Professional Documents
Culture Documents
THIS IS ONLY ESTIMATED FOR PLANNING THE JOB WITHIN TA WORKS. IF OWNER WANTS TO KNOW THE DETAIL, PLEASE REFER TO E+I PROJECT SCHEDULE.
PULLING CABLE CAN BE DONE BEFORE TURN AROUND. IN THIS CASE WE DO TERMINATION CABLING ACTIVITY, INSTEAD.
OWNER QUESTION IS NOT RELATED WITH THE METHOD STATEMENT PURPOSED. PLEASE UNDERSTOOD WHAT THE METHOD STATEMENT MEANS FOR. IF OWNER
1 WANT TO KNOW THE DETAIL ACTIVITY, PLEASE REFER TO PROJECT CONTROL SCHEDULE.
3
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 2 of 76
NO.
TABLE OF CONTENT
1. PROJECT DESCRIPTION 5
2. DEFINITION 5
3. PURPOSE 5
4. SCOPE OF WORK 6
5. INSTALLATION PROCEDURE 10
INSTALLATION FLOWCHART 10
INSTRUMENTATION MAINTENANCE AND REPLACEMENT ACTIVITIES 18
7. IDENTIFICATON TAG 74
INSTRUMENT TAGGING AND LINE IDENTIFICATION 74
POST INSTALLATION TEST 74
REACTOR: 15 - R - 101 76
CO BOILER: 15 - B -101 76
STEAM SUPERHEATER: 15 - F - 102 76
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 5 of 76
NO.
1. PROJECT DESCRIPTION
PT PERTAMINA intends to perform a Revitalization to the existing Residue Catalytic Cracking
(RCC) at Refinery Unit VI Balongan due to the incapability of RCC to achieve maximum capacity
since early start up and it has never been able to achieve 4 years’ continuous operation. The
objective of the EPC Revitalization Project of RCC RU VI Balongan is to conduct Major Turn
Around to improve Overall Reliability of the unit for 4 years Turn Around Cycle and to improve
Mechanical Integrity.
2. DEFINITION
PROJECT Revitalization Project of RCC Unit PERTAMINA RU VI Balongan
3. PURPOSE
This Method Statement formalizes the requirements for the field instrument installation. The
specifications, procedures, and guidelines contained in this Method Statement specify the
technical requirements to be followed and also act as a reference to clearly establish defined
standards for work assessment. Moreover, this document shall provide guidelines to check that
specified materials are installed and agreed procedures are implemented during the execution of
work and to define the responsibilities for controlling the execution.
This procedure shall be applied for Field Instrument installation. This work will be carried out
during TA period should be executed according to applicable standard industries.
All workers are required to comply with safety requirements in accordance with the HSSE
standards of Contractor and Pertamina.
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 6 of 76
NO.
4. SCOPE OF WORK
The scope of this Method Statement is to describe the sequence of activities involved in Field
Instrument Installation as per the requirements of contract specifications, and codes, standards
of the project titled as under: “EPC Revitalization project of RCC RU VI, Balongan”
The reference documents and drawing required to works with this procedure are:
- General Specification for Instrumentation
- Instrument Index.
- Instrument function test procedure.
- Instrument Location Plan.
- Instrument Hook up Drawing.
- Instrument Equipment Layout.
- Instrument Loop Diagram
- Instrument cable schedule list
- MS for Instrument Equipment Installation
- MS for Instrument Cable Tray Installation
- MS for Instrument Cable Pulling
- MS for Instrument Cable Termination
- MS for FO Cable Installation & splicing
- MS for FO Cable Testing Procedure
- MS for Junction Boxes Replace & Installation
- MS for Instrument Calibration & Loop Test Procedure
- Related P&ID.
There are ten types of field instrument installation shall be concerned in this procedure.
1. Flow Instrument Installation.
2. Level Instrument Installation.
3. Temperature Instrument Installation.
4. Pressure Instrument Installation.
5. Flow element (Orifice Plate) and Restriction Orifice Installation
6. Control Valves and On-Off Valves Installation.
7. Actuator and accessories Installation For Dampers
8. HPCU and Control System for Diverter Valves and Slide Valves
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 7 of 76
NO.
9. Special check valves accessories (such as Air Cylinder, regulator, solenoid and flexible
hose) Installation
10. Process Analysers Installation (included CEMS)
11. Flame scanner Installation for COB and DFAH area.
The following checks and confirmation shall be made prior to starting the works:
a) Confirm safety and security regulations (concerning work permit, safety training, etc.)
b) Confirm documents (project specifications, working drawings, manufacturer's drawings,
work specifications, etc.) required for executing the installation work.
c) Confirm whether the work schedules have been prepared.
d) Materials shall be checked as per material list and Vendor's drawings in accordance
with the availability of all hook-up fittings and other material for supports.
e) Material shall be checked in accordance with the construction drawings, shortage
material shall be informed to Engineering Group.
f) Confirm whether field instrument and material that will be used meet the specification.
g) Before installation, the area concerned shall be inspected, and the schedule of work
shall be adjusted.
h) Since instrument installation involves work at high place, scaffolding shall be provided.
i) Protection against other activities shall be provided to avoid dirt, damages or lost.
