1320.00

159623.60
7981.18

3192.47
3192.47

7981.18

181970.90
182000.00

5V free standing
eet steel after 7 tank
uitable rating TPN
MC barriers and
our out going cables
owing switch gear .
including internal
Nos

IIIT-HYD ELEC-Data 170 of 354


Amount
2
2
3
1
1
10
1

61027.37

25685.00

42306.00

11878.00

7232.00

2000.00

2000.00

344.00

IIIT-HYD ELEC-Data 171 of 354


Amount
396.00

1320.00

154188.37
7709.42

3083.77
3083.77

7709.42

175774.74
175800.00

5V free standing
eet steel after 7 tank
uitable rating TPN
MC barriers and
our out going cables
owing switch gear .
including internal
Nos

2
2
2
3
1
1
10
1

IIIT-HYD ELEC-Data 172 of 354


Amount
61027.37

20403.00

42306.00

11878.00

7232.00

2000.00

2000.00

344.00

396.00

1320.00

148906.37

IIIT-HYD ELEC-Data 173 of 354


Amount

7445.32

2978.13
2978.13

7445.32

169753.26
169800.00

5V free standing
eet steel after 7 tank
uitable rating TPN
MC barriers and
our out going cables
owing switch gear .
including internal
Nos

2
2
2
6
0
1
3
3

83916.70

20403.00

IIIT-HYD ELEC-Data 174 of 354


Amount
0.00

0.00

12090.00

2000.00

2000.00

344.00

396.00

1320.00

122469.70
6123.48

2449.39
2449.39

6123.48

139615.46
139700.00

IIIT-HYD ELEC-Data 175 of 354


Amount

5V free standing
eet steel after 7 tank
uitable rating TPN
MC barriers and
our out going cables
owing switch gear .
including internal
Nos

2
2
2
5
0
1
10
0

66275.01

20403.00

7051.00

25326.00

2000.00

IIIT-HYD ELEC-Data 176 of 354


Amount
2000.00

344.00

396.00

1320.00

125115.01
6255.75

2502.30
2502.30

6255.75

142631.11
142700.00

5V free standing
eet steel after 7 tank
uitable rating TPN
MC barriers and
our out going cables
owing switch gear .
including internal
Nos

2
2
2
4
1

IIIT-HYD ELEC-Data 177 of 354


Amount
0
3
3

57265.15

20403.00

0.00

0.00

21105.00

2000.00

2000.00

344.00

396.00

IIIT-HYD ELEC-Data 178 of 354


Amount
1320.00

104833.15
5241.66

2096.66
2096.66

5241.66

119509.80
119600.00

5V free standing
eet steel after 7 tank
uitable rating TPN
MC barriers and
our out going cables
owing switch gear .
including internal
Nos

2
2
2
4
1
0
3
3

57265.15

IIIT-HYD ELEC-Data 179 of 354


Amount
12210.00

22512.00

2000.00

2000.00

344.00

396.00

1320.00

98047.15
4902.36

1960.94
1960.94

4902.36

111773.76
111800.00

IIIT-HYD ELEC-Data 180 of 354


Amount
415V free mounted
7 tank process and
ing TPN. The panel
fixing the same and
d conveyance of all

4161.70

6678.00

10839.70
0.00

0.00
108.40

54.20

11002.29
11100.00

, 50 Hz, oil
designed and
ed delta on primary
oad side, 1100V /
d and temporature
ding after
mountings.
1007000.00

1007000.00

IIIT-HYD ELEC-Data 181 of 354


Amount

907.00

907.00

17640.00

430.00

2738.88
279.56
651.30

74.00

356.40
2136.00
293.70
1114.44
25714.28

352.80
48.21

26115.29
26120.00

IIIT-HYD ELEC-Data 182 of 354


Amount

6500.00

540.00
450.00
400.00
85.00

7975.00

3600.00

540.00
450.00
400.00
85.00

5075

530.00

530.00

600.00

600.00

1400.00

1400.00

IIIT-HYD ELEC-Data 183 of 354


Amount

8029.00

8029.00

12176.00

12176.00

unted metal clad


out , horizantal

IIIT-HYD ELEC-Data 184 of 354


Amount

1257000.00

62850.00
25140.00
1344990.00
1345000.00

IIIT-HYD ELEC-Data 185 of 354


Amount

2548000.00

20000

IIIT-HYD ELEC-Data 186 of 354


Amount

154.00

154.00
235.00

235.00
310.00

310.00
401.00

401.00
637.00

637.00
889.00

889.00
1128.00

1128.00

IIIT-HYD ELEC-Data 187 of 354


Amount
1378.00

1378.00

all be provided at the


95 Sqmm up to 400
viding route indicator
nce of materials and
864.00
1485.00
1062.50

892.50

4304.00
43.04

9000.00

2400.00

3808.00

200.00

1056.00

16464.00

164.64

207.00

28.18
235.18
235.00

all be provided at the


70 sqmm covering
dded in C.C
mplete.

540.00

IIIT-HYD ELEC-Data 188 of 354


Amount
900.00
1062.50

892.50

3395.00
33.95

IIIT-HYD ELEC-Data 189 of 354


Amount

9000.00

2400.00

3808.00

200.00

1056.00

16464.00

164.64

198.00

26.96
224.96
225.00

mm fixing on
directed by the
harges etc.,

810.00
1035.00
1845.00
18.45

1.24

5.52

10.68

17.44
36.00

4.90
40.90
41.00

IIIT-HYD ELEC-Data 190 of 354


Amount
hromium plated
partment including

810.00
1035.00
1845.00
18.45

1.24

4.04

10.68

15.96

35.00

4.77
39.77
40.00

ing with required


y the department
complete.

14.58
9.00
9.00
32.58

94.00

48.00

142.00
174.00

23.69
197.69
198.00

IIIT-HYD ELEC-Data 191 of 354


Amount
cable glands, Lugs
cluding cost and

14.58
9.00
9.00
32.58

138.00

12.00

51.00

201.00
233.00

31.72
264.72
265.00

cable glands, Lugs


cluding cost and

10.80
9.00
12.60
32.40

138.00

14.00

60.00

212.00
244.00

33.22
277.22
277.00

IIIT-HYD ELEC-Data 192 of 354


Amount
cable glands, Lugs
cluding cost and

10.80
9.00
13.50
33.30

264.00

17.00

75.00

356.00
389.00

52.96
441.96
442.00

d cable glands, Lugs


cluding cost and

16.20
13.50
18.00
47.70

264.00

25.00

105.00

394.00
441.00

60.04
501.04
501.00

IIIT-HYD ELEC-Data 193 of 354


Amount
d cable glands, Lugs
cluding cost and

32.40
27.00
32.40
91.80

491.00

27.00

138.00

656.00
747.00

101.70
848.70
849.00

d cable glands, Lugs


cluding cost and

61.02
45.00
45.00
151.02

491.00

35.00

213.00

739.00
890.00

121.17
1011.17
1011.00

IIIT-HYD ELEC-Data 194 of 354


Amount

IIIT-HYD ELEC-Data 195 of 354


Amount
d cable glands, Lugs
cluding cost and

62.10
45.00
45.00
152.10

578.00

40.00

276.00

894.00
1046.00

142.41
1188.41
1188.00

725.00

725.00
-217.50

507.50

/flats including two


bour charges etc
61.00

24.00

IIIT-HYD ELEC-Data 196 of 354


Amount
85.00

154.00

4200.00

500.00

250.00

1200.00

300.00

1100.00

40000.00

ble walled
30 Part-II etc.,
g the exacavated
n the top and as
als and labour

540.00
1485.00

IIIT-HYD ELEC-Data 197 of 354


Amount
1062.50

3087.50
51.46

9130.00

9130.00
91.30

124.00

215.30

36.22
36.22
302.00
381.00

itable for
ion as per IS:13032
having Breaking
s : L&T / Schneider /
A ISI Mark of Makes
ions and labour

9823.00

11816.00

IIIT-HYD ELEC-Data 198 of 354


Amount

8700.00
30339.00

875.00
600.00
600.00
2075.00

4413.17
4413.17
36827.00

unted indoor unit


or operation on
fying air circulating
ping, insulation kit
nge 160- 264 volts)

39600.00
1500.00
792.00

41892
5703.60
47595.60
47596.00

IIIT-HYD ELEC-Data 199 of 354


Amount
50250.00
1500.00
1005.00

52755
7182.59
59937.59
59938.00
59938.00

215380.00

10769.00

4307.60
230456.60
230457.00

682.00

34.10

13.64
729.74
730.00

IIIT-HYD ELEC-Data 200 of 354


Amount

907.50

45.38

18.15
971.03
971.00

4180.00

209.00

83.60
4472.60
4473.00

11275.00

563.75

225.50
12064.25
12064.00

IIIT-HYD ELEC-Data 201 of 354


Amount
655.00

32.75

13.10
700.85
701.00

538.00

26.90

10.76
575.66
576.00

682.00

34.10

13.64
729.74
730.00

IIIT-HYD ELEC-Data 202 of 354


Amount
864.00

43.20

17.28
924.48
924.00

98.00

4.90

1.96
104.86
105.00
694:1990 for
Medal /RPG /Havells/

175.10
400.00
200.00
775.10
7.75
54.30

54.30

54.30

IIIT-HYD ELEC-Data 203 of 354


Amount

8.45
8.45
70.00

694:1990 for
Medal /RPG /Havells/

175.10
400.00
240.00
815.10
8.15
125.10

125.10

125.10
133.25

18.14
151.39
151.00

/flats including two


bour charges etc
61.00

24.00

85.00

IIIT-HYD ELEC-Data 204 of 354


Amount

2057.00

0.00

2057.00
298.27

102.85

41.14
2499.26
2500.00

9345.00

467.25

186.90
9999.15
10000.00

2657.00

132.85

IIIT-HYD ELEC-Data 205 of 354


Amount
53.14
2842.99
2843.00

3795.00

189.75

75.90
4060.65
4061.00

8300.00

415.00

166.00
8881.00
8881.00

IIIT-HYD ELEC-Data 206 of 354


Amount
14750.00

737.50

295.00
15782.50
15783.00

15500.00

775.00

310.00
16585.00
16585.00

16095.00

804.75

321.90
17221.65
17222.00

IIIT-HYD ELEC-Data 207 of 354


Amount

6300.00

315.00

126.00
6741.00
6741.00

10647.00

103354.00

IIIT-HYD ELEC-Data 208 of 354


Amount
4500.00

4950.00

4500.00

28073.00

28884.00

IIIT-HYD ELEC-Data 209 of 354


Amount

11969.10

962.00

1206.00

IIIT-HYD ELEC-Data 210 of 354


Amount
405.00

14542.10
727.11

1134.27
145.42

727.11

17276.00
17276.00

13100.00

of high grade
, having protective
al & Electrical
P.F, ≥ 0.90, high
e < 75°C, with
ution Type II
0K, minimum
er load, Open
vertical or horizontal
anufacture has to
ance Complies to
mpany fixed on the
copper cable wire

/Surya/Syska.128.75
100.00
100.00
328.75

IIIT-HYD ELEC-Data 211 of 354


Amount
834.00

834.00

8900.00

9734.00

1459.10

1459.10
11521.00
made of pressure
s cover,IP 65/66
otected, input
ED's having efficacy
65 with optics, total
% etc complete with
runs 2.50 Sq.mm
d.
urya/Syska.

257.50
200.00
200.00
657.50

IIIT-HYD ELEC-Data 212 of 354


Amount
2085.00

2085.00
19970.00

19970.00

3293.24
3293.24
26005.00

29400.00

1500.00

9900.00

IIIT-HYD ELEC-Data 213 of 354


DATA FOR WATER SUPPLY AND SANITARY ITEMS
Sl.No Description Qty Unit Rate Per Unit Amount
1 Supplying, laying, filling, jointing and testing SWG SP-1 pipe conforming to ISI 651 & 4127 with air
tight Cement joints in CM (1.5:1) prop. including excavation of trenches and socket pits in any soil (except
rock requiring blasting) and refilling with watering and tamping to the required slope including cost and
conveyance of all materials to site and all labour charges etc., complete for finished item of work (APSS NO
1301 & 1318)

a) 101.60mm dia upto 914.40mm (3') depth


Rate as per market 1.00 RM 423.00 1 RM 423.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.14615 423.00 61.82
Rate per 1 RM 484.82
say 485

b) 152.40mm dia upto 1524.0mm (5') depth


Rate as per market 1.00 RM 708.00 1 RM 708.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.14615 708.00 103.47
811.47
Rate per 1 RM say 811

c) 203.20mm dia upto 1524mm (5') depth


Cost of SWG pipe 1.00 RM 504.00 1 RM 504.00
labour charges for laying , jointing , testing 1.00 RM 313.00 1 RM 313.00
Add for MA @ 40% 0.40 313.00 125.20
942.20
Overheads&Contractors Profit &Labour
cess@14.615% 0.14615 942.20 137.70
Rate per 1 RM 1079.90
say 1080
2 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with
cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a
minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both
inside and outside fitted with 20” dia RCC manhole covers and frames including excavating pits up to a
depth of 904 mm (3'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm thick
using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard specification
and including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, cost of
seigniorage charges on all materials and all incidental and operational, labour charges like mixing cement
mortar, constructing masonry, lift charges, curing etc., complete for finished item of work as per Standard
specification.

Rate as per SSR 1 No. 7321.00 Each 7321.00


Overheads&Contractors Profit &Labour
cess@14.615% 0.15 7321.00 1069.96
8390.96
Rate per Each say 8391

IIIT-Gachibowli WS & SA DATA 1 of 354


Sl.No Description Qty Unit Rate Per Unit Amount
3 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with
cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a
minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both
inside and outside fitted with 20” dia RCC manhole covers and frames including excavating pits up to a
depth of 1524 mm (5'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm
thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard
specification and including cost and conveyance of all materials like cement, sand, bricks, water etc., to site,
cost of seigniorage charges on all materials and all incidental and operational, labour charges like mixing
cement mortar, constructing masonry, lift charges, curing etc., complete for finished item of work as per
Standard specification.

Rate as per SSR 1 No. 11649.0 Each 11649.00


Overheads&Contractors Profit &Labour
cess@14.615% 0.15 11649.0 1702.50
13351.50
Rate per Each say 13352

3 Constructing 457.2 mm x 457.2 mm (1'6"x1'6") brick in CM 1:6 prop. Masonry. Inspection chamber
upto 914.4 mm (3'0") and fitted with light weight 457.2 mm x 457.2 mm (1'6"x1'6") C.I frame and cover of 20
Kg including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, all incidental
and operational, labour charges like mixing cement mortar, constructing masonry, lift charges, curing etc.,
complete for finished item of work as per Standard specification.

Rate as per SSR 1 No. 3813.00 Each 3813.00


Overheads&Contractors Profit &Labour
cess@14.615% 0.15 3813.00 557.27
4370.27
Rate per Each say 4370

4 Supplying and fixing of SWG Gully traps 150mm x 100mm of ISI make confirming to IS 651 & 4127 with
C.I grating & constructing cement brick masonry in CM (1:6) prop., intermediate chamber and fitted with
304.8 mm X 288.6 mm (12"x9") C.I Frame with hinged cover of standard make as approved including cost
and conveyance of all materials to site, labour charges etc., complete for finished item of work.

Rate as per SSR 1 No. 619.00 1 Each 619.00


Deduct cost of CI frame and cover 1 No. 124.00 1 No. -124.00
Add for RCC Cover 1 No. 100.00 1 No. 100.00
595.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 595.00 86.96
681.96
Rate per Each say 682
5 Supplying and fixing of 4" (101.6mm) multi floor trap with jali - UPVC/SWR pipe fittings as per site
requirements with standard practice for all floors including cost and conveyance of all materials to site,
labour charges etc., complete for finished item of work.

Rate as per SSR 1 No. 143.00 1 Each 143.00


Overheads&Contractors Profit &Labour
cess@14.615% 0.15 143.00 20.90
163.90
Rate per Each say 164

IIIT-Gachibowli WS & SA DATA 2 of 354


Sl.No Description Qty Unit Rate Per Unit Amount
6 Supplying and fixing 580mm x 440mm long Orissa Pan white glazed Water Closet 1st quality ISI
marked confirming to IS:2556-Part-3-2004 with "P" or "S" trap, ISI marked and providing masonry seat, CC
squatting plate and 10 litres capacity single flush PVC low level cistern with internal components fixed on 2
Nos. of teak wood blocks of size 76.20mm x 101.60mm using required size of nails, screws as approved by
Engineer-in-charge, 15 mm brass angle stop valve of quarter turn spindle type of not less than 400 grams
weight with internal threaded conforming to IS 8931, 15mm PVC connection with brass union nuts CP
coated , 31.75mm brass plumber union, P trap or S trap of Indian W.C. shall be encased on CC (1:2:4)
150mm alround well above the joint to stop leakage at the joint etc., complete including cost and
conveyance of all materials to site, cost of CC bed, labour charges etc., complete for finished item of work.

Cost of Orissa pan 1 No. 1306.00 1 Each 1306.00


Add MA on labour charges for fixing Orissa pan 0.40 409.00 163.60
Cost of Brick masonry seat 1 No. 271.00 1 Each 271.00
Cost of C C squatting plate 1 No. 81.00 1 Each 81.00
Cost of slim line PVC flush tank 10 Ltrs. capacity
single flush 1 No. 1439.00 1 Each 1439.00
Angle stop valve 15.00mm 1 No. 215.00 1 Each 215.00
Add MA on labour charges for fixing angle stop cock
0.40 99.00 39.60
15 mm nominal size PVC connection
with brass union nut C.P coated 1 No. 101.00 1 Each 101.00
Add MA on labour charges for fixing PVC
connection with brass union nuts 0.40 0.00 0.00
31.75mm brass plumber union 1 No. 63.00 1 Each 63.00
Add MA on labour charges for fixing 31.75mm brass
plumber union 0.40 0.00 0.00
Cutting holes in brick masonry 1 No. 47.00 1 Each 47.00
Add MA on labour charges for cutting holes in brick
masonry 0.40 47.00 18.80
Teak wood blocks 76.2mm x 101.6mm 2 Nos. 24.00 1 Each 48.00
Add MA on labour charges for fixing Teak wood
blocks 0.40 0.00 0.00
3793.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 3793.00 554.35
4347.35
Rate per Each 4347

IIIT-Gachibowli WS & SA DATA 3 of 354


Sl.No Description Qty Unit Rate Per Unit Amount
7 Supplying and fixing approved make wash down European Water Closet of 1st quality conforming to
IS:2556-Part-2-2004 of white glazed with 'S' trap,supplying and fixing best Indian make plastic seat and lid
for European water closets with rubber or plastic Buffers as per IS 2548-1996 and 10 litres capacity single
flush PVC low level cistern with internal components and fixed using required size of nails and screws, 15
mm brass angle stop valve of quarter turn spindle type of not less than 400 grams weight with internal
threaded conforming to IS 8931, 15mm PVC connections with brass union nuts CP coated including cost
and conveyance of all materials to site etc., complete for finished item of work for all floors.

