DAILY REPORT OF FIELD ACTIVITIES

EPCC Contractor : Contract Title : Day/ Date


DIALOG PLANT & SERVICES SDN BHD IDPT - INDEPENDENT DEEPWATER PETROLEUM TERMINAL PROJECT AT PENGERANG, JOHOR DARUL
Monday, 2 July, 2018
Sub - Contractor : TA'ZIM - PHASE 1E EXPANSION

EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD PACKAGE - Bundwall, Road and Drainage, Underground Composite, Pipe Sleepers, Pipe Supports and Misc. Works.

INDIRECT
No. of Manhours Cum. Hours
Dicipline Men Construction Equipment No Hours
Worked Regular OT Total Yesterday Today

Project Management & Supervision Mobile Crane 25T 1 8.0


Project Manager 1 8.0 2.0 10.0 323 333 Excavator 3 30.0
Construction Manager 1 8.0 2.0 10.0 323 333 Backhoe 1 10.0
QA/QC Engineer 1 8.0 2.0 10.0 265 275 Bar Bending Machine 2 20.0
HSSE Officer 1 8.0 2.0 10.0 263 273 Bar Cutting Machine 2 20.0
QC Supervisor 1 8.0 2.0 10.0 239 249 Compressor 175CFM 2 20.0
HSSE Supervisor 2 8.0 2.0 10.0 331 351 1T Roller 2 20.0
Site Supervisor 2 8.0 2.0 10.0 596 616 4 x 1000w Tower Light 4 40.0
10T Lorry 1 10.0
Welding machine 500A 1 10.0
5T Boom Truck 1 8.0

Total Indirects : 9 2,340 2,430


DIRECT Total : 20 196.0
No. of Manhours Cum. Hours Worked
Type
Dicipline Men
Worked Regular OT Total Yesterday Today Indirect 9
OPERATOR Direct 102
Crane Operator 1 8.0 2.0 10.0 325 335
Excavator operator 2 8.0 2.0 10.0 574 594 Total 111
Backhoe Operator 1 8.0 2.0 10.0 246 256 Outer Ring = PM
Lorry Driver 1 8.0 2.0 10.0 270 280 Inter Ring = AM
Boom Truck Driver 1 8.0 2.0 10.0 221 231

Subtotal : 6 1,636 1,696


DIRECT WORKERS
Foreman 3 8.0 2.0 10.0 730 760
Store Keeper 1 8.0 2.0 10.0 451 461
Rigger 3 8.0 2.0 10.0 545 575
Carpenter 25 8.0 2.0 10.0 4,836 5,086
Concretor 29 8.0 2.0 10.0 7,236 7,526
Bar Bender 21 8.0 2.0 10.0 4,812 5,022
Mason 1 8.0 2.0 10.0 240 250
Skill Worker 13 8.0 2.0 10.0 3,428 3,558
General Worker - - - - -

Rain during working hours:


15:00 to 16:00 Hrs

Subtotal : 96 22,278 23,238


Total Directs : 102 23,914 24,934
Description of Today Activities : Description of Activities Plan Next Day :

Precast Yard Area ; Precast Yard Area ;


1) Formworks preparation for pipe sleepers, & drainage. 1) Continue formworks preparation for pipe sleepers & drainage.
2) Rebar fabrication of bundwall,pipe sleeper & drainage in progress. 2) Continue rebar fabrication of bundwall & drainage.
3) Concreting work for pipe sleeper pedestal (SL3=12 nos, SL5=3 nos) 3) Continue Install embedded plate and dismantle formwork for pipe sleeper pedestal.

