Project: HKLX IVS1

Daily Site Report


Date: 1/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 1900HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 0 1 Container Office / Store / Changing room 9
2 Site Manager 0 2 Lab Container (8' x 4') 1
3 Site Engineer 0 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 0 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 0 5 Water Pump 3
6 Site Supervisor 0 6 Tsurumi Pump 2
7 Safety & Health Officer / Superviso 0 7 Bentonite Mixer 1
8 Site Clerk 0 8 Water Tank 1
9 Grab Operator 0 9 Welding Set/ MIG 6
10 BG Operator 0 10 DB Box 4
11 Crane Operator 0 11 Tower Light 6
12 Excavator Operator 0 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 0 13 Steel Plates 99
14 Welder 0 14 Silo 23
15 General Worker 1 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 0 16 Water Stop End (sets) 3
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 6
21 Bar cutting machine 3
22 Mud tank 5
23 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
24 Boring Rig (BG28, Zoomlion ZR280) 2
25 Service Crane 3
26 Excavator (EX225, SH200, CAT320) 3
27 Clamshell (Mechanical/Hydraulic) 4
28 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
29 C-Mixer 1
Total 1

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 16a - 30.5m - - 32m 32m - - -
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m Backfilled to ground level
Panel C04 - 38.3m 38.5m 38.5m 37m 37m 38.5m 38.5m No activity
Panel C09 - 38.2m 38.2m 38m - - - - -
Panel C14 - 38.3m 38m 38m 38m 38m 38m 38m No activity
Panel C19 - 23m - 10.5m - - - - -
Breakdown GB34 (Breakdown), JPN HS855 (Machine cannot start)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Nil Dwall 87 76 0 11
Cross wall 56 33 0 23
Total: 143 109 0 34

Other Activities Material Delivered to Site: Unit Quantity


1. Public Holiday Nil

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 2/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 1900HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 0 1 Container Office / Store / Changing room 9
2 Site Manager 1 2 Lab Container (8' x 4') 1
3 Site Engineer 2 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 1 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 2 5 Water Pump 3
6 Site Supervisor 3 6 Tsurumi Pump 2
7 Safety & Health Officer / Superviso 0 7 Bentonite Mixer 1
8 Site Clerk 1 8 Water Tank 1
9 Grab Operator 3 9 Welding Set/ MIG 6
10 BG Operator 2 10 DB Box 4
11 Crane Operator 2 11 Tower Light 6
12 Excavator Operator 2 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 1 13 Steel Plates 99
14 Welder 2 14 Silo 23
15 General Worker 22 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 0 16 Water Stop End (sets) 3
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 6
21 Bar cutting machine 3
22 Mud tank 5
23 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
24 Boring Rig (BG28, Zoomlion ZR280) 2
25 Service Crane 3
26 Excavator (EX225, SH200, CAT320) 3
27 Clamshell (Mechanical/Hydraulic) 4
28 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
29 C-Mixer 1
Total 44

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 16a TRN 855 30.5m - 31m - - 32m 32m - - Continue excavation
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m Backfilled to ground level
Panel C04 - 38.3m 38.5m 38.5m 37m 37m 38.5m 38.5m No activity
Panel C09 - 38.2m 38.2m 38m - - - - No activity
Panel C14 - 38.3m 38m 38m 38m 38m 38m 38m Start desanding
Panel C19 HS885 23m - 38.1m - 10.5m - - - - Continue excavation
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Mortar 1:10 C27 108m³ Backfilled until guidewall level Dwall 87 76 0 11
Cross wall 56 33 0 23
Total: 143 109 0 34

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. Start and finished install cage for C39F
4. Cement grouting for Sonic logging at Panel 60
5. Mechanic reparing desander vibrator motor
6. Start desanding C14 with JPN HS855
7. C39F concrete casting postponed as per IDET instruction due no activities is allowed beyond 12 mid nig

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 3/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 1900HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 1 1 Container Office / Store / Changing room 9
2 Site Manager 1 2 Lab Container (8' x 4') 1
3 Site Engineer 2 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 1 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 2 5 Water Pump 3
6 Site Supervisor 3 6 Tsurumi Pump 2
7 Safety & Health Officer / Superviso 1 7 Bentonite Mixer 1
8 Site Clerk 1 8 Water Tank 1
9 Grab Operator 3 9 Welding Set/ MIG 5
10 BG Operator 2 10 DB Box 4
11 Crane Operator 2 11 Tower Light 6
12 Excavator Operator 2 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 0 13 Steel Plates 99
14 Welder 2 14 Silo 23
15 General Worker 22 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 0 16 Water Stop End (sets) 3
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 6
21 Bar cutting machine 3
22 Mud tank 5
23 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
24 Boring Rig (BG28, Zoomlion ZR280) 2
25 Service Crane 3
26 Excavator (EX225, SH200, CAT320) 3
27 Clamshell (Mechanical/Hydraulic) 4
28 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
29 C-Mixer 1
Total 45

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 16a - 31m - - 32m 32m - - No activity, C14 cages lowering
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m Backfilled to ground level
Panel C04 - 38.3m 38.5m 38.5m 37m 37m 38.5m 38.5m Start desanding
Panel C09 - 38.2m 38.2m 38m - - - - No activity
Panel C19 HS885 38.1m - 30m - 31.5m - - - - Continue excavation, welding 2 pcs of teeth holder
Panel C32 TRN HS855 20.4m - 29.5m - - - - - - Continue excavation
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G40 C39F - Casting ongoing Dwall 87 76 0 11
Cross wall 56 33 0 23
Total: 143 109 0 34

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. Offhire one unit of Daiden welding set (DW333)
4. Start and finished lowering cage for C14
5. Soil removing out at Dwall P21 to P16a for access
6. Start desanding C04 with JPN HS855

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 4/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 1900HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR HEAVY RAIN HEAVY RAIN
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 1 1 Container Office / Store / Changing room 9
2 Site Manager 1 2 Lab Container (8' x 4') 1
3 Site Engineer 2 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 1 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 2 5 Water Pump 3
6 Site Supervisor 3 6 Tsurumi Pump 2
7 Safety & Health Officer / Superviso 1 7 Bentonite Mixer 1
8 Site Clerk 1 8 Water Tank 1
9 Grab Operator 3 9 Welding Set/ MIG 5
10 BG Operator 2 10 DB Box 4
11 Crane Operator 2 11 Tower Light 6
12 Excavator Operator 2 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 0 13 Steel Plates 99
14 Welder 2 14 Silo 23
15 General Worker 22 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 0 16 Water Stop End (sets) 3
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 6
21 Bar cutting machine 3
22 Mud tank 5
23 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
24 Boring Rig (BG28, Zoomlion ZR280) 2
25 Service Crane 3
26 Excavator (EX225, SH200, CAT320) 3
27 Clamshell (Mechanical/Hydraulic) 4
28 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
29 C-Mixer 1
Total 45

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 05F HS885 25.5m - 32m - 1m - 23m - - - - Hit Rock at 32m FB
Panel 16a - 31m - - 32m 32m - - No activity, C14 casting and mortar backfilling
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m Backfilled to ground level
Panel C04 - 38.3m 38.5m 38.5m 37m 37m 38.5m 38.5m Finished desanding and installed 2 cages
Panel C09 - 38.2m 38.2m 38m - - - - No activity
Panel C19 - 38.1m - 34m - - - - No Activity
Panel C32 TRN HS855 33m - 36m - - - - - - Continue excavation
Panel C40aF JPN HS855 1m - 22m - - - - - - Start Excavation
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G40 C14 175m³ Cast time: 1202hrs - 1600hrs Dwall 87 76 0 11
Mortar 1:10 C14 116m³ Backfilling in progress Cross wall 56 34 1 21
Total: 143 110 1 32

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. Return one unit of stop end chisel and 2 tremie hopper back to yard
4. Finsihed desanding and lowering 2 cages for C04

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 5/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 1900HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 1 1 Container Office / Store / Changing room 9
2 Site Manager 1 2 Lab Container (8' x 4') 1
3 Site Engineer 2 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 1 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 2 5 Water Pump 3
6 Site Supervisor 3 6 Tsurumi Pump 2
7 Safety & Health Officer / Superviso 1 7 Bentonite Mixer 1
8 Site Clerk 1 8 Water Tank 1
9 Grab Operator 3 9 Welding Set/ MIG 5
10 BG Operator 2 10 DB Box 4
11 Crane Operator 2 11 Tower Light 6
12 Excavator Operator 2 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 2 13 Steel Plates 99
14 Welder 2 14 Silo 23
15 General Worker 22 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 12 16 Water Stop End (sets) 3
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 6
21 Bar cutting machine 3
22 Mud tank 5
23 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
24 Boring Rig (BG28, Zoomlion ZR280) 2
25 Service Crane 3
26 Excavator (EX225, SH200, CAT320) 3
27 Clamshell (Mechanical/Hydraulic) 4
28 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
29 C-Mixer 1
Total 59