There are several method of field instrument installation shall be concerned in this
procedure.
a) All field instruments shall be installed by Instrument Group.
b) All related field instrument replacement, the accessories (gasket, bolt & nuts) will be
provided by Instrument Group.
c) All Piping replacement, the accessories (Gaskets and Bolt & nuts) for Control Valves,
Thermocouple, Orifice plate will be provided by Piping
d) Ship loose and field instrument installed on the Mechanical Packages (such as Flame
Scanner on Burner, Reactor Skin on Reactor 101/102, Air cylinder c/w accessories
for Special Check Valve Packages of supply and HPCU & Actuator for Diverter Valves
and Slide Valves)
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 8 of 76
NO.
All test equipment which is used for verification of fiscal measurement instruments shall
possess a current test certificate which has been issued by a laboratory with traceability to
National Standards. This requirement however does not extend to equipment which is used
only for electrical current or original generation and which is not used for measurement; the
output of such equipment shall however be shown to be stable and repeatable.
4.7. Manpower
Field instrument installation work shall be done by qualified technician's skill. The
technicians shall have capability of tubing and wiring skill and knowledge of field instrument
to be installed or combination of technician skill as a team in field instrument activity.
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 9 of 76
NO.
Due to the work area safety regulation, every people which work in this activity shall have
high safety awareness. All the man power shall be provided with the PPE include full body
harness.
Personnel requirement:
i. QA/QC Engineers
ii. OEM Personnel
iii. Supervisors
iv. Technicians/Foremans
v. Skillers (tubing & fitting)
vi. Helpers
vii. Welders
5. INSTALLATION PROCEDURE
Installation Flowchart
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 11 of 76
NO.
5.1.1 General
a) All documents received at site shall be approved for construction revision
status such as datasheet, specification and drawings.
b) All field instrument received at site shall be checked and inspected as per
instrument datasheet and requisition.
c) All field instruments shall be stored in a dry, clean and safe area, new, unused,
undamaged and free of dirt.
d) All field instruments shall be protected from damage during fabrication,
painting, sandblasting, insulation and other construction activities.
- Instrument tubing & fittings shall be match with the material standard as stated
on project specification.
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 13 of 76
NO.
- Tube fittings, such as double ferrule, pressure seat, no torque type for use on
heavy or thin wall tubing. Only one make of fittings shall be used throughout the
plant.
- All instrument tubing and fittings shall be IMPERIAL (inches), the VENDOR shall
ensure that only imperial fittings and tubing is used throughout the installation.
- Impulse lines (piping / tubing) shall be installed using the practical minimum
number of fittings bearing in mind the possible requirement for future removal
and maintenance of the attached instruments.
- The primary requirements for single or double block and bleed isolations for all
instruments shall be as per the piping specifications. Additional block and
bleed manifolds (2 or 5 way-valve) and gauge isolation valves shall be as
detailed in the Instrument Hook-up diagrams for each instrument type.
- Instrument tubing shall be run and laid in a neat and methodical manner, in
vertical and horizontal planes only, for ease of identification and fault rectification.
Vertical impulse lines shall be installed using plumb lines.
- All tubing shall be fully supported and suitably clamped in dedicated tubing trays
except where it is self-supporting around devices. The maximum permissible
unsupported length shall not exceed three feet (approx 1m). Impulse tubing
shall not be run in cable-tray or raceways.
- All horizontal impulse piping / tubing shall be run with a minimum slope of 1 in
12, such that the direction of slope is downwards from the process for liquid
service and upwards from the process for gas services. Wherever this is not
possible due to access requirements for instruments or to avoid long impulse
lines, suitable drain / vent shall be provided at low / high points.
- All tubing shall be reamed out at the ends prior to flaring and fitting out to
maintain the internal diameter of the tubing. All tubing shall be blown out until
completely free of shavings or foreign materials prior to connection.
- Tubing shall not be installed such that it would provide a convenient foothold for
routine climbing. Tubing shall also be routed such that it does not interfere with
the removal of grating.
- All tubing shall be joined using double compression type fittings. Piping shall
be joined using the appropriate pipe fittings or flanges as detailed in the piping
specification.
- For parallel multiple tubing runs, tubing shall be spaced such that in-line
connectors can be assembled and disassembled without disturbing adjacent
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 14 of 76
NO.