Cost of EWC with 'S' trap 1 No 1619.00 1 Each 1619.00


Add MA on labour charges for fixing EWC 0.40 287.00 114.80
Supply and fixing of 10 lts. Capacity lowdown PVC
flushing tank 1 No 1439.00 1 Each 1439.00
Plastic seat and lid for European Water Closet and
rubber buffers 1 No 734.00 1 Each 734.00
Add MA on labour charges for fixing Plastic seat
and lid for EWC and rubber buffers 0.40 83.00 33.20
Angle stop valve 15.00mm 1 No. 215.00 1 Each 215.00
Add MA on labour charges for fixing angle stop cock
0.40 99.00 39.60
15 mm nominal size PVC connection
with brass union nut C.P coated 1 No 101.00 1 Each 101.00
Add MA on labour charges for fixing PVC
connection with brass union nuts 0.40 0.00 0.00
Cutting holes in brick masonry 1 No. 47.00 1 Each 47.00
Add MA on labour charges for cutting holes in brick
masonry 0.40 47.00 18.80
Cost of 76.2 x 101.60 mm teakwood blocks
2 Nos 24.00 1 Each 48.00
Add MA on labour charges for fixing Teak wood
blocks 0.40 0.00 0.00
4409.40
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 4409.40 644.43
5053.83
Rate per Each 5054

IIIT-Gachibowli WS & SA DATA 4 of 354


Sl.No Description Qty Unit Rate Per Unit Amount
8 Supplying and fixing Indian make Flat Back Wash Hand Basin 1st quality conforming to IS:2556-Part-
4:1972 of size 550mm x 400mm with waste fittings like rubber plug, chain, 32 mm nominal size C.P. Fitting
with parallel pipe thread conforming to IS:2963-1979 and fitted with 15 mm nominal bore Chromium Plated
Pillar Tap of 1st quality Indian make heavy duty complete with standard CI brackets including wooden blocks
,1 No.15mm PVC connection with brass union nuts CP coated , 15 mm brass angle stop valve of quarter
turn spindle type of not less than 400 grams weight with internal threaded conforming to IS 8931, 30 mm
nominal size dia PVC flexible waste pipe of 914.4 mm length of Ist quality including cost and conveyance of
all materials to site, labour charges etc., complete for finished item of work

Cost of Wash hand basin 1 No. 1469.00 1 Each 1469.00


Add MA on labour charges for fixing Wash hand
basin 0.40 409.00 163.60
Angle stop valve 15.00mm 1 No. 215.00 1 Each 215.00
Add MA on labour charges for fixing angle stop cock
0.40 99.00 39.60
15 mm nominal size PVC connection
with brass union nut C.P coated 1 No. 101.00 1 Each 101.00
Add MA on labour charges for fixing PVC
connection with brass union nuts 0.40 0.00 0.00
Deduct cost of NP chain and rubber plug 1 No. 38.00 1 Each -38.00
30mm nominal size fia PVC flexible waste pipe 1 No. 26.00 1 Each 26.00
1976.20
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 1976.20 288.82
2265.02
Rate per Each say 2265

9 Supplying and fixing CP finish brass soap dish of approved make ISI quality with CP screws etc.,
complete including cost and conveyance of all materials, labour charges for fixing etc., complete for finished
item of work in all floors

Cost of CP finish brass soap dish 1 No. 514.00 1 Each 514.00


Add for MA @ 40% 0.40 99.00 39.60
553.60
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 553.60 80.91
634.51
Rate per Each say 635

10 Supplying and fixing TV shape mirror with plastic frame of size 609.6mm x 457.2mm, plywood back
with NP screws 1st quality including cost and conveyance of all materials, labour charges etc., complete for
finished item of work in all floors.

Rate as per SSR 1 No. 466.00 Each 466.00


Add for MA @ 40% 0.40 0.00 0.00
466.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 466.00 68.11
534.11
Rate per Each say 534

IIIT-Gachibowli WS & SA DATA 5 of 354


Sl.No Description Qty Unit Rate Per Unit Amount
11 Supplying and fixing of 25 mm nominal size dia and 609.6mm long aluminium anodized towel rod
with brackets and aluminium screws including cost and conveyance of all materials, labour charges etc.,
complete for finished item of work in all floors.

Rate as per SSR 1 No. 149.00 Each 149.00


Add for MA @ 40% 0.40 0.00 0.00
149.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 149.00 21.78
170.78
Rate per Each say 171

12 Supplying and fixing 15 mm brass body CP finish bib tap of not less than 300 grams weight screw
type (full turn) with internal / external threaded connection conforming to IS 8931 as approved by the
Engineer-In-Charge including cost and conveyance of all materials, labour charges etc., complete for
finished item of work in all floors.

Rate as per SSR 1 No. 223.00 Each 223.00


Add for MA @ 40% 0.40 51.00 20.40
243.40
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 243.40 35.57
278.97
Rate per Each say 279
13 Supplying and fixing Chromium plated finish brass body quarter turn Bibcock cum Health Faucet
with 1m long tube and wall hook with 7 - 10 years warranty with necessary fittings etc., complete
including cost and conveyance of all materials, labour charges etc., complete for finished item of work in all
floors.

Rate as per SSR 1 No. 2914.00 Each 2914.00


Add for MA @ 40% 0.40 51.00 20.40
2934.40
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 2934.40 428.86
3363.26
Rate per Each say 3363

14 Supplying and fixing of SWR PVC pipes (Prince/Sudhakar/Kisan/Supreme or any ISI brand) 4 Kg/Sq.cm.
and fixing all special such as plain bends, off sets, door bends, single junctions, double junctions as per site
requirement, fixing with PVC clamps if necessary with required number of Bombay nails including cost and
conveyance of all materials to site, labour charges etc., complete for finished item of work at all floor levels. (
(APSS No. 1302 1319 & 1326)

a) 75mm dia
Data for 6 RM
Cost of 75mm dia pipe 6.00 RM 252.00 3 RM 504.00
Cost of PVC clamps 3 Nos. 15.00 Each 45.00
Labour charges 6.00 RM 76.00 1 RM 456.00
1005.00
Rate per 1 RM 167.50
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 167.50 24.48
191.98
say 192

IIIT-Gachibowli WS & SA DATA 6 of 354


Sl.No Description Qty Unit Rate Per Unit Amount
c) 110mm dia
Data for 6 RM
Cost of 110mm dia pipe 6.00 RM 479.00 3 RM 958.00
Cost of PVC clamps 3 Nos. 18.00 Each 54.00
Labour charges 6 RM 76.00 1 RM 456.00
1468.00
Rate per 1 RM 244.67
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 244.67 35.76
280.43
say 280
15 Supply and fixing of Ashirvad/ Ajay/ Astral Flowguard or equivalent CPVC Pipes and Fittings SDR 11
to meet the requirement of ASTM-D 2846 and are produced in CTS (Copper Tube Sizes 1/2" to 2") for hot
and cold water (IS 15778:2007) including cost and conveyance of all materials to site, labour charges for
fixing etc., complete for finished item of work at all floor levels.

a) 15.90mm OD pipe
Rate as per SoR 1 RM 141.00 RM 141.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 141.00 20.61
Rate per 1 RM 161.61
say 162

b) 22.20mm OD pipe
Rate as per SoR 1 RM 172.00 RM 172.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 172.00 25.14
Rate per 1 RM 197.14
say 197

c) 28.60mm OD pipe
Rate as per SoR 1 RM 206.00 RM 206.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 206.00 30.11
Rate per 1 RM 236.11
say 236
d) 34.90mm OD pipe
Rate as per SoR 1 RM 281.00 RM 281.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 281.00 41.07
Rate per 1 RM 322.07
say 322

e) 41.30mm OD pipe
Rate as per SoR 1 RM 348.00 RM 348.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 348.00 50.86
Rate per 1 RM 398.86
say 399
f) 54.00mm OD pipe
Rate as per SoR 1 RM 508.00 RM 508.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 508.00 74.24
Rate per 1 RM 582.24
say 582

IIIT-Gachibowli WS & SA DATA 7 of 354


Sl.No Description Qty Unit Rate Per Unit Amount
16 Supplying and fixing 65 mm Nominal Bore GI pipe Medium Grade properties & weight as per IS 1239
in ground or on wall with GI fittings such as elbows tees couplings, nipples, plugs including excavation for
trenches and refilling the trenches ,chiselling masonry walls and making good the walls & floors to the
original surface and fixing MS clamps on TW blocks on walls including cost and conveyance of all materials
and labour charges etc., complete for finished item of work except for GI bends union and GI connectors
with checkout and socket Tata or Zenith make or equivalent

Rate as per SSR 1.00 RM 802.00 1 RM 802.00


Overheads&Contractors Profit &Labour
cess@14.615% 0.15 802.00 117.21
919.21
Rate per 1 RM say 919

17 Supplying and fixing Gunmetal Gate (GM) Bronze Gate/ Globe valves as per IS-778 Class - I , Indian
make heavy type including cost and conveyance of all materials, labour charges etc., complete for finished
item of work.

c) 25mm Nominal bore


Rate as per SSR 1 No. 1119.00 Each 1119.00
Add for MA @ 40% 0.40 0.00 0.00
1119.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.14615 1119.00 163.54
1282.54
Rate per Each say 1283

d) 32mm Nominal bore


Rate as per SSR 1 No. 1700.00 Each 1700.00
Add for MA @ 40% 0.40 0.00 0.00
1700.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 1700.00 248.46
1948.46
Rate per Each say 1948

e) 40mm Nominal bore


Rate as per SSR 1 No. 2297.00 Each 2297.00
Add for MA @ 40% 0.40 0.00 0.00
2297.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 2297.00 335.71
2632.71
Rate per Each say 2633

f) 50mm Nominal bore


Rate as per SSR 1 No. 3365.00 Each 3365.00
Add for MA @ 40% 0.40 0.00 0.00
3365.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 3365.00 491.79
3856.79
Rate per Each say 3857

IIIT-Gachibowli WS & SA DATA 8 of 354


Sl.No Description Qty Unit Rate Per Unit Amount
18 Providing and Placing on Terrace (at all floor levels) polyetheylene water storage tank with double
layer approved brand and manufacture with cover and suitable locking arrangement and making necessary
holes for inlet and outlets and over flow pipes but without fittings and base support for tanks including cost
and conveyance of all materials and labour charges etc., complete for finished item of work.

Rate as per SSR 1 Ltr 7.00 1 Ltr 7.00


Add for MA @ 40% 0.40 0.00 0.00
7.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 7.00 1.02
Rate per 1 Ltr 8.02
19 Supplying and fixing of stainless steel sink of size 914.4 mm x457.2mm, 1mm thick of Indian make
fixed on cantilever brackets including supply and fixing 32mm dia nominal size C.P. waste coupling, 30 mm
nominal size dia PVC flexible waste pipe of 914.4 mm length of Ist quality including chiselling brick masonry
wall and making good & restoring to original surfaces etc., complete.for finished item of work in all floors.

Rate as per SSR 1 No 6224.00 Each 6224.00


Add for MA @ 40% 0.40 0.00 0.00
6224.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 6224.00 909.64
7133.64
Rate per Each say 7134
20 Construction of Brick masonry support for GI pipe of size 304.80mm x 228.60mm x 228.60 mm with
Brick in CM (1:6) prop including plastering and finishing with 12mm thick in CM (1:5) including cost and
conveyance of all materials and all labour charges etc.,complete for finished item of work for all floors.

Rate as per SSR 1 No 76.00 1 Each 76.00


Add for MA @ 40% 0.40 0.00 0.00
76.00
Overheads&Contractors Profit &Labour
cess@14.615% 0.15 76.00 11.11
87.11
Rate per Each Say 87

IIIT-Gachibowli WS & SA DATA 9 of 354


Name of Work : Construction of Proposed Apartment building at Moosapet , Hyderabad.
COST BREAK UP DETAILS
Area in Area in
Sl. No. Description of Item Amount Area in Sft Steel /Sft
Sqm Sft
1 Staff Quarters Block-1
a Stilt Floor
i Cost of Framed structure `. #REF! 750.65 8079.98 #REF!
Cost of Finishings (Brickmasonry,plastering,flooring
ii `. #REF! 750.65 8079.98 #REF!
etc.,)
Total Amount #REF! 750.65 8079.98 #REF!

b Upper Floors
i Cost of Framed structure `. #REF! 3671.34 39518.30 #REF!
Cost of Finishings (Brickmasonry,plastering,flooring
ii `. #REF! 3671.34 39518.30 #REF!
etc.,)
Provision towards Architectural features @ 2.0%
iii `. #REF! 3671.34 39518.30 #REF!
on civil works to upper floors
Total Amount #REF! 3671.34 39518.30 #REF!

Staff Quarters Block-1 ( Stilt + 5 Floors)


i Civil works `. #REF! 4519.95 48652.73 #REF!
ii Internal Water Suppply & Sanitary `. 0 4519.95 48652.73 0
iii Internal Electrification `. 12399247 4519.95 48652.73 255
iv Lifts -2 Nos @ 2500000 / Each `. 5000000 4519.95 48652.73 103
Sub total: `. #REF! 4519.95 48652.73 #REF! #DIV/0!
2 Staff Quarters Block-2
a Stilt Floor
i Cost of Framed structure `. #REF! 819.93 8825.68 #REF!
Cost of Finishings (Brickmasonry,plastering,flooring
ii `. #REF! 819.93 8825.68 #REF!
etc.,)
Total Amount #REF! 819.93 8825.68 #REF!

b Upper Floors
i Cost of Framed structure `. #REF! 4099.63 44128.42 #REF!
Cost of Finishings (Brickmasonry,plastering,flooring
ii `. #REF! 4099.63 44128.42 #REF!
etc.,)
Provision towards Architectural features @ 2.0%
iii `. #REF! 4099.63 44128.42 #REF!
on civil works to upper floors
Total Amount #REF! 4099.63 44128.42 #REF!

Staff Quarters Block-2 ( Stilt + 5 Floors)


a Civil works `. #REF! 4980.58 53610.97 #REF!
b Internal Water Suppply & Sanitary `. #REF! 4980.58 53610.97 #REF!
c Internal Electrification `. 5787929 4980.58 53610.97 108
d Provision for Lifts -2 Nos @ 2500000 / Each `. 5000000 4980.58 53610.97 93
Sub total: `. #REF! 4980.58 53610.97 #REF! #REF!
3 Staff Quarters Block-3
a Stilt Floor
i Cost of Framed structure `. #REF! 819.93 8825.68 #REF!
Cost of Finishings (Brickmasonry,plastering,flooring
ii `. #REF! 819.93 8825.68 #REF!
etc.,)
Total Amount #REF! 819.93 8825.68 #REF!

b Upper Floors
i Cost of Framed structure `. #REF! 4099.63 44128.42 #REF!
Cost of Finishings (Brickmasonry,plastering,flooring
ii `. #REF! 4099.63 44128.42 #REF!
etc.,)
Provision towards Architectural features @ 2.0%
iii `. #REF! 4099.63 44128.42 #REF!
on civil works to upper floors
Total Amount #REF! 4099.63 44128.42 #REF!

Staff Quarters Block-3 ( Stilt + 5 Floors)


a Civil works `. #REF!
b Internal Water Suppply & Sanitary `. #REF!
c Internal Electrification `. 5621352
d Provision for Lifts -2 Nos @ 2500000 / Each `. 5000000
Sub total: `. #REF! 4980.58 53610.97 #REF! #REF!
Name of Work : Construction of Proposed Apartment building at Moosapet ,
Hyderabad.

SUMMARY
Sl. No. Description of Item Amount
1 Staff Quarters Block-1 ( Stilt + 5 Floors)
a Civil works
i Stilt Floor `. #REF!
ii Upper Floors `. #REF!
Provision towards Architectural features @ 2.0% on
iii `. #REF!
civil works to upper floors
iv Head Room & Lift Machine Room `. #REF!
b Internal Water Suppply & Sanitary `. 0
c Internal Electrification `. 12399247
d Provision for Lifts -2 Nos @ 2500000 / Each `. 5000000
Sub total: `. #REF!

2 Staff Quarters Block-2 ( Stilt + 5 Floors)


a Civil works
i Stilt Floor `. #REF!
ii Upper Floors `. #REF!
Provision towards Architectural features @ 2.0% on
iii `. #REF!
civil works to upper floors
iv Head Room & Lift Machine Room `. #REF!
b Internal Water Suppply & Sanitary `. #REF!
c Internal Electrification `. #REF!
d Provision for Lifts -2 Nos @ 2500000 / Each `. 5000000
Sub total: `. #REF!

3 Staff Quarters Block-3 ( Stilt + 5 Floors)


a Civil works
i Stilt Floor `. #REF!
ii Upper Floors `. #REF!
Provision towards Architectural features @ 2.0% on
iii `. #REF!
civil works to upper floors
iv Head Room & Lift Machine Room `. #REF!
b Internal Water Suppply & Sanitary `. #REF!
c Internal Electrification `. #REF!
d Provision for Lifts -2 Nos @ 2500000 / Each `. 5000000
Sub total: `. #REF!
Provision for Consultancy charges @ 3 % inclusive
4 `.
GST
5 Provision towards GHMC Building permit fee `.
Total ECV `. #REF!
6 Provision towards GST @ 18% `. #REF!
GRAND TOTAL `. #REF!
Name of Work : Construction of Proposed Apartment building at Moosapet , Hyderabad.

