You are on page 1of 4

CONTRACTOR's DAILY REPORT

Contractor: Contract Title: Date


Design and Build the Temporary Structures and Landscaping works
WATER IN MOTION LLC for opening of Marinas in Deira Island
10-Oct-2022

Contract No.: Report No. Area


WME20221022 WME20221022-WIM-CDR00033
Issued by: WATER IN MOTION LLC Date Issued: 10-Oct-22 Time: 11:00 AM
Received by: NAKHEEL Date Received: 10-Oct-22 Time: 11:00 AM
Shift: Day Hours Worked: 10 hours Weather: Sunny
Day Work: 10 hours
Night Work:
Manpower NO. Total Major Equipment NO. Total
Hours Hours
Project Manager 1 10 Shovel 1 10
Engineer 1 10 JCB 0 0
Foreman 3 10 Bobcat 1 10
Time Keeper 1 10
Chargehand 2 10
Carpenter 8 10
Mason 6 10
Steel Fixer 11 10
Helper 3 10
Pipefitter 3 10
Electrician 0 0
Chainman 2 10
Operator 2 10
Store assistant 1 10
Sub contractor 0 0
Total 43 130 20
DESCRIPTION OF WORK PERFORMED TILL TODAY
1. Excavation & disposal of debris works at Zone 2 - 1500 M3 out of 1650 M3 (90.9%)

2.Compaction works for subgrade at Zone 2 - 5500 M2 out of 8044 M2 (68.6%)

3. Roadbase filling works at Zone 2 - 1400 M2 out of 8044 M2 (18%)

4. Roadbase compaction works at Zone 2 - 1300 M2 out of 8044 M2 (16%)


5. Shuttering works at Zone 3 & 4 for banding PCC - 89 LM out of 900 LM (10 %)

REMARKS BY CONTRACTOR (Delays, Interruptions, Deviations, Extra Work Activities, Conferences, etc. Relevant to Today's Work).

CONTRACTOR'S AUTHORIZED REPRESENTATIVE (Signature) TITLE DATE


Abishek.v Site Engineer 10-Oct-22

CLIENT COMMENTS AND/OR EXCEPTIONS:

ENGINEER: DATE

(Signature)
ZONING LAYOUT

ZONE-01 ZONE-04 ZONE-03


ZONE-02

You might also like