- All take off lines and fittings from the main header shall be either galvanized
carbon steel (inside and out) or stainless steel and shall be fitted with a local
(full bore) isolation valve adjacent to the manifold.
- The size of the take-off lines and the permissible number of consumers is
dependent on the size according to the following table:
- The differential and static pressure lines shall not exceed 20 feet in length for
direct connected or locally mounted instrument.
- For gas services, where practical, the flow meter or transmitter shall be installed
above the orifice taps with impulse lines sloped such that any condensation
formed in the meter body or impulse lines will drain into the orifice taps.
- Flow instruments using orifice plates as the primary element shall have a 316SS
5-Way Valve manifold near the instrument in addition to the primary block valves
at the orifice fitting. Piping specification to be followed for rating and materials.
SS 316 is the minimum material to be used unless not recommended for the
service.
- The primary valves located at the orifice fitting shall be 1/2" full opening and
installed so as to permit cleaning the orifice connection.
- Adequate instrument supply headers and branch lines shall be provided for all
operating areas. Take-offs for branch lines shall be from the top of the main
header with block valves equal in size to the branch line. All low points shall
have a 1/2" ball valve installed.
- Piping and tubing shall be blown clean with clean dry air before connected.
Note: for 15-SLV-105B, material for control system will be provided by OWNER.
CSO will install and configure the controller in OS14.
5.2.1.2 Sequence Of Works Maintenance For Slide Valves (supervised by MEA Field Services
Engineer)
a) Inspection and repair for Actuators
b) Inspect cylinder assembly as per manual manufacturers
c) Do visual inspection of position transducer
d) Check operating pressures, thrust and speed for possible binding in the
Cylinder Rod and Valve Stem
e) Check the temperature, pressure, and for any possible leaks
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 19 of 76
NO.
5.2.1.2.1 Inspection and repair for HPCU (supervised by MEA Field Services Engineer)
1) Do flushing procedure
2) Do visual inspection of all pilot check and flow control valve
3) Do visual inspection of accumulator and nitrogen pre-charge
4) Do visual inspection of breather valve functionality
5) Check level switch at reservoir, Ensure fluid operating level should be
somewhere between the initial fill and low level marks.
6) Do replacement of hydraulic fluid and filter as per manual instruction standard
7) Replace recommended Spare part as per Vendor (MEA) requirement
8) Check status pump (main and stand) and set pump pressure and flow as
required
9) Check relief valve pressure and do pop up test in order to check its functionality.
10) Re-set of the relief valve setting pressure once deviated from design original
11) Test Running of HPCU System
12) Service & Function test by OEM Vendor (MEA. Inc)
5.2.1.2.2 Electronic & Control Initial Settings and Check (supervised by MEA Field Services
Engineer)
5.2.1.2.3 Mounting Actuator & Setting Mechanical Stops (supervised by MEA Field
Services Engineer)
CATALYST
No. REACTOR RISER REGENERATOR COOLER A:
15 - R - 101 15 - L - 108 15- R-103/104 15 - E - 113A
1 15-SLV-101 - 15-SLV-105A/B 15-SLV-104A
5.2.1.3 Sequence of Works Replace and Upgrade of Slide Valve (supervised by MEA Field
Services Engineer)
a) Prepare permit work before starting dismantle and install new HPCU and
Actuator.
b) Coordinate with Heavy Lifting team to embark and disembark the main
equipment (HPCU and Actuator) for slide valves
c) Ensure that the existing base frame of HPCU has been cleaned and fitted to
accommodate new HPCU.
b) Remove and dismantling existing tube and pipe that attached in hydraulic local
control unit.
c) Remove existing cable signal from Actuator unit & Hydraulic Power Control
Unit
d) Remove existing cable power from Actuator unit & Hydraulic Power Control
Unit
e) Disembark the dismantling of existing HPCU & actuator to the ground
f) Relocate and store the existing HPCU and Actuator to the temporare
warehouse.
l) Conduct fiber optic termination and splicing in Optical Termination Box both
in HPCU in Field and SLV control panel in OS14. Detail instrument
termination of Fiber Optical cable refer to MS for FO Cable Installation &
splicing
a) Ensure that all wiring inside of new HPCU and new Actuator already installed
properly
b) Ensure all tubing installation that connected HPCU and valve actuator
assembly already installed properly and no found leakage.
c) Do megger test to ensure cable condition (test shall conduct before and after
installation cable) from HPCU to outstation 14
d) Do Continuity test after cable installation from HPCU to outstation 14
e) Commissioned all equipment and related accessories from HPCU to Existing
DCS at Control Room
CATALYST
No. REACTOR RISER REGENERATOR COOLER A:
15 - R - 101 15 - L - 108 15- R-103/104 15 - E - 113A
1 - 15-SLV-102 15-UV-007 15-SLV-104B
2 15-SLV-103
5.2.1.4 Control System replacement in OS14 (supervised by MEA Field Services Engineer)
i. Dismantle the existing PLC cabinet slide valves and replace with new PLC
cabinet slide valves
ii. Control System Upgrade for RCC Slide Valve Actuator Systems
iii. Upgrade 2nd generation technology to latest generation technology & latest
firmware include :
a) Replace all the control components and installing new rack cabinet with
redundant PLC for each actuator.