ABSTRACT ESTIMATE FOR STAFF QUARTERS BLOCK-1


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
1 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary soils 4320.00 CUM One CUM 119.00 514080.00
and depositing on bank for all lifts and with an initial lead of 10m and up to 3m depth including
all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc.,
complete for finished item of work excluding dewatering charges etc., as per SS 20 B(APSS
308)

2 Earth work excavation for foundations (Mechanical Means) for buildings in ordinary rock 4320.00 CUM One CUM 148.00 639360.00
(not requiring blasting) and depositing on bank for all lifts and with an initial lead of 10m and up
to 3m depth including all operational,incidental, labour charges such as shoring, sheeting,
planking, strutting etc.,complete for finished item of work excluding dewatering charges etc., as
per SS 20 B(APSS 308)

3 Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse aggregate) for foundations 180.00 CUM One CUM 7760.00 1396800.00
and under flooring bed using coarse aggregate 40mm size hard , machine crushed
granite from approved quarry including cost and conveyance of all materials like cement,
sand, coarse aggregate, water,electricity etc. to site, including seigniorage charges, machine
mixing charges, laying concrete in foundations and under flooring bed, ramming in 15 cm layers
finishing top surface to the required level curing etc.,complete for finished item of work. (APSS
No. 402)

4 Plain Cement Concrete (1:5:10) (cement: fine aggregate: Coarse aggregate) for foundations 50.00 CUM One CUM 7523.00 376150.00
and under flooring bed using coarse aggregate 40mm size hard , machine crushed
granite from approved quarry including cost and conveyance of all materials like cement, sand,
coarse aggregate, water,electricity etc. to site, including seigniorage charges , machine mixing
charges, laying concrete in foundations and under flooring bed, ramming in 15 cm layers
finishing top surface to the required level curing etc., complete for finished item of work. (APSS
No. 402)

5 Filling with useful available excavated earth (excluding rock) with a lead of 50 m in trenches, 2000.00 CUM One CUM 59.00 118000.00
sides of foundations and basement with initial lead in layers not exceeding 15cm thick, watering
and ramming including cost and conveyance of water to work site and all operaitonal,
incidental, labour charges, hire charges of T&P etc., complete for fnished item of work (APSS
NO.309&310)

6 Filling with carted gravel in trenches,sides of foundations and basement with initial lead in 0.00 CUM One CUM 485.00 0.00
layers not exceeding 15cm thick,watering and ramming including cost and conveyance of water
to work site, electrcity, seigniorage charges and all operaitonal,incidental, labour charges,hire
charges of T&P etc., complete for fnished item of work(APSS NO.309&310)

7 Pre construction Anti termite treatment is a process in which chemical toxic to subterrean 1000.00 SQM One SQM 183.38 183384.00
tremites is apply/ inject into soil during early stage of building Construction 2. Treatement of soil
Beneath the building and around the foundations conduct and chemical use as per BIS - IS
6313 (Part -2) 2013 code specification & CIB RC registered termiticide which creates a
continuous chemical barrier beneath the building which kills or repels terminates & impervious
to tremite entry 3. Imidacloprid 30.5% SC (IS 63131) dissolve 2.1 Ml/1 liter of water and apply
emulsion/solution @ 7.5 Litres/Square meter (Sqm) of internal, external vertical surface of the
colums, plinth beams (Back filling) walls and floor junction, external perimeters, along reatining
wall @ 5.0 Liters/Sqm of the horizontal surface of basement top surface of the basement filling
below flooring bed (Plinth) & @ 2.0 Litres/ Line meter at expansion joints. The substructure of a
depth of 500mm around coulmns & 300mm deep around plinth beams, basements & floor filling
area including excavation channel along the wall & rodding etc. cost & Conveyance of all
materials to the site, cost of labour for sparying, rodding etc. complete for furnished item of work
as per the approval of the Engineer-in-charge.

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 14of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
8 Supply and placing of the VRCC of Design Mix Concrete M 25 grade corresponding to IS 456 1023.00 CUM One CUM 10549.00 ###
with minimum cement content of 380 kgs per 1 cum of concrete using WEIGH BATCHER /
MIXER with 20mm size graded machine crushed hard granite metal (coarse aggregate - as per
IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate,
water,electricity etc., to site and including seigniorage charges , centering using Steel
scaffolding pipes , jack props , wallers , Foot plates , brackets , steel centering plates etc.,
including all operational, incidental and labour charges such as weigh batching, machine
mixing, laying concrete, vibrating, curing etc., complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402) RCC Retaing wall

9 Supply and placing of the VRCC of Design Mix Concrete M 25 grade corresponding to IS
456 with minimum cement content of 380 kgs per 1 cum of concrete using WEIGH
BATCHER / MIXER with 20mm size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate,
water,electricity etc., to site and including seigniorage charges , centering using Steel
scaffolding pipes , jack props , wallers , Foot plates , brackets , steel centering plates etc.,
including all operational, incidental and labour charges such as weigh batching, machine
mixing, laying concrete, vibrating, curing etc., complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402)

a Footings 200.00 CUM One CUM 15128.00 3025600.00

b Column pedestals 128.00 CUM One CUM 16314.00 2088192.00

c Plinth beams 55.00 CUM One CUM 17962.00 987910.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 15of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
10 Supply and placing of the VRCC of Design Mix Concrete M 25 grade corresponding to IS
456 with minimum cement content of 380 kgs per 1 cum of concrete using WEIGH
BATCHER / MIXER with 20mm size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate,
water, electricity etc., to site and including seigniorage charges , centering using Steel
scaffolding pipes, jack Props, Steel Centering Plates,etc., including all operational,
incidental and labour charges such as weigh batching, machine mixing, lifting of concrete
mechanically, laying concrete, vibrating, curing etc., complete but excluding cost of steel and
its fabrication charges for finished item of work (APSS No. 402)

a) COLUMNS :

BASEMENT 2 : 54.00 CUM One CUM 18645.00 1006830.00

BASEMENT 1 : 54.00 CUM One CUM 18645.00 1006830.00

First Floor 47.00 CUM One CUM 18645.00 876315.00

Second Floor : 47.00 CUM One CUM 20379.00 957813.00

Third Floor : 47.00 CUM One CUM 21073.00 990431.00

Fourth Floor : 47.00 CUM One CUM 21766.00 1023002.00

Fifth Floor : 47.00 CUM One CUM 22460.00 1055620.00

Sixth Floor : 47.00 CUM One CUM 23153.00 1088191.00

Terrace Floor : 12.00 CUM One CUM 23847.00 286164.00

b) Lintels

BASEMENT 2 : 1.00 CUM One CUM 17290.00 17290.00

BASEMENT 1 : 1.00 CUM One CUM 17290.00 17290.00

First Floor 3.00 CUM One CUM 17290.00 51870.00

Second Floor : 4.00 CUM One CUM 18858.00 75432.00

Third Floor : 4.00 CUM One CUM 19385.00 77540.00

Fourth Floor : 4.00 CUM One CUM 19912.00 79648.00

Fifth Floor : 4.00 CUM One CUM 20439.00 81756.00

Sixth Floor : 4.00 CUM One CUM 20967.00 83868.00

Seventh Floor/ Terrace Floor : 1.00 CUM One CUM 21494.00 21494.00

c) 150mm thick Watertank side wall


Terrace Floor : 35.00 SQM One SQM 7135.00 249725.00

11 Supply and placing of the VRCC of Design Mix Concrete M 25 grade corresponding to IS
456 with minimum cement content of 380 kgs per 1 cum of concrete using WEIGH
BATCHER / MIXER with 20mm size graded machine crushed hard granite metal(coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including
cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate,
water,electricity etc., to site and including seigniorage charges , centering using steel
scaffolding pipes, jack props, steel centering plates etc., including all operational, incidental
and labour charges such as weigh batching, machine mixing, lifting of concrete mechanically,
laying concrete, vibrating, curing etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 16of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
a Roof beams upto un supported height of 3.66 m

Stilt Floor/ First Floor : CUM One CUM 14281.00

Second Floor : CUM One CUM 14997.00

Third Floor : CUM One CUM 15505.00

Fourth Floor : CUM One CUM 16012.00

Fifth Floor : CUM One CUM 16520.00

Sixth Floor : CUM One CUM 17027.00

Seventh Floor/ Terrace Floor : CUM One CUM 17535.00

b Roof Slabs upto un supported height of 3.66 m


i Roof Slabs 125mm thick :
Stilt Floor/ First Floor : SQM One SQM 1735.00

Second Floor : SQM One SQM 1818.00

Third Floor : SQM One SQM 1876.00

Fourth Floor : SQM One SQM 1933.00

Fifth Floor : SQM One SQM 1990.00

Sixth Floor : SQM One SQM 2047.00

Seventh Floor/ Terrace Floor : SQM One SQM 2105.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 17of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
ii Roof Slabs 150mm thick :
Stilt Floor/ First Floor : SQM One SQM 1993.00

Second Floor : SQM One SQM 2083.00

Third Floor : SQM One SQM 2140.00

Fourth Floor : SQM One SQM 2198.00

Fifth Floor : SQM One SQM 2256.00

Sixth Floor : SQM One SQM 2314.00

Seventh Floor/ Terrace Floor : SQM One SQM 2372.00

12 Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with
minimum cement content of 380 kgs per 1 cum of concrete using WEIGH BATCHER /
MIXER with 20mm size graded machine crushed hard granite metal (coarse aggregate - as per
IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse aggregate,
water,electricity etc., to site and including seigniorage charges , centering using Steel
scaffolding pipes, jack Props, Steel Centering Plates,etc. for 60cm wide sun-shades 7.5cm
thick at fixed end and 5cm thick at free end with an average thickness of 6.25cm including all
operational, incidental and labour charges such as weigh batching, machine mixing, lifting of
concrete mechanically, laying concrete, curing etc., but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402, 403 & 903).

Second Floor : RM One RM 691.00

Third Floor : RM One RM 725.00

Fourth Floor : RM One RM 758.00

Fifth Floor : RM One RM 792.00

Sixth Floor : RM One RM 825.00

Seventh Floor/ Terrace Floor : RM One RM 859.00

13 Reinforced Cement Concrete M 20 design mix using 12mm size hard granite machine
crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concrete
using WEIGH BATCHER / MIXER including cost and conveyance of all materials ,
water,electricity etc., to site and including seigniorage charges including steel centering,
shuttering, machine mixing, laying concrete, lift charges, curing etc., but excluding cost of steel
and its fabrication charges complete for finished item of work (APSS No. 402 & 403) for sill
slabs.

Second Floor : CUM One CUM 13138.00

Third Floor : CUM One CUM 13561.00

Fourth Floor : CUM One CUM 13984.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 18of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
Fifth Floor : CUM One CUM 14407.00

Sixth Floor : CUM One CUM 14830.00

Seventh Floor/ Terrace Floor : CUM One CUM 15253.00

14 Reinforced Cement Concrete M 20 design mix using 12mm size hard granite machine
crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concrete
using WEIGH BATCHER / MIXER including cost and conveyance of all materials,
water,electricity etc., to site and seigniorage charges including steel centering, shuttering,
labour charges such as weigh batching, machine mixing, laying concrete, lift charges, curing
etc., but excluding cost of steel and its fabrication charges complete for finished item of work
(APSS No. 402 & 403) for platforms and shelves.

i 50mm thick Platforms & Lofts


Second Floor : SQM One SQM 754.00

Third Floor : SQM One SQM 782.00

Fourth Floor : SQM One SQM 810.00

Fifth Floor : SQM One SQM 838.00

Sixth Floor : SQM One SQM 866.00

ii 25mm thick shelves


Second Floor : SQM One SQM 377.00

Third Floor : SQM One SQM 391.00

Fourth Floor : SQM One SQM 405.00

Fifth Floor : SQM One SQM 419.00

Sixth Floor : SQM One SQM 433.00

15 Brick masonry for panel walls in superstructure with CM (1:8) prop: (Cement : Screened sand)
using light weight common burnt clay bricks of class as per Table- I of IS:1077-1992, Non-
Modular or traditional size 23 x 11 x 7 cms from approved source having minimum crushing
strength of 50 Kg/Sqcm. including cost and conveyance of all materials like cement, screened
sand, bricks, water,electricity etc., to site, including seigniorage charges , labour charges for
mixing cement mortar, scaffolding charges, constructing masonry, lift charges, curing, etc.,
complete for finished item of work. (APSS No. 501 & 504).

Stilt Floor/ First Floor : CUM One CUM 11473.00

Second Floor : CUM One CUM 11969.00

Third Floor : CUM One CUM 12464.00

Fourth Floor : CUM One CUM 12960.00

Fifth Floor : CUM One CUM 13455.00

Sixth Floor : CUM One CUM 13950.00

Seventh Floor/ Terrace Floor : CUM One CUM 14446.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 19of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
16 Reinforced Brick Masonry for partition walls (11.0 cm thick) in CM (1:4) prop. (Cement :
Screened sand) using light weight common burnt clay bricks of class as per Table- I of IS:1077-
1992, Non- Modular or traditional size 23 x 11 x 7 cms from approved source having minimum
crushing strength of 50 Kg/Sq.cm and placing 2 Nos. of 6mm M.S plain rods in every third layer
with free ends of the reinforcement pegged into mortar joints of main brick walls where
applicable including cost and conveyance of all materials like cement, steel, sand, bricks,
water,electricity etc., to site, including seigniorage charges , all operational, incidental charges
such as labour charges for mixing cement mortar, scaffolding charges, constructing masonry,
lift charges, curing, etc., but excluding cost of steel and its fabrication charges complete for
finished item of work. (APSS No. of 501 & 509)

Second Floor : SQM One SQM 1561.00

Third Floor : SQM One SQM 1655.00

Fourth Floor : SQM One SQM 1748.00

Fifth Floor : SQM One SQM 1841.00

Sixth Floor : SQM One SQM 1934.00

17 Plain Cement Concrete M 20 design mix using WEIGH BATCHER / MIXER, 20mm size
hard granite machine crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS
2386 Part 1 to Part 8) from approved quarry, using a minimum quantity of 350 kgs. of cement
per 1 cum of concrete including cost and conveyance of all materials, water, electricity etc.,
and seigniorage charges including steel centering, shuttering, machine mixing, lift charges,
laying concrete,vibrating, curing etc., complete for finished item of work (APSS No. 402 & 403)
for steps

Stilt Floor/ First Floor : CUM One CUM 11911.00

Second Floor : CUM One CUM 12259.00

Third Floor : CUM One CUM 12606.00

Fourth Floor : CUM One CUM 12954.00

Fifth Floor : CUM One CUM 13301.00

Sixth Floor : CUM One CUM 13648.00

18 Plain Cement Concrete (1:3:6) nominal mix using 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry including cost and conveyance of all materials like cement, fine
aggregate(sand), coarse aggregate, water, electricity etc., to site, including seigniorage
charges, mixing charges, laying concrete in position, curing etc., & lift chargesfor Bed Blocks
& Hold Fasts for finished item of work. (APSS No. 402)

For bed blocks and hold fasts


Second Floor : CUM One CUM 10502.00

Third Floor : CUM One CUM 10698.00

Fourth Floor : CUM One CUM 10893.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 20of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)

Fifth Floor : CUM One CUM 11089.00

Sixth Floor : CUM One CUM 11285.00

Seventh Floor/ Terrace Floor : CUM One CUM 11481.00

19 Filling with light weight concrete in Cement Concrete (1:5:10) proportion using brick jelly for
low roofs including cost and conveyance of all materials like cement, sand, brick bats, water,
electricty etc., to site including cost of all labour charges for laying concrete, ramming,
curing ,all incidental charges and seigniorage charges etc., complete for finished item of work.
(APSS. No. 402)

Second Floor : CUM One CUM 8604.00

Third Floor : CUM One CUM 8740.00

Fourth Floor : CUM One CUM 8875.00

Fifth Floor : CUM One CUM 9011.00

Sixth Floor : CUM One CUM 9146.00

20 Reinforced cement concrete (1:5:10) proportion (Cement: fine aggregates: coarse


aggregate) using 40mm size (SS5) hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand),
coarse aggregate, water,elecricity etc., to site including centering using Steel scaffolding
pipes, jack Props, Steel Centering Plates,etc., shuttering, machine mixing, laying concrete,
lifting concrete manually , curing,all incidental charges, seigniorage charges etc., complete as
per drawings but excluding cost of steel and it's fabrication charges for finished item of work
(APSS NO. 402 & 403) for Dummy columns.

Seventh Floor/ Terrace Floor : CUM One CUM 21915.00

21 Providing Thermo Mechanically Treated (TMT) (from Primary Producers like TATA, SAIL,
VSP, JSW and Shyam Steel as approved by Ministry of Steel) (Fe 500 grade as per IS
1786-1979) of different diameters for RCC works , including labour charges for straightening,
cutting, bending to required sizes and shapes, placing in position with cover blocks of approved
materials and size and tying and lap-splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars including
cost and conveyance of binding wire, cover blocks and all incidental, operational, labour
charges such as cutting, bending, placing in position, tying etc. ,complete for finished item of
work.( APSS No.126)

Stilt Floor/ First Floor : MT One MT 53697.00

Second Floor : MT One MT 53858.00

Third Floor : MT One MT 54018.00

Fourth Floor : MT One MT 54179.00

Fifth Floor : MT One MT 54339.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 21of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)

Sixth Floor : MT One MT 54499.00

Seventh Floor/ Terrace Floor : MT One MT 54660.00

21 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS 432) of different diameters
including labour charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying and lap-splicing
with binding wire of 18 SWG, forming grills for reinforcement work as per approved designs and
drawings, including cost and conveyance of steel bars, including all wastages such as overlaps,
couplings, chairs, spacer bars including cost and conveyance of binding wire, cover blocks and
all incidental, operational, labour charges such as cutting, bending, placing in position, tying
etc. , complete for finished item of work.( APSS No.126)

Stilt Floor/ First Floor : MT One MT 53697.00

Second Floor : MT One MT 53858.00

Third Floor : MT One MT 54018.00

Fourth Floor : MT One MT 54179.00

Fifth Floor : MT One MT 54339.00

Sixth Floor : MT One MT 54499.00

Seventh Floor/ Terrace Floor : MT One MT 54660.00

22 Ornamental ceiling plastering 12mm thick in two coats using screened sand) with base
coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) with dubara sponge
finishing including cost and conveyance of all materials like cement, sand, water,electricity etc.,
to site, including seigniorage charges and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing, scaffolding, lift charges, curing,
including cutting grooves as directed by Engineer - in - charge etc., complete for finished item
of work. (SS 901,903 & 904)

Stilt Floor/ First Floor : SQM. One SQM. 774.00

Second Floor : SQM. One SQM. 843.00

Third Floor : SQM. One SQM. 911.00

Fourth Floor : SQM. One SQM. 980.00

Fifth Floor : SQM. One SQM. 1048.00

Sixth Floor : SQM. One SQM. 1117.00

Seventh Floor/ Terrace Floor : SQM. One SQM. 1185.00

23 Plastering 12mm thick in two coats using screened sand with base coat of 8mm thick in CM
(1:6) and top coat of 4mm thick in CM (1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water,electricity etc., to site, including
seigniorage charges and all operational, incidental charges on materials and including cost of
all labour charges for mixing mortar, finishing, scaffolding, lift charges, curing, including cutting
grooves as directed by Engineer - in - charge etc., complete for finished item of work. (SS
901,903 & 904)

i Internal walls

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 22of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
Stilt Floor/ First Floor : SQM. One SQM. 760.00

Second Floor : SQM. One SQM. 823.00

Third Floor : SQM. One SQM. 886.00

Fourth Floor : SQM. One SQM. 950.00

Fifth Floor : SQM. One SQM. 1013.00

Sixth Floor : SQM. One SQM. 1077.00

Seventh Floor/ Terrace Floor : SQM. One SQM. 1140.00

24 Plastering 20mm thick in two coats for weather exposed exterior walls using screened
sand with base coat of 16mm thick in CM(1:6) and top coat of 4mm thick in CM(1:4) with
dubara sponge finishing including cost and conveyance of all materials like cement, sand,
water,electricity etc., to site, including seigniorage charges and all operational, incidental
charges on materials and including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as directed by Engineer-in-charge
etc., complete for finished item of work .(SS 901,903 & 904)

i external walls
Stilt Floor/ First Floor : SQM. One SQM. 834.00

Second Floor : SQM. One SQM. 897.00

Third Floor : SQM. One SQM. 960.00

Fourth Floor : SQM. One SQM. 1024.00

Fifth Floor : SQM. One SQM. 1087.00

Sixth Floor : SQM. One SQM. 1150.00

Seventh Floor/ Terrace Floor : SQM. One SQM. 1214.00

25 Plastering 12mm thick single coat in CM(1:5) using screened sand including cost and
conveyance of all materials like cement, sand, water,electricity etc., to site, including
seigniorage charges and all operational, incidental charges on materials and including cost of
all labour charges for mixing mortar, finishing, curing as directed by Engineer-in-charge etc.,
complete for finished item of work .(SS 901,903 & 904)

Basement : SQM. One SQM. 327.00

26 Providing impervious coat to exposed RCC roof slab surfaces to required slopes with
CM (1:3) prop. using screened sand 20mm thick (average) mixed with integral cement water
proofing liquid confirming to IS: 2645-2003 manufactured by reputed manufacturers as
approved by Engineer-in-charge at 200ml per one bag of cement, laid over roof slab when it is
green, finished smooth with a floating coat of neat cement and thread lining at regular intervals
of 45cmx45cm including cost and conveyance of all materials like cement, sand, water proofing
compound, water,electricity etc., to site, including seigniorage charges and operational,
incidental, and labour charges for mixing mortar, laying, lift charges, rendering smooth and
thread lining, curing including rounding off junctions of wall and slab etc., complete for finished
item of work. (APSS No. 901 & 903).