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 05F Zoomlion 32m - 26m 32m - 35m 32m - 35m - - Hit Rock at 32m FB
Panel 16a HS885 31m - 32m - 1m - 12m 32m 32m - - No activity, C14 casting and mortar backfilling
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m Backfilled to ground level
Panel C09 BG28 38.2m 38.2m 38m - - - - Cleaning and prepare for desanding
Panel C19 - 38.1m - 34m - - - - No Activity
Panel C32 TRN HS855 37.5m - 38m - 1m - 9m - - - - Continue excavation
Panel C40aF JPN HS855 36.5m - 37.8m - 1m - 30m - - - - Hit rock at 37.8m FB
Breakdown GB34 (Breakdown), TRN HS855 (Hydraulic leaking)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G40 C04 177m³ Cast time: 1618hrs - 2035hrs Dwall 87 76 0 11
Mortar 1:10 C04 110m³ Backfilled Cross wall 56 35 1 20
Total: 143 111 1 31

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Bentonite ton 10
2. General housekeeping
3. Replaced HS885 body wire 36mm 110m LHLL
4. TRN HS855 hydraulic motor pump leaking
5. Welding TRN HS855 teeth holder
6. Demobilized 200T service crane out from site

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 6/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 1900HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 1 1 Container Office / Store / Changing room 9
2 Site Manager 1 2 Lab Container (8' x 4') 1
3 Site Engineer 2 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 1 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 2 5 Water Pump 3
6 Site Supervisor 3 6 Tsurumi Pump 2
7 Safety & Health Officer / Superviso 1 7 Bentonite Mixer 1
8 Site Clerk 1 8 Water Tank 1
9 Grab Operator 3 9 Welding Set/ MIG 5
10 BG Operator 2 10 DB Box 4
11 Crane Operator 2 11 Tower Light 6
12 Excavator Operator 2 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 2 13 Steel Plates 99
14 Welder 2 14 Silo 23
15 General Worker 22 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 12 16 Water Stop End (sets) 3
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 6
21 Bar cutting machine 3
22 Mud tank 5
23 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
24 Boring Rig (BG28, Zoomlion ZR280) 2
25 Service Crane 2
26 Excavator (EX225, SH200, CAT320) 3
27 Clamshell (Mechanical/Hydraulic) 4
28 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
29 C-Mixer 1
Total 59

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 05F HS885 32m - 33.5m - 26m 35m 35m - - Hit Rock at 32m FB
Panel 16a Zoomlion 32m - 24m 32m - 34m 32m - 34m - - Hit rock at 24m NB
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m Backfilled to ground level
Panel C09 - 38.2m 38.2m 38m - - - - Start and finished desanding
Panel C19 - 38.1m - 34m - - - - No Activity
Panel C32 JPN HS855 38m - 9m - 36.6m - - - - Continue excavation
Panel C40aF BG28 37.8m - 34m - - 34m - 36m 34m - 36m Hit rock at 37.8m FB
Breakdown GB34 (Breakdown), TRN HS855 (Hydraulic leaking)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Nil Dwall 87 76 0 11
Cross wall 56 36 0 20
Total: 143 112 0 31

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Steel Rebar T40 bdl 44
2. General housekeeping
3. Finished installed cages for C09
4. Hacking platform for KP4 Barret pile guidewall making
5. P32 and P33 Sonic Logging pipes grouting on going
6. Replaced JPN HS855 clamshell 43m length LHOL wire rope

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 7/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 1900HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 0 1 Container Office / Store / Changing room 9
2 Site Manager 1 2 Lab Container (8' x 4') 1
3 Site Engineer 1 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 0 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 1 5 Water Pump 3
6 Site Supervisor 3 6 Tsurumi Pump 2
7 Safety & Health Officer / Superviso 1 7 Bentonite Mixer 1
8 Site Clerk 0 8 Water Tank 1
9 Grab Operator 3 9 Welding Set/ MIG 5
10 BG Operator 2 10 DB Box 4
11 Crane Operator 2 11 Tower Light 6
12 Excavator Operator 1 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 0 13 Steel Plates 99
14 Welder 2 14 Silo 23
15 General Worker 22 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 0 16 Water Stop End (sets) 3
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 6
21 Bar cutting machine 3
22 Mud tank 5
23 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
24 Boring Rig (BG28, Zoomlion ZR280) 2
25 Service Crane 2
26 Excavator (EX225, SH200, CAT320) 3
27 Clamshell (Mechanical/Hydraulic) 4
28 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
29 C-Mixer 1
Total 39

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 05F Zoomlion 33.5m - 26m 35m - 36m 35m - 36m - - Hit Rock at 32m FB
Panel 16a - 33m - 24m 34m 34m - - Hit rock at 24m NB
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m Backfilled to ground level
Panel C19 - 38.1m - 34m - - - - No Activity
Panel C32 JPN HS855 38m 1m - 38m 37m - 38.2m - - - - Finished excavation and start desanding
Panel C40aF - 37.8m - 37m - - 36m 36m Removed one length of stopend
Breakdown GB34 (Breakdown), TRN HS855 (Hydraulic leaking)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G40 C09 176m³ Cast Time: 1430hrs - 1915hrs Dwall 87 76 0 11
Cross wall 56 36 1 19
Total: 143 112 1 30

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Steel Rebar T12 bdl 5
2. General housekeeping Steel Rebar T16 bdl 25
3. Chiseling and taking out one stop end for C40aF Steel Rebar T25 bdl 20
4. Liebherr mechanic servicing HS885
5. Remove one length of stop end at C40aF

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 8/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 1900HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day RAIN FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 1 1 Container Office / Store / Changing room 9
2 Site Manager 1 2 Lab Container (8' x 4') 1
3 Site Engineer 2 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 1 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 2 5 Water Pump 3
6 Site Supervisor 3 6 Tsurumi Pump 2
7 Safety & Health Officer / Superviso 1 7 Bentonite Mixer 1
8 Site Clerk 1 8 Water Tank 1
9 Grab Operator 3 9 Welding Set/ MIG 5
10 BG Operator 2 10 DB Box 4
11 Crane Operator 2 11 Tower Light 6
12 Excavator Operator 2 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 0 13 Steel Plates 99
14 Welder 2 14 Silo 23
15 General Worker 22 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 12 16 Water Stop End (sets) 3
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 57

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F HS885 1m - 2m - - - - - - Start excavation
Panel 05F HS885 33.5m - 35m - 26m - 26.5m 36m 36m - - Hit Rock at 32m FB
Panel 16a Zoomlion 33m - 24m 34m - 36m 34m - 36m - - Hit rock at 24m NB
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m Backfilled to ground level
Panel C19 JPN HS885 38.1m - 34m - 36m - - - - Welding 2 holders and replaced 1 teeth
Panel C40aF BG28 37.8m - 37m 37.8m 37.8m 37m - 38m 37m - 38m Removed another one of stopend
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G30 - 32m³ Concrete slab between CW7 - CW8 Dwall 87 76 0 11
Cross wall 56 37 0 19
Total: 143 113 0 30

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Bentonite ton 10
2. General housekeeping
3. Continue removing another stop end at C40aF and P05F
4. Liebherr mechanic checking HS885 free fall brake paddle
5. Fnished desanding and fnished lowering cages for C32
6. Reparing TRN HS855 hydraulic motor and replaced O-Ring, resumed work 1100hrs

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 9/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 1900HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day RAIN RAIN RAIN RAIN FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 1 1 Container Office / Store / Changing room 9
2 Site Manager 1 2 Lab Container (8' x 4') 1
3 Site Engineer 2 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 1 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 2 5 Water Pump 3
6 Site Supervisor 3 6 Tsurumi Pump 2
7 Safety Supervisor 1 7 Bentonite Mixer 1
8 Site Clerk 1 8 Water Tank 1
9 Grab Operator 3 9 Welding Set/ MIG 5
10 BG Operator 2 10 DB Box 4
11 Crane Operator 2 11 Tower Light 6
12 Excavator Operator 2 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 0 13 Steel Plates 99
14 Welder 2 14 Silo 23
15 General Worker 17 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 12 16 Water Stop End (sets) 3
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 52

