Project OVERALL RATING 100.

00%

Item Description

Item No

Document
Process Data sheet for Equipments
Description

Document No.

Adherence to the
Sr. No Parameter Description Checks subject Parameter Remarks if any
(Y/N)

Min., Max. & Normal operating parameters. Eg.


Temperature, pressure, flow rates, Max. & Min.
1 Process parameters Y
Design conditions, Fluid properties, volumes, heat
loads.

Correct Material of Construction as per corrosion


2 Material of Construction Y
report

Applicable Codes & Check for data in line with accepted project
3 Y
standards engineering codes, practices and latest standards.

Preliminary sizing of package items based on


Preliminary selection/
4 calculations, heat transfer areas, requirement of Y
Design check
internals.

Check for operating & standby requirements and


5 Standby Requirements Y
quantity specified properly.

6 Utility Requirements Availablity of utilities with specifications defined. Y

Nozzles, manways & sizes included considering


control, draining, venting, purging & Isolation.
7 Nozzle Details Y
Instrument/Process equipment connections to be
specified as per agreed standards.

Battery limit of vendor/package supply clearly


8 Scope of Supply Y
defined along with utility connections.

Measurement of units as per project standards,


equipment tag no., description as per PEFS,
9 General Requirements Y
correct data sheet no. & revision, Hold list, notes
included

Check for completeness/veracity of inputs


10 Input Adequacy Y
specified for other Disciplines to proceed.