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 23 of 76
NO.
5.2.1.4.2 Sequence of Works replacement of Control System in OS14 (supervised by MEA Field
Services Engineer)
Following activites must be done prior and after control system replacement:
1) Ensure the power to the existing PLC cabinet is Off before dismantle the
existing PLC cabinet in OS14.
2) Dismantling of all existing power control unit assembly and others
supporting material.
3) Install New PLC cabinet for Slide Valves. Refer to U2004-015-JUV-JY00-
T0677 MS for Instrument Equipment Installation
4) Conduct instrument cable termination, signal, and power to new PLC
cabinet slide valves as design engineering drawing.
5) Remove and install new cable (Instrument cable, cable tray and buried
cable) as refer to design engineering drawing. Detail cable installation refer
to MS for Instrument Cable Pulling.
6) Install hardware and software facilities to accommodate new PLC Controller
Slide Valve in OS14.
7) Do setting and simulation of new PLC controller of slide valve
8) Connect to existing FCS DCS YOKOGAWA in Control Room
9) Do modification of graphics existing DCS in Control Room to accommodate
new upgrading of 15-UV-007 and 15-SLV-103
10) Do function test as per Vendor Manual Instruction Procedure
11) Conduct loop test and communication test between Field Instrument, Local
Panel, Outstation 14 & Control room
CATALYST
No. REACTOR RISER REGENERATOR COOLER A:
15 - R - 101 15 - L - 108 15- R-103/104 15 - E - 113A
1 15-SLV-102 15-SLV-103 15-SLV-104B
2 15-UV-007
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 24 of 76
NO.
5.2.2.1 General Scope of works Diverter Valves (Under supervised by TAPCO Field
Services Engineer)
a) Remove and replace existing actuator diverter valves (15-A-103)
b) Remove and replace existing HPCU diverter valves (15-A-103)
c) Disembark and lift the HPCU and Actuator to the ground (by Construction)
d) Field Piping Installation HPCU and Actuator for Diverter Valves
e) Install new PLC controller diverter valve in OS14.
f) Instrument Cable Installation from Field to OS14 (refer to MS Instrument Cable
Pulling and MS Instrument cable installation and Termination)
5.2.2.2 Sequence works of replacement actuator and HPCU for Diverter Valves
1) Ensure that all wiring inside of new HPCU and new Actuator already installed
properly
2) Ensure all tubing installation that connected HPCU and valve actuator
assembly already installed properly and no found leakage.
3) Do megger test to ensure cable condition (test shall conduct before and after
installation cable) from HPCU to outstation 14
4) Do Continuity test after cable installation from HPCU to outstation 14
5) Commissioned all equipment and related accessories from field to Existing
DCS at Control Room
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 26 of 76
NO.
5.2.3 TRANSMITTERS
REACTOR REGEN’TOR
No.
15 - R - 101 15-R-103/104
1 15-LT-003 15-LT-010
2 15-LT-004 15-LT-011
3 15-XT-105
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 32 of 76
NO.
1 15-LT-515 15-LT-008
2 15-LT-521 15-LT-051
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 33 of 76
NO.
Remove and install existing field instrument c/w instrument cable and
consumable material.
Loop check.
Function test.
1) Remove and install existing field instrument c/w instrument cable and
consumable material.
2) Loop check.
3) Function test.
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 34 of 76
NO.
RAISER
No
15 - L - 108
1 15-PDT-585
Remove and install existing field instrument c/w instrument cable and
consumable material.
Loop check.
Function test.
RAISER
No
15 - L - 108
1 15-PT-586
2 15-PT-587
Remove and install existing field instrument c/w instrument cable and
consumable material.
Loop check.
Function test.
RAISER
No REGENERATOR
15 - L - 108
1 15-FT-035A 15-FT-009
2 15-FT-035B
3 15-FT-039A
4 15-FT-039B
1 15-LT-001A
2 15-LT-001B
3 15-LT-001C
Remove and install existing field instrument c/w instrument cable and
consumable material.
Loop check.
Function test.
