EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A. General Requirements
Data Sheet PIP INSH1000-D2 specifying Project insulation for piping and
equipment is reviewed and approved.
This data sheet describes the surfaces to be insulated and the materials SAES-N-001,
A2
to be used. Section 3
(PIP INSH 1000,Para. 4.1.2)
REMARKS:
REFERENCE DOCUMENTS:
1. SAES-N-001 -- Basic Criteria, Industrial Insulation. (6 September 2008)
2. PIP INSH1000 Hot Service Insulation Materials and Installation Specification. (August 2007)
3. PIP INSR1000 Installation of Flexible, Removable/Reusable Insulation Covers for Hot Insulation Service.(July 2007)
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date: