PROJECT : EPCI PENGEMBANGAN DPPU SEPINGGAN

Customer : PT. PERTAMINA PATRA NIAGA

Contractor : PT. BANGUN BEJANA BAJA

No. Contrac : SPB 007/ F20000/2015/S-5

LAPORAN HARIAN
Report No : SPG/BBB-LH-XII-21 Area DPPU 22/12/2021
Over Over
No Man Power Qty Hours No Man Power Qty Hours Keterangan
Time Time
I Direct II Inderect
1 Project Manager 1 8 0 1 Spv. Mechanical 0 0 0
2 Contruction Manager 0 0 0 2 Welder 0 0 0
3 Koordinator Asset 1 8 0 3 Fitter 0 0 0
4 Koordinator HSE 1 8 0 4 Grinder 0 0 0
5 Contruction Supertendent 0 0 0 5 Helper Mechanical 0 0 0
6 Project Control 1 8 0 6 Tukang Tim Civil Siang 0 0 0
7 Quality Control 0 0 0 7 Helper Tim Civil Siang 0 0 0
8 Drafter 1 8 0 8 Helper Tim Civil Malam 0 0 0
9 Document Control 1 8 0 9 Rigger 0 0 0
10 Spv. Civil 0 0 0 10 Operator Excavator 0 0 0
11 Spv. Electrical 0 0 0 11 Operator Crane 45 T 0 0 0
12 Admin Warehouse 1 8 0 12 Driver 0 0 0
13 Admin HRD 0 0 0 13 Helper Electrical 1 8 0
14 Finance 1 8 0 14 Warehouse 0 0 0
15 Safetyman 0 0 0 15 Housekeeping 1 8 0
16 Operator Fuko Crane 1 8 0 Sub Total 2 16 0
17 Security 3 24 0 Total (Direct + Indirect) 14
18 Painter Commulative Hours 112
Over
Total 12 96 0 No Major Equipment & Tools Qty Hours Keterangan
Time
Kondisi Cuaca 1 Excavator 1
Sift Siang Sift Malam 2 Genset 1 6
Time (WITA) Cerah Hujan Time (WITA) Cerah Hujan 3 Compressor 1
08.00 - 09.00 √ 19.00 - 20.00 √ 4 Crane 45 T 1
09.00 - 10.00 √ 20.00 - 21.00 √ 5 Jack Hammer 1
10.00 - 11.00 √ 21.00 - 22.00 √ 6 Cutting Weld Machine 1
11.00 - 12.00 √ 22.00 - 23.00 √ 7 Mesin Bor 2
12.00 - 13.00 √ 23.00 - 24.00 √ 8 Truck/ Dump Truck 1
13.00 - 14.00 √ 00.00 - 01.00 √ 9 Travo Las 1
14.00 - 15.00 √ 01.00 - 02.00 √ 10 Gerinda 7'' 1
15.00 - 16.00 √ 02.00 - 03.00 √ 11 Tronton/ Trailer/ Fuco 1
16.00 - 17.00 √ 03.00 - 04.00 √ 12 Submersible Pump 5
17.00 - 18.00 √ 04.00 - 05.00 √ 13 Hand Tools 1
14 Stemper 1
Jumlah hujan ( jam ) 0 Jumlah hujan ( jam ) 1
Total 19 6 0
Description of Work Performed Today Progres Yang Tercapai (%) Description of Work Performed Tomorrow

Pekerjaan Civil Vol. Sat. Punchlist Kemarin Hari ini Komulatif Pekerjaan Civil

x 1 Ls 0% 100% 100%
PROJECT : EPCI PENGEMBANGAN DPPU SEPINGGAN

Customer : PT. PERTAMINA PATRA NIAGA


Contractor : PT. BANGUN BEJANA BAJA
No. Contrac : SPB 007/ F20000/2015/S-5
DOKUMENTASI KEGIATAN
Report No : SPG/BBB-LH-XII-21 Area DPPU 22/12/2021

x x

x x

x x

x x
PROJECT : EPCI PENGEMBANGAN DPPU SEPINGGAN
Customer : PT. PERTAMINA PATRA NIAGA
Contractor : PT. BANGUN BEJANA BAJA
No. Contrac : SPB 007/ F20000/2015/S-5

