Gentlemen,
We would like to have your presence for inspection according to the following schedules.
- Rebar
- Formwork
6/20/2023 Utility Building - Elevation
FF Plant - Dewatering
- Joint Survey
- Joint Inspection
COMMENTS :
Signature
Date
SDO DATES PROJECT (Contractor Logo)
REBAR
Size ( diameter ) & Length
Bending radius / shape
Spacing & position
Overlapping length
Concrete cover
Cleaning
Rebar chair
FORM WORK
Surface quality
Position
Verticality
Dimension
Straightness
Bottom elevation
Top elevation ( marking )
Bracing / Strength
Champer
CONCRETE
Grade
Slump
Volume
Finishing
CONSTRUCTION JOINT
BLOCK OUT
WHEATER
EMBEDDED PARTS ( FROM M / E )
EQUIPMENT USED
COMMENTS :
Signature
: F-QC-278-2023 6/20/2023
SIGNATURE: