TABULATION OF HOLDS
Table of Contents
1. PURPOSE.......................................................................................................................................... 4
2. SCOPE ............................................................................................................................................... 4
3. DEFINITIONS/ABBREVIATIONS..................................................................................................... 4
4. REFERENCES .................................................................................................................................. 5
5. RESPONSIBILITY & AUTHORITY .................................................................................................. 6
6. DESCRIPTION OF ACTIVITIES ....................................................................................................... 7
1. PURPOSE
This procedure defines a structured approach and the standard requirements for tracking
repair defective items necessary for the completion of systems/sub-systems and for the
subsequent handover of the FACILITY from Construction to Commissioning and to
Operations (COMPANY)
2. SCOPE
This procedure describes the standard work process for controlling punch list items where
CONTRACTOR is responsible for Construction, Pre-commissioning and Commissioning in
both Yards & Islands.
3. DEFINITIONS/ABBREVIATIONS
The following are definitions for key terms used in this document:
COMPANY ZADCO
Petrofac Emirates and Daewoo Shipbuilding and Marine
CONTRACTOR
Engineering COMPANY
Drawing or document amended to reflect the final installation as
As Built
Constructed, Pre-commissioned and Commissioned.
Note: Outstanding work that has open checks and inspections (check
sheets) covering the outstanding work scope is not to be regarded as
a punch list item (i.e. incomplete "work to go" is not to be punch listed
if it has open check sheets related to the "work to go").
Abbreviations used:
4. REFERENCES
The following documents are used as source of reference and may be read in conjunction with
this procedure.
Contract requirements
Part IV Exhibit Z.38 - Acceptance
Part IV Exhibit Z.50 - Mechanical Completion and Commissioning
Planning and Documentation
Project documents
Responsible for generating, approving and signing off completed punch list
COMPANY
items. COMPANY shall have the “WRITE” access to verify all the Punch
Representatives
items in PetroPCS Software.
6. DESCRIPTION OF ACTIVITIES
6.1 GENERAL
a) An assessment that all tasks have been completed. This is achieved through a review
of all documentation in the System/Sub-system handover package; i.e. check sheets,
QA/QC reports, testing sheets, vendor reports, etc. for accuracy and completeness, and
that all inspection and test requirements have been carried out as specified in the
relevant procedures.
b) Review of the “As Built” drawings to verify that they reflect the actual build in the field
including a “red line” mark up of all the changes or modifications.
c) Verification that the System/Sub-system conforms to all project requirements.
6.2 PUNCH LIST CLASSIFICATION
Punch list items shall be classified according to their degree of impact on HSSE, equipment
integrity, and subsequent scheduled activities. The assignment of punch list classification
shall be agreed between CONTRACTOR Construction, CONTRACTOR Commissioning and
COMPANY Projects and Operations.
Category “A” Punch: Must be completed prior to Mechanical completion. It signifies that
the punch list item, defect, missing item, or omission is deemed critical such as those
which prevent safe operation of plant, equipment, system and may jeopardize personnel
UPPER ZAKUM 750
ISLANDS SURFACE FACILITIES PROJECT – EPC2
PROJECT No. P7512
& or equipment and must be repaired without which the next activity cannot be
undertaken safely. This category shall also include points that cannot be attended to at
a later stage of the project
Category “B” Punch: Must be completed prior to Handover (Ea System). It signifies that
the punch list item, defect, missing item, or omission which will not affect the safe
progression of the System /Sub-system to the next stage
Category “C” Punch: Must be completed prior to PROVISIONAL ACCEPTANCE, or as
soon as practicable thereafter in accordance with a schedule to be agreed with
COMPANY. These punches should not affect the safe operation of the System /Sub
system
All Punch list items identified in the Yard and not completed in the Yard will be subject to
the same classification stipulated in section 6.2. However the Punch list items not
executed in Yard prior to module transportation, and thus required to be undertaken post
module arrival at Island, must be agreed at Yard by CONTRACTOR, FABRICATION
CONTRACTOR and COMPANY and the cost of the defect repair will remain the
responsibility of the FABRICATION CONTRACTOR after the transportation of the module
from the Yard to the Island.
Load out certificate does not represent that Yard obligation to close Punch list items has
been either discharged or waived.
Upon generation of punch items, CONTRACTOR and COMPANY will identify the re-
categorization code of the generated punch items during Pre-Commissioning and
Commissioning phases and update them on the punch list form (Refer 8.1 Appendix A –
Blank Punch list).
When a sub-system is progressed from one stage to the other, the turnover coordinator
will automatically update PetroPCS to reflect the new category of the punch item based
on the agreed re-categorization codes.
Refer Section 8 Appendix C – Punch Listing Flow Chart
Punch list items may be raised, reviewed, and resolved throughout the life of the Project. A
formal inspection and verification assessment shall be carried out on System/Sub-system
level at the following phases of the project:
Prior to hydrostatic or pneumatic testing of pipe work
Outstanding FAT Punch items which cannot be closed at factory
Punch items outstanding from Yard
At Mechanical Completion handover phase prior to issuing the “Sub-System Mechanical
Completion Certificate”
At Pre-commissioning stage prior to issue “Ready for Commissioning certificate”.