LAPORAN HARIAN
Report No : SPG/BBB-LH-XII-21 Area APRON 22/12/2021
Over
No Man Power Qty Hours No Man Power Qty Hours Over Time Keterangan
Time
I Direct II Inderect
1 Project Manager 0 0 0 1 Spv. Mechanical 1 8 0
2 Contruction Manager 0 0 0 2 Welder 1 8 0
3 Koordinator Asset 0 0 0 3 Fitter 1 8 0
4 Koordinator HSE 0 0 0 4 Grinder 1 8 0
5 Contruction Supertendent 0 0 0 5 Helper Mechanical 2 16 0
6 Project Control 0 0 0 6 Tukang Tim Civil Siang 1 8 0
7 Quality Control 1 8 0 7 Helper Tim Civil Siang 2 16 0
8 Drafter 0 0 0 8 Helper Tim Civil Malam 6 48 0
9 Document Control 0 0 0 9 Rigger 0 0 0
10 Spv. Civil 1 8 0 10 Operator Excavator 2 16 0
11 Spv. Electrical 0 0 0 11 Operator Crane 45 T 0 0 0
12 Admin Warehouse 0 0 0 12 Driver 2 16 0
13 Admin HRD 0 0 0 13 Helper Electrical 2 16 0
14 Finance 0 0 0 14 Flagman 1 8 0
15 Safetyman 2 16 0 15
16 Operator Fuko Crane 0 0 0 Sub Total 22 176 0
17 Security 0 0 0 Total (Direct + Indirect) 26
Commulative Hours 208

Total 4 32 0 No Major Equipment & Tools Qty Hours Over Time Keterangan

Kondisi Cuaca 1 Excavator 1 6


Sift Siang Sift Malam 2 Genset 1 6
Time (WITA) Cerah Hujan Time (WITA) Cerah Hujan 3 Compressor 1
08.00 - 09.00 √ 19.00 - 20.00 √ 4 Crane 45 T 1
09.00 - 10.00 √ 20.00 - 21.00 √ 5 Jack Hammer 1
10.00 - 11.00 √ 21.00 - 22.00 √ 6 Cutting Weld Machine 1
11.00 - 12.00 √ 22.00 - 23.00 √ 7 Mesin Bor 1
12.00 - 13.00 √ 23.00 - 24.00 √ 8 Truck/ Dump Truck 2 6
13.00 - 14.00 √ 00.00 - 01.00 √ 9 Travo Las 1 6
14.00 - 15.00 √ 01.00 - 02.00 √ 10 Gerinda 4'' 1 6
15.00 - 16.00 √ 02.00 - 03.00 √ 11 Tronton/ Trailer/ Fuco 1
16.00 - 17.00 √ 03.00 - 04.00 √ 12 Submersible Pump 1
17.00 - 18.00 √ 04.00 - 05.00 √ 13 Hand Tools 1 6
14 Stemper 1
Jumlah hujan ( jam ) 0 Jumlah hujan ( jam ) 1
Total 14 36 0
Description of Work Performed Today Progres Yang Tercapai (%) Description of Work Performed Tomorrow

Pekerjaan Mechanical & Piping Vol. Sat. Kemarin Hari ini Komulatif Pekerjaan Mechanical & Piping

Fabrikasi spool pipa 2" VC 3 1 Ls 20,0% 20,0% 40,0% Fabrikasi spool pipa 2" VC 3

Pemasangan spool pipa 2" VC 3 1 Ls 20,0% 20,0% 40,0% Pemasangan spool pipa 2" VC 3

Pelepasan Bracing bagian bawah luar VC3 arah apron 1 Ls 0,0% 30,0% 30,0% Pelepasan Bracing bagian bawah luar VC3 arah apron

Pekerjaan Civil Vol. Sat. Kemarin Hari ini Komulatif Pekerjaan Civil

Tim Civil Siang Tim Civil Siang

Perbaikan dan perapian dinding VC1 1 Ls 20,0% 20,0% 40,0% Perbaikan dan perapian dinding VC1

Tim Civil Malam Tim Civil Malam

Penimbunan tanah area luar VC3 arah service road 1 Ls 50,0% 10,0% 60,0% Penimbunan tanah area luar VC3 arah service road

Dilaporkan Oleh, Diperiksa Oleh, Diketahui oleh,


PT. Bangun Bejana Baja PT. Bangun Bejana Baja PT. Pertamina Patra Niaga PT. Pertamina Patra Niaga

Ade Putra Hendrikus GD Parera Mohamad Somani Heri Ashari


Project Control Project Manager MK RPF OH DPPU Sepinggan

Note :
- Izin pekerjaan dari angkasa pura setelah last fligth jam 19.00 WITA
- Site hujan jam 04.00 WITA s/d 05.00 WITA, pekerjaan terhenti 1 jam
PROJECT : EPCI PENGEMBANGAN DPPU SEPINGGAN
Customer : PT. PERTAMINA PATRA NIAGA
Contractor : PT. BANGUN BEJANA BAJA

No. Contrac : SPB 007/ F20000/2015/S-5


DOKUMENTASI KEGIATAN
Report No : SPG/BBB-LH-XII-21 Area APRON 22/12/2021

Perbaikan dan perapian dinding VC1 Perbaikan dan perapian dinding VC1

Fabrikasi spool pipa 2" VC 3 Pemasangan spool pipa 2" VC 3

Pelepasan Bracing bagian bawah luar VC3 arah apron Site hujan

Penimbunan tanah area luar VC3 arah service road Penimbunan tanah area luar VC3 arah service road