You are on page 1of 4

Daily Progress Report

Date: Tuesday, May 25, 2021


Project Title: Infrastructure Development of Qurtaba City, Chakri, Rawalpindi Weather: Sunny
Site Location: Rawalpindi Contractor: M/s HSSR Consultant: M/s Techno Legal Consultants (Pvt) Ltd.
Yesterday Works Detail
1) Yesterday Activities at site
Location Target Manpower
Total
Sr. # Activity ID Activity Description Planned Units Achieved/N Tentative Time
Zone Section Quantity Skilled Un-Skilled
ot
1 Aggregate Base Course Spreading R/S (32+00-36+00) Phase - 1 Access Road Achieved 1

2 Embankment 1st Layer Compaction L/S (48+00-51+00) Phase - 1 Access Road Achieved 1 6

3 Sub base 2nd Layer Levelling L/S (12+00-14+50) Phase - 1 Access Road Achieved 3 3

4 Sub base 2nd Layer Compaction R/S (44+00-53+50) Phase - 1 Access Road Achieved 1

5 Cutting & Preparation of subgrade R/S (2+00-4+00) Phase - 1 Access Road Achieved 5

6 Batching Plant, (Daily Basis) Phase - 1 9

7 Kerb & Tuff Tile Factory, (Daily Basis) Phase - 1 8

8 Sewer Pipe Factory, (Daily Basis) Phase - 1 7

9 Watering of Plants, (Daily Basis) Phase - 1 2

10 Grass Cutting, trimming, (Daily Basis) Phase - 1 10

11 Concrete bed drain (21+00-25+00) L/S Phase - 1 MR-2 Achieved 6

12 Shuttering & Steel Fixing (9+00-16+00) L/S Phase - 1 MR-2 In progress 5

13 Concrete Drain Bed (80+00-82+00) R/S Phase - 1 MR-2 Achieved 6

14 Shuttering Drain (76+00-82+00) L/S Phase - 1 MR-2 Achieved 5

15 Excavation of Drain (70+00-72+00) R/S Phase - 1 MR-2 Achieved 2

16 Road Cutting (LN-59) Phase - 1 Block - A In progress 2

17 Shuttering Removal Phase - 1 Main Gate In progress 3

18 Plaster Work in Baths Phase - 1 Main Gate In progress 1 1

Sr. Project Manager CRE

Page 1 of 4
Daily Progress Report
3) Status of Plant & Equipment

Please attach page separately duly initialled.

4) Status of Manpower

Please attach page separately duly initialled.

5) Bottlenecks / Problems
Sr. # Description Responsibility of Decision
1
2
3
4

Sr. Project Manager CRE

Page 2 of 4
Daily Progress Report
Date: Wednesday, May 26, 2021
Project Title: Infrastructure Development of Qurtaba City, Chakri, Rawalpindi Weather: Sunny
Site Location: Rawalpindi Contractor: M/s HSSR Consultant: M/s Techno Legal Consultants (Pvt) Ltd.
Today Works Detail
1) Today Activities at site
Location Total Executed in Executed Manpower
Sr. # Activity ID Activity Description Units Tentative Time
Zone Section Quantity Period To date Skilled Un-Skilled

1 Aggregate Base Course Dumping R/S (44+00-48+00) Phase - 1 Access Road 1

3 Sub base 2nd Layer preparation L/S (8+00-12+00) Phase - 1 Access Road 3 3

5 Dumping sub-base 1st layer R/S (70+00-75+00) Phase - 1 Access Road 5

Cutting in Commercial Area Phase - 1 2

6 Batching Plant, (Daily Basis) Phase - 1 9

7 Kerb & Tuff Tile Factory, (Daily Basis) Phase - 1 8

8 Sewer Pipe Factory, (Daily Basis) Phase - 1 7

9 Watering of Plants, (Daily Basis) Phase - 1 2

10 Grass Cutting, trimming, (Daily Basis) Phase - 1 10

12 Shuttering & Steel Fixing (13+00-16+00) R/S Phase - 1 MR-2 5

13 Concrete Drain Wall (80+00-82+00) R/S Phase - 1 MR-2 6

14 Concrete of Drain Bed (76+00-80+00) L/S Phase - 1 MR-2 5

15 Bed Dressing of Drain (70+00-72+00) R/S Phase - 1 MR-2 2

16 Road Cutting (LN-59) Phase - 1 Block - A 2

17 Shuttering Removal Phase - 1 Main Gate 3

18

Sr. Project Manager CRE

Page 3 of 4
Daily Progress Report
3) Status of Plant & Equipment

Please attach page separately duly initialled.

4) Status of Manpower

Please attach page separately duly initialled.

5) Bottlenecks / Problems
Sr. # Description Responsibility of Decision
1
2
3
4

Sr. Project Manager CRE

Page 4 of 4

You might also like