No.

Uraian Pekerjaan Satuan Vol / Harga Satuan  Jumlah Harga


Indeks
(Rp) (Rp)

1 Tenaga Kerja
- Pekerja OH 0.39 100,000.00 39,000.00
- Tukang Besi / Las OH 0.7 120,000.00 84,000.00
- Kepala Tukang Besi / Las OH 0.07 150,000.00 10,500.00
- Mandor OH 0.007 200,000.00 1,400.00

Sub Total 134,900.00

2 Peralatan dan Alat Bantu


- Sewa Stager (2set) set 0.02 110,000.00 2,200.00
- Listrik Kerja ls 1 5,000.00 5,000.00
- Alat bantu lainnya ls 1 10,000.00 10,000.00
Sub Total 17,200.00

3 Material dan Bahan


- Alumunium Composite m2 1.1 420,500.00 462,550.00
- Hollow Besi Galvanis Uk 4 x 4 x 1 mm btg 0.8 115,000.00 92,000.00
- Braket Siku / spigot / stiffener btg 0.267 60,000.00 16,020.00
- Paku Skrup Beton Kg 0.08 21,600.00 1,728.00
- Paku Skrup Kg 0.11 21,600.00 2,376.00
- Sealant tube 0.25 25,000.00 6,250.00
Sub Total 580,924.00

4 Bahan Bakar & Pelumas

Sub Total -

5 Lain-Lain

Sub Total -

Jumlah Harga A 733,387.05


Over Head and Profit B 10% 73,338.70
=  A  x
Total Harga C=A+ 806,725.75
B
Harga Satuan Pekerjaan C:P 806,725.75
No. Uraian Pekerjaan Satuan Vol / Harga Satuan  Jumlah Harga
Indeks
(Rp) (Rp)

1 Tenaga Kerja
- Pekerja OH 0.39 100,000.00 39,000.00
- Tukang Besi / Las OH 0.7 120,000.00 84,000.00
- Kepala Tukang Besi OH 0.07 150,000.00 10,500.00
/ Las
- Mandor OH 0.007 200,000.00 1,400.00

Sub Total 134,900.00

2 Peralatan dan Alat


Bantu
- Sewa Stager (2set) set 0.02 110,000.00 2,200.00
- Listrik Kerja ls 1 5,000.00 5,000.00
- Alat bantu lainnya ls 1 10,000.00 10,000.00
Sub Total 17,200.00

3 Material dan Bahan


- Alumunium m2 1.1 420,500.00 462,550.00
Composite
- Hollow Besi btg 0.8 115,000.00 92,000.00
Galvanis Uk 4 x 4 x 1
mm
- Braket Siku / btg 0.267 60,000.00 16,020.00
spigot / stiffener
- Paku Skrup Beton Kg 0.08 21,600.00 1,728.00
- Paku Skrup Kg 0.11 21,600.00 2,376.00
- Sealant tube 0.25 25,000.00 6,250.00
Sub Total 580,924.00

4 Bahan Bakar &


Pelumas

Sub Total -

5 Lain-Lain

Sub Total -

Jumlah Harga A 733,024.00


Over Head and Profit B 10% 73,338.70
=  A  x
Total Harga C=A+ 806,725.75
B
Harga Satuan Pekerjaan C:P 806,725.75
AHS
Pek. Pipa Medium Galvanis 2" + Finishing, per ttk t. 50cm

Pipa Medium Galvanis 2" 0.25 btg 610,000 152,500


Cat dasar + finishing 1.00 ls 38,000 38,000
Las + support alat bantu 1.00 ls 45,000 45,000
Plat Dudukan angkur + mur 1.00 ls 350,000 350,000
Upah pasang 1.00 ls 65,000 65,000
Jumlah 650,500