5.2.3.12 Analyzer Transmitter (Density & CO/CO2 Analyser Installed and supervised by OEM
vendor)
Turn off power line of existing Analyser (density and CO/CO2 Analyser type)
before it will replace with a new analysers
Loose up all tubing connection and connectors from process to existing
local panel Analyser.
Loose up termination and remove existing signal, sensor, and power cable.
Release residue of gas pressure/flow trapped in tube/pipe.
Remove existing density probe sensor from pipe line properly.
Remove existing analyser transmitter from its support.
Install new analyser (density and CO/CO2 analysers type) as per manual
instruction given by Manufacturers.
Install new sampling system for new density analyser and CO/CO2
analysers
Install new tubing and required consumables material between filter
sampling system and probe analyser.
Install and pull new signal cable from new Analyser to the existing Junction
Boxes based on existing Field Cable Schedule and Junction Boxes
Termination drawing.
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 39 of 76
NO.
COB
No
15-B-101
1 15-AT-001
2 15-AT-002/003
5.2.3.13 Process Analysers for orifice chamber area (15-A-102) Installed and supervised by
OEM Vendor
Ensure new support to accommodate new Local Panel for analysers have
been installed before Turn Around start. It should be built during Pre-Turn
Around Activity.
Coordinate with lifting construction to handle new local panel of analysers
to be positioned on the higher platform.
Located and positioned the local panel on the designation area where the
support has been installed.
Secured new local panel on the new support by bolted altogether
Install new sampling filter on designated piping as OEM manufacturer
supervision.
Install all tubing and connectors from filter sampling to new local panel
Analyser.
Pull and install new cabling (signal & power) from probe to new local panel
and secure it by cable glands.
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 40 of 76
NO.
Orifice
No Chamber
15-A-102
1 15-AT-901
2 15-AT-902
Replace a new control valve assembly c/w accessory (smart positioner, air
regulator).
Replace signal cable from field to junction box.
Replace signal cable from junction box to outstation-14
Replace gasket flange, bolt & nut.
Install cable tray.
Loop check.
Function test.
Replace a new control valve assembly c/w accessory (smart positioner, air
regulator).
Replace signal cable from field to junction box.
Replace signal cable from junction box to outstation-14
Replace gasket flange, bolt & nut.
Install cable tray.
Loop check.
Function test.
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 42 of 76
NO.
Replace a new control valve assembly c/w accessory (smart positioner, air
regulator).
Replace signal cable from field to junction box.
Replace signal cable from junction box to outstation-14
Replace gasket flange, bolt & nut.
Install cable tray.
Loop check.
Function test.
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 43 of 76
NO.
CO BOILER
No.
15 - B - 101
1 15-TV-039
2 15-TV-043
DFAH
No.
15 - F - 101
1 15-TV-013
Remove and install existing control valve c/w instrument cable and
consumable material.
Loop check.
Function test.
REGEN'TOR
No.
15 - R - 103/104
1 15-FV-035B
2 15-FV-039B
Remove and install existing on-off valve c/w instrument cable and
consumable material.
Loop check.
Function test.
RAISER
No
15 - L - 108
1 15-HV-045
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 46 of 76
NO.
5.2.4.8 Aircylinder/ Actuator, Regulator, and Solenoid Valve complete with accessories for
Special Check Valves
REGEN'TOR DFAH
No
15 - R - 103/104 15 - F - 101
1 15-SCV-201 15-SCV-206
2 15-SCV-202
3 15-SCV-203
4 15-SCV-204
5 15-SCV-205
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 48 of 76
NO.
5.2.4.9 Aircylinder/ Actuator, Regulator, and Solenoid Valve complete with accessories for
Dampers (15-UV-013/014, 15-FV-027/028 and 15-HV-048/049)
CO BOILER
No.
15 - B - 101
1 15-FV-027
2 15-FV-028
3 15-UV-013
4 15-UV-014
5 15-HV-048
6 15-HV-049
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 49 of 76
NO.
CAT. HOPPER
No.
15-V-104
1 15-TI-107
2 15-TI-098
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 52 of 76
NO.
REACTOR
No
15 - R - 101
1 15-TI-032
5.2.6 SWITCHES
Ensure power has been shut off before dismantle the existing flow switch
from cabinet in OS14
Remove existing flow switch.
Install new flow switch
Set up flow switch
Function test new flow switch.
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 55 of 76
NO.
OS14
No
MR
1 15-FSLL-061
CO BOILER
No
15 - B - 101
1 15-LSLL-014
CO BOILER
No
15 - B - 101
1 15-ZSH-049A
2 15-ZSH-049B
3 15-ZSH-049C
4 15-ZSH-049D
5 15-ZSH-049E
6 15-ZSH-049F
Ensure power has been shut off before dismantle the existing temp. switch
from cabinet in OS14
Install new temperature switch on cabinet as it was located.
