Role of Calendars in Project Scheduling
Now activity having duration of 4 days, will take 7 calendar days to complete
Defining and Assigning Calendars
To add, modify or delete calendar go to main menu and click enterprise then calendars
Defining and Assigning Calendars
Global Calendar
can be assigned
to any project or
resource.
Calendars are
divided intro three
categories
Defining and Assigning Calendars
To change starting day of week go to main menu and click admin then admin preferences
In general tab
select starting
day of week as
Monday
Defining and Assigning Calendars
Different modify options of Global Calendar
Defining and Assigning Calendars
To create a new calendar click on add button