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F HS885 30m - 38.2m - 1m - 3m - - - - Continue excavation
Panel 05F Zoomlion 35m - 26.5m 36m 36m 26m - 27.5m 26m - 29m Hit Rock at 32m FB
Panel 16a TRN HS885 33m - 24m - 26.5m 36m 36m - - Hit rock at 24m NB
Panel 19 TRN HS885 1m - 4m - - - - - - Start excavation
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C19 JPN HS885 38.1m 1m - 38.2m 38.3m - - - - Trimming NB from 17m - 25m
Panel C40aF BG28 37.8m - 37m 37.8m - 39m 37.8m - 39m 38m 38m Continue coring
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G40 C32 176m³ Cast Time: 1200hrs - 1600hrs Dwall 87 76 0 11
Mortar 1:10 C32 - Backfilling Cross wall 56 37 1 18
Total: 143 113 1 29

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Steel Rebar T32 bdl 45
2. General housekeeping
3. Prepare for C19 desanding
4. Cage fabrication for P16a ongoing
5. Dismantle one stop end length and ready to send back to yard

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 10/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 1900HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day RAIN RAIN FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR Drizzling RAIN
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 1 1 Container Office / Store / Changing room 9
2 Site Manager 1 2 Lab Container (8' x 4') 1
3 Site Engineer 2 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 1 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 2 5 Water Pump 3
6 Site Supervisor 3 6 Tsurumi Pump 2
7 Safety Supervisor 1 7 Bentonite Mixer 1
8 Site Clerk 1 8 Water Tank 1
9 Grab Operator 3 9 Welding Set/ MIG 5
10 BG Operator 2 10 DB Box 4
11 Crane Operator 2 11 Tower Light 6
12 Excavator Operator 2 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 2 13 Steel Plates 99
14 Welder 2 14 Silo 23
15 General Worker 18 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 11 16 Water Stop End (sets) 2.5
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 54

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F HS885 38.2m - 3m - - - - Continue excavation
Panel 05F Zoomlion 35m - 26.5m 36m 36m 27.5m - 29m 29m Hit Rock at 32m FB and 27m NB
Panel 05F JPN HS885 35m - 26.5m - 31m 36m 36m 29m 29m Hit Rock at 32m FB and 27m NB
Panel 16a JPN HS885 34m - 36m - 26.5m 36m 36m - - Hit rock at 24m NB
Panel 19 TRN HS885 4m - 1m - 26m - - - - Shift to second bite and start excavation
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C19 - 38.1m 38.2m 38.3m - - - - Finished desanding
Panel C33K HS885 1m - 5m - - - - - - Start excavation
Panel C40aF BG28 38.5m - 38.5m 39m 39m 38m - 41m 38m Continue coring
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Nil Dwall 87 76 0 11
Cross wall 56 38 0 18
Total: 143 114 0 29

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting OPC Cement bags 90
2. General housekeeping
3. Start and finish desanding for C19
4. Replaced HS885 clamshell wire rope 9m and 43m
5. Send out one length of stop end (11.5m + 9m + 4m + 1m end + 0.7m lifting)

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 11/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0000HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day RAIN RAIN RAIN RAIN RAIN RAIN RAIN RAIN RAIN RAIN RAIN RAIN RAIN
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 1 1 Container Office / Store / Changing room 9
2 Site Manager 1 2 Lab Container (8' x 4') 1
3 Site Engineer 2 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 1 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 2 5 Water Pump 3
6 Site Supervisor 3 6 Tsurumi Pump 2
7 Safety Supervisor 1 7 Bentonite Mixer 1
8 Site Clerk 1 8 Water Tank 1
9 Grab Operator 3 9 Welding Set/ MIG 5
10 BG Operator 2 10 DB Box 4
11 Crane Operator 2 11 Tower Light 6
12 Excavator Operator 2 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 2 13 Steel Plates 99
14 Welder 2 14 Silo 23
15 General Worker 18 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 11 16 Water Stop End (sets) 2.5
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 54

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 3m - - - - No Activity
Panel 05F Zoomlion 35m - 31m 36m - 38m 36m - 38m 29m 29m Hit Rock at 32m FB and 27m NB
Panel 16a JPN HS885 36m - 26.5m - 28.5m 36m 36m 28m 28m Hit rock at 24m NB
Panel 19 TRN HS885 4m (P20) - 28m - 38.2m (P18) - - - - Shift to second bite and start excavation
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C33K HS885 23m - 30m - 1m - 28m - - - - Hit hard layer (suspected cement grout)
Panel C40aF BG28 38.5m - 38.5m 39m - 40.5m 39m - 40.5m 41m 38m - 41m Continue coring
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G40 C19 173m³ Cast time: 1434hrs - 2055hrs Dwall 87 76 0 11
Mortar 1:10 C19 60m³ Backiflling in progress Cross wall 56 38 1 17
Total: 143 114 1 28

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Liebherr Coolant pail 8
2. General housekeeping
3. Finished lowering C19 cages
4. Welding teeth holder for TRN HS855 & JPN HS855

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 12/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0000HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day RAIN RAIN RAIN RAIN RAIN RAIN RAIN RAIN RAIN RAIN RAIN RAIN RAIN
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 1 1 Container Office / Store / Changing room 9
2 Site Manager 1 2 Lab Container (8' x 4') 1
3 Site Engineer 2 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 1 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 2 5 Water Pump 3
6 Site Supervisor 3 6 Tsurumi Pump 2
7 Safety Supervisor 1 7 Bentonite Mixer 1
8 Site Clerk 1 8 Water Tank 1
9 Grab Operator 2 9 Welding Set/ MIG 5
10 BG Operator 2 10 DB Box 4
11 Crane Operator 2 11 Tower Light 6
12 Excavator Operator 2 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 2 13 Steel Plates 88
14 Welder 2 14 Silo 23
15 General Worker 19 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 11 16 Water Stop End (sets) 2.5
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 54

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 3m - - - - No Activity
Panel 05F JPN HS855 35m - 38m - 31m 38m 38m 29m 29m Hit Rock at 32m FB and 27m NB
Panel 16a Zoomlion 36m - 28.5m 36m 36m 28m - 31.3m28m - 31.3mHit rock at 24m NB
Panel 16a JPN HS855 36m - 28.5m - 29.5m 36m 36m 28m - 31.3m28m - 31.3mHit rock at 24m NB
Panel 19 - 4m (P20) - 38.2m (P18) - - - - Shift to second bite and start excavation
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C33K HS885 30m - 28m - 29m - - - - Hit hard layer (suspected cement grout)
Panel C33K BG28 30m - 29m 29m - 31m - - - Trimming and coring from 29m - 31m
Panel C40aF BG28 38.5m - 38.5m 40.5m - 41m 40.5m - 41m 41m 41m Continue coring
Panel C40aF HS885 38.5m - 39m - 38.5m - 39m 41m 41m 41m 41m Continue grabbing
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Mortar 1:10 C19 72m³ Continue and finished backfiling Dwall 87 76 0 11
G30 Guidewall 17m³ Barrete pile KP4 Cross wall 56 39 0 17
Total: 143 115 0 28

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. Grouting Sonic Logging tubes at P56
4. Guidewall Barrete pile KP4 steel and formwork installation
5. Cages fabrication for C40aF (GFRP cage) ongoing
6. Send back 11 pcs of steel plates and one 4m length stop end (Disconnect from C40aF full length) to yar

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 13/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0000HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day RAIN RAIN RAIN RAIN RAIN RAIN RAIN CLOUY CLOUY CLOUY CLOUY CLOUY CLOUY
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 1 1 Container Office / Store / Changing room 9
2 Site Manager 1 2 Lab Container (8' x 4') 1
3 Site Engineer 2 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 1 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 2 5 Water Pump 3
6 Site Supervisor 3 6 Tsurumi Pump 2
7 Safety Supervisor 1 7 Bentonite Mixer 1
8 Site Clerk 1 8 Water Tank 1
9 Grab Operator 2 9 Welding Set/ MIG 5
10 BG Operator 2 10 DB Box 4
11 Crane Operator 2 11 Tower Light 6
12 Excavator Operator 2 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 2 13 Steel Plates 88
14 Welder 2 14 Silo 23
15 General Worker 19 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 11 16 Water Stop End (sets) 2.5
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 54