UPPER ZAKUM 750
ISLANDS SURFACE FACILITIES PROJECT – EPC2
PROJECT No. P7512
Punch items shall also be captured during the Pre-Start-Up safety audit and resolved prior
to introducing hydrocarbons into the plant or prior to the Project Completion depending on
their effect on the safe operation of the FACILITY.
1. The primary objective of this punch list is to identify items which will jeopardize the well-
being of personnel and the integrity of the pipe work or equipment, if not corrected prior
to testing.
2. Second objective is to identify items that if not corrected prior to testing will result in re-
work and re-testing.
Following the re-instatement after the test, all outstanding items shall be consolidated and
transferred to PetroPCS, with each item classified in accordance with Para 6.2 of this
document and entered into the PetroPCS Database.
All the punch items that are originated from factory shall be cleared prior to shipment to the
Yard/Island. However, some items cannot be closed during factory and these items shall be
identified by Quality Control Team and categorized as A, B or C with the entity responsible for
closure identified and loaded in to PetroPCS. These items must be closed out at the earliest
opportunity. COMPANY/CONTRACTOR Commissioning manager shall agree on the
outstanding FAT punch items that cannot be closed at yard prior to sign the Ready for Load
out Certificate.
UPPER ZAKUM 750
ISLANDS SURFACE FACILITIES PROJECT – EPC2
PROJECT No. P7512
Yard punch items shall be tracked and closed as specified in this document and all
referenced documents. In addition, any punch items that remain open at time of load out,
shall be clearly identified as an attachment to the "Ready for Load Out " certificate and
include categorization and entity responsible for closure.
When all Construction ‘A’ check sheets have been completed for a sub-system and loaded
into PetroPCS, CONTRACTOR shall notify COMPANY for a joint walk down prior to issuing
the “Mechanical Completion Certificate”. Each discipline representative records
discrepancies and non-conformances found during the walk down. The Punch List items
shall be categorised in accordance with section 6.2 of this document and recorded in the
PetroPCS database.
The Mechanical Completion Walk down will verify that Mechanical Completion has been
sufficiently progressed so as to move into Pre-Commissioning phase.
All ‘A’ punch list items for Sub-System Mechanical Completion stage of the project shall be
cleared before the “Sub-System Mechanical Completion Certificate” is issued.
When all Pre-commissioning B check sheets have been completed for a System/ Sub
system and loaded in to PetroPCS, CONTRACTOR shall notify COMPANY for a joint walk
down to issuing the “Ready for Commissioning Certificate”. The Punch List items shall be
categorized in accordance with section 6.2 of this document and recorded in the PetroPCS
database.
When all Commissioning ‘C’ check sheets have been completed for a system and loaded
into PetroPCS, CONTRACTOR shall notify COMPANY for a joint walk down. The Punch
List items shall be categorised in accordance with Para 6.2 of this document and recorded
in the PetroPCS database.
Punch List coordinator shall arrange a walk down close out meeting within 24 hours to verify
the legitimacy and agree the categorization of punch items after each walk down. Any
disputed items shall be verified and agreed prior to handover the punch list to PetroPCS for
data entry.
UPPER ZAKUM 750
ISLANDS SURFACE FACILITIES PROJECT – EPC2
PROJECT No. P7512
All inspections and verifications shall be made against the latest revision IFC, P&IDs, PFDs,
SLDs, isometric drawings and relevant discipline standards, specifications, and checklists.
The boundaries for verification of the physical works are defined in the system/sub-system
identification marked up drawings which shall be attached to the walk down notification.
Verification shall not include components, equipment, etc outside these boundaries.
Punch items will be limited to not installed as per IFC drawings, defective items & items that
pose a safety hazard to personnel or may lead to unsafe operation of the plant and shall
not include “preferential engineering” items.
Significant observations regarding the design of the facilities made during walk downs
should be treated as either Non-conformance if not built as per specification with NCRs
issued by Company, or if additional requirements are identified above the base scope,
treated as Contract variations. In either case, these design observations should not be
loaded as punch items as they do not meet the definition of a punch list item (see section
2.0).
Upon readiness of a system/sub-system for a walk down, as detailed in Para 6.3, the
turnover coordinator shall issue a “Request for Inspection” (RFI) to the concerned parties for
any one of the phases listed in Section 6.3 of this document. When issuing an RFI,
CONTRACTOR shall provide sufficient notice (Five Days) to all concerned parties to ensure
that the required resources are available at the time requested. Minimum requirements for
names of walk down participants must be agreed at the time of RFI issue and the walk down
shall be rescheduled if any required participant is missing. Therefore, it is important that key
walk down personnel be available and where necessary any alternates pre-agreed. The
notice shall include all relevant documentation with the boundaries of the inspection clearly
indicated and Punch List for the subsystem with the current close out status. If deemed
necessary and agreed in between COMPANY & CONTRACTOR walk down for a particular
system / sub-system may be split up as per discipline.