Function test temperature switch.
OS14
No
MR
1 15-TSHH-120
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 58 of 76
NO.
OS14
No
MR
1 15-FSLL-079A
2 15-FSLL-079B
3 15-FSLL-079C
4 15-FSLL-068
5 15-FSLL-069
6 15-FSLL-070
7 15-FSLL-071
REGENERATOR
No 15 - R -
103/104
1 15-FSLL-062
2 15-FSLL-063
3 15-FSLL-064
4 15-FSLL-065
5 15-FSLL-066
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 60 of 76
NO.
DFAH
No
15 - F - 101
1 15-BE-001
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 63 of 76
NO.
CO BOILER
No
15 - B - 101
1 15-BE-015A/16A/17A
2 15-BE-015B/16B/17B
3 15-BE-015C/16C/17C
4 15-BE-015D/16D/17D
5 15-BE-015E/16E/17E
6 15-BE-015F/16F/17F
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 64 of 76
NO.
5.2.12 AUXILIARIES
No 15 - S - 102
1 15-RO-001
2 15-RO-003
3 15-RO-005
Loop check.
Function test.
JB Area distribution
NO. AREA
1 CO Boiler
15-B-101
2 REGEN
15-R-103/104
3 RAISER
15-L-108
4 CAT. COOLER
15-E-113A/B/C/D
5 DFAH
15-F-101
6 REACTOR
15-R-101
7 CAT. HOPPER
15-V-102/103/104
8 ORIFICE CHAMBER
15-A-102
9 PRESSURE LET DOWN AREA
Cable tray detail installation is refered to Method Statement for Cable Tray
Installation_R1 doc.no. U2004-015-JUV-ERT0-T0678
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 71 of 76
NO.
NO. AREA
1 CO Boiler
15-B-101
2 REGEN
15-R-103/104
3 RAISER
15-L-108
4 CAT. COOLER
15-E-113A/B/C/D
5 DFAH
15-F-101
6 REACTOR
15-R-101
7 CAT. HOPPER
15-V-102/103/104
8 ORIFICE CHAMBER
15-A-102
9 PRESSURE LET DOWN
AREA
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 72 of 76
NO.
All electrical earthing works shall conform to Specification for Grounding, earthing and
lightning.
Earthing pits shall be provided for instrument earthing. The resistance for the earth pit shall
be less than 1 ohm. The instrument earth pits shall be connected to the instrument earth
bar in IER and to the individual marshalling cabinet earthing busbar. All the shielded cable
drain wires shall be terminated to the earth busbar.
All panel and cabinet bodies shall be earthed with to power earthing grid in control room
and IER. The power earth grid is provided by electrical contractor.
The field instrument panels, junction boxes and instrument housings shall be power earthed
to the grid at two points.
Cable tray joint locations shall be connected together electrically with jumpers on both ends
and the trays shall be connected to power earth grid.
Protection
Sub-CONTRACTOR shall protect all instruments, tubing and piping during construction or
while in storage, from physical damage, contamination by dirt, sand or any other foreign
material.
Sub-CONTRACTOR shall cover all instruments with polyethylene bags to ensure that the
instruments are adequately protected from weather. The bags shall be kept in place at all
times, except during work on the device they protect, until they are removed for start-up.
Drying agent with humidity indicator shall be put inside the polyethylene bags and it shall
be replaced when the colour changes from blue to pink.
Installation Checks
All the installation works of instruments, valves, cables, tubes and other accessories shall
be checked for the correctness of installation prior to the pre-commissioning checks and
tests. Sub-CONTRACTOR shall prepare the installation check sheets for all instruments,
valves (Shutdown / Blowdown / Control / Safety), panels, junction boxes, cables, Tubing
and fittings, and other accessories for the proper installation and functional requirements.
The installation check sheets shall be submitted to CONTRACTOR / COMPANY for
approval.
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 74 of 76
NO.
7. IDENTIFICATON TAG
Permanent identification tag shall be attached to each instrument, control valve, shutdown
valve, relief valve, junction box, panel and cabinet in accordance with the project numbering
procedure, the P&ID’s and the instrument index.
Nametags for instruments and valves shall be 316 SS and attached to the device with 316
SS wire.
Nametags for junction boxes, panels and cabinets shall be fabricated from laminated plastic
with white outer lamination and black inner lamination, unless otherwise specified by the
Contractor or Company.
All field mounted Instruments, junction boxes, pneumatic headers, tubing and wiring
termination shall be labeled or tagged in a manner approved by COMPANY. The tag
plates shall be made of laminated plastic in white / black / white. Individual Instruments
shall have Stainless Steel tags.
Tubing shall be pressurized as above for at least one hour and monitored with a test
gauge, leaks in excess of 0.25 bar/hour shall be considered a defect and shall be
rectified.