Seventh Floor/ Terrace Floor : SQM. One SQM. 1188.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 23of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
27 Providing impervious coat to exposed RCC roof slab surfaces of sump , sump side
wall,sump bottom slab,in side of septic tank , in sunken slabs etc. to required slopes
with CM (1:3) prop. using screened sand 12mm thick mixed with integral cement water
proofing liquid confirming to IS: 2645-2003 manufactured by reputed manufacturers as
approved by Engineer-in-charge at 200ml per one bag of cement, laid over roof slab when it is
green, finished smooth with a floating coat of neat cement and thread lining at regular intervals
of 45cmx45cm where ever necessary including cost and conveyance of all materials like
cement, sand, water proofing compound, water,electricity etc., to site, including seigniorage
charges and operational, incidental, and labour charges for mixing mortar, laying, lift charges,
rendering smooth and thread lining, curing including rounding off junctions of wall and slab etc.,
complete for finished item of work. (APSS No. 901 & 903).

Second Floor : SQM. One SQM. 371.00

Third Floor : SQM. One SQM. 387.00

Fourth Floor : SQM. One SQM. 403.00

Fifth Floor : SQM. One SQM. 419.00

Sixth Floor : SQM. One SQM. 435.00

Seventh Floor/ Terrace Floor : SQM. One SQM. 452.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 24of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
28 Flooring with non-skid full body ceramic floor tiles of size 300mm x 300mm and thickness
between 7 - 8mm 1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Part 1 to 15) of any
colour and finish in all shades and designs as approved by Engineer-in-charge, set over base
coat of cement mortar (1:8), 12mm thick using screened sand over CC bed already laid or RCC
roof slab, including neat cement slurry of honey like consistency spread @ 3.3 Kgs per Sqm &
jointed neatly with white cement paste to full depth mixed with pigment of matching shade,
including cost of all materials like cement, screened sand , water,electricity and tiles,
seigniorage charges etc., complete for finished item of work.( In toilets) (APSS No.701 & 707)

Second Floor : SQM. One SQM. 1236.00

Third Floor : SQM. One SQM. 1301.00

Fourth Floor : SQM. One SQM. 1366.00

Fifth Floor : SQM. One SQM. 1431.00

Sixth Floor : SQM. One SQM. 1496.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 25of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
29 Flooring with Double charged / multi charged stain free full body porcelain vitrified tiles
with double layer pigment of size 600 x 600 mm and thickness between 8-10 mm 1st
quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all
shades and design as per the approved flooring pattern as directed by the Engineer-In -Charge,
laying tiles using spacers of 2mm thick, set over a base coat of CM (1:8) prop. 12mm thick
using screened sand over CC bed already laid or RCC roof slab , including neat cement slurry
of honey like consistancy spread @ 3.3 kgs per Sqm. and jointed neately with white cement
paste to full depth mixed with pigment of matching shade including cost and conveyance of all
materials like cement, sand, water,electricity, tiles, white cement etc., to site (excluding cost
of C.C. bed) including cost of base coat and all labour charges for mixing of cement mortar,
laying tiles to required slope as directed by the Engineer- in-charge including seigniorage
charges etc., complete for finished item of work. (APSS No.701 & 707)

Second Floor : SQM. One SQM. 1554.00

Third Floor : SQM. One SQM. 1619.00

Fourth Floor : SQM. One SQM. 1683.00

Fifth Floor : SQM. One SQM. 1748.00

Sixth Floor : SQM. One SQM. 1813.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 26of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
30 Flooring with 16 to 18mm thick High Polished granite stone slabs other than black and
regular colours (i.e. of shades like paradiso / bala flower / copper silk / laka red / lavender
blue) with borders and design as per the pattern approved by the Engineer-in-Charge of length
not less than 2.43 mts set over base coat of cement mortar (1:8) , 20mm thick using screened
sand over CC bed already laid or RCC roof slab including neat grey cement slurry of honey like
consistency spread @ 3.3 Kg per sqm and jointed neatly with white cement paste mixed with
pigment of matching shade to full depth including cost and conveyance of all materials like
cement , sand , water , electricity, granite slabs etc., to work site and all operational, incidental
labour & lift charges, polishing charges , seigniorage charges , cost of base coat etc., complete
for finished item of work (S.S.701 & special) for Staircase MIdlanding

Stilt Floor/ First Floor : SQM. One SQM. 4747.00

Second Floor : SQM. One SQM. 4866.00

Third Floor : SQM. One SQM. 4986.00

Fourth Floor : SQM. One SQM. 5105.00

Fifth Floor : SQM. One SQM. 5225.00

Sixth Floor : SQM. One SQM. 5344.00

31 Flooring with chequered cement concrete heavy duty tiles confirming to IS:13801 using
aggregates, cement, pigments of size 300mm x 300mm and thickness 25mm of any shade
as approved by Engineer - In - Charge set over base coat of cement mortar (1:6), 12 mm thick
using screened sand over CC bed alredy laid or RCC roof slab including neat cement slurry of
honey like consistency spread @ 3.3 kgs per sqm and jointed with neat white cement to full
depth mixed with pigment of matching shade including cost and conveyance of all materials like
cement, sand, water , electricity and tiles, seigniorage charges etc., complete for finished item
of work.

Stilt Floor/ First Floor : SQM. One SQM. 1145.00

32 Granolithic Concrete flooring 20 mm thick with (1:1:2), using 6mm to 12 mm size hard
granite machine crushed metal and screened sand laid over CC bed already laid or RCC roof
slab, in alternate panels of size not exceeding 1.50 m x 1.50 m, using glass strips and finishing
the top surface to required smoothness and slopes and thread lining including cost of all
materials like cement, metal, sand and water , electricity, seigniorage charges etc., complete
for finished item of work. (APSS No.701 & 710)

Seventh Floor/ Terrace Floor : SQM. One SQM. 881.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 27of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
33 Providing 16 to 18mm thick high polished granite stone slabs other than black and
regular colours (i.e. of shades like paradiso / bala flower / copper silk / laka red / lavender
blue) with borders and design as per the pattern approved by the Engineer-in-Charge of length
not less than 2.43 mts set over base coat of cement mortar (1:5) , 12mm thick using screened
sand over CC bed already laid or RCC roof slab including neat grey cement slurry of honey
like consistency spread @ 3.3 Kg per sqm and jointed neatly with white cement paste mixed
with pigment of matching shade to full depth including cost and conveyance of all materials like
cement , sand , water ,electricity, granite slabs etc., to work site and all operational, incidental
labour & lift charges, half rounding the edges of treads , polishing charges , seigniorage
charges , cost of base coat etc., complete for finished item of work for treads and risers
(S.S.701 & special)

a Treads of 0.30m wide :


Stilt Floor/ First Floor : SQM. One SQM. 6336.00

Second Floor : SQM. One SQM. 6456.00

Third Floor : SQM. One SQM. 6575.00

Fourth Floor : SQM. One SQM. 6695.00

Fifth Floor : SQM. One SQM. 6814.00

Sixth Floor : SQM. One SQM. 6934.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 28of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
b Risers of 0.15m height :
Stilt Floor/ First Floor : SQM. One SQM. 4335.00

Second Floor : SQM. One SQM. 4405.00

Third Floor : SQM. One SQM. 4475.00

Fourth Floor : SQM. One SQM. 4546.00

Fifth Floor : SQM. One SQM. 4616.00

Sixth Floor : SQM. One SQM. 4686.00

34 Flooring with 16 to 18 mm thick High Polished Granite stone slabs black colour as
approved by the Engineer-in-Charge of length not less than 2.43 mts set over base coat of
cement mortar (1:8) , 20mm thick using screened sand over CC bed already laid or RCC roof
slab including neat grey cement slurry of honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with pigment of matching shade to full depth
including cost and conveyance of all materials like cement , sand , water , elecricity, granite
slabs etc., to work site and all operational, incidental labour & lift charges, half rounding the
edge , polishing charges , seigniorage charges , cost of base coat etc.,complete for finished
item of work for platforms (S.S.701 & special)

Second Floor : SQM. One SQM. 5203.00

Third Floor : SQM. One SQM. 5323.00

Fourth Floor : SQM. One SQM. 5442.00

Fifth Floor : SQM. One SQM. 5562.00

Sixth Floor : SQM. One SQM. 5681.00

35 Flooring with 16 to 18 mm thick High Polished Granite stone slabs black colour as
approved by the Engineer-in-Charge of length not less than 2.43 mts set over base coat of
cement mortar (1:8) , 20mm thick using screened sand over CC bed already laid or RCC roof
slab including neat grey cement slurry of honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with pigment of matching shade to full depth
including cost and conveyance of all materials like cement , sand , water , electricty, granite
slabs etc., to work site and all operational, incidental labour & lift charges, half rounding the
edge , polishing charges, seigniorage charges , cost of base coat etc., complete for finished
item of work for Sill slabs (S.S.701 & special)

Second Floor : SQM. One SQM. 5203.00

Third Floor : SQM. One SQM. 5323.00

Fourth Floor : SQM. One SQM. 5442.00

Fifth Floor : SQM. One SQM. 5562.00

Sixth Floor : SQM. One SQM. 5681.00

Seventh Floor/ Terrace Floor : SQM. One SQM. 5801.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 29of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
36 Providing dadooing to walls with glazed full body ceramic tiles of any size and thickness
between 5 to 7mm 1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Parts 1 to 15) of
any colour and finish in all shades and designs with borders as approved by Engineer-in-
Charge set over base coat of CM(1:5) 12 mm thick using screened sand with cement slurry of
honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement
paste mixed with pigment of matching shade to full depth, including cost and conveyance of all
materials like tiles, cement, sand , water , electricity etc., to site, cost of base coat,all
operational charges, incidental , labour and lift charges, seigniorage charges etc., complete for
finished item of work.

Second Floor : SQM. One SQM. 947.00

Third Floor : SQM. One SQM. 964.00

Fourth Floor : SQM. One SQM. 981.00

Fifth Floor : SQM. One SQM. 998.00

Sixth Floor : SQM. One SQM. 1015.00

37 Providing cladding to walls with High Polished Granite 16 to 18 mm thick up to 8'-00


(2.43 M) other than black and regular colours, length equal to flooring slabs set over base
coat of CM(1:5) 12 mm thick using screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white cement paste mixed with pigment
of matching shade to full depth, including cost of all materials like tiles, cement, sand , water,
electricity etc., to site, cost of base coat, all operational charges, incidental , labour and lift
charges, seigniorage charges etc., complete for finished item of work.

Stilt Floor/ First Floor : SQM. One SQM. 4335.00

Second Floor : SQM. One SQM. 4405.00

Third Floor : SQM. One SQM. 4475.00

Fourth Floor : SQM. One SQM. 4546.00

Fifth Floor : SQM. One SQM. 4616.00

Sixth Floor : SQM. One SQM. 4686.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 30of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
38 Providing skirting to internal walls to 10 cm height with Double charged / multi charged
stain free full body porcelain vitrified tiles with double layer pigment of size 600 x 600
mm and thickness between 8-10 mm 1st quality conforming to IS:13711, IS:13712, IS:13630
(Parts 1 to 15) of any colour and finish in all shades and design , length equal to flooring tiles,
set over base coat of CM(1:5) 12 mm thick using screened sand with cement slurry of honey
like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement paste
mixed with pigment of matching shade to full depth, including cost of all materials like tiles,
cement, sand, water,electricity, all operational, incidental , labour and lift charges, seigniorage
charges etc. complete for finished item of work.(APSS No.701 &707)

Second Floor : RM One RM 155.00

Third Floor : RM One RM 161.00

Fourth Floor : RM One RM 168.00

Fifth Floor : RM One RM 174.00

Sixth Floor : RM One RM 181.00

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 31of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
39 Providing skirting to internal walls 10cm height with High Polished Granite 16 to 18 mm
thick up to 8'-00 (2.43 M) other than black and regular colours, length equal to flooring slabs
set over base coat of CM(1:5) 12 mm thick using screened sand with cement slurry of honey
like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement paste
mixed with pigment of matching shade to full depth, including cost of all materials like tiles,
cement, sand , water , electricity, all operational, incidental , labour and lift charges, seigniorage
charges etc., complete for finished item of work.

Stilt Floor/ First Floor : RM One RM 433.00

Second Floor : RM One RM 441.00

Third Floor : RM One RM 448.00

Fourth Floor : RM One RM 455.00

Fifth Floor : RM One RM 462.00

Sixth Floor : RM One RM 469.00

40 Providing 110 mm Dia ISI marked PVC down water take pipes with socket , 2.5mm thick 4.0
kg/sq.cm pressure of ISI marked including cost of necessary PVC Bends, shoes, iron / PVC
clamps and all other accessories and fixing in position including cost and conveyance of all
materials, operational & incidental charges including all labour charges for fixing at site etc.,
complete for finished item of work. (APSS No. 1328)

Seventh Floor/ Terrace Floor : RM One RM 285.00

41 Supply & Fixing of Powder Coated Mild Steel doors, frames & shutters made of Skin pass
galvanized Iron sheet conforming to Base Steel as per IS 513 “D” Quality, Galvanized as per IS
277 with Hot Zinc Coating of 120 grams / Sq.Mtr with powder coating of thickness 60-65
Microns, frame with 1.2mm thick Skin pass Galvanized Iron sheet formed to single rebate
profile of size 100 mm X 58 mm and filled with in-fill Polyurethane foam, the Door Shutters are
with 0.80 mm thick Skin pass Galvanized Iron Sheet formed to provide a 46 mm thick fully flush,
double skin door shell with Lock Seam joints at stile edges, fitted with in-fill of Honeycomb Kraft
Paper and coated with polyester powders of Pure polyester/ epoxy polyester or polyurethane
powder for powder coating of thickness 60 – 65 microns and are coated with Zinc Phosphate
Primer to receive any paint on site or finished with Thermosetting Polyurethane paint of
Aliphatic Grade providing high levels of scratch resistance and durability,

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 32of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
the Shutter provided with 6 MM clear float vision glass in Circular, Square or Rectangular
shapes, Stainless Steel Ball Bearing Butt Hinges 3 mm thick fixed flush to the frame and shutter
(Profile 102x76x3mm thick).Mortise Sash Lock with Lever Handles, Mortise Dead Bolt, etc for
industrial, commercial, residential, clean room applications etc., including cost and conveyance
of all materials and labour charges etc., complete for finished item of work(1050mm x
2100mm) For All Floors

Second Floor : SQM

Third Floor : SQM

Fourth Floor : SQM

Fifth Floor : SQM

Sixth Floor : SQM

Seventh Floor/ Terrace Floor : SQM

SQM One SQM 11110.00

42 Providing and fixing factory made solid Wood Polymer Composite (WPC) single extruded
Door Frame section of 100*65 MM with encapsulation of 6 MM rigid layer on all external
surfaces. The door frame will have a rebate of 32MM/ 37 MM. The two Vertical members are to
be joined together with the horizontal member using 8x75 MM long MS Star full thread screws
to be used with reverse forward speed control hand drilling machine. The ready/assembled
door frame is fixed to wall using Z Hand fast 300 MM long hold fast including cost and
conveyance of all materials, labour charges for fixing etc., complete for finished item of work.

