You are on page 1of 2

DAILY PROGRESS REPORT

Project: DEVELOPMENT OF INFRASTRUCTURE WORKS OF QURTABA CITY CHAKRI, RAWALPINDI

Client: M/s QURTABA ALLIED DEVELOPMENT AND MANAGEMENT COMPANY (QADAM)

Consultant: TECHNO LEGAL CONSULTANTS (PVT.) LTD. (TLC)

Contractor: M/s HASNAAT BROTHERS, SULTAN ESTATE AND ROYAL REAL ESTATE JV (HSSR)

Site Activities: Weather: Sunny Date: 05/03/2022

Sr. # Block Street Name RD Description of Work Remarks

1 Access Road 0+00 Pipe laying for Utility crossing

2 Mini Gate Foundation Work

3 Main Gate Stone Work & Wall Putty Paint

4 Marketing Office Tile Work & Ceiling Work

5 Property Office Ceiling Work

6 Civic Center MR-1 (200') 10+00-15+00 Earthwork (Embankment)

7 Civic Center MR-1 (200') 67+00-75+00 Drain Work (Top Slab Shuttering + Concrete)L/S

8 Civic Center MR-1 (200') 67+00-75+00 Drain Work (Bed Shuttering + Concrete)R/S

9 Block - A Sewer Work

10 Block - B Sewer Work

11 Block - M Earthwork (Cutting)

12 Kerb Factory Kerb Stone (Precasting)

13 Sewer Factory RCC Pipe (Precasting)

14 Asphalt Plant Plant Fixing

15 Block - G Transformer Pad Foundation Precasting

HSSR Rep: Consultant Rep:


DAILY MANPOWER & T/P REPORT

Project: Development of Qurtaba City Chakri, Rawalpindi


Client: MADINA TUL ILM
Consultant: TLC
Contractor: HSSR

S.No Office Staff Nos. S.No Equipments / Machinery Nos.


1 Senior Project Manager 1 1 Motor Grader 7
2 Project Manager 1 2 Plain Roller 7
3 Planning Engineer 1 3 Sheep Foot Roller 1
4 SQS 1 4 Excavator 8
5 Project Superintendent 1 5 Loader 2
6 Finance Manager 1 6 Dump Truck 7
7 Senior Accountant 1 7 Transit Mixer 2
8 Assistant Accountant 1 8 Tractor With Trolley 14
9 Office Boy 1 9 Tractor Loader 1
Field Staff 10 Water Tanki 2
1 Asst. Project Manager 1 11 Trolley Hyd Jack 12
2 Site Engineer Civil 6 12 Water Bowser Truck 10
3 Site Engineer Electrical 2 13 Truck Fotan (Diesel Bowser) 1
4 Site Supervisor 5 14 Gen 200 KVA 1
5 Survey Section 16 15 Gen 100 KVA 1
6 Foreman (Civil) 4 16 Gen 30 KVA 1
7 Lab Technician 4 17 Gen 05 KVA 3
Admin Staff 18 Gen 03 KVA 1
`2 Plant Supervisor 1 19 Double Cabin 3
`3 Admin Supervisor 1 20 Shehzore 1
`4 Store Keeper 1 21 Suzuki Pick up 1
`5 Cook 3 22 Suzuki Van 1
`6 Cook Helper 2 23 Jeep 1
`7 MT Supervisor 1 24 Motor Cycle 8
Horticulture Staff 25 Bed Compactor 2
1 Horticulture Engineer 1 26 Steel Bending Machine 1
2 Horticulture Supervisor 1 27 Steel Cutting Machine 1
3 Mali 12 28 Vibrator 3
Drivers / Operators 29 Mud Pump 3
1 T&P Operators 14 30 Air Compressor 1
2 Driver LTV 5 31 Jumper Compactor 1
3 Mechanic Section 4 32 Concrete Mixer Machine 3
Mason / Labour / Security 33 Concrete Batching Plant 1
1 Security Guard 6 34 Sewer Pipe Factory 1
2 Company Labour 13 35 Kerb Stone Factory 1
3 Sub Contractor Labour 110 36 Crane Mounted Low bed Trailer 1
37 Asphalt Plant 1
38 Block Factory 1
Total Manpower 222 Total T&P 117