You are on page 1of 7

METHOD STATEMENT OF

ROOF PLATFORM INSTALLATION

Document No Instal Platform & Tangga Akses Cerobong Rev : 0


Sheet No
LREF-00-PR-20-0252S-A4
1 of 6

CLIENT : WIKA – PEN CONSORTIUM


CONTRACTOR : PT. BANGUN BEJANA BAJA
PROJECT TITLE : Pekerjaan Engineering, Procurement &
Construction (EPC) Proyek Pembangunan Terminal
LPG Refrigerated
LOCATION : Tanjung Sekong di Merak Mas – Banten
CONTRACT NO. : PEN-150099001

0 19-07-2018 IFI AF IW SG

PRE CHK APP CHK CHK APP


REV DATE DESCRIPTION PT. BANGUN BEJANA
WIKA-PEN PTM
BAJA
METHOD STATEMENT OF
ROOF PLATFORM INSTALLATION

Document No Instal Platform & Tangga Akses Cerobong Rev : 0


Sheet No
LREF-00-PR-20-0252S-A4
2 of 6

REVISION SHEET

No Rev Page Subject Description of Change

Issued For Information


1 0
METHOD STATEMENT OF
ROOF PLATFORM INSTALLATION

Document No Instal Platform & Tangga Akses Cerobong Rev : 0


Sheet No
LREF-00-PR-20-0252S-A4
3 of 6

CONTENTS

1. Purpose...................................................................................................................... 4

2. Scope.......................................................................................................................... 4

3. Terms of implementation..........................................................................................4

4. Preparation of Roof Platform Installation................................................................5

5. Method statement of Roof Platform Installation.....................................................6

6. Housekeeping............................................................................................................7
METHOD STATEMENT OF
ROOF PLATFORM INSTALLATION

Document No Instal Platform & Tangga Akses Cerobong Rev : 0


Sheet No
LREF-00-PR-20-0252S-A4
4 of 6

1. Purpose 1. Tujuan
This method statement is made for Method statement ini dibuat bertujuan untuk
Engineering, Procurement & Construction pelaksanaan pekerjaan pada proyek Pekerjaan
(EPC) Projects Construction of Terminals LPG Engineering, Procurement & Construction (EPC)
Refrigerated by following of safe and secure Proyek Pembangunan Terminal LPG Refrigerated
working steps on the work of Roof Platform dengan mengikuti langkah-langkah kerja yang aman
Installation. dan selamat pada pekerjaan Roof Platform
2. Scope Installation.
This method statement is cover all scope of 2. Ruang Lingkup
work directly or indirectly performed on the Method statement ini mencakup pada semua lingkup
Roof Platform Installation. pekerjaan yang dilakukan pada proses pekerjaan Roof
3. Terms of implementation Platform Installation. Baik pekerjaan yang
Requirements to be fulfilled for the execution berhubungan secara langsung maupun tidak langsung
of the work in this method statement are : yang dilakukan dipekerjaan Roof Platform
a. Permission to work Installation.
Before starting this work, first must obtain 3. Syarat-syarat Pelaksanaan
a work permit from Personnel from Syarat-syarat yang harus dipenuhi untuk pelaksanaan
Operation Construction (EPC) Refrigerated pekerjaan yang ada pada Prosedur Operasi Standar ini
LPG Terminal adalah:
Construction Project, such as: a. Ijin untuk pekerjaan
 General work permit Sebelum memulai pekerjaan ini terlebih dahulu
 Job safety analysis harus mendapatkan ijin kerja dari Personnel dari
 Meetings to discuss of the work to be Operation Construction (EPC) Proyek
done and the impact of safety in the Pembangunan Terminal LPG Refrigerated, seperti :
workplace.  General Work Permit (GWP).
b. Tools & Equipment  JSA (Job Safety Analysis).
Kinds of equipment that used to support  Mengadakan Pertemuan / Meeting untuk
the work of Roof Platform Installation membahas pekerjaan yang akan dilakukan dan
are: dampak keselamatan pada pekerjaan tersebut.
 Crawler Crane 100T. b. Peralatan kerja
 Shackle. Jenis-jenis peralatan yang digunakan untuk
 Webing Sling / Wire Sling.
METHOD STATEMENT OF
ROOF PLATFORM INSTALLATION