The CONTRACTOR shall protect all instruments, tubing and piping during construction, or
whilst in storage, from physical damage, contamination by dirt, sand or any other foreign
material. The CONTRACTOR shall cover all installed instruments with polyethylene or bags to
ensure that the instruments are adequately protected from the weather. The bags shall be
kept in place at all times except when work is in progress on the device until required for service
and shall be periodically checked for excess moisture.
EPC REVITALIZATION PROJECT
OF RCC RU VI BALONGAN
METHOD STATEMENT FOR FIELD INSTRUMENT
INSTALLATION
PAGE
REV.NO. 1F 76 of 76
NO.
9.1.1 D-15-1225-205F-B-RC
REACTOR: 15 - R - 101
CO BOILER: 15 - B -101
ALL AREA All Field Instrument Ensure all scaffolding has erected in the designation area.
1. Field Instrument (Transmitter, Switch, Gauges) 1 Dismantle existing Field Instruments (Control/ on-off valves, Thermocouple, Analysers,Transmitter, Switches, Gauges)
2. Flame Scanner for Burner Element Packages 2 Dismantle and remove existing signal cables & cable tray and relocate to the warehouse
3. Control Valves & On-Off Valves 3 Install new replacement field Instruments (Control/ on-off valvesThermocouple, Analysers,Transmitter, Switches, Gauges)
4. Thermocouple 4 Install and pull new instrument cable and cable trays from Existing JB to Field Instrument
COB AREA
YES
(15-B-101)
5 Do Continuity test for All Signal/control cables Installed
5. CO/CO2 Analyser, Density analyser replacement and
CEMS reinstallement
6 Do Function Test
Solenoid Vaves (24 Pcs) 1 Dismantle existing Field Instruments (Solenoid Control/ on-off valves, Thermocouple, Analysers,Transmitter, Switches, Gauges)
Control Valves 2 Dismantle and remove existing signal cables & cable tray and relocate to the warehouse
Level Transmitter (LT Radar Type) & PDT 3 Install new replacement field Instruments (Solenoid Control/ on-off valvesThermocouple, Analysers,Transmitter, Switches, Gauges)
CATALYST HOPPER AREA
Pressure Switch & Local Indicator 4 Install and pull new instrument cable and cable trays from Existing JB to Field Instrument
(15-V-102/103/104)
NO
RO, FE 5 Do Continuity test for All Signal/control cables Installed
Control Valves 5 Install new Transmitter complete with tubing/piping and accessories
UTILITY RISER SECTION
NO
Transmitter 6 Install and pull new instrument cable and cable trays from Existing JB to Control Valves/ Transmitter
8 Do Function Test
Transmitter & Switch 1 Dismantle existing Control Valves complete with tubing and accessories, and Special check valve's accessories (Air Cylinder, Regulator etc)
SCV (Control only) 2 Dismantle existing Transmitter, Flame Detector, Gauges, Thermocouple complete with tubing/piping attached on it
Control Valves 3 Dismantle existing signal control valves/transmitter to Existing Junction Boxes
Flame Detector 4 Install new control valves complete with tubing and accessories
Pressure Gauges 5 Install new Transmitter complete with tubing/piping and accessories
8 Install and pull new instrument cable and cable trays from Existing JB to Field Instrument (CV, Flame scanner, transmitter)
10 Do Function Test
1 Dismantle existing Control Valves complete with tubing and accessories, and Special check valve's accessories (Air Cylinder, Regulator etc)
3 Dismantle existing HCPU and Actuator for slide valves 15-SLV-103 in Field complete with cables and tray
4 Dismantle all control cabinet existing slide valves in OS14 complete with cable & tray
Control Valves 7 Install new control valves complete with tubing and accessories
Special Check Valves (Instrument Part) 8 Install new air cylinder and accessories for Special check valves
REGENERATOR AREA
YES
(15-R-103)
Slide Valves (Instrument Control Parts only) 15-SLV-103 9 Install new HPCU and Actuator for Slde Valves (15-SLV-103) complete with accessories (tubing, piping etc)
Replace Thermocouple Junction Boxes (3 Pcs) 10 Install new Control Cabinet for Slide Valve 15-SLV-103 in OS14 complete with wiring and termination