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 3m - - - - No Activity
Panel 05F Zoomlion 38m - 31m 38m 38m - 31m - 32.5mHit Rock at 32m FB and 27m NB
Panel 16a JPN HS855 36m - 29.5m 36m 36m 31.3m 31.3m Clamshell stuck inside panel (0930hrs - 2130hrs)
Panel 19 BG28 4m (P20) - 38.2m (P18) 4m - 12m - - - Coring Concrete G5
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C33K HS885 30m - 31m - 29m 31m - - - Continue grabbing
Panel C40aF HS885 39m - 39.2m - 39m 41m 41m 41m 41m Continue grabbing & Chiseling
Panel C40aF Zoomlion 39.2m - 39m 41m - 41.5m 41m - 41.5m41m - 41.5m41m - 41.5mContinue coring middle point between 2 points
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G30 P17-P19 24m³ Concrete slab behind guidewall Dwall 87 76 0 11
Cross wall 56 39 0 17
Total: 143 115 0 28

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. JPN HS855 clamshell stuck in P16A and succesfully take out
4. Continue cages fabrication for C40aF
5. Liebherr HS885 breakdown, computer sensor problem
6. Dismantle formwork for guidewall barrette pile KP4

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 14/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0000HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day RAIN RAIN RAIN RAIN RAIN RAIN RAIN CLOUY CLOUY CLOUY CLOUY CLOUY CLOUY
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 0 1 Container Office / Store / Changing room 9
2 Site Manager 0 2 Lab Container (8' x 4') 1
3 Site Engineer 1 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Environmental Engineer 0 4 Air Compressor 1
5 Lifting Supritendent / Supervisor 1 5 Water Pump 3
6 Site Supervisor 1 6 Tsurumi Pump 2
7 Safety Supervisor 1 7 Bentonite Mixer 1
8 Site Clerk 0 8 Water Tank 1
9 Grab Operator 2 9 Welding Set/ MIG 5
10 BG Operator 1 10 DB Box 4
11 Crane Operator 1 11 Tower Light 6
12 Excavator Operator 1 12 Diesel Tank 1000L / 15000L 2
13 Mechanic / Assitant 0 13 Steel Plates 88
14 Welder 1 14 Silo 23
15 General Worker 10 15 Tremie Pipe (length) 150m
16 Diaphragm Wall Steel fixer 0 16 Water Stop End (sets) 2.5
17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 20

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 3m - - - - No Activity
Panel 05F - 38m - 31m 38m 38m - 32.5m Hit Rock at 32m FB and 27m NB
Panel 16a - 36m - 29.5m 36m 36m 31.3m 31.3m No Activity
Panel 19 TRN HS855 4m - 18m (P20) - 38.2m (P18) - - - - Continue grabbing
Panel 19 BG28 18m (P20) - 38.2m (P18) - 18m - 19.2m - - Coring Concrete G5
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C33K - 31m - 29m 31m - - - Continue grabbing
Panel C40aF BG28 39.2m - 39m 41.5m 41.5m 41.5m 41.5m Continue coring middle point between 2 points
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Nil Dwall 87 76 0 11
Cross wall 56 39 0 17
Total: 143 115 0 28

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. Zoomlion changed wire rope for Kelly bar

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 15/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0000HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 1 1 Container Office / Store / Changing room 9
2 Site Manager 0 2 Lab Container (8' x 4') 1
3 Site Superintendent 1 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Site Engineer 2 4 Air Compressor 1
5 Environmental Engineer 1 5 Water Pump 3
6 Lifting Supritendent / Supervisor 2 6 Tsurumi Pump 2
7 Site Supervisor 4 7 Bentonite Mixer 1
8 Safety Supervisor 2 8 Water Tank 1
9 Site Clerk 1 9 Welding Set/ MIG 5
10 Grab Operator 3 10 DB Box 4
11 BG Operator 2 11 Tower Light 6
12 Crane Operator 2 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 2 13 Steel Plates 88
14 Mechanic / Assitant 2 14 Silo 23
15 Welder 2 15 Tremie Pipe (length) 150m
16 General Worker 22 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 12 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 61

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 3m - - - - No Activity
Panel 05F Zoomlion 38m - 31m 38m 38m 31m - 31.7m 32.5m Trimming 31m - 31.7m
Panel 16a - 36m - 29.5m 36m 36m 31.3m 31.3m No Activity
Panel 19 BG28 18m (P20) - 38.2m (P18) 18m - 21m 19.2m - - Hit rock at SB 18m
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C33K - 31m - 29m 31m - - - Continue grabbing
Panel C40aF HS885 39.2m - 39m - 39.8m 41.5m 41.5m 41.5m 41.5m Continue chisel and grabbing
BRP KP04 TRN HS855 1m - 20m - - - - - - Start excavation
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Nil Dwall 87 76 0 11
Cross wall 56 39 0 17
Total: 143 115 0 28

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. JPN HS855 engine cannot start from 1000hrs - 1650hrs (Sensor problem)
4. Liebherr checking HS885 computer error code
5. Replaced one wire rope 32mm LHOL for HS885 and 32mm 9m LHLL for JPN HS855

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 16/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0000HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Shift
Site Personnel Machinery / Equipment Qty
Day
1 Project Manager 1 1 Container Office / Store / Changing room 9
2 Site Manager 0 2 Lab Container (8' x 4') 1
3 Site Superintendent 1 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Site Engineer 2 4 Air Compressor 1
5 Environmental Engineer 1 5 Water Pump 3
6 Lifting Supritendent / Supervisor 2 6 Tsurumi Pump 2
7 Site Supervisor 4 7 Bentonite Mixer 1
8 Safety Supervisor 1 8 Water Tank 1
9 Site Clerk 1 9 Welding Set/ MIG 5
10 Grab Operator 5 10 DB Box 4
11 BG Operator 2 11 Tower Light 6
12 Crane Operator 2 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 3 13 Steel Plates 88
14 Mechanic / Assitant 2 14 Silo 23
15 Welder 3 15 Tremie Pipe (length) 150m
16 General Worker 32 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 12 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 74

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 3m - - - - No Activity
Panel 05F JPN HS855 38m - 31m - 32.1m 38m 38m 31.7m 32.5m Continue grabbing
Panel 16a Zoomlion 36m - 29.5m 36m 36m 31.3m - 33m31.3m - 33mNo Activity
Panel 16a JPN HS855 36m - 29.5m - 33.2m 36m 36m 33m 33m No Activity
Panel 19 BG28 18m (P20) - 38.2m (P18) 21m - 21.5m19.2m - 21.5m - - Hit rock at SB 18m
Panel 19 TRN HS855 18m - 21.5m (P20) - 38.2m (P18) 21.5m 21.5m - - Hit rock at SB 18m
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C33K TRN HS855 31m - 32.7m - 29m 31m 31m - - Continue grabbing
Panel C33K BG28 32.7m - 29m 32.7m - 34m 32.7m - 34m - - Continue coring
Panel C40aF HS885 39.2m - 41m 1m - 40m 39.8m - 41m 41.5m 41.5m 41.5m 41.5m Continue chisel and grabbing
BRP KP04 - 33m - - - - - - Start and finish desanding
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Nil Dwall 87 76 0 11
Cross wall 56 39 0 17
Total: 143 115 0 28

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting 32mm 43m LHOL reel 2
2. General housekeeping
3. Replaced 32mm 43m clamshell wire rope for JPN HS855
4. Desanding and koden testing for Panel BRP01
5. Welding teeth hodler HS885 Keller clamshell at Panel C40aF

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 17/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY & NIGHT
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0700HRS (18/1/18) PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR HEAVY RAINHEAVY RAIN
Night FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR

Site Personnel Day Night Machinery / Equipment Qty


1 Project Manager 1 0 1 Container Office / Store / Changing room 9
2 Site Manager 1 1 2 Lab Container (8' x 4') 1
3 Site Superintendent 1 0 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Site Engineer 2 0 4 Air Compressor 1
5 Environmental Engineer 1 0 5 Water Pump 3
6 Lifting Supritendent / Supervisor 1 1 6 Tsurumi Pump 2
7 Site Supervisor 3 1 7 Bentonite Mixer 1
8 Safety Officer / Supervisor 1 1 8 Water Tank 1
9 Site Clerk 1 0 9 Welding Set/ MIG 5
10 Grab Operator 3 2 10 DB Box 4
11 BG Operator 2 0 11 Tower Light 6
12 Crane Operator 2 1 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 2 1 13 Steel Plates 88
14 Mechanic / Assitant 2 0 14 Silo 23
15 Welder 2 1 15 Tremie Pipe (length) 150m
16 General Worker 22 16 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 0 0 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 47 25