PIT 107 Area ; PIT 107 Area ;


1) Bundwall (S / CH 98 - CH 78) - install drain wall formwork completed 1) Bundwall (S / CH 98 - CH 78) - drain wall concreting work.
2) Bundwall (S / CH 78 - CH 58) - touch up work completed. 2) Bundwall (S / CH 78 - CH 58) - to start install drain wall formwork.
3) Bundwall (S / CH 58 - CH 40) - touch up work in progress. 3) Bundwall (S / CH 58 - CH 40) - to continue touch-up work.
4) Bundwall (S / CH 40 - CH 22) - - 4) Bundwall (S / CH 40 - CH 22) - to start touch-up work.
5) Bundwall (S / CH 22 - CH 4) - - 5) Bundwall (S / CH 22 - CH 4) - to start touch-up work.
6) Bundwall (W / CH 4 - CH 787) - - 6) Bundwall (W / CH 4 - CH 787) - to start touch-up work.
7) Bundwall (W / CH 787 - CH 767) - dismantle wall formwork completed. 7) Bundwall (W / CH 787 - CH 767) - to start touch-up work.
8) Bundwall (W / CH 767 - CH 747) - wall concreting work completed. 8) Bundwall (W / CH 767 - CH 747) - to start dismantle wall formwork and touch up work.
9) Bundwall (W / CH 747 - CH 727) - preparation work for pipes penetration openings. 9) Bundwall (W / CH 747 - CH 727) - to continue preparation work opening for pipe sleeve at wall
10) Bundwall (W / CH 727 - CH 707) - installation of wall formwork commenced 10) Bundwall (W / CH 727 - CH 707) - to continue install wall formwork.
11) Bundwall (W / CH 707 - CH 690) - - 11) Bundwall (W / CH 707 - CH 690) - to start install wall formwork.
12) Bundwall (N / CH 671- CH 651) - base concreting work completed. 12) Bundwall (N / CH 671 - CH 651) - to start dismantle base formwork.
13) Bundwall (N / CH 651 - CH 631) - installation of base form and rebar completed. 13) Bundwall (N / CH 651 - CH 631) - to continue install base formwork and rebar.
Installation of waterstop in progress. - to continue install waterstop and kicker form.
14) Bundwall (N / CH 631 - CH 611) - installation of base form, rebar and waterstop in progress. 14) Bundwall (N / CH 631 - CH 611) - to continue install base form, rebar and waterstop.
15) Bundwall (N / CH 611 - CH 591) - installation of base form ,rebar and waterstop in progress. 15) Bundwall (N / CH 611 - CH 591) - to continue install base form, rebar and waterstop.
16) Bundwall (N / CH 591 - CH 571) - installation of base form commenced. 16) Bundwall (N / CH 591 - CH 571) - to continue install base formwork and rebar.
17) Bundwall (S / CH 98 - CH 118) - lean concrete work completed 17) Bundwall (S / CH 98 - CH 118) - to start install base rebar and formwork.
18) Bundwall (S / CH 118 - CH 138) - lean concrete work completed 18) Bundwall (S / CH 98 - CH 118) - to start install base rebar and formwork.
19) Bundwall (S / CH 138 - CH 158) - excavation and base preperation work commenced. 19) Bundwall (S / CH 98 - CH 118) - to continue base preparation work and lean concrete.

Road Ramp Area ; Road Ramp Area ;


1) Road Ramp Foundation (P1,P2,P3) for Pit 107: installation of pier form in progress. 1) Road Ramp Foundation (P1,P2,P3) for Pit 107 :to continue install pier form and concreting P1.
2) Road Ramp Foundation (P1,P2,P3) for Pit 108: pier rebar in progress. 2) Road Ramp Foundation (P1,P2,P3) for Pit 108: to start install pier form.

PIT 108 Area ; PIT 108 Area ;


1) RC drain (S/ S9 to high point; 284 m) 1) RC drain (S/ S9 to high point ; 284 m)
- CH 0 to 22; - - CH 0 to 22; -
- CH 22 to 45; - - CH 22 to 45; -
- CH 45 to 60; wall concreting work completed. - CH 45 to 60; to start dismantle wall formwork and touch up.
- CH 60 to 80; base concreting work completed - CH 60 to 80; to continue install wall form and rebar.
- CH 80 to 100; excavation and lean concreting work. - CH 80 to 100; to continue excavation and lean concrete, to start install wall rebar and formwork.

Remarks by Contractor (Delays, Interruptions, Deviations, Extra Work activities)

Sub - Contractor Representative Signature / ESEC Title Date


Augustin Lang Sandah QA/QC Engineer 2-Jul-18
Company Comments

EPCC Contractor Representative Signature / DIALOG Title Date

EPCC Contractor Comments