12 Install and pull new instrument cable and cable trays from Existing JB to Control Valves/ Transmitter/SCV etc.
14 Do Function Test
3 Dismantle existing HCPU and Actuator for slide valves 15-SLV-102 in Field complete with cables and tray
4 Dismantle all control cabinet existing slide valves in OS14 complete with cable & tray
Field Instrument (Transmitter, Gauges, Thermocouple) 6 Dismantle existing Junction Boxes for thermocouple
Control Valves 7 Install new control valves complete with tubing and accessories
REACTOR RISER AREA
NO Slide Valves (Instrument Control Parts only) 15-SLV-102 8 Install new air cylinder and accessories for Special check valves
(15-L-108
9 Install new HPCU and Actuator for Slde Valves (15-SLV-102) complete with accessories (tubing, piping etc)
10 Install new Control Cabinet for Slide Valve 15-SLV-102 in OS14 complete with wiring and termination
11 Install and pull new instrument cable and cable trays from Existing JB to Control Valves/ Transmitter/SCV etc.
13 Do Function Test
2 Dismantle existing Transmitter, Gauges and Thermocouple complete with tubing/piping attached on it
3 Do maintenance for HPCU and Actuator for Slide valves 15-SLV-101 in field
Field Instrument (Transmitter, Gauges, Thermocouple) 5 Dismantle existing signal control valves/transmitter to Existing Junction Boxes
REACTOR AREA Control Valves 6 Install new control valves complete with tubing and accessories
(15-R-101/102) YES
Slide Valves (maintenance only) 15-SLV-101 7 Install new Field Instrument (Transmitter, gauges & Thermocouple) complete with accessories (Tubing/Piping, fitting etc)
8 Install and pull new instrument cable and cable trays from Existing JB to Control Valves/ Transmitter.
10 Do Function Test
2 Dismantle existing HCPU and Actuator for slide valves 15-UV-007 in Field complete with cables and tray
3 Dismantle all control cabinet existing slide valves in OS14 complete with cable & tray
Thermocouples c/w Thermowells 4 Dismantle existing signal Thermocouple to Existing Junction Boxes
Slide Valves (maintenance only) 15-UV-007 5 Install new Self contained electro-hydraulic actuator for Slde Valves (15-UV-007) complete with accessories (tubing, piping etc)
WITHDRAWAL CATALYST
6 Install and terminate wiring for control system 15-UV-007 to Existing FCS YOKOGAWA in OS14
COOLER AREA
NO
15-V-110
7 Install new thermocouple/thermowell and accessories
8 Install and pull new instrument cable and cable trays from Existing JB to Thermocouples
10 Do Function Test
3 Dismantle existing HCPU and Actuator for slide valves 15-SLV-104B in Field complete with cables and tray
4 Dismantle all control cabinet existing slide valves 15-SLV-104B in OS14 complete with cable & tray
FLOW THROUGH CATALYST 6 Install new control valves complete with tubing and accessories
Field Instrument (Transmitter, Gauges, Thermocouple)
COOLER AREA
NO 7 Install new HPCU and Actuator for Slde Valves (15-SLV-104B) complete with accessories (tubing, piping etc)
(15-E-113A/D & 15-V-101)
Control Valves 8 Install new Control Cabinet for Slide Valve 15-SLV-104B in OS14 complete with wiring and termination
Slide Valves (Instrument/Control only) 15-SLV-104B 9 Install and pull new instrument cable and cable trays from Existing JB to Control Valves/ Transmitter/SCV etc.
11 Do Function Test
Analyser 15-AT-004 (Remove & Install) 4 Install and pull new instrument cable and cable trays from Existing JB to Field Instrument
CATALYST COOLER STEAM
SUPERHEATER YES 5 Remove and Install existing Analyser 15-AT-004 which impacted on construction activity (if any)
(15-F-102)
6 Do Continuity test for All Signal/control cables Installed
2 Dismantle existing Control Valves/ On-off valves complete with tubing and accessories
3 Dismantle and remove existing signal cables & cable tray and relocate to the warehouse
Field Instrument (Transmitter, Gauges, Indicator, etc) 4 Install new replacement field Instruments (Transmitter, Indicator, Gauges)
Control Valves & On-Off Valves (7Pcs) 5 Install new control valves & On-off valves complete with tubing and accessories
SUPERHEATER BURNER & RAW
NO
OIL SURGE SECTION
6 Install and pull new instrument cable and cable trays from Existing JB to Field Instrument
8 Do Function Test
3 Do maintenance for HPCU and Actuator for Slide valves 15-SLV-105A/B in field
Control Valves 8 Install new Analyser signal cables from new analyser local panel to Existing JB
Process Analysers (15-AT-901 & 15-AT-902) 9 Install and pull new instrument cable and cable trays from Existing JB to Field
Control Valves Replacement (15-FV-020A) 4 Install new control valves complete with tubing and accessories
HP, MP, & LP STEAM SYSTEM Transmitter (15-FT-020A) 5 Install new Transmitter complete with tubing/piping and accessories
AREA NO
6 Install and pull new instrument cable and cable trays from Existing JB to Control Valves/ Transmitter
8 Do Function Test