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 3m - - - - No Activity
Panel 05F JPN HS855 38m - 32.1m 38m 38m 31.7m 32.5m Trimming with box chisel from 26m - 31m
Panel 16a Zoomlion 36m - 33.2m 36m - 38.5m 36m - 37m 33m 33m Continue coring
Panel 19 BG28 21.5m (P20) - 38.2m (P18) 21.5m - 23m 21.5m - 23m - - Hit rock at SB 18m
Panel 19 TRN HS855 21.5m - 23.5m(P20) - 38.2m (P18) 23m 23m - - Hit rock at SB 18m
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C33K BG28 32.7m - 29m 34m 34m 29m - 30m 29m - 31m Continue coring
Panel C33K TRN HS855 32.7m - 38.5m - 29m (C32) 34m 34m - - Continue coring
Panel C40aF HS885 41m 40m - 41m 41m 41.5m 41.5m 41.5m 41.5m Continue chisel and grabbing
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G40 BRP01 56m³ Cast Time: 2135hrs - 2348hrs Dwall 87 76 0 11
Cross wall 56 39 0 17
Total: 143 115 0 28
Barrete Pile 1 0 1 0

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Bentonite ton 10
2. General housekeeping
3. Cages installation for BRP KP04 and start casting concrete
4. Installed KP 04 in BRP 01
5. Start desandig C40aF

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 18/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY & NIGHT
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0700HRS (19/1/18) PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR HEAVY RAINHEAVY RAIN
HEAVY RAIN
Night FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR

Site Personnel Day Night Machinery / Equipment Qty


1 Project Manager 1 0 1 Container Office / Store / Changing room 9
2 Site Manager 0 1 2 Lab Container (8' x 4') 1
3 Site Superintendent 1 0 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Site Engineer 2 0 4 Air Compressor 1
5 Environmental Engineer 1 0 5 Water Pump 3
6 Lifting Supritendent / Supervisor 1 1 6 Tsurumi Pump 2
7 Site Supervisor 3 1 7 Bentonite Mixer 1
8 Safety Officer / Supervisor 1 1 8 Water Tank 1
9 Site Clerk 1 0 9 Welding Set/ MIG 5
10 Grab Operator 3 2 10 DB Box 4
11 BG Operator 2 0 11 Tower Light 6
12 Crane Operator 2 1 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 2 1 13 Steel Plates 88
14 Mechanic / Assitant 2 0 14 Silo 23
15 Welder 2 1 15 Tremie Pipe (length) 150m
16 General Worker 22 16 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 0 0 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 46 25

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F HS885 38.2m - 3m - 26.5m - - - - Continue grabbing
Panel 05F JPN HS855 38m - 32.1m 38m 38m 31.7m 32.5m Continue trimming with box chisel from 26m - 31m
Panel 16a Zoomlion 36m - 33.2m 38.5m 37m - 38.5m 33m - 36m 33m - 36m Continue coring
Panel 16a JPN HS855 36m - 37.4m - 33.2m - 36m 38.5m 38.5m 36m 36m Continue grabbing
Panel 19 BG28 23.5m(P20) - 38.2m (P18) 23m - 26m 23m - 26m - - Hit rock at SB 18m
Panel 19 HS885 23.5m - 24.5m(P20) - 38.2m (P18) 26m 26m - - Hit rock at SB 18m
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C33K BG28 38.5m - 29m 34m 34m 30m - 31m 31m Continue coring
Panel C33K TRN HS855 38.5m 1m - 38.5m29m - 38.5m (C32) 34m 34m - - Continue grabbing
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G40 C40aF - Ready for Casting Dwall 87 76 0 11
Cross wall 56 39 0 17
Total: 143 115 0 28
Barrete Pile 1 1 0 0

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. Completed cages installation for C40aF
4. Reduce soil pit capacity for C21 and C30 crosswall panel platform
5. Welding teeth holder for HS885 and JPN HS855

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 19/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY & NIGHT
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0700HRS (20/1/18) PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR RAIN FAIR FAIR FAIR FAIR FAIR
Night FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR

Site Personnel Day Night Machinery / Equipment Qty


1 Project Manager 1 0 1 Container Office / Store / Changing room 9
2 Site Manager 0 1 2 Lab Container (8' x 4') 1
3 Site Superintendent 1 0 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Site Engineer 2 0 4 Air Compressor 1
5 Environmental Engineer 1 0 5 Water Pump 3
6 Lifting Supritendent / Supervisor 1 1 6 Tsurumi Pump 2
7 Site Supervisor 3 1 7 Bentonite Mixer 1
8 Safety Officer / Supervisor 1 1 8 Water Tank 1
9 Site Clerk 1 0 9 Welding Set/ MIG 5
10 Grab Operator 3 1 10 DB Box 4
11 BG Operator 2 0 11 Tower Light 6
12 Crane Operator 2 1 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 2 1 13 Steel Plates 88
14 Mechanic / Assitant 0 0 14 Silo 23
15 Welder 2 1 15 Tremie Pipe (length) 150m
16 General Worker 20 13 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 0 0 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 42 21

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 26.5m - - - - No Activity
Panel 05F - 38m - 32.1m 38m 38m 31.7m 32.5m No Activity
Panel 16a Zoomlion 37.4m - 36m 38.5m 38.5m 36m - 38.4m36m - 38.4mContinue coring
Panel 16a HS885 37.4m - 36m - 38.1m 38.5m 38.5m 36m 36m Continue grabbing
Panel 19 BG28 24.5m(P20) - 38.2m (P18) 26m - 27m 26m - 27m - - Hit rock at SB 18m
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C12 TRN 855 1m - 10m - - - - - - Start grabbing
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G40 C40aF 315m³ Cast Time: 0701hrs - 1550hrs Dwall 87 76 0 11
Cross wall 56 39 1 16
Total: 143 115 1 27
Barrete Pile 1 1 0 0

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. Shifting Stage 2 materials to Stage 1 (Handover to MGKT)
4. Start desanding C33K and installed 2 bottom cages
5. HS885 clamshell stuck at inside P16A

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 20/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY & NIGHT
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0700HRS (21/1/18) PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Night FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR HEAVY RAIN FAIR FAIR FAIR

Site Personnel Day Night Machinery / Equipment Qty


1 Project Manager 1 0 1 Container Office / Store / Changing room 9
2 Site Manager 0 1 2 Lab Container (8' x 4') 1
3 Site Superintendent 1 0 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Site Engineer 2 0 4 Air Compressor 1
5 Environmental Engineer 1 0 5 Water Pump 3
6 Lifting Supritendent / Supervisor 1 1 6 Tsurumi Pump 2
7 Site Supervisor 3 1 7 Bentonite Mixer 1
8 Safety Officer / Supervisor 1 1 8 Water Tank 1
9 Site Clerk 1 0 9 Welding Set/ MIG 5
10 Grab Operator 3 1 10 DB Box 4
11 BG Operator 1 0 11 Tower Light 6
12 Crane Operator 2 1 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 2 1 13 Steel Plates 88
14 Mechanic / Assitant 0 0 14 Silo 23
15 Welder 2 1 15 Tremie Pipe (length) 150m
16 General Worker 19 15 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 0 0 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 40 23

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 26.5m - - - - No Activity
Panel 05F JPN HS855 38m - 32.1m 38m 38m 31.7m 32.5m Box chisel trimming 31.2m
Panel 16a HS885 37.4m 1m - 36.2m 38.1m 38.5m 38.5m 38.4m 38.4m Continue grabbing
Panel 19 HS885 24.5m - 26.5m(P20) - 38.2m (P18) 27m 27m - - Hit rock at SB 18m
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C12 TRN 855 10m - 38.2m - - - - - - Continue grabbing
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G40 Panel C33K 183m³ Cast Time: 1550hrs - 2015hrs Dwall 87 76 0 11
Cross wall 56 40 1 15
Total: 143 116 1 26
Barrete Pile 1 1 0 0

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. Sent back P189A toyo pump to Daiden for repairing
4. JPN 855 holder broken 1 pcs
5. HS885 clamshell 9m wire rope broken

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 21/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY & NIGHT
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0700HRS (22/1/18) PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Night FAIR FAIR FAIR FAIR FAIR FAIR RAIN RAIN FAIR FAIR FAIR FAIR FAIR

Site Personnel Day Night Machinery / Equipment Qty


1 Project Manager 0 0 1 Container Office / Store / Changing room 9
2 Site Manager 0 1 2 Lab Container (8' x 4') 1
3 Site Superintendent 1 0 3 Generator 25kVA, 45 kVA, 90 kVA, 150 kVA, 200kVA, 300 kVA 6
4 Site Engineer 1 0 4 Air Compressor 1
5 Environmental Engineer 0 0 5 Water Pump 3
6 Lifting Supritendent / Supervisor 1 0 6 Tsurumi Pump 2
7 Site Supervisor 1 1 7 Bentonite Mixer 1
8 Safety Officer / Supervisor 1 1 8 Water Tank 1
9 Site Clerk 0 0 9 Welding Set/ MIG 5
10 Grab Operator 2 2 10 DB Box 4
11 BG Operator 0 0 11 Tower Light 6
12 Crane Operator 1 0 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 1 1 13 Steel Plates 88
14 Mechanic / Assitant 0 0 14 Silo 23
15 Welder 2 1 15 Tremie Pipe (length) 150m
16 General Worker 19 13 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 0 0 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 30 20