Second Floor : RM

Third Floor : RM

Fourth Floor : RM

Fifth Floor : RM

Sixth Floor : RM

RM One RM 756.00

43 Providing and fixing 28 -30 MM thick solid Wood Polymer Composite(WPC) single
extruded door shutter with 3MM top and bottom rigid layer with an overall density of
750kg/Cum.It will be fixed to the frame using 3 inch /4 inch hinges. A minimum of 4 hinges will
be required for fixing the door with the frame including ISI marked Stainless steel fixtures 3
Nos. butt hinges (IS:12817) of 150mm long, 1 No. aldrop (IS:15834) 250 mm long, 1 No.
Tower Bolt-10 mm Bolt (IS:15833) 50 mm Long , 2 Nos. 125mm long handles ,1 No. Rubber /
Nylon door stop bushes including labour charges for fixing the shutter to frame etc., including
cost and conveyance of all materials and labour charges etc., complete for finished item of work
( 800mm x 2100mm )

Second Floor : SQM

Third Floor : SQM

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 33of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
Fourth Floor : SQM

Fifth Floor : SQM

Sixth Floor : SQM

SQM One SQM 4327.00

44 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) 3 track sliding windows with
mesh shutter – (2-glass shutters and 1-mesh shutter) duly manufactured using UPVC
reinforced profiles (Composition of profile shall consists a minimum of 5.5 PHR of TiO2 and not
more than 12 PHR of CaCo3 for every 100 parts of PVC resin) of (94 mm x 45 mm)/(80 mm x
52 mm) x 2.20 mm for outer frames, (58 mm x 39 mm)/(54 mm x 38 mm) x 2.20 mm for sliding
shutter frames capable of mounting single glazing system structurally reinforced with hot dip
galvanized up to 50 microns of minimum thickness of 1.0/1.2 mm prefabricated & welded
through fusion welding. The window sash shall be fitted with 5 mm thick clear float glass of
reputed make and mesh shutter frame shall be (42 mm x 25 mm)/(52 mm x 21.5 mm) x 2.0 mm
fitted with Vinyl Coated Fiber mesh- on rollers/ pulley duly fixed with Grey colour TPV Gasket
for sash & Glazing bead shall be co-extruded with Grey colour soft PVC. System shall have
single point locking with Touch Lock and the system is to be installed at the site using anchor
fasteners, silicon rubber sealant, easy glazing/ deglazing at site etc., including cost and
conveyance of all materials, accessories, labour charges for transportation, erection at site etc.,
including cost and conveyance of all materials, accessories, labour charges for transportation,
erection at site etc., complete for finished item of work

i W - 1800 X 1300
Second Floor : SQM

Third Floor : SQM

Fourth Floor : SQM

Fifth Floor : SQM

Sixth Floor : SQM

SQM One SQM 5860.00 0

ii KW - 900 X 1000
Second Floor : SQM

Third Floor : SQM

Fourth Floor : SQM

Fifth Floor : SQM

Sixth Floor : SQM

SQM One SQM 5860.00 0

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 34of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)

iii W2 - 1200 X 1300


Seventh Floor/ Terrace Floor : SQM One SQM 5860.00 0

45 Providing, supplying & fixing of Fixed Louvered Ventilator made out of multi chambered uPVC
sections with Glazing bead shall be co-extruded with Grey colour soft PVC. having isolated
drainage and reinforced with Galvanized Iron profiles throughout the window. The outer frame
having an overall size of 60 mm x 55 mm x 2.40 with reinforcement of 1 mm thickness and
Mullion with overall size of 74 mm x 60 mm x 2.40 mm with reinforcement of 1 mm thickness.
(Composition of profile shall consists a minimum of 5.5 PHR of TiO2 and not more than 12 PHR
of CaCo3 for every 100 parts of PVC resin).Ventilator shall be provided with 4.5 mm Pin Head
glass, standard hardware. Wall thickness of frame & Mullion shall be 2.4 mm.,including cost
and conveyance of all materials, accessories, labour charges for transportation, erection at site
etc., complete for finished item of work

Second Floor : SQM

Third Floor : SQM

Fourth Floor : SQM

Fifth Floor : SQM

Sixth Floor : SQM


SQM One SQM 5552.00 0

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 35of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
46 Supplying and fixing of MS Grill to windows using 25mm x 6mm MS flat alround and 10mm
MS square bars horizontally at 125mm centre to centre and vertically at 30cm centre to centre
including fixing with 4 Nos of MS Z holdfasts (2 on each side) duly making cutting brick
masonry, fixing and making to original surface neatly and painting grill with one coat of red
oxide primer including cost and conveyance of all materials including cutting, bending, welding
including all operational charges and all labour charges etc., complete for finished item of work.

Second Floor : SQM

Third Floor : SQM

Fourth Floor : SQM

Fifth Floor : SQM

Sixth Floor : SQM

Seventh Floor/ Terrace Floor : SQM

SQM One SQM 1025.00 0

47 Supplying and fixing of stainless steel ( grade 304 ) hand railing as per approved drawing
with top rail of 50mm dia pipe and 2mm thick medium class and vertical posts of 25mm dia and
1.6mm thick medium class 2 Nos for each step fixed with base plate of 75mm dia using
bonding agent and anchor fastner and welding, drilling of 25mm dia holes with pneumatic
compressor for fixing railing, buffing, polishing all members of the railing thouroughly , lacquer
finishing to present seamless finish including cost and conveyance of all materials, electrodes,
welding charges, cost of all consumables, labour charges etc., complete for finished item of
work.

Stilt Floor/ First Floor : SQM

Second Floor : SQM

Third Floor : SQM

Fourth Floor : SQM

Fifth Floor : SQM

Sixth Floor : SQM

SQM One SQM 5323.00 0

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 36of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
48 RCM facia 50mm thick using screened sand for drop walls, fins with rabbit wire mesh &
nomianl reinforcement as directred by Engineer - In - Charge with dubara sponge
finishing,including cost and conveyance of all materials to site,water,electricity and seigniorage
charges ,operationals & incidental,cost and conveyance of cement,wire mesh,water to work
site,centering,scaffolding and form work,lift charges etc., complete for finished item of work but
excluding cost of steel and its fabrication charges for finished item of work(APSS NO.403&903)

Stilt Floor/ First Floor : SQM One SQM 2870.00 0

Second Floor : SQM One SQM 3080.00 0

Third Floor : SQM One SQM 3290.00 0

Fourth Floor : SQM One SQM 3501.00 0

Fifth Floor : SQM One SQM 3711.00 0

Sixth Floor : SQM One SQM 3922.00 0

Seventh Floor/ Terrace Floor : SQM One SQM 4132.00 0

49 Supply & application of one coat water based cement primer of interior grade I and two
coats of acrylic emulsion paint having VOC (Volatile Organic Compound) content less than
50 grams/litre for internal walls including cost and conveyance of all materials to site,
incidental, operational and all labour charges etc., complete for finished item of work in all floors
for Ceiling.

Stilt Floor/ First Floor : SQM

Second Floor : SQM

Third Floor : SQM

Fourth Floor : SQM

Fifth Floor : SQM

Sixth Floor : SQM

Seventh Floor/ Terrace Floor : SQM

SQM One SQM 247.00 0

50 Providing and applying Wall putty of White Cement or Polymer or Cement based of
average 1 to 2 mm thickness over plastered surface to prepare the surface even and
smooth after thoroughly brushing the surface to remove all dirt and remains of loose powdered
materials, applying emery paper, Sand the surface, clean & wipe off loose dust, applying knifing
paste filler by putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 180 and 320 No., emery
paper for the surface preparation including cost and conveyance of all materials to work site
and all operational, incidental, labour charges etc., complete for finished item of work in all
floors for Internal walls

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 37of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
Stilt Floor/ First Floor : SQM

Second Floor : SQM

Third Floor : SQM

Fourth Floor : SQM

Fifth Floor : SQM

Sixth Floor : SQM

SQM One SQM 290.00 0

51 Supply & application of one coat water based cement primer of interior grade I and two
coats of acrylic emulsion paint having VOC (Volatile Organic Compound) content less than
50 grams/litre for internal walls including cost and conveyance of all materials to site,
incidental, operational and all labour charges etc., complete for finished item of work in all
floors.

Stilt Floor/ First Floor : SQM

Second Floor : SQM

Third Floor : SQM

Fourth Floor : SQM

Fifth Floor : SQM

Sixth Floor : SQM

Seventh Floor/ Terrace Floor : SQM

SQM One SQM 247.00 0

52 Providing and applying Exterior grade Texture ready mixed plaster made with natural
minerals - granite flakes/ marble flakes/ powder, sand and other carefully selected and
sieved minerals in an acrylic binding medium of average 2 to 3 mm thickness over plastered
surface to prepare the surface even and smooth after thoroughly brushing the surface to
remove all dirt and remains of loose powdered materials, applying emery paper, Sand the
surface, clean & wipe off loose dust, applying putty/ texture paint filler by putty knife / muslin
pad, air dry for 2 - 3 hrs for the surface preparation including cost and conveyance of all
materials to work site and all operational, incidental, labour charges, scaffolding charges etc.,
complete for finished item of work in all floors for external walls

Stilt Floor/ First Floor : SQM

Second Floor : SQM

Third Floor : SQM

Fourth Floor : SQM

Fifth Floor : SQM

Sixth Floor : SQM

Seventh Floor/ Terrace Floor : SQM

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 38of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)

SQM One SQM 398.00 0

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 39of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
53 Painting two coats with synthetic enamel paint Grade-II VOC (Volatile Organic
Compound) content less than 50 grams/litre over primer coat of red oxide to new iron
work including cost and conveyance of all materials to site, incidental, operational and all
labour charges etc., complete for finished item of work in all floors. (SS No. 1201, 1212 &
1207).

Second Floor : SQM

Third Floor : SQM

Fourth Floor : SQM

Fifth Floor : SQM

Sixth Floor : SQM

Seventh Floor/ Terrace Floor : SQM


SQM One SQM 235.00 0

54 Supplying and fixing of two shutter cupboards as per drawing with medium teak wood
frames of size 75mm x 40mm and MDF Board Interior grade both sides laminated 18mm thick
for shutters with 18mm x 12mm teak wood beading alround and supplying and fixing powder
coated MS fixtures 3 Nos. butt hinges of size 100mm long(for each shutter), tower bolt 2 Nos.
of 100mm x 10mm, 2 Nos of handles 100mm long and standard locking arrangements for
shutters including cost and conveyance of all materials to site, labour charges, etc., complete
for finished item of work.

Second Floor : SQM

Third Floor : SQM

Fourth Floor : SQM

Fifth Floor : SQM

Sixth Floor : SQM

SQM One SQM 3715.00 0

55 Providing and fixing of Expansion joint filler board for buildings, columns, beams and
slabs 25 mm thick including cost and conveyance of all materials to site, all incidental,
operational, labour charges etc. complete for finished item of work as per approved drawing for
all floors

Stilt Floor/ First Floor : SQM

Second Floor : SQM

Third Floor : SQM

Fourth Floor : SQM

Fifth Floor : SQM

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 40of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
Sixth Floor : SQM

SQM One SQM 419.00 0

56 Providing and fixing of 24 gauge alluminium sheet over expansion joint groove of width 15cm
fixed to walls / columns at one edge and resting over the other block walls/columns concealing
expansion joint with slotted holes for free edge of aluminium sheet to facilitate free movement of
aluminium sheet over the finished surface of expansion joint and wall face using sheet metal
screws with nylon receiver complete including cost and conveyance of all materials to site, all
incidental, operational, labour charges etc., complete for finished item of work as per approved
drawing (for all floors for vertical joints and bottom of slab)

Stilt Floor/ First Floor : RM

Second Floor : RM

Third Floor : RM

Fourth Floor : RM

Fifth Floor : RM

Sixth Floor : RM

RM One RM 77.00 0

57 Providing specialized polysulphide sealant treatment to the expansion joints (Size : 25mm x
12mm) duly a].Chipping and removing of existing covering on expansion joints b]. Cleaning of
the surface from dirt, dust and other contaminations c].Application of one coat of - High
performance specially designed SBR latex polymer based bonding agent d]. Providing and
application of Acrylic Polymer modified reinstatement concrete /mortar to the damaged edges of
joint and making the groove. e]. Providing and fixing of masking tape on top of the joint both
sides f]. Providing and fixing of Back up support material of Backer rod to leave the depth of
12mm on the joint g]. Providing and application of one coat of polysulphide primer on inner
edges of Joint. h]. Providing and application of Two part Polysulphide sealant to a width of
25mm and 12mm depth with putty knife and neat finish i]. Removing of masking tape and
providing and application of two coats of Acrylic elastomeric cementitious coating of approved
make including cost and conveyance of all materials to site, all incidental, operational, labour
charges etc., complete for finished item of work as per approved drawing (for all floors on top of
slab i.e in the flooring and for internal vertical joints of grooves in dadooing surface).
+C373

Stilt Floor/ First Floor : 2.00 RM

Second Floor : 2.00 RM

Third Floor : 2.00 RM

Fourth Floor : 2.00 RM

Fifth Floor : 2.00 RM

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 41of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
Sixth Floor : 2.00 RM

12.00 RM One RM 738.00 8856

Sub Total ::(Civil Works) 29177068

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 42of 354


Name of Work : Construction of Proposed Apartment building at Moosapet , Hyderabad.

ABSTRACT ESTIMATE FOR STAFF QUARTERS BLOCK-1 (Typical Floor)


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)

1 Supply and placing of the Design Mix Concrete M 25


grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using WEIGH
BATCHER / MIXER with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS
383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water,
electricity etc., to site and including all taxes and seigniorage
charges except GST on all materials, centering using Steel
scaffolding pipes, jack Props, Steel Centering Plates,etc.,
including all operational, incidental and labour charges such
as weigh batching, machine mixing, lifting of concrete
mechanically, laying concrete, curing , overheads &
contractors profit etc., complete but excluding cost of steel
and its fabrication charges for finished item of work (APSS
No. 402)

a) COLUMNS :
Second Floor : #REF! One CUM 20379.00 #REF!

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 43of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
b) Lintels
Second Floor : #REF! One CUM 18858.00 #REF!

2 Supply and placing of the Design Mix Concrete M 25


grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using WEIGH
BATCHER / MIXER with 20mm size graded machine
crushed hard granite metal(coarse aggregate - as per IS 383
- 1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water,electricity etc.,
to site and including all taxes and seigniorage charges
except GST on all materials , centering using steel
scaffolding pipes, jack props, steel centering plates etc.,
including all operational, incidental and labour charges such
as weigh batching, machine mixing, lifting of concrete
mechanically, laying concrete, curing , overheads &
contractors profit etc., complete but excluding cost of steel
and its fabrication charges for finished item of work (APSS
No. 402)

a Roof beams upto un supported height of 3.66 m


Second Floor : #REF! One CUM 14997.00 #REF!

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 44of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
b Roof Slabs upto un supported height of 3.66 m
i Roof Slabs 125mm thick :
Second Floor : #REF! One SQM 1818.00 #REF!

ii Roof Slabs 150mm thick :


Second Floor : #REF! One SQM 2083.00 #REF!

3 Supply and placing of the Design Mix Concrete M 25


grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using WEIGH
BATCHER / MIXER with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970
and IS 2386 Part 1 to Part 8) from approved quarry including
cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water,electricity etc., to
site and including all taxes and seigniorage charges except
GST on all materials , centering using Steel scaffolding
pipes, jack Props, Steel Centering Plates,etc. for 60cm
wide sun-shades 7.5cm thick at fixed end and 5cm thick at
free end with an average thickness of 6.25cm including all
operational, incidental and labour charges such as weigh
batching, machine mixing, lifting of concrete mechanically,
laying concrete, curing, overheads & contractors profit
complete etc., but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402, 403 & 903)

Second Floor : #REF! One RM 691.00 #REF!

4 Reinforced Cement Concrete M 20 design mix using


12mm size hard granite machine crushed graded metal
(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1
to Part 8) from approved quarry, using a minimum quantity of
350 kgs. of cement per 1 cum of concrete using WEIGH
BATCHER / MIXER including cost and conveyance of all
materials , water,electricity etc., to site and including all taxes
and seigniorage charges excluding GST on all materials like
cement, fine aggregate (Sand), coarse aggregate, water etc.,
to site including steel centering, shuttering, machine mixing,
laying concrete, lift charges, curing, all taxes except GST etc.,
and overheads & contractors profit complete for finished item
of work (APSS No. 402 & 403) for sill slabs.

Second Floor : #REF! One CUM 13138.00 #REF!

5 Reinforced Cement Concrete M 20 design mix using


12mm size hard granite machine crushed graded metal
(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1
to Part 8) from approved quarry, using a minimum quantity of
350 kgs. of cement per 1 cum of concrete using WEIGH
BATCHER / MIXER including cost and conveyance of all
materials, water,electricity etc., to site and including all taxes
and seigniorage charges excluding GST on all materials like
cement, fine aggregate (Sand), coarse aggregate, water etc.,
to site including steel centering, shuttering, labour charges
such as weigh batching, machine mixing, laying concrete, lift
charges, curing etc., and overheads & contractors profit
complete for finished item of work (APSS No. 402 & 403) for
platforms and shelves.

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 45of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
i Platforms & Lofts
Second Floor : #REF! One SQM 754.00 #REF!
ii shelves
Second Floor : #REF! One SQM 377.00 #REF!

6 Brick masonry for panel walls in superstructure with CM (1:8)


prop: (Cement : Screened sand) using Macommon burnt clay
bricks of class as per Table- I of IS:1077-1992, Non- Modular
or traditional size 23 x 11 x 7 cms from approved source
having minimum crushing strength of 40 Kg/Sqcm. including
cost and conveyance of all materials like cement, screened
sand, bricks, water,electricity etc., to site, including all taxes
and seigniorage charges except GST on all materials and
such as labour charges, like mixing cement mortar,
scaffolding charges, constructing masonry, lift charges,
curing, etc.,and overheads & contractors profit complete for
finished item of work. (APSS No. 501 & 504).

Second Floor : #REF! One CUM 11969.00 #REF!

7 Reinforced Brick Masonry for partition walls (11.0 cm thick) in


CM (1:4) prop. (Cement : Screened sand) using common
burnt clay bricks of class as per Table- I of IS:1077-1992,
Non- Modular or traditional size 23 x 11 x 7 cms from
approved source having minimum crushing strength of 40
Kg/Sq.cm and placing 2 Nos. of 6mm M.S plain rods in every
third layer with free ends of the reinforcement pegged into
mortar joints of main brick walls where applicable including
cost and conveyance of all materials like cement, steel, sand,
bricks, water,electricity etc., to site, including all taxes and
seigniorage charges except GSTon all materials, all
operational, incidental charges such as labour charges for
mixing cement mortar, scaffolding charges, constructing
masonry,
Second Floorlift :charges, curing, etc., and overheads & #REF! One SQM 1561.00 #REF!
contractors profit but excluding cost of steel and its
7 fabrication
Reinforced charges complete
Brick Masonry for for finished
partition item
walls of work.
(11.0 (APSS
cm thick) in
No. of 501 & 509)
CM (1:4) prop. (Cement : Screened sand) using common
burnt clay bricks of class as per Table- I of IS:1077-1992,
Non- Modular or traditional size 23 x 11 x 7 cms from
approved source having minimum crushing strength of 40
Kg/Sq.cm and placing 2 Nos. of 6mm M.S plain rods in every
third layer with free ends of the reinforcement pegged into
mortar joints of main brick walls where applicable including
cost and conveyance of all materials like cement, steel, sand,
bricks, water,electricity etc., to site, including all taxes and
seigniorage charges except GSTon all materials, all
operational, incidental charges such as labour charges for
mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, etc., and overheads &
contractors profit but excluding cost of steel and its
fabrication charges complete for finished item of work. (APSS
No. of 501 & 509)

Second Floor : #REF! One SQM 1561.00 #REF!

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 46of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
8 Plain Cement Concrete M 20 design mix using WEIGH
BATCHER / MIXER, 20mm size hard granite machine
crushed graded metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry,
using a minimum quantity of 350 kgs. of cement per 1 cum of
concrete including cost and conveyance of all materials,
water, electricity etc., all taxes and seigniorage charges
except GST on all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site including steel
centering, shuttering, machine mixing, lift charges, laying
concrete,vibrating, curing, overheads & contrctors profit etc.,
complete for finished item of work (APSS No. 402 & 403) for
steps

Second Floor : #REF! One CUM 12259.00 #REF!