A “Request for Inspection” log shall be kept in the CONTRACTOR turnover office and shall
be used by all parties.
During all joint walk downs, as further defined in this document and exhibit Z.38, a
"nominated punch items recorder" shall be named prior to the walk down. During the walk
down and immediately following the walk down, all punch list items from all participants are
to be consolidated on the master punch list. The master punch list will then be reviewed
within 24 hrs jointly with participants to agree punch item categorization. These meetings
will be termed "agreement meetings". Where punch item categorization cannot be agreed,
then the punch item in question shall be elevated to Commissioning/Completions leads and
when necessary Commissioning/Completions Managers for assignment of category. The
escalation process for all punch listing disputes must be agreed prior to beginning walk
UPPER ZAKUM 750
ISLANDS SURFACE FACILITIES PROJECT – EPC2
PROJECT No. P7512
down process." In addition, the "Master Punch List" shall be generated by Contractor and
approved by Company for each walk down.
FAT / Yard pending items shall be recorded in PetroPCS for further follow up. All punch list
generated during the handover from Construction Sub-Contractor to CONTRACTOR shall
be recorded and included with the RFI.
The Turnover Team is responsible for entering the punch items listed into the PetroPCS
database for monitoring and tracking purposes.
Subsequently, all deficiencies and non-conformances discovered during walk downs the
various phases described in section 6.3 shall be recorded and entered into the PetroPCS
Database or rejected. Rejected Punch items will be returned for submission as change
order.
Sub-system Number
Punch Listing Phases
Date of walk down
Punch List No.
Originator Name
Tag Number
Material Required (Yes / No)
Discipline
Description of the deficiency
Punch list item Category (A, B and C)
Signature of CONTRACTORS Accepting Authority for closing out a punch item (Closure
will be tracked electronically in Petro-PCS. Clearing by CONTRACTOR, Verification by
COMPANY.).
Signature Blocks for CONTRACTOR and COMPANY representative
Walk down participants
A Blank Punch List Form is attached as Appendix A
Punch number will be given by Turnover Team as per the following numbering terminology
for the various Yards/ Islands
Eg: Punch item originate at GPC Yard shall start with “PL-GPC-0001”.
However, FAT punch items outstanding from across the manufactures will be loaded in to
PetroPCS in accordance with Par 6.7 and the numbering shall be start with “PL-FAT-0001”.
UPPER ZAKUM 750
ISLANDS SURFACE FACILITIES PROJECT – EPC2
PROJECT No. P7512
The Construction and Commissioning engineers shall regularly monitor the progress of
outstanding punch list items clearance and they shall plan/assign the priorities in line with
scheduled completion dates.
During punching it is conceivable that some punch items identified will require Engineering
review and action. The responsible engineer will communicate these punch queries to
Engineering for mitigation and subsequent corrective implementation at site.
The punch list coordinator will review the status of all punch list items and will closely follow
with the Construction and Commissioning engineers to complete punch list items that would
be deemed critical for releasing completion certificates at the different stages of the project
phase. The punch list coordinator will periodically issue a status report showing the balance
of all open punch list items to the Construction and Commissioning manager highlighting
priorities for their action.
Resolution of punch list items shall be carried out by CONTRACTOR. Once the Punch list is
physically closed out in field, as per IFC drawings, CONTRACTOR will sign it off on the
original Project Punch List form and submit it to Turnover Operator to enter “Cleared date”
by CONTRACTOR in PetroPCS. COMPANY shall verify the punch item against IFC
drawings and the Accepted Date and the name of person who has accepted will be updated
in PetroPCS. If any rejected items will be treated as per Section 6.19 of this document
The responsibility for clearing punch list items shall rest with the CONTRACTOR
Construction unless these punch list items are agreed to be completed by CONTRACTOR
Commissioning or CONTRACTOR Commissioning requested that something within the
Construction work scope be left out to assist with the progression of the Commissioning
work scope; e.g., insulation flange or valve covers left off for a leak test, blind installed in a
closed position, etc.
The responsibility for accepting and signing-off cleared punch list items shall be the
responsibility of COMPANY for any punch list items generated in the PetroPCS. Also
COMPANY shall update in to the PetroPCS software for all punch list acceptance.
Disputed punch item will be resolved before they are entered in to PetroPCS. They will be
resolved at the post walk down meeting between Sub-Contractor, Contractor and
COMPANY. If no agreement can be reached at that level then it will be escalated to
Management level for resolution
Rejected Punch items are a result of COMPANY not agreeing with CONTRACTOR that the
quality of the defect repair is adequate and the defect required further remedial action. If no
UPPER ZAKUM 750
ISLANDS SURFACE FACILITIES PROJECT – EPC2
PROJECT No. P7512
agreement can be reached that the quality of the defect repair is adequate then it will be
escalated to Management level for resolution
7. RECORDS
8. APPENDICES