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 26.5m - - - - No Activity
Panel 05F - 38m - 32.1m 38m 38m 31.7m 32.5m No Activity
Panel 16a HS885 37.4m - 38.3m36.2m - 38.2m 38.1m 38.5m 38.5m 38.4m 38.4m Continue grabbing
Panel 19 - 26.5m(P20) - 38.2m (P18) 27m 27m - - Hit rock at SB 18m
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C12 TRN 855 38.2m 1m - 38.4m 1m - 38.3m - - - - Continue grabbing
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Nil Dwall 87 76 0 11
Cross wall 56 41 0 15
Total: 143 117 0 26
Barrete Pile 1 1 0 0

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. Continue welding JPN HS855 teeth holder 3 pcs
3. Cut and joint wire rope for TRN HS855 machine body wire rope
4. Replaced wire rope for HS885 clamshell 43m and 9m wire rope

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 22/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY & NIGHT
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0700HRS (23/1/18) PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR RAIN FAIR FAIR FAIR FAIR FAIR
Night FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR

Site Personnel Day Night Machinery / Equipment Qty


1 Project Manager 1 0 1 Container Office / Store / Changing room 9
2 Site Manager 1 0 2 Lab Container (8' x 4') 1
3 Site Superintendent 0 1 3 Generator 25kVA, 45 kVA, 150 kVA, 200kVA, 300 kVA 5
4 Site Engineer 2 0 4 Air Compressor 1
5 Environmental Engineer 1 0 5 Water Pump 3
6 Lifting Supritendent / Supervisor 1 1 6 Tsurumi Pump 2
7 Site Supervisor 3 1 7 Bentonite Mixer 1
8 Safety Officer / Supervisor 1 1 8 Water Tank 1
9 Site Clerk 1 0 9 Welding Set/ MIG 5
10 Grab Operator 2 2 10 DB Box 4
11 BG Operator 2 0 11 Tower Light 5
12 Crane Operator 2 0 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 2 1 13 Steel Plates 88
14 Mechanic / Assitant 1 0 14 Silo 23
15 Welder 2 1 15 Tremie Pipe (length) 150m
16 General Worker 18 13 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 10 0 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 50 21

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 26.5m - - - - No Activity
Panel 05F Zoomlion 38m - 32.1m 38m 38m 31.7m - 33m 32.5m Trimming 4th point
Panel 16a HS885 38.3m 38.2m 38.1m 38.5m 38.5m 38.4m 38.4m Continue grabbing
Panel 19 BG28 26.5m(P20) - 38.2m (P18) 27m - 28.3m 27m - 28.4m - - Hit rock at SB 18m
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C03 HS885 1m - 27m - - - - - - Start Excavation
Panel C12 - 38.2m 38.4m 38.3m - - - - No Activity
Panel C21 JPN HS855 1m - 28m - - - - - - Start Excavation, RC pile at 2m & 19m FB, Hit rock 2
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Nil Dwall 87 76 0 11
Cross wall 56 41 0 15
Total: 143 117 0 26
Barrete Pile 1 1 0 0

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. Offhire 1 unit of 90kVa generator and 1 unit of tower light back to TTL
4. Stage 2 materials clearing and shifting to Stage 1
5. Start and finish desanding for P16A
6. Received one Fuchi guidewall, replaced 1 unit of toku pump and 1 unit of toyo pump from Daiden
7. Taken 14 nos DB34 of GRFP 10.83m from Tuksu for C12 hanger bar
8. Start and finished installed cages P16A

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 23/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY & NIGHT
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0700HRS (24/1/18) PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR RAIN RAIN RAIN FAIR
Night FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR

Site Personnel Day Night Machinery / Equipment Qty


1 Project Manager 1 0 1 Container Office / Store / Changing room 9
2 Site Manager 1 0 2 Lab Container (8' x 4') 1
3 Site Superintendent 0 1 3 Generator 25kVA, 45 kVA, 150 kVA, 200kVA, 300 kVA 5
4 Site Engineer 2 0 4 Air Compressor 1
5 Environmental Engineer 1 0 5 Water Pump 3
6 Lifting Supritendent / Supervisor 1 1 6 Tsurumi Pump 2
7 Site Supervisor 3 1 7 Bentonite Mixer 1
8 Safety Officer / Supervisor 1 1 8 Water Tank 1
9 Site Clerk 1 0 9 Welding Set/ MIG 5
10 Grab Operator 2 2 10 DB Box 4
11 BG Operator 2 0 11 Tower Light 5
12 Crane Operator 2 0 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 2 1 13 Steel Plates 88
14 Mechanic / Assitant 1 0 14 Silo 23
15 Welder 2 1 15 Tremie Pipe (length) 150m
16 General Worker 18 13 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 10 0 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 50 21

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 26.5m - - - - No Activity
Panel 05F Zoomlion 38m - 32.1m 38m 38m 33m - 36m 32.5m - 33mTrimming 4th point
Panel 19 BG28 26.5m(P20) - 38.2m (P18) 28.3m - 29m 28.4m - 29m - - Hit rock at SB 18m
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C03 HS885 27m - 1m - 20m - - - - Start Excavation
Panel C12 - 38.2m 38.4m 38.3m - - - - Start desanding
Panel C21 JPN HS855 28m - 32.5m - - - - - - Start Excavation, RC pile at 2m & 19m FB, Hit rock 2
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G40 P16a 312m³ Cast Time: 1215hrs - 2210hrs Dwall 87 76 1 10
Cross wall 56 41 0 15
Total: 143 117 1 25
Barrete Pile 1 1 0 0

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. Stop work order from Ministry of Health as they found mosquito breeding at MGKT tunnel team area (12
4. Welding teeth holder for JPN HS855 clamshell

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 24/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY & NIGHT
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0700HRS (25/1/18) PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR RAIN RAIN RAIN RAIN
Night RAIN RAIN RAIN RAIN RAIN FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR

Site Personnel Day Night Machinery / Equipment Qty


1 Project Manager 1 0 1 Container Office / Store / Changing room 9
2 Site Manager 1 0 2 Lab Container (8' x 4') 1
3 Site Superintendent 0 1 3 Generator 25kVA, 45 kVA, 150 kVA, 200kVA, 300 kVA 5
4 Site Engineer 2 0 4 Air Compressor 1
5 Environmental Engineer 1 0 5 Water Pump 3
6 Lifting Supritendent / Supervisor 1 1 6 Tsurumi Pump 2
7 Site Supervisor 3 1 7 Bentonite Mixer 1
8 Safety Officer / Supervisor 1 1 8 Water Tank 1
9 Site Clerk 1 0 9 Welding Set/ MIG 5
10 Grab Operator 3 2 10 DB Box 4
11 BG Operator 2 0 11 Tower Light 5
12 Crane Operator 2 0 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 2 1 13 Steel Plates 88
14 Mechanic / Assitant 1 0 14 Silo 23
15 Welder 2 1 15 Tremie Pipe (length) 150m
16 General Worker 19 15 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 15 0 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 57 23

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 26.5m - - - - No Activity
Panel 05F Zoomlion 38m - 32.1m 38m 38m 36m 33m - 36m Trimming 4th point
Panel 05F HS885 38m - 32.1m - 35.6m 38m 38m 36m 36m Continue excavation
Panel 16 JPN HS855 1m - 15.5m - - - - - - Start Excavation, Hard layer @ 14m depth
Panel 19 JPN HS855 26.5m - 28.8m (P20) - 38.2m (P18) 29m 29m - - Hit rock at SB 18m
Panel 19 BG28 28.8m (P20) - 38.2m (P18) 29m - 31m 29m - 31m - - Hit rock at SB 18m
Panel 19 JPN HS855 28.8m - 31.7m(P20) - 38.2m (P18) 31m 31m - - Hit rock at SB 18m
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C03K HS885 27m - 20m - 22m - - - - Continue excavation
Panel C03K Zoomlion 27m - 22m 27m - 28.5m - - - Continue coring
Panel C21 BG28 32.5m - - 32.5m - 33.5m
32.5m - 33.5m - - Continue Coring
Panel C30 TRN HS855 1m - 25m - 1m - 23m - - - - Start Excavation, Hit rock at FB 25m, SB 23m
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Nil Dwall 87 77 0 10
Cross wall 56 41 0 15
Total: 143 118 0 25
Barrete Pile 1 1 0 0