Document No Instal Platform & Tangga Akses Cerobong Rev : 0


Sheet No
LREF-00-PR-20-0252S-A4
5 of 6

 Palu. mendukung pekrjaan Roof Platform Installation


 Linggis. adalah:
 Welding Machine  Crawler Crane 100T.
 Aluminium ladder  Shackle.
c. Use of PPE  Webing Sling / Wire Sling.
While start to work and entering the Tank  Palu.
Site location, all employees obligate to use  Linggis.
Personal Protective Equipment (APD)  Mesin Las
according to with Safety Standards, such  Tanggal Almunium
as: c. Penggunaan PPE
 Helmet. Pada saat akan melakukan pekerjaan dan memasuki
 Safety Glass. daerah lokasi tangki, semua karyawan yang terlibat
 Safety Shoes. harus/Wajib menggunakan Alat Pelindung Diri
 Hand Gloves. (APD) yang sesuai dengan standar keselamatan
 Full Body Harness. kerja, seperti :
4. Preparation of Roof Platform  Helmet.
Installation.  Welding Tools.
Preparation of roof platform installation  Kacamata safety.
can be do by following these steps:  Sepatu safety.
a. Prepare all materials of roof platform  Sarung tangan.
that will installed on lifted location.  Full Body Harness.
b. Prepare all tools and equipment to be 4. Proses persiapan untuk Roof Platform
used for roof platform installation. Installation.
c. Install barricade and sign board at Persiapan untuk pekerjaan Roof Platform. dapat
location of lifting and installation. dilakukan dengan mengikuti langkah-langkah berikut:
d. Make sure the area is safe to do the job. a. Persiapkan material roof platform yang akan di
5. Method statement for Roof Platform. instal di lokasi pengangkatan.
If all preparations complete, Roof Platform b. Persiapkan semua tools & equipments yang akan
Installation can be started by following the digunakan untuk aktivitas roof platform
steps as follows: installation.
a. Ground assembly part of roof platform to c. Pasang barikade dan rambu rambu di area
be installed with support facing up
METHOD STATEMENT OF
ROOF PLATFORM INSTALLATION

Document No Instal Platform & Tangga Akses Cerobong Rev : 0


Sheet No
LREF-00-PR-20-0252S-A4
6 of 6

(above roof platform fame) to minimize fit pengangkatan dan Installation.


up activity at high. d. Pastikan alokasi sudah aman untuk melakukan aktivitas
b. After ground assembly complete, reverse pekerjaan.
the part of roof platform before lifted with 5. Langkah pekerjaan Roof Platform Installation.
support of roof platform facing down Jika semua persiapan sudah selesai maka
(below of roof platform frame). pekerjaan Roof Platform dapat dimulai dengan
c. Install lifting tools to the part of roof mengikuti langkah-langkah seperti berikut :
platform according to lifting plan. a. Ground assembly bagian roof platform yang
d. Lift and installed the part of roof platform akan di install dengan posisi support menghadap
to the position according to drawing. ke atas.
e. Tack weld the support of roof platform b. Setelah ground assembly selesai, balikkan roof
while already on position, add more platform dengan posisi support menghadap ke
temporary support if necessary. bawah.
f. After inspected and approved by QC, roof c. Pasangkan lifting tools pada bagian roof platform
platform can be full weld. yang akan diinstal sesuai dengan lifting plan.
6. Housekeeping d. Angkat dan pasang bagian roof platform ke posisi
If the roof platform installation work is sesuai gambar.
completed, all work locations must be cleaned e. Tack weld support roof platform ketika sdh di
from the waste. All waste should be disposed posisi yang tepat, tambahkan support sementara
of in its place and adjusted to the type of apabila diperlukan.
waste. Arrange and organize all materials and f. Setelah dicek dan disetujui oleh QC, bisa
equipment in its place. dilakukan full weld pada roof platform.
6. Housekeeping
Jika pekerjaan roof platform installation selesai,
maka semua lokasi pekerjaan harus dibersihkan dari
sampah dan semua sampah harus dibuang pada
tempatnya serta disesuaikan dengan jenis sampahnya.
Tata dan atur semua material dan peralatan pada
tempatnya.
Risk Assessment

Title : Working at Height

R/A No. : MJPP-RA-01

Subcontractor

Name : Position : Signature : Date :

SCT Construction Engineer

Name : Position : Signature : Date :

SCT HSE Manager

Name : Position : Signature : Date :

SCT Construction Manager

Name : Position : Signature : Date :

You might also like