PROJECT : EPCI PENGEMBANGAN DPPU SEPINGGAN

Customer : PT. PERTAMINA PATRA NIAGA


Contractor : PT. BANGUN BEJANA BAJA
No. Contrac : SPB 007/ F20000/2015/S-5

LAPORAN HARIAN
Report No : SPG/BBB-LH-XII-21 Area APRON 24/12/2021
Over
No Man Power Qty Hours No Man Power Qty Hours Over Time Keterangan
Time
I Direct II Inderect
1 Project Manager 0 0 0 1 Spv. Mechanical 1 8 0
2 Contruction Manager 0 0 0 2 Welder 1 8 0
3 Koordinator Asset 0 0 0 3 Fitter 1 8 0
4 Koordinator HSE 0 0 0 4 Grinder 1 8 0
5 Contruction Supertendent 0 0 0 5 Helper Mechanical 2 16 0
6 Project Control 0 0 0 6 Tukang Tim Civil Siang 0 0 0
7 Quality Control 1 8 0 7 Helper Tim Civil Siang 0 0 0
8 Drafter 0 0 0 8 Helper Tim Civil Malam 5 40 0
9 Document Control 0 0 0 9 Rigger 0 0 0
10 Spv. Civil 1 8 0 10 Operator Excavator 2 16 0
11 Spv. Electrical 0 0 0 11 Operator Crane 45 T 1 8 0
12 Admin Warehouse 0 0 0 12 Driver 1 8 0
13 Admin HRD 0 0 0 13 Helper Electrical 1 8 0
14 Finance 0 0 0 14 Flagman 1 8 0
15 Safetyman 1 8 0 15
16 Operator Fuko Crane 0 0 0 Sub Total 17 136 0
17 Security 0 0 0 Total (Direct + Indirect) 20
Commulative Hours 160

Total 3 24 0 No Major Equipment & Tools Qty Hours Over Time Keterangan

Kondisi Cuaca 1 Excavator 1 6


Sift Siang Sift Malam 2 Genset 1 6
Time (WITA) Cerah Hujan Time (WITA) Cerah Hujan 3 Compressor 1
08.00 - 09.00 √ 19.00 - 20.00 √ 4 Crane 45 T 1
09.00 - 10.00 √ 20.00 - 21.00 √ 5 Jack Hammer 1
10.00 - 11.00 √ 21.00 - 22.00 √ 6 Cutting Weld Machine 1
11.00 - 12.00 √ 22.00 - 23.00 √ 7 Mesin Bor 1
12.00 - 13.00 √ 23.00 - 24.00 √ 8 Truck/ Dump Truck 1 6
13.00 - 14.00 √ 00.00 - 01.00 √ 9 Travo Las 1 6
14.00 - 15.00 √ 01.00 - 02.00 √ 10 Gerinda 4'' 1 6
15.00 - 16.00 √ 02.00 - 03.00 √ 11 Tronton/ Trailer/ Fuco 1
16.00 - 17.00 √ 03.00 - 04.00 √ 12 Submersible Pump 1
17.00 - 18.00 √ 04.00 - 05.00 √ 13 Hand Tools 1 6
14 Stemper 1
Jumlah hujan ( jam ) 0 Jumlah hujan ( jam ) 0
Total 13 36 0
Description of Work Performed Today Progres Yang Tercapai (%) Description of Work Performed Tomorrow

Pekerjaan Mechanical & Piping Vol. Sat. Kemarin Hari ini Komulatif Pekerjaan Mechanical & Piping

Pemasangan spool pipa 2" VC 3 1 Ls 50,0% 10,0% 60,0% Pemasangan spool pipa 2" VC 3

Fabrikasi dan Pemasangan Bracing VC 3 1 Ls 0,0% 100,0% 100,0%

Pekerjaan Civil Vol. Sat. Kemarin Hari ini Komulatif Pekerjaan Civil

Tim Civil Malam Tim Civil Malam

Cleaning dan pengurasan air di Hydrant Pit Area Apron 1 Ls 0,0% 20,0% 20,0% Cleaning dan pengurasan air di Hydrant Pit Area Apron

Penimbunan tanah area luar VC3 arah Apron 1 Ls 0,0% 10,0% 10,0% Penimbunan tanah area luar VC3 arah Apron

Dilaporkan Oleh, Diperiksa Oleh, Diketahui oleh,

PT. Bangun Bejana Baja PT. Bangun Bejana Baja PT. Pertamina Patra Niaga PT. Pertamina Patra Niaga

Ade Putra Alan Novaldi Mohamad Somani Heri Ashari


Project Control Pjs. Project Manager MK RPF OH DPPU Sepinggan

Note :
- Izin pekerjaan dari angkasa pura setelah last fligth jam 19.00 WITA