9 Plain Cement Concrete (1:3:6) nominal mix using 20mm


size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part
8) from approved quarry including cost and conveyance of all
materials like cement, fine aggregate(sand), coarse
aggregate, water, electricity etc., to site, including all taxes
and seigniorage charges except GST on all materials and
including all charges for mixing, laying concrete in position,
curing etc., & lift charges , and overheads & contractors profit
for Bed Blocks & Hold Fasts for finished item of work.
(APSS No. 402)

For bed blocks and hold fasts


Second Floor : #REF! One CUM 10502.00 #REF!

10 Filling with light weight concrete in Cement Concrete


(1:5:10) proportion using brick jelly for low roofs including
cost and conveyance of all materials like cement, sand, brick
bats, water, electricty etc., to site including cost of all labour
charges for laying concrete, ramming, curing ,all incidental
charges, all taxes and seigniorage charges except GST on all
materials, overheads & contractors profit etc., complete for
finished item of work. (APSS. No. 402)

Second Floor : #REF! One CUM 8604.00 #REF!

11 Providing Thermo Mechanically Treated (TMT) (from


Primary Producers like TATA, SAIL, VSP, JSW and
Shyam Steel as approved by Ministry of Steel) (Fe 500
grade as per IS 1786-1979) of different diameters for RCC
works , including labour charges for straightening, cutting,
bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and
lap-splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks
and all incidental, operational, labour charges such as cutting,
bending, placing in position, tying including all taxes except
GST on all materials etc. ,and overheads & contractors profit
complete for finished item of work.( APSS No.126)

Second Floor : #REF! One MT 53858.00 #REF!

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 47of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)

12 Providing Mild steel (MS) steel bars (Fe 250 grade as per
IS 432) of different diameters including labour charges for
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials
and size and tying and lap-splicing with binding wire of 18
SWG, forming grills for reinforcement work as per approved
designs and drawings, including cost and conveyance of steel
bars, including all wastages such as overlaps, couplings,
chairs, spacer bars including cost and conveyance of binding
wire, cover blocks and all incidental, operational, labour
charges such as cutting, bending, placing in position, tying
including all taxes except GST on all materials etc. ,and
overheads & contractors profit complete for finished item of
work.( APSS No.126)

Second Floor : #REF! One MT 53858.00 #REF!

13 Ornamental ceiling plastering 12mm thick in two coats


using screened sand) with base coat of 8mm thick in CM
(1:6) and top coat of 4mm thick in CM (1:4) with dubara
sponge finishing including cost and conveyance of all
materials like cement, sand, water,electricity etc., to site,
including all taxes and seigniorage charges except GST on all
materials, and all operational, incidental charges on materials
and including cost of all labour charges for mixing mortar,
finishing, scaffolding, lift charges, curing, including cutting
grooves as directed by Engineer - in - charge etc., and
overheads & contractors profit complete for finished item of
work. (SS 901,903 & 904)

Second Floor : #REF! One SQM. 843.00 #REF!

14 Plastering 12mm thick in two coats using screened sand


with base coat of 8mm thick in CM (1:6) and top coat of 4mm
thick in CM (1:4) with dubara sponge finishing including cost
and conveyance of all materials like cement, sand,
water,electricity etc., to site, including all taxes and
seigniorage charges except GST on all materials, and all
operational, incidental charges on materials and including
cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer - in - charge etc., and overheads &
contractors profit complete for finished item of work. (SS
901,903 & 904)

i Internal walls
Second Floor : #REF! One SQM. 823.00 #REF!

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 48of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
15 Plastering 20mm thick in two coats for weather exposed
exterior walls using screened sand with base coat of 16mm
thick in CM(1:6) and top coat of 4mm thick in CM(1:4) with
dubara sponge finishing including cost and conveyance of all
materials like cement, sand, water,electricity etc., to site,
including all taxes and seigniorage charges except GST on all
materials, and all operational, incidental charges on materials
and including cost of all labour charges for mixing mortar,
finishing, scaffolding, lift charges, curing, including cutting
grooves as directed by Engineer-in-charge etc., and
overheads & contractors profit complete for finished item of
work .(SS 901,903 & 904)

i external walls
Second Floor : #REF! One SQM. 897.00 #REF!

16 Providing impervious coat to exposed RCC roof slab


surfaces of sump , sump side wall,sump bottom slab,in
side of septic tank , in sunken slabs etc. to required
slopes with CM (1:3) prop. using screened sand 12mm
thick mixed with integral cement water proofing liquid
confirming to IS: 2645-2003 manufactured by reputed
manufacturers as approved by Engineer-in-charge at 200ml
per one bag of cement, laid over roof slab when it is green,
finished smooth with a floating coat of neat cement and
thread lining at regular intervals of 45cmx45cm where ever
necessary including cost and conveyance of all materials like
cement, sand, water proofing compound, water,electricity
etc., to site, including all taxes and seigniorage charges
except GST on all materials and operational, incidental, and
labour charges for mixing mortar, laying, lift charges,
rendering smooth and thread lining, curing including rounding
off junctions of wall and slab etc., and overheads &
contractors profit complete for finished item of work. (APSS
No. 901 & 903).

Second Floor : #REF! One SQM. 371.00 #REF!

17 Flooring with non-skid full body ceramic floor tiles of size


300mm x 300mm and thickness between 7 - 8mm 1st quality
conforming to IS: 13711, IS: 13712, IS: 13630(Part 1 to 15) of
any colour and finish in all shades and designs as approved
by Engineer-in-charge, set over base coat of cement mortar
(1:8), 12mm thick using screened sand over CC bed already
laid or RCC roof slab, including neat cement slurry of honey
like consistency spread @ 3.3 Kgs per Sqm & jointed neatly
with white cement paste to full depth mixed with pigment of
matching shade, including cost of all materials like cement,
screened sand , water,electricity and tiles, all taxes and
seigniorage charges except GST on all materials and
overheads & contractors profit etc., complete for finished
item of work.( In toilets) (APSS No.701 & 707)

Second Floor : #REF! One SQM. 1236.00 #REF!

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 49of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)

18 Flooring with Double charged / multi charged stain free


full body porcelain vitrified tiles with double layer
pigment of size 600 x 600 mm and thickness between 8-
10 mm 1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 to 15) of any colour and finish in all shades
and design as per the approved flooring pattern as directed
by the Engineer-In -Charge, laying tiles using spacers of 2mm
thick, set over a base coat of CM (1:8) prop. 12mm thick
using screened sand over CC bed already laid or RCC roof
slab , including neat cement slurry of honey like consistancy
spread @ 3.3 kgs per Sqm. and jointed neately with white
cement paste to full depth mixed with pigment of matching
shade including cost and conveyance of all materials like
cement, sand, water,electricity, tiles, white cement etc., to
site (excluding cost of C.C. bed) including cost of base coat
and all labour charges for mixing of cement mortar, laying
tiles to required slope as directed by the Engineer- in-
charge including all taxes and seigniorage charges except
GST on all materials and overheads & contractors profit etc.,
complete for finished item of work. (APSS No.701 & 707)

Second Floor : #REF! One SQM. 1554.00 #REF!

19 Flooring with 16 to 18mm thick High Polished granite


stone slabs other than black and regular colours (i.e. of
shades like paradiso / bala flower / copper silk / laka red /
lavender blue) with borders and design as per the pattern
approved by the Engineer-in-Charge of length not less than
2.43 mts set over base coat of cement mortar (1:8) , 20mm
thick using screened sand over CC bed already laid or RCC
roof slab including neat grey cement slurry of honey like
consistency spread @ 3.3 Kg per sqm and jointed neatly with
white cement paste mixed with pigment of matching shade to
full depth including cost and conveyance of all materials like
cement , sand , water , electricity, granite slabs etc., to work
site and all operational, incidental labour & lift charges,
polishing charges , all taxes and seigniorage charges excet
GST on all materials, cost of base coat and overheads &
contractors profit complete for finished item of work (S.S.701
& special) for Staircase MIdlanding

Second Floor : #REF! One SQM. 4866.00 #REF!

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 50of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
20 Providing 16 to 18mm thick high polished granite stone
slabs other than black and regular colours (i.e. of shades
like paradiso / bala flower / copper silk / laka red / lavender
blue) with borders and design as per the pattern approved by
the Engineer-in-Charge of length not less than 2.43 mts set
over base coat of cement mortar (1:5) , 12mm thick using
screened sand over CC bed already laid or RCC roof slab
including neat grey cement slurry of honey like consistency
spread @ 3.3 Kg per sqm and jointed neatly with white
cement paste mixed with pigment of matching shade to full
depth including cost and conveyance of all materials like
cement , sand , water ,electricity, granite slabs etc., to work
site and all operational, incidental labour & lift charges, half
rounding the edges of treads , polishing charges , all taxes
and seigniorage charges except GST on all materials, cost of
base coat and overheads & contractors profit complete for
finished item of work for treads and risers (S.S.701 & special)

a Treads of 0.30m wide :


Second Floor : #REF! One SQM. 6456.00 #REF!

b Risers of 0.15m height :


Second Floor : #REF! One SQM. 4405.00 #REF!

21 Flooring with 16 to 18 mm thick High Polished Granite


stone slabs black colour as approved by the Engineer-in-
Charge of length not less than 2.43 mts set over base coat of
cement mortar (1:8) , 20mm thick using screened sand over
CC bed already laid or RCC roof slab including neat grey
cement slurry of honey like consistency spread @ 3.3 Kg per
sqm and jointed neatly with white cement paste mixed with
pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water ,
elecricity, granite slabs etc., to work site and all operational,
incidental labour & lift charges, half rounding the edge ,
polishing charges , all taxes and seigniorage charges except
GST on all materials, cost of base coat and overheads &
contractors profit complete for finished item of work for
platforms (S.S.701 & special)

Second Floor : #REF! One SQM. 5203.00 #REF!

22 Flooring with 16 to 18 mm thick High Polished Granite


stone slabs black colour as approved by the Engineer-in-
Charge of length not less than 2.43 mts set over base coat of
cement mortar (1:8) , 20mm thick using screened sand over
CC bed already laid or RCC roof slab including neat grey
cement slurry of honey like consistency spread @ 3.3 Kg per
sqm and jointed neatly with white cement paste mixed with
pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water ,
electricty, granite slabs etc., to work site and all operational,
incidental labour & lift charges, half rounding the edge ,
polishing charges, all taxes and seigniorage charges except
GST on all materials, cost of base coat and overheads &
contractors profit complete for finished item of work for Sill
slabs (S.S.701 & special)

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 51of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
Second Floor : #REF! One SQM. 5203.00 #REF!

23 Providing dadooing to walls with glazed full body


ceramic tiles of any size and thickness between 5 to 7mm
1st quality conforming to IS: 13711, IS: 13712, IS:
13630(Parts 1 to 15) of any colour and finish in all shades
and designs with borders as approved by Engineer-in-Charge
set over base coat of CM(1:5) 12 mm thick using screened
sand with cement slurry of honey like consistency spread at
the rate of 3.30 kgs per sqm and jointing with white cement
paste mixed with pigment of matching shade to full depth,
including cost and conveyance of all materials like tiles,
cement, sand , water , electricity etc., to site, cost of base
coat,all operational charges, incidental , labour and lift
charges, all taxes and seigniorage charges except GST and
overheads & contractors profit etc., complete for finished item
of work.

Second Floor : #REF! One SQM. 947.00 #REF!

24 Providing cladding to walls with High Polished Granite


16 to 18 mm thick up to 8'-00 (2.43 M) other than black
and regular colours, length equal to flooring slabs set over
base coat of CM(1:5) 12 mm thick using screened sand with
cement slurry of honey like consistency spread at the rate of
3.30 kgs per sqm and jointing with white cement paste mixed
with pigment of matching shade to full depth, including cost of
all materials like tiles, cement, sand , water, electricity etc., to
site, cost of base coat, all operational charges, incidental ,
labour and lift charges, all taxes and seigniorage charges
except GST and overheads & contractors profit etc., complete
for finished item of work.

Second Floor : #REF! One SQM. 4405.00 #REF!

25 Providing skirting to internal walls to 10 cm height with


Double charged / multi charged stain free full body
porcelain vitrified tiles with double layer pigment of size
600 x 600 mm and thickness between 8-10 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of
any colour and finish in all shades and design , length equal
to flooring tiles, set over base coat of CM(1:5) 12 mm thick
using screened sand with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm and
jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials
like tiles, cement, sand, water,electricity, all operational,
incidental , labour and lift charges, all taxes and seigniorage
charges except GST ,and overheads & contractors profit etc.
complete for finished item of work.(APSS No.701 &707)

Second Floor : #REF! One RM 155.00 #REF!

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 52of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
26 Providing skirting to internal walls 10cm height with High
Polished Granite 16 to 18 mm thick up to 8'-00 (2.43 M)
other than black and regular colours, length equal to flooring
slabs set over base coat of CM(1:5) 12 mm thick using
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand ,
water , electricity, all operational, incidental , labour and lift
charges, all taxes and seigniorage charges except GST
etc.,and overheads & contractors profit complete for finished
item of work.

Second Floor : #REF! One RM 441.00 #REF!

27 Supply and fixing doors as per drawings with medium teak


wood frame of section 100mm x 65 mm and ISI marked
Moulded panel solid core flush doors using water-
resistant hardwood fibre HDF / MDF fibre boards skins of
2.5 mm thick Masonite or equivalent doors of 35 mm
thick single shutter with internal lipping on all sides
including cost and conveyance to site of teak wood frame,
flush shutter including supply and

fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm


including cost of ISI marked Stainless steel fixtures of 3
Nos. butt hinges (IS:12817) 150mm long, 1 No. aldrop
(IS:15834) 300mm long, 1 No. Tower Bolt-10 mm Bolt
(IS:15833) 200 mm Long at top, 2 Nos. 150 mm long handles
, 1 No. MS powder coated door stopper and 1 No. rubber
bush including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for
fixing the frame in position, fixing the shutter to the frame etc,
including all taxes except GST, overheads & contractors profit
etc., complete for finished item of work as per APSS 1001 &
1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm)(1050mm x
2100mm)

Second Floor : #REF!

#REF! One SQM 4836.00 #REF!

28 Supply and fixing doors as per drawings with medium teak


wood frame of section 100mm x 65mm and ISI marked
Moulded panel solid core flush doors using water-
resistant hardwood fibre HDF / MDF fibre boards skins of
2.5 mm thick of Masonite or equivalent doors of 30mm
thick single shutter with internal lipping on all sides
including cost and conveyance to site of medium teak wood
door frame, flush shutter, including suply and fixing 6 Nos.
MS Z hold fasts of size 300mm x 40mm x 5mm including ISI
marked Stainless steel fixtures 3 Nos. butt hinges
(IS:12817) of 150mm long, 1 No. aldrop (IS:15834) 250 mm
long,

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 53of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
1 No. Tower Bolt-10 mm Bolt (IS:15833) 150 mm Long , 2
Nos. 125mm long handles ,1 No. rubber bush including
supplying and fixing 1.20mm thick PVC sheet to full
height of the shutter inside including labour charges for
fixing the frame in position, fixing the shutter to the frame etc.,
including all taxes except GST on all materials, overheads &
contractors profit etc., complete for finished item of work as
per APSS 1001 & 1002. (The vertical frame of door shall be
embedded in flooring for deth of not less than 10mm)
( 800mm x 2100mm )

Second Floor : #REF!


#REF! One SQM 5437.00 #REF!

29 Supplying and fixing of Unplasticised Poly Vinyl Chloride


(UPVC) 3 track sliding windows with mesh shutter – (2-glass
shutters and 1-mesh shutter) duly manufactured using UPVC
reinforced profiles (Composition of profile shall consists a
minimum of 5.5 PHR of TiO2 and not more than 12 PHR of
CaCo3 for every 100 parts of PVC resin) of (94 mm x 45
mm)/(80 mm x 52 mm) x 2.20 mm for outer frames, (58 mm x
39 mm)/(54 mm x 38 mm) x 2.20 mm for sliding shutter
frames capable of mounting single glazing system structurally
reinforced with hot dip galvanized up to 50 microns of
minimum thickness of 1.0/1.2 mm prefabricated & welded
through fusion welding. The window sash shall be fitted with 5
mm thick clear float glass of reputed make and mesh shutter
frame shall be (42 mm x 25 mm)/(52 mm x 21.5 mm) x 2.0
mm fitted with Vinyl Coated Fiber mesh- on rollers/ pulley duly
fixed with Grey colour TPV Gasket for sash & Glazing bead
shall be co-extruded with Grey colour soft PVC. System shall
have single point locking with Touch Lock and the system is
to be installed at the site using anchor fasteners, silicon
rubber sealant, easy glazing/ deglazing at site etc., including
cost and conveyance of all materials, accessories, labour
charges for transportation, erection at site, including all taxes
except GST on all materials, overheads and contractors profit
etc., complete for finished item of work

i W - 1800 X 1300
Second Floor : #REF!
#REF! One SQM 5860.00 #REF!

ii KW - 900 X 1000
Second Floor : #REF!
#REF! One SQM 5860.00 #REF!

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 54of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
30 Providing, supplying & fixing of Fixed Louvered Ventilator
made out of multi chambered uPVC sections with Glazing
bead shall be co-extruded with Grey colour soft PVC. having
isolated drainage and reinforced with Galvanized Iron profiles
throughout the window. The outer frame having an overall
size of 60 mm x 55 mm x 2.40 with reinforcement of 1 mm
thickness and Mullion with overall size of 74 mm x 60 mm x
2.40 mm with reinforcement of 1 mm thickness. (Composition
of profile shall consists a minimum of 5.5 PHR of TiO2 and
not more than 12 PHR of CaCo3 for every 100 parts of PVC
resin).Ventilator shall be provided with 4.5 mm Pin Head
glass, standard hardware. Wall thickness of frame & Mullion
shall be 2.4 mm.,including cost and conveyance of all
materials, accessories, labour charges for transportation,
erection at site, including all taxes except GST on all
materials, overheads and contractors profit etc., complete for
finished item of work

Second Floor : #REF!


#REF! One SQM 5552.00 #REF!

31 Supplying and fixing of MS Grill to windows using 25mm


x 6mm MS flat alround and 10mm MS square bars
horizontally at 125mm centre to centre and vertically at 30cm
centre to centre including fixing with 4 Nos of MS Z holdfasts
(2 on each side) duly making cutting brick masonry, fixing and
making to original surface neatly and painting grill with one
coat of red oxide primer including all taxes except GST on all
materials and conveyance of all materials including cutting,
bending, welding including all operational charges and all
labour charges etc., complete for finished item of work.

Second Floor : #REF!


#REF! One SQM 1025.00 #REF!

