Professional Documents
Culture Documents
7
Monthly and Cumulative invoice
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10
TOTAL 0.25 24.2 52.3 68.25 92.55 92.6 85.38 50.525 21.95 12
CUM 0.25 24.45 76.75 145 237.55 330.15 415.5 466.05 488 500
8
Cash Inflow
Work done by
measurement 0.25 24.2 52.3 68.25 92.55 92.6 85.38 50.525 21.95 12
Recoveries
towards advance
payment of 50 10 10 10 10 10
Retention @ 10%
of gross invoice
(0.1* row 1) 0.03 2.42 5.23 6.83 9.26 9.26 8.54 5.05 2.20 1.20
Payment due (1-3) 0.23 21.78 37.07 51.43 73.30 73.34 66.84 45.47 19.76 10.80
Cash received
(one month delay) 0.23 21.78 37.07 51.43 73.30 73.34 66.84 45.47 19.76 10.80
Release of
retention 25.00 25.00
Total Incomings 50.00 0.00 0.23 21.78 37.07 51.43 73.30 73.34 66.84 45.47 19.76 35.80 25.00
Cumulative
incomings 50.00 50.00 50.23 72.01 109.08 160.50 233.80 307.14 373.97 419.45 439.2 475.00 475 475 500.00
9
Cash Outflow
t=0 M1 M2 M3 M4 M5 M6 M7 M8 M9M10 M11 M15 M16
439.
Cumulative incomings 50 50 50.225 72.01 109.075 160.5 233.8 307.1 373.97 419.4 2 475 475 475 500
Work done by 12.0
measurement 0.25 24.20 52.30 68.25 92.55 92.60 85.38 50.53 21.95 0
Total cost (0.9 of total 10.8
bill) 0.23 21.78 47.07 61.43 83.30 83.34 76.84 45.47 19.76 0
Labor @ 20% of total
cost 0.05 4.36 9.41 12.29 16.66 16.67 15.37 9.09 3.95 2.16
Material @ 55% of
total cost 0.12 11.98 25.89 33.78 45.81 45.84 42.26 25.01 10.87 5.94
Subcontractors @
10% of total cost 0.02 2.18 4.71 6.14 8.33 8.33 7.68 4.55 1.98 1.08
Plant & machinery @
10% of total cost 0.02 2.18 4.71 6.14 8.33 8.33 7.68 4.55 1.98 1.08
Project overheads @
5% of total cost 0.01 1.09 2.35 3.07 4.16 4.17 3.84 2.27 0.99 0.54
Labor Payment (no
delay) 0.05 4.36 9.41 12.29 16.66 16.67 15.37 9.09 3.95
2.16
Material payment (one 10.8
month delay) 0.12 11.98 25.89 33.78 45.81 45.84 42.26 25.01 7 5.94
Subcontractors
Payment (one month
delay) 0.02 2.18 4.71 6.14 8.33 8.33 7.68 4.55 1.98 1.08
Plant & machinery
payment (one month
delay) 0.02 2.18 4.71 6.14 8.33 8.33 7.68 4.55 1.98 1.08
Overhead cost
payment (no delay) 0.01 1.09 2.35 3.07 4.16 4.17 3.84 2.27 0.99
0.54
17.5
Outgoing Total 0.06 5.61 28.10 50.66 66.89 83.31 81.71 69.00 39.04 2 8.10
441.
10
Cumulative Outgoings 0.06 5.67 33.78 84.44 151.33 234.63 316.35 385.34 424.39 9 450.0 450.0 450.0 450.0
Cash Flow Diagram
11
Factors Affecting Project Cash Flows
• Advances such as Mobilization Advance etc.
• The Margin in a project,
• Retention,
• Extra claims,
• Distribution of margin such as front loading or back
loading;
• Certification type such as over measurement and
under measurement;
• Certification Period;
• Credit Arrangement of the contractor with labor,
material, and plant and equipment suppliers, and
other subcontractors.
12
Gemechis Tamiru
13
Factors Affecting Project Cash Flows
• Advances such as Mobilization Advance etc.
• The Margin in a project,
• Retention,
• Extra claims,
• Distribution of margin such as front loading or back
loading;
• Certification type such as over measurement and
under measurement;
• Certification Period;
• Credit Arrangement of the contractor with labor,
material, and plant and equipment suppliers, and
other subcontractors.
14
Profit Margin
• The margin (profit margin or contribution) is the
excess over costs.
• Thus higher is the margin in a project better it is for
the contractor cash flow.
Exercise
• Assume a fictitious project of 10 months duration.
• It is also assumed that ETB 100 (cost) is incurred
every month and the margin is 10% of the cost.
• The retention amount is 5% of the bill value and the
whole retention money is to be released 6 months
after practical completion (i.e. 10 months).
• Further it is also assumed that owner delays the
payment by one month.
15
Retention
• Retention tends to reduce the margin obtained from a
project.
• In case of very low margins the retention can even
reduce the margin to zero or less.
• Thus retention affects the contractor’s cash flow in a
negative manner. The higher the retention the bigger
is the cash flow problem.
Exercise
• Compute the effect of retention percentage (0% to
5% to 10%) on cash flow for the fictitious problem.
16
Extra Claims
17
Distribution of Margin
19
Certification type
Over measurement
• Over measurement is the device whereby the amount
of work certified in the early months of a contract is
greater than the amount of work done.
• This is compensated for in later measurements.
• Thus, over measurement has the same effect as front-
end loading;
• It improves the cash flow in the early stages and
reduces the capital lock-up.
20
Certification type
Under Measurement
• Under measurement is the situation whereby the
amount of work certified in the early months of a
contract is less than the amount actually done.
• This has the effect of increasing the negative cash
flow for the contractor in a project.
21
Certification type
23
Captim
• A measure of the interest payable is obtained by
calculating area between the cash-out and cash-in.
• The area under the negative cash flow period is used
to calculate the financing charges for the project by
the contractor.
• The total area would have a unit of Birr x Months
and is also known as captim standing for capital x
time.
• Interest on the capital required for the project =
(captim in Birr month x interest charges per
annum)÷12
• For a captim value of 10,000 Birr Month, and the
interest rate = 12% per annum; the interest charges
for financing the project would be Birr 10,000. 24