Format Daily Report

This document is a daily report from a renovation project at Pantai Indah Kapuk garage. It summarizes the labor and equipment used on the project. It lists 60 workers across various roles who worked a total of 8 hours each. It also lists 21 pieces of equipment used on site including generators, lasers, saws, and compressors. The report describes 19 tasks completed that day, such as installing plumbing, painting, tiling bathrooms, installing drop ceilings and doors.

Uploaded by

Mohammad Arief
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
220 views2 pages

Format Daily Report

This document is a daily report from a renovation project at Pantai Indah Kapuk garage. It summarizes the labor and equipment used on the project. It lists 60 workers across various roles who worked a total of 8 hours each. It also lists 21 pieces of equipment used on site including generators, lasers, saws, and compressors. The report describes 19 tasks completed that day, such as installing plumbing, painting, tiling bathrooms, installing drop ceilings and doors.

Uploaded by

Mohammad Arief
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

PROYEK : PEKERJAAN RENOVASI GR GARAGE No 01/FORM/ESPE

PANTAI INDAH KAPUK Revisi 00

PEMILIK PROYEK KONSULTAN PENGAWAS/MK KONTRAKTOR PELAKSANA


PT. ASTRA INTERNATIONAL, Tbk PT. ESPE KONTRAKTOR INDO
AUTO 2000 KONSULTAN PERENCANA
PT. ARSITEK ARUPADATU

LAPORAN HARIAN
No. Lap. Har 15 /LH/ESPE-ARUPADATU/PIK/VI/23 Minggu Ke IX Tanggal/Bulan 24 Agustus 2023 Hari Kamis

Tenaga Kerja staff (Main & SC) Jumlah Total jam kerja Tenaga Kerja mandor Jumlah Total jam kerja
Jabatan Main Subc Main Subc Jabatan Main Subc Main Subc
1. Project Manager 0 - 1. Mandor Sipil 0 0
2. Site Manager 1 8 ` 2. Mandor MEP 0 0
3. Drafter 1 8 3. Mandor Baja 1 0
4. Supervisor/Pelaksana 2 8 4. Wakil Mandor Sipil 2 8
5. Admin project 0 8 5. Wakil Mandor MEP 0 8
6. Logistik/Gudang 0 8 6. Wakil Mandor Baja 0 0
7. Mekanik 0 8 7. Tukang Batu 10 8
8. [Link] 0 8 8. Tukang Besi 4 8
9. [Link] 0 8 9. Tukang Kayu 2 0
10. Koordinator Scurity 0 10. Pembantu Tukang 6 8
11. Satpam 1 11. Tukang Baja 2 0
12. Pekerja Baja 1 0
13. Tukang Plumbing 4 8
14. Pekerja ME 13 8
15. Tukang Kusen alumunium 6 0
17. Tukang plafon 5 8
- 18. Tukang Pintu 4 0
Total 5 Total 60
Material yang masuk Jumlah Unit Peralatan lapangan Jumlah Unit
1. 1 Gergaji Kayu 3 bh
2. 2 Total Stasion 0 Unit
3 3 Bodem 1 bh
4 4 Jack Hamer 3 Unit
5 5 Electrik Mini Hoist / Katrol Listrik 1 Ton 1 Unit
6 6 Trailer & Vibrator 1 Unit
7 7 Arco 2 Unit
8 8 Roskam 2 bh
9 9 Lampu HD 500 Watt 4 Unit
10 10 Elemen PPR 2 Unit
11 11 Bending Pipa 1 Unit
12 12 Auto Leveling Laser ( Deco ) 1 Unit
13 13 Alat Potong Keramik Manual 2 Unit
14 14 Kompresor 1 Unit
15 15 Mesin Finish Trowel 1 Unit
16
17
18
19
20
21
22

Deskripsi pekerjaan yang dilaksanakan (sebutkan waktunya)


1. Pasang Sanitair Toilet Lantai 1, 2 dan 3
2 Pasang Closet duduk Existing Toilet Mekanik Lantai 3
3 Pasang Duckting freshair Genset
4 Cat perkutan lampu dyno
5 Fabrikasi ramp portable
6 Pasang Keramik lantai eksisting Toilet Staff
7 Pasang Keramik existing exs jalur installasi Stopkontak dan data
8. Cat Ceiling exspose lantai 1
9. Body Coating finish area tahap 2 lantai 1 uit 11
10. Pasang ragka ceiling soundproof
11. Pasang Pintu UPVC Folding door dyno
12 Pasang Pintu Folding door unit 11
13. Plesteran acian dinding atap
14. Connection Outdoor AC lantai atap
15 Bongkar dinding Use oil
16. Instalasi Armatur lampu Lantai 1
17 Pasang Keramik lantai eksisting Toilet Staff
18. Pasang Pintu Toilet Customer Lt.1
19 Cat Dining Balkon Lantai 3
20 Cat ceiling gypsum R server
21 Pasang Kembali Kermaik lantai existing R Maintenance lt.2
22
23.
24
25.

Gambar dan instruksi yang di terima dari MK ( dengan rujukan dan lisan ataupun tertulis)

Kejadian Keselamatan Kerja (K3)

Cuaca (Deskripsi dari keadaan cuaca dan catatan cuaca buruk yang mempengaruhi kemajuan pekerjaan)
Hujan 0 JAM
Berawan 0 JAM
Cerah 15 JAM
Manajemen Konstruksi Kontraktor
PT. ARSITEK ARUPADATU PT. ESPE KONTRAKTOR INDO

SAMSUL
Site Manager Site Manager
No. Doc. : ESPE-CA-FRM-15
Revisi : 00

DOKUMENTASI FOTO PROGRESS No. Dok. :


PT ESPE KONTRAKTOR INDO
EXECUTION WORK Halaman :

DOKUMENTASI FOTO PROGRESS

Periode ke : IX
Tanggal : 24 Agustus 2023
Proyek : Renovasi G Garage Deviasi periode lalu : %
Pemilik Proyek : PT. Astra Internasional Akumulasi Progres Rencana : %
Kontraktor : [Link] Kontraktor Indo Akumulasi Progres Aktual : %
No. SPK/SI : Deviasi 0%

Jenis Pekerjaan : Bongkar dinding untuk panel LVMDP Jenis Pekerjaan : Body Coating Epoxy
Lokasi : R Use Oile Lokasi : Unit 11 lantai 1

Jenis Pekerjaan : Pasang Pintu Besi R Fresh Air Lantai 3 Jenis Pekerjaan : Pasang Hand drayer Toilet

Lokasi : Fresh Air Shaft Lanatai 3 Lokasi : Toilet Customer Unisex Lantai 2

Jenis Pekerjaan : Cat Fiish Ceiling Jenis Pekerjaan : Pasang partisi kaca dan pintu frameless

Lokasi : R Co working space lantai 3 Lokasi : R Penerimaan lantai 1

Jenis Pekerjaan : Foldingdoor Pintu utama Jenis Pekerjaan : Pasang Pintu Folding door Upvc
Lokasi : Pintu utama unit 10 Lokasi : R Dyno lantai 1 unit 10

Photo Progress Proyek Renovasi G Garage PT ESPE KONTRAKTOR INDO 1/1