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting 32mm 4x39 43m length roll 2
2. General housekeeping 32mm 35x7 9m length length 1
3. Replaced office generator due to leaking of water tank 4 leg wire rope with masterlink set 1
4. Oil Filter changed for JPN HS855 machine, clamshell bucket washer broken and fixed back
5. Continue cages fabrication and inspection for C12
6.Mechanic repairing 2 units of desander
7. Continue desanding C12

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 25/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY & NIGHT
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0700HRS (26/1/18) PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Night FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR

Site Personnel Day Night Machinery / Equipment Qty


1 Project Manager 1 0 1 Container Office / Store / Changing room 9
2 Site Manager 1 0 2 Lab Container (8' x 4') 1
3 Site Superintendent 0 1 3 Generator 25kVA, 45 kVA, 150 kVA, 200kVA, 300 kVA 5
4 Site Engineer 2 0 4 Air Compressor 1
5 Environmental Engineer 1 0 5 Water Pump 3
6 Lifting Supritendent / Supervisor 1 1 6 Tsurumi Pump 2
7 Site Supervisor 2 1 7 Bentonite Mixer 1
8 Safety Officer / Supervisor 1 1 8 Water Tank 1
9 Site Clerk 1 0 9 Welding Set/ MIG 5
10 Grab Operator 3 2 10 DB Box 4
11 BG Operator 2 0 11 Tower Light 5
12 Crane Operator 2 0 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 2 1 13 Steel Plates 88
14 Mechanic / Assitant 1 0 14 Silo 23
15 Welder 2 1 15 Tremie Pipe (length) 150m
16 General Worker 18 13 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 12 0 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 52 21

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 26.5m - - - - No Activity
Panel 05F Zoomlion 38m - 35.6m 38m 38m 36m 36m Continue excavation
Panel 16 JPN HS855 15.5m - 1m - 24.5m - - - - Start Excavation, Hard layer @ 14m depth
Panel 19 BG28 31.7m(P20) - 38.2m (P18) 31m - 33.5m 31m - 33.5m - - Hit rock at SB 18m
Panel 19 HS885 31.7m(P20) - 38.2m (P18) 33.5m 33.5m - - Continue chiseling until 35m
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C03K Zoomlion 27m - 22m 28.5m - 30m 28.5m - 30m 22m - 24m - Continue coring
Panel C21 HS885 32.5m - 34.1m - - 34.1m 34.1m - - Continue grabbing
Panel C21 BG28 34.1m - - 34.1m - 35m 34.1m - - Continue Coring, trimming from 33.5m FB
Panel C30 TRN HS855 25m - 23m - 26m - - - - Hit rock at FB 25m, SB 23m
Panel C30 Zoomlion 25m - 26m 26m - 30m 26m - 30m - 25m - 28m Hit rock at FB 25m, SB 23m
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G40 Panel C12 186m³ Cast Time: 2254hrs - 0445hrs Dwall 87 77 0 10
Cross wall 56 41 1 14
Total: 143 118 1 24
Barrete Pile 1 1 0 0

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting 32mm 4x39 43m length roll 1
2. General housekeeping 32mm 35x7 9m length length 2
3. Desanding, lowering cages and cast Panel C12
4. HS885 body machine wire rope broken, 34mm 110m RHLL
5. Replaced 6m wirer rope for TRN HS855
6. Received 4 loads of aggregate and backill at C33K

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 26/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY & NIGHT
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0700HRS (27/1/18) PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR RAIN RAIN RAIN RAIN FAIR
Night FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR

Site Personnel Day Night Machinery / Equipment Qty


1 Project Manager 1 0 1 Container Office / Store / Changing room 9
2 Site Manager 1 0 2 Lab Container (8' x 4') 1
3 Site Superintendent 0 1 3 Generator 25kVA, 45 kVA, 150 kVA, 200kVA, 300 kVA 5
4 Site Engineer 2 0 4 Air Compressor 1
5 Environmental Engineer 1 0 5 Water Pump 3
6 Lifting Supritendent / Supervisor 1 1 6 Tsurumi Pump 2
7 Site Supervisor 2 1 7 Bentonite Mixer 1
8 Safety Officer / Supervisor 1 1 8 Water Tank 1
9 Site Clerk 1 0 9 Welding Set/ MIG 5
10 Grab Operator 3 2 10 DB Box 4
11 BG Operator 2 0 11 Tower Light 4
12 Crane Operator 2 0 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 2 1 13 Steel Plates 77
14 Mechanic / Assitant 1 0 14 Silo 23
15 Welder 2 1 15 Tremie Pipes / Stand 2 sets
16 General Worker 21 13 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 12 0 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 55 21

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 26.5m - - - - No Activity
Panel 05F Zoomlion 38m - 35.6m 38m 38m 36m - 38.2m36m - 38.5mContinue coring
Panel 16 JPN HS855 15.5m - 24.5m - 26.5m - - - - Continue excavation, Hard layer @ 14m depth
Panel 19 TRN 855 31.7m - 35m (P20) - 38.2m (P18) 33.5m 33.5m - - Continue chiseling and grabbing
Panel 19 BG28 35m (P20) - 38.2m (P18) 35m - 38.4m 35m - 38.4m - - Continue coring
Panel 19 JPN HS855 35m - 38.4m (P20) 1m - 28.5m 38.2m (P18) 35m - 38.4m 35m - 38.4m - - Continue grabbing
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C03K HS885 27m - 27.5m - 22m 30m 30m 24m - Continue grabbing
Panel C21 BG28 34.1m - - 35m 34.1m - 35m - - Continue Coring, trimming from 33.5m FB
Panel C21 TRN 855 34.1m - 35.8m - - 35m 35m - - Continue grabbing
Panel C30 - 25m - 26m 30m 30m - 28m No activity. Hit rock at FB 25m, SB 23m
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Mortar 1:10Panel C12 116m³ Finished Backfilling Dwall 87 77 0 10
Cross wall 56 42 0 14
Total: 143 119 0 24
Barrete Pile 1 1 0 0

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. Offhire one unit tower light to TTL
4. Send back 2 sets of tremie stand with tremie pipes, 2 nos of steel casting platform, 11 pcs of steel plate
5. Continue backfill and levelling Crosswall 5 with crusher run for cages storage area

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 27/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY & NIGHT
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0700HRS (28/1/18) PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Night FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR

Site Personnel Day Night Machinery / Equipment Qty


1 Project Manager 1 0 1 Container Office / Store / Changing room 9
2 Site Manager 1 0 2 Lab Container (8' x 4') 1
3 Site Superintendent 0 1 3 Generator 25kVA, 45 kVA, 150 kVA, 200kVA, 300 kVA 5
4 Site Engineer 2 0 4 Air Compressor 1
5 Environmental Engineer 1 0 5 Water Pump 3
6 Lifting Supritendent / Supervisor 1 1 6 Tsurumi Pump 2
7 Site Supervisor 2 1 7 Bentonite Mixer 1
8 Safety Officer / Supervisor 1 1 8 Water Tank 1
9 Site Clerk 1 0 9 Welding Set/ MIG 5
10 Grab Operator 3 2 10 DB Box 4
11 BG Operator 2 0 11 Tower Light 4
12 Crane Operator 2 0 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 2 1 13 Steel Plates 77
14 Mechanic / Assitant 2 0 14 Silo 23
15 Welder 2 1 15 Tremie Pipes / Stand 2 sets
16 General Worker 21 13 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 15 0 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 59 21

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 26.5m - - - - No Activity
Panel 05F JPN HS855 38m 1m - 28m
35.6m - 38.2m 38m 38m 38.2m 38.5m Continue grabbing
Panel 16 JPN HS855 15.5m - 26.5m - - - - Hard layer@14m depth, trimming 8m -15.8m
Panel 19 JPN HS855 38.4m (P20) 28.5m - 33m 38.2m (P18) 38.4m 38.4m - - Continue grabbing
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C03K HS885 27.5m - 30m - 22m 30m 30m 24m - Continue grabbing
Panel C21 TRN 855 35.8m - 37.8m - 1m - 28m 35m 35m - - Continue grabbing
Panel C30 - 25m - 26m 30m 30m - 28m No activity. Hit rock at FB 25m, SB 23m
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Nil Dwall 87 77 0 10
Cross wall 56 42 0 14
Total: 143 119 0 24
Barrette Pile 1 1 0 0

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Bentonite ton 10
2. General housekeeping
3. Continue cages fabrication for P19
4. TRN HS855 hydrauli hose burst
5. 100T crane swing brake problem
6. Start desanding P19

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Project: HKLX IVS1
Daily Site Report
Date: 28/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 1900HRS PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Night FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR

Site Personnel Day Night Machinery / Equipment Qty


1 Project Manager 0 0 1 Container Office / Store / Changing room 9
2 Site Manager 0 0 2 Lab Container (8' x 4') 1
3 Site Superintendent 0 0 3 Generator 25kVA, 45 kVA, 150 kVA, 200kVA, 300 kVA 5
4 Site Engineer 0 0 4 Air Compressor 1
5 Environmental Engineer 0 0 5 Water Pump 3
6 Lifting Supritendent / Supervisor 1 0 6 Tsurumi Pump 2
7 Site Supervisor 2 0 7 Bentonite Mixer 1
8 Safety Officer / Supervisor 1 0 8 Water Tank 1
9 Site Clerk 0 0 9 Welding Set/ MIG 5
10 Grab Operator 1 0 10 DB Box 4
11 BG Operator 1 0 11 Tower Light 4
12 Crane Operator 2 0 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 1 0 13 Steel Plates 77
14 Mechanic / Assitant 0 0 14 Silo 23
15 Welder 0 0 15 Tremie Pipes / Stand 2 sets
16 General Worker 11 2 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 12 0 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 32 2

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 26.5m - - - - No Activity
Panel 05F - 38m 28m 38.2m 38m 38m 38.2m 38.5m No Activity
Panel 16 - 15.5m - 26.5m - - - - No Activity
Panel 19 - 38.4m (P20) 33m 38.2m (P18) 38.4m 38.4m - - No Activity
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C03K - 30m - 22m 30m 30m 24m - No Activity
Panel C21 JPN HS855 37.8m - 28m - 35.5m 35m 35m - - Continue grabbing
Panel C30 BG28 25m - 26m 30m 30m 25m - 28.5m28m - 28.5mHit rock at FB 25m, SB 23m
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
Nil Dwall 87 77 0 10
Cross wall 56 42 0 14
Total: 143 119 0 24
Barrette Pile 1 1 0 0

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. Continue cages fabrication for P19
4. Continue desanding P19

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date
Container Office / Store / Changing room 9 9 9 9
Lab Container (8' x 4') 1 1 1 1
Generator 25kVA, 45 kVA, 150 kVA, 200kVA, 300 kV 5 5 5 5
Air Compressor 1 1 1 1
Water Pump 3 3 3 3
Tsurumi Pump 2 2 2 2
Bentonite Mixer 1 1 1 1
Water Tank 1 1 1 1
Welding Set/ MIG 5 5 5 5
DB Box 4 4 4 4
Tower Light 5 5 5 5
Diesel Tank 1000L / 15000L 2 2 2 2
Steel Plates 88 88 88 88
Silo 23 23 23 23
Tremie Pipe (length) 150m 150m 150m 150m
Water Stop End (sets) 2.5 2.5 2.5 2.5
Desander 2 2 2 2
Toyo pump 2 2 2 2
Float alarm detector 6 6 6 6
Bar Bending/ Cutting Machine 4 4 4 4
Mud tank 5 5 5 5
Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4 4 4 4
Boring Rig (BG28, Zoomlion ZR280) 2 2 2 2
Service Crane 2 2 2 2
Excavator (EX225, SH200, CAT320) 3 3 3 3
Clamshell (Mechanical/Hydraulic) 4 4 4 4
Boring bucket 1200mm (cross cutter, core barrel, c 15 15 15 15
C-Mixer 1 1 1 1
9 9 9
1 1 1
5 5 5
1 1 1
3 3 3
2 2 2
1 1 1
1 1 1
5 5 5
4 4 4
4 4 4
2 2 2
77 77 77
23 23 23
2 sets 2 sets 2 sets
2.5 2.5 2.5
2 2 2
2 2 2
6 6 6
4 4 4
5 5 5
4 4 4
2 2 2
2 2 2
3 3 3
4 4 4
15 15 15
1 1 1
Project: HKLX IVS1
Daily Site Report
Date: 29/1/2018
Projek Mass Rapid Transit Lembah Kelang Laluan Sungai Buloh-Serdang-Putrajaya KELLER No: 1015B SHIFT: DAY & NIGHT
Diaphragm Wall & Cross Wall WORKING HOUR: 0700HRS - 0700HRS (30/1/18) PAGE
Mon Tue Wed Thu Fri Sat Sun

Weather Records
Time 7⁰ Clock 8⁰ Clock 9⁰ Clock 10⁰ Clock 11⁰ Clock 12⁰ Clock 1⁰ Clock 2⁰ Clock 3⁰ Clock 4⁰ Clock 5⁰ Clock 6⁰ Clock 7⁰ Clock
Day FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR
Night RAIN RAIN RAIN RAIN FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR FAIR

Site Personnel Day Night Machinery / Equipment Qty


1 Project Manager 1 0 1 Container Office / Store / Changing room 9
2 Site Manager 1 0 2 Lab Container (8' x 4') 1
3 Site Superintendent 0 0 3 Generator 25kVA, 45 kVA, 150 kVA, 200kVA, 300 kVA 5
4 Site Engineer 1 0 4 Air Compressor 1
5 Environmental Engineer 1 0 5 Water Pump 3
6 Lifting Supritendent / Supervisor 1 1 6 Tsurumi Pump 2
7 Site Supervisor 2 1 7 Bentonite Mixer 1
8 Safety Officer / Supervisor 1 1 8 Water Tank 1
9 Site Clerk 1 0 9 Welding Set/ MIG 5
10 Grab Operator 2 2 10 DB Box 4
11 BG Operator 2 0 11 Tower Light 4
12 Crane Operator 3 2 12 Diesel Tank 1000L / 15000L 2
13 Excavator Operator 2 1 13 Steel Plates 77
14 Mechanic / Assitant 2 0 14 Silo 23
15 Welder 2 1 15 Tremie Pipes / Stand 2 sets
16 General Worker 22 14 16 Water Stop End (sets) 2.5
17 Diaphragm Wall Steel fixer 15 0 17 Desander 2
18 Toyo pump 2
19 Float alarm detector 6
20 Bar Bending/ Cutting Machine 4
21 Mud tank 5
22 Grabbing Rig (Liebherr 855, Liebherr 885,GB34) 4
23 Boring Rig (BG28, Zoomlion ZR280) 2
24 Service Crane 2
25 Excavator (EX225, SH200, CAT320) 3
26 Clamshell (Mechanical/Hydraulic) 4
27 Boring bucket 1200mm (cross cutter, core barrel, cleaning bucket) 15
28 C-Mixer 1

Total 59 23

Excavation:
Depth (Grab) Depth (BG)
Panel No. Machinery Remarks
FB CB NB ⃝ 1st ⃝ 2nd ⃝ 3rd ⃝ 4th
Panel 02F - 38.2m - 26.5m - - - - No Activity
Panel 05F - 38m 28m 38.2m 38m 38m 38.2m 38.5m No Activity
Panel 16 TRN HS855 15.5m - 26.5m - 27.3m - - - - Hard layer@14m depth, trimming 8m - 16m FB
Panel 21 - 35.8m - 21.5m 38.5m 38.5m 26m 26m No Activity
Panel C03K Zoomlion 30m - 22m 30m 30m 24m - 25m 22m - 25m Continue coring
Panel C21 JPN HS855 37.8m - 35.5m - 36.8m 35m 35m - - Continue grabbing
Panel C30 HS885 25m - 30.8m - 26m - 30m 28.5m 28.5m 30m 30m Hit rock at FB 25m, SB 23m
Breakdown GB34 (Breakdown)

Concrete Work Progress:


Grade Panel No. Cast Vol Remarks Scope Completed Today Balance
G40 P19 - Start casting from 0624hrs Dwall 87 77 0 10
Cross wall 56 42 0 14
Total: 143 119 0 24
Barrette Pile 1 1 0 0

Other Activities Material Delivered to Site: Unit Quantity


1. Toolbox meeting Nil
2. General housekeeping
3. JPN HS855 replaced broken fan belt (1310hrs - 1720hrs)
4. Replaced TRN hydraulic hose (0800hrs - 1150hrs)
5. Start and finished lowering cages for P19

Signature Signature Signature

Keller (M) Sdn Bhd IDETJV Client's Representative


Name Name Name
Date Date Date