Daily Progress Report

Project Name Construction of Tehrathum District Hospital Report Date 15/Jun/2023

Contract No PUDBC/DKT/NCB/WORKS/03/079/080 Report No. 17

Client :- PUDBC Contractor:- Chainlink Himalyan J.V.

Weather ( ✔ ) Clear ( ) Windy ( ) P-cloudy ( ) Cloudy ( ) Rainy


Item Today 15/Jun/2023 Tomorrow

Laboratory Concrete cubes prepared for compressive strength test : 6


Building Works
Item Today 15/Jun/2023 Tomorrow 6/16/2023
Actual/Achieved Target (Tomorrow)

Concreting of F5 Footing (C3 grid) (Total = 20.23cum) Concreting of F4 Footing (F2 grid)

Back filling of footing Back filling of footing cont..

Work Rebar work of Columns for MAT- 3 (D2 &E2 grid) Rebar work of shear wall inside MAT- 3
Contents

Rebar work of new retaining wall RCC of new retaining wall

M/S work of middle retaining wall (Total = 13.2 cum) M/S work of middle retaining wall Cont…

Description Nos Worker Detail


Project Manager 1 Today Actual Next Day Plan
Quality Assurence (Lab) 1 Type of Work Skilled Unskilled Working Hrs Skilled Unskilled Working hour
Surveyor 1 Rebar Work 5 9 10 5 10 8
Staff List
Supervisor 1 Stone Masonry 3 9 10 5 10 10
Engineer 1 Formwork 0 0 0 0 0 0
Quantity Engineer 1 Concrete (RCC) 5 17 10 5 17 8
Procurement 1 Company Worker 0 2 10 0 2 10
Total= 7 Total= 8 28
Material Detail
Type of Material Code and Grade Today Income Consumed Remarks
Concrete M/S work
Cement (Bag) NS/ ISO 0.00 133.00 13.00 For concreting : 63 bag saurya cement (53 grade) , 70 bag Saptakoshi cement (43 Grade)and 6 lit.admixture.

Sand (m3) 7.50 7.78 2.90


Materials
Aggregate (m3) 0.00 15.57
Rebar (kg) NS 191,Fe500 0.00 0.00
Stones (m3) 6.00 10.30
Fuel Consumed (Ltr) 0.00 0.00
Equipment & Machineries
Working
Today 15/Jun/2023 Nos. Tomorrow 16/Jun/2023 Nos. Working hour
hour
JCB 1 8.7 JCB 1

Tipper 1 8 Tipper 1
In Use
Tractor 2 10 Tractor 2

Mixture 4 10 Mixture 4

Rebar bending machine 1 2 Rebar bending machine 1

Rebar cutting machine 1 1 Rebar cutting machine 1


Suggestion and
No suggestion and changes at site
Changes
Isuues in
Tractor No.6423 didn't work today due to mechanical problem.
the site

….................................. ….........................................