32 Supplying and fixing of stainless steel ( grade 304 ) hand


railing as per approved drawing with top rail of 50mm dia
pipe and 2mm thick medium class and vertical posts of
25mm dia and 1.6mm thick medium class 2 Nos for each
step fixed with base plate of 75mm dia using bonding agent
and anchor fastner and welding, drilling of 25mm dia holes
with pneumatic compressor for fixing railing, buffing, polishing
all members of the railing thouroughly , lacquer finishing to
present seamless finish including cost and conveyance of all
materials, electrodes, welding charges, cost of all
consumables, labour charges , all taxes except GST,
overheads & contractors profit etc., complete for finished item
of work.

Second Floor : #REF!

#REF! One SQM 5323.00 #REF!

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 55of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
33 RCM facia 50mm thick using screened sand for drop walls,
fins with rabbit wire mesh & nomianl reinforcement as
directred by Engineer - In - Charge with dubara sponge
finishing,including cost and conveyance of all materials to
site,water,electricity all taxes and seigniorage charges except
GST on all materials,operationals & incidental,cost and
conveyance of cement,wire mesh,water to work
site,centering,scaffolding and form work,lift charges etc., and
overheads & contractors profit complete for finished item of
work but excluding cost of steel and its fabrication charges for
finished item of work(APSS NO.403&903)

Second Floor : #REF! One SQM 3080.00 #REF!

34 Supply & application of one coat water based cement


primer of interior grade I and two coats of acrylic
emulsion paint having VOC (Volatile Organic Compound)
content less than 50 grams/litre for internal walls including
cost and conveyance of all materials to site, all taxes except
GST on all materials, incidental, operational and all labour
charges etc., and overheads & contractors profit complete for
finished item of work in all floors for Ceiling.

Second Floor : #REF!


#REF! One SQM 247.00 #REF!

35 Providing and applying Wall putty of White Cement or


Polymer or Cement based of average 1 to 2 mm
thickness over plastered surface to prepare the surface
even and smooth after thoroughly brushing the surface to
remove all dirt and remains of loose powdered materials,
applying emery paper, Sand the surface, clean & wipe off
loose dust, applying knifing paste filler by putty knife / muslin
pad, air dry for 2 - 3 hrs, sand with 180 and 320 No., emery
paper for the surface preparation including cost and
conveyance of all materials to work site and all operational,
incidental, labour charges, ,all taxes except GST on all
materials, over heads and contractors profit etc., complete for
finished item of work in all floors for Internal walls

Second Floor : #REF!

#REF! One SQM 290.00 #REF!

36 Supply & application of one coat water based cement


primer of interior grade I and two coats of acrylic
emulsion paint having VOC (Volatile Organic Compound)
content less than 50 grams/litre for internal walls including
cost and conveyance of all materials to site, all taxes except
GST on all materials, incidental, operational and all labour
charges etc., and overheads & contractors profit complete for
finished item of work in all floors.

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 56of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
Second Floor : #REF!
#REF! One SQM 247.00 #REF!

37 Providing and applying Exterior grade Texture ready


mixed plaster made with natural minerals - granite flakes/
marble flakes/ powder, sand and other carefully selected
and sieved minerals in an acrylic binding medium of
average 2 to 3 mm thickness over plastered surface to
prepare the surface even and smooth after thoroughly
brushing the surface to remove all dirt and remains of loose
powdered materials, applying emery paper, Sand the surface,
clean & wipe off loose dust, applying putty/ texture paint filler
by putty knife / muslin pad, air dry for 2 - 3 hrs for the
surface preparation including cost and conveyance of all
materials to work site and all operational, incidental, labour
charges, scaffolding charges,all taxes except GST on all
materials, overheads and contractors profit etc., complete for
finished item of work in all floors for external walls

Second Floor : #REF!


#REF! One SQM 398.00 #REF!

38 Painting to new wood work and flush shutters with


lappam finish , over a primary coat and painting two coats
of synthetic enamel paint Grade-I VOC (Volatile Organic
Compound) content less than 50 grams/litre of approved
shade including cost and conveyance of all materials to site
cost of primer coat and all labour charges etc. complete
including applying sand paper on lappam coats for neat finish
including all taxes except GST on all materials and overheads
& contractors profit etc., complete in all floors (APSS
No.1200, 1207 & 1211).

Second Floor : #REF!


#REF! One SQM 274.00 #REF!

39 Painting two coats with synthetic enamel paint Grade-II


VOC (Volatile Organic Compound) content less than 50
grams/litre over primer coat of red oxide to new iron work
including cost and conveyance of all materials to site, sales &
other taxes, incidental, operational and all labour charges, all
taxes except GST on all materials, overheads and contractors
profit etc., complete for finished item of work in all floors. (SS
No. 1201, 1212 & 1207).

Second Floor : #REF!


#REF! One SQM 235.00 #REF!

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 57of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
40 Supplying and fixing of two shutter cupboards as per
drawing with medium teak wood frames of size 75mm x
40mm and MDF Board Interior grade both sides laminated
18mm thick for shutters with 18mm x 12mm teak wood
beading alround and supplying and fixing powder coated MS
fixtures 3 Nos. butt hinges of size 100mm long(for each
shutter), tower bolt 2 Nos. of 100mm x 10mm, 2 Nos of
handles 100mm long and standard locking arrangements for
shutters including cost and conveyance of all materials to site,
labour charges,all taxes except GST on all materials, over
heads and contractor profit etc., complete for finished item of
work.

Second Floor : #REF!


#REF! One SQM 3715.00 #REF!

41 Providing and fixing of Expansion joint filler board for


buildings, columns, beams and slabs 25 mm thick including
cost and conveyance of all materials to site, all incidental,
operational, labour charges, all taxes except GST on all
materials, overheads & contractors profit etc. complete for
finished item of work as per approved drawing for all floors

Second Floor : #REF!


#REF! One SQM 419.00 #REF!

42 Providing and fixing of 24 gauge alluminium sheet over


expansion joint groove of width 15cm fixed to walls / columns
at one edge and resting over the other block walls/columns
concealing expansion joint with slotted holes for free edge of
aluminium sheet to facilitate free movement of aluminium
sheet over the finished surface of expansion joint and wall
face using sheet metal screws with nylon receiver complete
including cost and conveyance of all materials to site, all
incidental, operational, labour charges , all taxes except GST
on all materials, overheads & contractors profit etc., complete
for finished item of work as per approved drawing (for all
floors for vertical joints and bottom of slab)

Second Floor : #REF!


#REF! One RM 77.00 #REF!

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 58of 354


Sl. Unit Rate Amount
Description of Work Quantity
No. (in words) In Figures (Rs.)
43 Providing specialized polysulphide sealant treatment to the
expansion joints (Size : 25mm x 12mm) duly a].Chipping and
removing of existing covering on expansion joints b]. Cleaning
of the surface from dirt, dust and other contaminations
c].Application of one coat of - High performance specially
designed SBR latex polymer based bonding agent d].
Providing and application of Acrylic Polymer modified
reinstatement concrete /mortar to the damaged edges of joint
and making the groove. e]. Providing and fixing of masking
tape on top of the joint both sides f]. Providing and fixing of
Back up support material of Backer rod to leave the depth of
12mm on the joint g]. Providing and application of one coat of
polysulphide primer on inner edges of Joint. h]. Providing and
application of Two part Polysulphide sealant to a width of
25mm and 12mm depth with putty knife and neat finish i].
Removing of masking tape and providing and application of
two coats of Acrylic elastomeric cementitious coating of
approved make including cost and conveyance of all
materials to site, all incidental, operational, labour charges ,all
taxes except GST on all materials, overheads & contractors
profit etc., complete for finished item of work as per approved
drawing (for all floors on top of slab i.e in the flooring and for
internal vertical joints of grooves in dadooing surface).

Second Floor : #REF!

#REF! One RM 738.00 #REF!

Sub Total ::(Civil Works) #REF!

IIIT-GACHIBOWLI Civil Abs-SQ Block-1 59of 354


Water Supply and Sanitary Arrangements
Amount
Sl.No Description of Work Quantity Unit Rate
(Rs.)
1 Supplying, laying, filling, jointing and testing SWG SP-1
pipe conforming to ISI 651 & 4127 with air tight Cement joints
in CM (1.5:1) prop. including excavation of trenches and socket
pits in any soil (except rock requiring blasting) and refilling with
watering and tamping to the required slope including cost and
conveyance of all materials to site and all labour charges etc.,
complete for finished item of work

a 152.40mm dia 100.00 Rmt 811.00 81100.00

b 200.00mm dia 80.00 Rmt 1080.00 86400.00

2 Constructing 904.0 mm (3’0”) dia brick masonry inspection 3.00 NO 13352.0 40056.00
chamber as per IS - 4111: Part-1:1986 with cement mortar (1:6)
prop using 2nd Class Clay Bricks of 225 mm thick from
approved source having a minimum crushing strength of 5
N/sq.mm including plastering with cement mortar 1:3 prop; ½”
thick both inside and outside fitted with 20” dia RCC manhole
covers and frames including excavating pits up to a depth of 904
mm (5'-0") in all sorts of soils (exculding rock) and laying cement
conrete (1:4:8) 150 mm thick using 40 mm HBG Metal and
P.C.C. 1:2:4 benching and channel 100 mm thick as per
Standard specification and including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, cost of
seigniorage charges on all materials and all incidental and
operational, labour charges like mixing cement mortar,
constructing masonry, lift charges, curing etc., complete for
finished item of work as per Standard specification.

3 Supplying and fixing of 4" (101.6mm) multi floor trap with 481.00 NO 164.00 78884.00
jali - UPVC/SWR pipe fittings as per site requirements with
standard practice for all floors including cost and conveyance of
all materials to site, labour charges etc., complete for finished
item of work.

4 Supplying and fixing approved make wash down European 284.00 NO 5054.00 1435336.00
Water Closet of 1st quality conforming to IS:2556-Part-2-2004
of white glazed with 'S' trap,supplying and fixing best Indian
make plastic seat and lid for European water closets with rubber
or plastic Buffers as per IS 2548-1996 and 10 litres capacity
single flush PVC low level cistern with internal components and
fixed using required size of nails and screws, 15 mm brass
angle stop valve of quarter turn spindle type of not less than 400
grams weight with internal threaded conforming to IS 8931,
15mm PVC connections with brass union nuts CP coated
including cost and conveyance of all materials to site etc.,
complete for finished item of work for all floors.

IIIT-GACHIBOWLI ABS-WS & SA-SQ-1 60 OF 354


Amount
Sl.No Description of Work Quantity Unit Rate
(Rs.)
5 Supplying and fixing Indian make Flat Back Wash Hand 284.00 NO 2265.00 643260.00
Basin 1st quality conforming to IS:2556-Part-4:1972 of size
550mm x 400mm with waste fittings like rubber plug, chain, 32
mm nominal size C.P. Fitting with parallel pipe thread
conforming to IS:2963-1979 and fitted with 15 mm nominal bore
Chromium Plated Pillar Tap of 1st quality Indian make heavy
duty complete with standard CI brackets including wooden
blocks ,1 No.15mm PVC connection with brass union nuts CP
coated , 15 mm brass angle stop valve of quarter turn spindle
type of not less than 400 grams weight with internal threaded
conforming to IS 8931, 30 mm nominal size dia PVC flexible
waste pipe of 914.4 mm length of Ist quality including cost and
conveyance of all materials to site, labour charges etc.,
complete for finished item of work

6 Supplying and fixing CP finish brass soap dish of approved 284.00 NO 635.00 180340.00
make ISI quality with CP screws etc., complete including cost
and conveyance of all materials, labour charges for fixing etc.,
complete for finished item of work in all floors

7 Supplying and fixing TV shape mirror with plastic frame of 284.00 NO 534.00 151656.00
size 609.6mm x 457.2mm, plywood back with NP screws 1st
quality including cost and conveyance of all materials, labour
charges etc., complete for finished item of work in all floors.

8 Supplying and fixing of 25 mm nominal size dia and 284.00 NO 171.00 48564.00
609.6mm long aluminium anodized towel rod with brackets
and aluminium screws including cost and conveyance of all
materials, labour charges etc., complete for finished item of
work.

9 S&F of 15 mm brass body CP finish long body bib tap 228.00 NO 279.00 63612.00
of not less than 400 grams weight with quarter turn
spindle internal / external threaded connection
conforming to IS 8931.

10 Supplying and fixing Chromium plated finish brass body 284 NO 3363.00 955092.00
quarter turn Bibcock cum Health Faucet with 1m long tube
and wall hook with 7 - 10 years warranty with necessary fittings
etc., complete including cost and conveyance of all materials,
labour charges etc., complete for finished item of work in all
floors.

11 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC)


pipes, having thermal stability for hot & cold water supply,
including all CPVC plain & brass threaded fittings i/c fixing the
pipe with clamps at 1.00 m spacing. This includes jointing of
pipes & fittings, with one step CPVC solvent cement and the
cost of cutting chases and making good the same including
testing of joints complete as per direction of Engineer-in-
Charge.Concealed work, including cutting chases and making
good the wall etc.
a) 15.90mm OD pipe 340.00 Rmt 162.00 55080.00

b) 22.20mm OD pipe 220.00 Rmt 197.00 43340.00

c) 28.60mm OD pipe 150.00 Rmt 236.00 35400.00

d) 34.90mm OD pipe 80.00 Rmt 322.00 25760.00

IIIT-GACHIBOWLI ABS-WS & SA-SQ-1 61 OF 354


Amount
Sl.No Description of Work Quantity Unit Rate
(Rs.)
e) 41.30mm OD pipe 120.00 Rmt 399.00 47880.00

f) 54.00mm OD pipe 80.00 Rmt 582.00 46560.00

12 Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, 130.00 Rmt 750.0 97500.00
having thermal stability for hot & cold water supply, including all CPVC
plain & brass threaded fittings including fixing the pipe with clamps at
1.00 m spacing. This includes jointing of pipes & fittings with one step
CPVC solvent cement and testing of joints complete as per direction of
Engineer-in-Charge.Internal work - Exposed on wall The Rate shall also
be inclusive of two coats of painting synthetic enamel paint of approved
colour over one coat of primer and pipe identification labels and
technical specification.

IIIT-GACHIBOWLI ABS-WS & SA-SQ-1 62 OF 354


Amount
Sl.No Description of Work Quantity Unit Rate
(Rs.)
13 Supplying and fixing of SWR PVC pipes (Prince/ Sudhakar/
Kisan/ Supreme or any ISI brand) 6 Kg/Sq.cm. and fixing all
special such as plain bends, off sets, door bends, single
junctions, double junctions as per site requirement, fixing with
PVC clamps if necessary with required number of Bombay nails
including cost and conveyance of all materials to site, labour
charges etc., complete for finished item of work at all floor
levels. (APSS No. 1302 1319 & 1326)

a) 75mmdia 950.00 Rmt 192.00 182400.00

b) 110mmdia 900.00 Rmt 280.00 252000.00

14 Construction of Brick masonry support for GI pipe of size 45 NO 87.00 3915.00


304.80mm x 228.60mm x 228.60 mm with Brick in CM (1:6)
prop including plastering and finishing with 12mm thick in CM
(1:5) including cost and conveyance of all materials and all
labour charges etc.,complete for finished item of work for all
floors.

15 Providing and fixing Stainless Steel A ISI 304 (18/8) kitchen 114.00 NO 5500.00 627000.00
sink as per IS 13983 with C.I. brackets and stainless steel plug
40 mm, including painting of fittings and brackets, cutting and
making good the walls wherever required:
Make:- Nirali elegance or Apollo AS28, AS5 or equivalent

Kitchen sink without drain board


610x510 mm bowl depth 200 mm
Kitchen sink with drain board
510x1040 mm bowl depth 250 mm

Supplying, installing, testing and commissioning of CP single


lever mixer unit comprising of shower arm , exposed kit, diverter,
spout, complete with necessary wall flanges, etc., complete All
complete as per directions of the Engineer-in-charge.
(Make :- Hindware Water Mixer F210012CP or Hindware
F200028CP or Polytuff 1057A or equivalent)
16 284.00 EACH 2800.00 795200.00

Providing and fixing C.P. brass shower rose with 15 or 20 mm inlet


inclusive of all fittings for installation as complete:
17 Make Polytuff Code 1067A or equivalent. 284.00 EACH 2500.00 710000.00
100 mm diameter

Supplying and wrapping closed cell nitrile rubber armaflex 6mm thick
tape for concealed piping
& 19 mm thick tube for exposed piping for hot water pipes thermal
insulation for toilet internals / roof as per manufacturer's instruction. The
exposed pipes
on roof shall be protected with aluminium cladding of 24 gauge sheet.

18

15 mm dia 50.000 meter 100.00 5000.00


20 mm dia 50.000 meter 125.00 6250.00
25 mm dia 50.000 meter 140.00 7000.00
32 mm dia 20.000 meter 220.00 4400.00
40 mm dia 20.000 meter 300.00 6000.00

Providing and fixing gun metal gate valve with


C.I. wheel of approved quality (screwed end) :
19

IIIT-GACHIBOWLI ABS-WS & SA-SQ-1 63 OF 354


Amount
Sl.No Description of Work Quantity Unit Rate
(Rs.)
25 mm nominal bore 120.00 each 850.00 102000.00
32 mm nominal bore 80.00 each 925.00 74000.00
40 mm nominal bore 40.00 each 1100.00 44000.00
50 mm nominal bore 44.00 each 1250.00 55000.00

Supplying, installing, testing and commissioning butterfly valves 'with


standard lever confirmingto IS 13039 with necessary connecting 'fittngs
20 like flanges, nuts and bolts etc., complete.
80 mm dia 1.00 each 4000.00 4000.00
65 mm dia 1.00 each 3500.00 3500.00
21 Hot water System
Solar Hot Water System
Design, supply, installation, testing & commissioning solar hot water
system in position, Alighning to correct position as per drawing,
finishing, sealing, testing and commissioning of the approved make
Solar Hot Water System confirming to IS 12933, designed for working
pressure of 3.5 bar and test pressure of 6 bar. Solar System includes
the SS304 Hot water insulated storage Tank, Skid Mounted Solar
collectors Panels, Collector support frame, including temperature
sensors and timer and wiring, etc. Hot Water re-circulation Pump
(1working+1standby), piping between collector pannel to tank in GI
class C, closed cell insulation with aluminium cladding, Valves &
accessories, electrical pannel, control panel for system etc complete as
per specifications. System shall be installed as per manufacturers
recommendations, fixtures and fittings as per specification. All work
complete as per direction of the Engineer-in-Charge, For capacities as
follows.

15000 liters per day 15000.00 Per Lit 200.00 3000000

9997485.00

IIIT-GACHIBOWLI ABS-WS & SA-SQ-1 64 OF 354


Name of Work : Construction of Proposed Apartment building at Moosapet ,
Hyderabad.
ABSTRACT ESTIMATE FOR STAFF QUARTERS BLOCK
S. Quantity Rate (Rs.)
Description of Work Unit Amount (Rs.)
NO. B1 in fig.
CONDUIT PIPE
1 17000.0 RM Supply and fixing of 25mm outer dia Heavy grade PVC ONE 71.0 1207000.00
pipe (ISI MARK) concealed in Roof Slabs with all required RM
PVC/MS deep boxes and all accessories including and
labour charges etc., complete.
Makes:- Sudhakar / Finolex / Modi / VIP / Precision
/ Universal / Million Plast

2 10000.0 RM Supply and fixing of 25mm outer dia Medium grade P.V.C. ONE 79.0 790000.00
pipe (ISI MARK) concealed in wall with all required RM
PVC/MS junction boxes and all accessories including
masonary work etc., complete.
Makes:- Sudhakar / Finolex / Modi / VIP / Precision
/ Universal / Million Plast

3 626.0 Nos Supply and fixing PVC / MS galvanished Fan hook box EACH 84.0 52584.00
with hook including all Labour charges etc., complete.

WIRING
4 1400.0 PTS Wiring with 2 runs of 22/0.3mm ( 1.5 Sq.mm) FRLS EACH 626.0 876400.00
P.V.C. insulated flexible copper cable (ISI MARK) in POINT
existing pipe with 6A Modular switch, Ceiling rose/BH/SBH
Modular switches with cover plate and GI switch box
including all labour charges etc., complete. (for
Residential Building)
Makes of wires :Finolex / RR kabel / Havells / APAR
EBXL / KEI / L&T / V- Guard.
Makes of switches:- Legrand Arteor / Schneider Zen
celo / Honeywell Blenge Plus / Cabtree Amare / Logus
Platina.

5 284.0 PTS Wiring with 2 runs of 22/0.3mm ( 1.5 Sq.mm) FRLS EACH 939.0 266676.00
P.V.C. insulated flexible copper cable (ISI MARK) in POINT
existing pipe with 6A Modular switch, Ceiling rose/BH/SBH
Modular switches with cover plate and GI switch box
including all labour charges etc., complete stairecase
points. (for Residential Building)
Makes of wires :- Finolex / RR kabel / Havells / APAR
EBXL / KEI / L&T / V- Guard.
Makes of switches:- Legrand Arteor / Schneider Zen
celo / Honeywell Blenge Plus / Cabtree Amare / Logus
Platina.

6 114.0 PTS Supply and fixing of 6A ISI Mark 3/2 pin Modular socket EACH 491.0 55974.00
with 6A 1way Modular switch, 3 Module box with cover POINT
frame and GI switch box on common switch board with
connections etc., complete.
Makes of wires :- Finolex / RR kabel / Havells / APAR
EBXL / KEI / L&T / V- Guard.
Makes of switches:- Legrand Arteor / Schneider Zen
celo / Honeywell Blenge Plus / Cabtree Amare / Logus
Platina.

IIIT-HYD ELEC-ABS-SQ-1 65 of 354


S. Quantity Rate (Rs.)
Description of Work Unit Amount (Rs.)
NO. B1 in fig.
7 456.0 PTS Wiring with 3 of 22/0.3mm ( 1.5 Sq.mm) FRLS / HFFR EACH 658.0 300048.00
P.V.C. insulated flexible copper cable (ISI MARK) in POINT
existing pipe with 6A switch and 6A, 3/2 pin socket
Modular type with 6A switch control and MS boxes with
cover plate and GI switch box fixing on separate board
including all labour charges etc., complete.
Makes of wires :- Finolex / RR kabel / Havells / APAR
EBXL / KEI / L&T / V- Guard.
Makes of switches:- Legrand Arteor / Schneider Zen
celo / Honeywell Blenge Plus / Cabtree Amare / Logus
Platina.

8 284.0 NOS Supply & fixing of 16A/6A, 2 in one socket with 16A switch EACH 675.0 191700.00
control modular type with and GI switch box with front
cover plate including all labour charges etc., complete.
Makes of wires :- Finolex / RR kabel / Havells / APAR
EBXL / KEI / L&T / V- Guard.
Makes of switches:- Legrand Arteor / Schneider Zen
celo / Honeywell Blenge Plus / Cabtree Amare / Logus
Platina.

RUN of MAINS
9 4000.0 RM Supply and run of 1 of 22 /0.3mm (1.5 Sq.mm) FRLS ONE 24.0 96000.00
P.V.C. insulated flexible copper cable in existing conduit RM
pipe for earth continuity including all labour charges etc.,
complete.
Makes of wires:-Finolex / RR kabel / Havells / APAR
EBXL / KEI / L&T / V- Guard.

10 400.0 RM Supply and run of 3 of 22 /0.3mm (1.5 Sq.mm) FRLS ONE 61.0 24400.00
P.V.C. insulated flexible copper cable in existing conduit RM
pipe for computer power points including all labour
charges etc., complete.
Makes of wires:- Finolex / RR kabel / Havells / APAR
EBXL / KEI / L&T / V- Guard.

11 7000.0 RM Supply and run of 3 of 2.5 sq.mm (phase neutral and ONE 105.0 735000.00
earth) FRLS PVC insulated flexible copper cable in RM
existing conduit pipe for individual lighting circuits
including labour charges etc., complete as required for
switch boards.
Makes of wires:- Finolex / RR kabel / Havells / APAR
EBXL / KEI / L&T / V- Guard.

12 6000.0 RM Supply and 3 runs of 4.0 sq mm (phase neutral and earth) ONE 151.0 906000.00
FRLS PVC insulated flexible copper cable in existing RM
conduit pipe including labour charges etc., complete for
16A sockets.
Makes of wires:- Finolex / RR kabel / Havells / APAR
EBXL / KEI / L&T / V- Guard.

13 3500.0 RM Supply and 3 runs of 6.0 sq mm (phase neutral and earth) ONE 216.0 756000.00
FRLS PVC insulated flexible copper cable in existing RM
conduit pipe including labour charges etc., complete for
SPNDB's & AC's.
Makes of wires:- Finolex / RR kabel / Havells / APAR
EBXL / KEI / L&T / V- Guard.

IIIT-HYD ELEC-ABS-SQ-1 66 of 354


S. Quantity Rate (Rs.)
Description of Work Unit Amount (Rs.)
NO. B1 in fig.
14 100.0 RM Supply & run of 5 of 10.0 Sqmm (phases, neutral and ONE 548.0 54800.00
earth) FRLS PVC insulated flexible copper cable in the RM
existing conduict pipe for run of mains from Power panel
board to TPN DB"s with pin type lugs and connections
etc., complete. [for PDBs]
Makes of wires:- Finolex / RR kabel / Havells / APAR
EBXL / KEI / L&T / V- Guard.

DISTRIBUTION BOARDS
15 284.0 NOS Supply and fixing of DP Metal Enclosure with IP 20 EACH 1426.0 404984.00
Protection DB Make with 1 No 20A , 10 KA DP MCB
including internal connections and concealing in wall with
labour charges etc., complete for AC's
Make: Legrand / Schneider.

16 284.0 NOS Supply and fixing of SPN 8 way distribution board IP-43 EACH 4775.0 1356100.00
in sheet Steel enclosure with 40 Amps DP Isolator as
incomer and 6 No of 20 Amps single pole, 10 KA breaking
capacity 'c' curve MCBs as outgoings including making
connections etc., complete concealing in wall.

Makes :
Legrand / Schneider.
17 6.0 NOS Supply and fixing of TPN 4 way distribution board IP-43 EACH 8055.0 48330.00
(8+12 Mofule) with provision to accommodate Isolator as
incomer and suitable for single pole outgoing MCB's in
sheet Steel enclosure with 63 Amps 4 pole Isolator as
incomer and 12 No of 20Amps single pole, 10 KA breaking
capacity 'c' curve MCBs as outgoings including making
connections etc., complete concealing in wall.

(POWER DB's) Makes : Legrand / Schneider.

18 6.0 Nos Supply and fixing TPN - 8 way Vertical type Distribution EACH 33982.0 203892.00
board with IP-43 Protection (Metal Door) suitable to
accommodate MCCB as incomer and single/three pole
MCBs as outgoings with 125A, TPN 25 kA MCCB as
incomer with 8 Nos of 63A, 10 KA TP MCBs 'c' curve as
outgoing including making connections and labour charges
etc., complete concealing in wall.
Makes : Legrand / Schneider.

Earthings
19 20.0 Nos Providing independent earthing by exacavating a pit to a Each 4603.0 92060.00
depth of 2.25Mtr in all soils as per size specified in the
data for Important equipment with 2.5Mtr length 40mm dia
'B' class G.I pipe and 18" dia 3" thick hume pipe ring with
R.C.C. Slab cover duly providing staggered holes filling
with 20Kg Salt and 40Kg Charcoal or 40Kg bentonite
powder from the bottom of the pipe giving earth
connection from electrode through G.I strip of 25 x 6mm x
200mm length to be bolted with nut bolts including supply
and termination of No.8 G.I.wire from bottm of the pipe
with all accessories and labour charges complete, as per
IS specifications 732/1982 (Part II)

IIIT-HYD ELEC-ABS-SQ-1 67 of 354


S. Quantity Rate (Rs.)
Description of Work Unit Amount (Rs.)
NO. B1 in fig.
20 200.0 Mtr Supply and Run of 25mm x 6mm G.I Strip including cost RM 98.0 19600.00
of all accessories and labour charges etc., complete.

21 200.0 Mtr upply and Run of 50mm x 6mm G.I Strip including cost of RM 199.0 39800.00
all accessories and labour charges etc., complete.

22 150.0 Mtrs Supply and run of No. 8SWG GI wire including cost of all RM 19.0 2850.00
accessories and labour charges etc complete.

FIXTURES
23 854.0 NOS Supply, transportation and fixing of 20W, 2000 EACH 1185.0 1011990.00
lumens, T8,1200mm length LED tube light (Industrial
Application) input voltage AC 220 - 260Volts with
PF≥0.9, Surge protection: 2KV,THD<10%, with inbuilt
driver and frosted cover CCT: 3000K - 5700K,
minimum CRI≥80,.etc., complete Manufacture has to
submit LM79,LM80 & Photobiological Safety Report.
Luminaire Performance Complies to IS10322 (Part 5/Sec
3) & IEC 60598-1,IEC 60529 ISO certified company.
MAKE: Phillips / OSRAM / GE / Crompton / VIN / Bajaj /
Havells / HPL/Surya/Syska.

24 626.0 NOS Supply and fixing of ISI mark batten holder / slanting EACH 119.0 74494.00
holder Makes : Anchor / Gold Medal Olive / Million Zoom in
lieu of ceiling rose of light point complete with all
connections and all labour charges with 0.5W LED Lamp
Makes: Phillips / OSRAM / GE / Crompton / VIN / Bajaj /
Havells / HPL/Surya.

25 626.0 NOS Supply of 48" (1200mm) Sweep ISI mark Ceiling Fan as EACH 2312.0 1447312.00
per IS 374 - 1979 and, with double ball bearings but
without Regulator.
Makes : Crompton High speed/ Bajaj Regal star / Havells
Fusion / Orient PSPO Summer King / Usha technix
decorative

26 626 NOS Supply and fixing of modular Electronic stept type fan EACH 527.0 329902.00
regulator hum free step type socket size with MS box,
front plate in the existing switch board ( Modular Type
)
Makes of switches:- GM Four-Five / Legrand Arteor /
Schneider Zen celo / Honeywell Blenge
Plus / Cabtree Verona / Million Logus / Gold Medal Curve /
Anchor Roma viola.

27 626 NOS Labour charges for Fixing of Ceiling fan including giving EACH 151.0 94526.00
connections with twin core wire etc., complete.

28 114.0 NOS Supply,Transportation of light duty exhaust fan 12"(300 EACH 1585.0 180690.00
mm) size 900 rpm with metal blades wiremesh with all
accessories etc complete. Makes : Crompton / Bajaj
Bahar WG / Havells Ventil Air-DB / Orient hill air.

29 114 NOS Labour charges for fixing of Exhaust fan in wall with EACH 669.0 76266.00
necessary connections and masonary work including
material of making hole, finishing etc., complete.

IIIT-HYD ELEC-ABS-SQ-1 68 of 354


S. Quantity Rate (Rs.)
Description of Work Unit Amount (Rs.)
NO. B1 in fig.
30 284 NOS Supply and fixing of louver shutter suitable for 12" Exhaust EACH 328.0 93152.00
fan including all labour charges etc complete with
connections and colouring matching to the wall with
enamel paint.

31 114.0 NOS Supply and fixing of Ding Dong Bell Makes : GM / Million / EACH 190.0 21660.00
Gold Medal / Anchor / Great white on 4"x7" decolam block
including giving connections, cost of all accessories and
labour charges etc., complete.

Telephone & EPABX-NETWORK


32 114.0 Nos Supply and fixing of Modular telephone Jack with each 261.0 29754.00
connector on modular box with cover frame Makes : GM
Four-Five / Legrand Arteor / Schneider Zen celo / Million /
Logus / Gold Medal Curve / Anchor Roma viola / CPL /
Great White in existing consealed pipe wiring including
cost and coveyance of all material and all labour charges
etc., complete in N.R.B. / R.B.

33 3420.0 Mtrs Supply, Transportation and Run of 1 of 2 Pair, 0.5mm RM 22.0 75240.00
telephone copper wire Makes : Finolex / Delton / Surabi /
Polycab in the existing cable tray/ conduit pipe and
labour charges etc., complete.

34 200.0 Mtrs Supply, Transportation and Run of 1 of 10 Pair, 0.5mm RM 55.0 11000.00
telephone copper wire Makes : Finolex / Delton / Surabi /
Polycab in the existing cable tray/ conduit pipe and labour
charges etc., complete.

35 12.0 No Supply, Transportation and Fixing of 10 pair MDF/ each 780.0 9360.00
Telephone distribution box with back mount frame, krone
connector, powder coated metal body of best quality and
make as directed with lock and key arrangement including
all accessories and labour charges etc., complete.

36 2.0 No Supply, Transportation and Fixing of 100 pair Telephone each 4384.0 8768.00
distribution box with back mount frame, krone connector,
powder coated metal body with lock and key arrangement
including all accessories and labour charges etc.,
complete.

LAN -NETWORK
37 60.0 Nos Supply, Transportation and Fixing of Cat 6 RJ-45 each 457.0 27420.00
information outlets Makes : D Link / AMP / Molex /
Legrand / Krone including duel face plate including all
accessories and labour charges etc., complete.

38 1800.0 Mtrs Supply, Transportation and Run of 1 of LAN Cable cat - 6 RM 36.0 64800.00
UTP cable Makes : D Link / AMP / Molex / Legrand /
Krone in the existing cable tray/ conduit pipe and labour
charges etc., complete.

39 3.0 Nos Supply, Transportation and Fixing of 24 Port manageble each 7220.0 21660.00
switches Makes : CISCO / Net Gear / HP / D link including
all accessories and labour charges etc., complete.

IIIT-HYD ELEC-ABS-SQ-1 69 of 354


S. Quantity Rate (Rs.)
Description of Work Unit Amount (Rs.)
NO. B1 in fig.
40 3.0 Nos Supply, Transportation and Fixing of 24 port patch panels each 7220.0 21660.00
Makes : D Link / AMP / Molex / Legrand / Krone including
all accessories and labour charges etc., complete.

41 1.0 Nos Supply, Transportation and Fixing of 19" 12U floor / Wall each 6995.0 6995.00
mounting net work rack Makes : HCL / Vall with power
spike including all accessories and labour charges etc.,
complete.

42 1000.0 RMS Supply, Transportation and Run of 1 of RG6 Co-axial One 33.0 33000.00
Cable Makes : Finolex / Delton / Surabi / Polycab for TVs RM
in the existing cable tray/ conduit pipe and labour charges
etc., complete.

Metering Sub-Panel - 1
43 2.0 No Supply installation testing and commissioning of 3 phase each 139700.0 279400.00
and neutral 415V free standing floor mounted Indoor Type
MV panel made out of No.16/14 gauge CRCA sheet steel
after 7 tank process and painting with powder coating.
The panel shall consists of suitable rating TPN Aluminium
bus bar ( with rating of 0.8A/ Sqmm)supported with
DMC /SMC barriers and colour coaded with heat
shrinkable sleeves, flexibility to accept the up four out
going cables and necessary cable chamber . The panel
shall have comprised of following switch gear . Including
supply and fixing the same and painting with powder
coating including internal connections cost and
conveyance of all materials & labour charges.

425A Aluminium Bus Bar with colour code.(0.8A/Sqmm).

Incomer:
250A 4 Pole MCCB, Adjustable, Confirms to IS/IEC
60947-2 having Breaking Capacity 35 KA with thermal
magnetic release Panel Mounted of makes L&T (DN2-
250N) / Schneider / Siemens / Hager as incomer. - 1 No.

Out goings:
40-63A 10KA TP MCB, C/D Curve ISI Mark of Makes :
Legrand-DX3 / Schneider-Acti9. - 26 Nos.
(25 Nos., for quarters+1 No for Common- 26 )

Supply and erection of 0-415V volt Digital meter of size


96x96mm on existing box / panel board including
connections etc., complete of CONZERVE /
ELMEASURE / MECO / HPL MAKE. - 1 No.
Supply and erection of 0-100 / 200 / 400 / 600 /1000 - 5A
CT Digital Ammeter of size 96x96mm on existing box /
panel board including connections etc., complete of
CONZERVE / ELMEASURE / MECO / HPL MAKE. - 1
No.

Supply and erection of Analog selector switch for voltmeter


/ Ammeter on the existing box / panel including
connections etc., complete. L&T / C&S / SALZAR / HPL
MAKE. - 2 Nos
Supply and erection of Analog LED indicator lamps on the
existing box / panel board.L&T / C&S / SALZAR / HPL
MAKE. - 3 Nos.

IIIT-HYD ELEC-ABS-SQ-1 70 of 354


S. Quantity Rate (Rs.)
Description of Work Unit Amount (Rs.)
NO. B1 in fig.
Supply and erection of Analog LT current transformer with
bar primary 100/5A to 1000 / 5A ratio in the existing box /
panel including connections etc., complete. KAPPA
MAKE. - 3 Nos
Provision for 26 three phase meters in the panel
Labour charges etc complete with connections for
Finished item of work.
TOTAL: 12399247.00

IIIT-HYD ELEC-ABS-SQ-1 71 of 354


Name of Work : Construction of Proposed Apartment building at
Moosapet , Hyderabad.
SUMMARY
Sl. No. Description of Item Amount
1 APARTMENT BLOCK
a Civil works `. 29177068
b Internal Water Suppply & Sanitary `. 0
c Internal Electrification `. 12399247
d Fire fighting system
Sub total: `. 41576315

Sub total: `. #REF!


2 Provision towards Architectural features @ 2.0% `. #REF!
3 Provision for Lifts -6 Nos @ 2500000 / Each `. 15000000
Total ECV `. #REF!

You might also like