Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
PANEL TAG:____________________
Page 1 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
DOCUMENT INFORMATION
No. Of Pages : - 22
CONTENTS
Page 2 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
1.0.0 Preface 04
1.1.0 Abbreviation 05
2.0.0 FAT Agenda 06
3.0.0 Required Documents List 07
3.1.0 Review of Testing Tools 08
3.2.0 Test Standards 08
1.0.0 PREFACE
Page 3 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Base Control Tech (FZC) has manufactured the MCC & PLC Panel as per Quality Standards given by
Johnson Controls Inc. The Factory Acceptance Test Procedure is given as per concurrence with Base
Control Tech Standards.
The Factory Acceptance Test is carried out in order to prove that the system should be validated and
demonstrated the compliance with Customer requirements
Validation based on design and requirement specifications, in order to determine the need for a validation of
the control systems. This will state, that the system and its components function properly, that
manufacturing, assembly, are done correctly and that system performance is in compliance with the
approved functional specifications and relevant documents.
Also, this report represents the actual quality status of the control system.
1.1.0 Abbreviations
Page 4 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Page 5 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Date :-
Responsible :- BCT :-
JCI :-
Page 6 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
* The changes marked in drawing will be incorporated in original drawing before Panel dispatch.
Page 7 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Instrument Calibration
S NO Description of Test Remarks
Make / Sr No Details
1 Multi-meter
2 Calibration source
Page 8 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Page 9 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Page 10 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Page 11 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
2 Doors bonded
Page 12 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Page 13 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Page 14 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Page 15 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
VALUES
Page 16 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Summary: - The purpose of this test is to verify during the startup of the PLC system processor has to go
normal operational mode without any error indication except for field inputs.
Objective: - The purpose of this test is to ensure that PLC automatically boots up when
going from ‘Power Off” environment to “Operating environment”.
Practice : -
1. Power on the entire system
2. Power off the PLC
3. Power on the PLC again
Principle: - Each component boots up automatically. All LED’s are normal. The plant is ready to resume
operation normally through the plc system
Comments:-
Page 17 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Summary: - The purpose of this test is to verify wiring of all the IO modules (includes DI, DO, AI and AO
modules) .
Objective: - The purpose of this test is to ensure that PLC IO modules are wired to
accept the field signals safely without damaging the hardware of the
system.
Practice : -
1. Check all the Digital inputs by injecting volts from TB and observe signals in module and
Programming Station.
2. Check all the Digital Outputs by forcing them one by one from Programming Station and
verify by using either relay or Lamps etc
3. Check all the Analogue input feed from terminals by 0%, 25%, 75% and 100%
proportional to 4 to 20mA using current source and read the values in Programming
Station.
4. Check all the AO by forcing 0%, 25%, 75% from Programming Station & read the
proportional mA values at Terminal Block on Process Meter.
5. Check all the IO-Link Modules communicating with PLC & DOL Starters
6. Check the SCADA Communication with PLC
Principle: - Depends upon the type of the IO module it has to perform as defined in the manual and the
indicated locations.
Comments:-
Page 18 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Summary: - The SCADA/HMI screens are drawn as per the P & I diagram given by the Company and the
same was approved by the Company.
Objective: - To verify that the screens are built to meet the Company requirement and operational
easiness, Identifiable for objects clearly.
Reference: -
1. P & I Diagram
2. Cause and effect chart
Note: For Document Number refer 3.0.0 Required Documents
Principle: - The controller should perform and produce output as expected in the control philosophy based
on the operation done on the HMI
Comments:-
Page 19 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Summary: - 1. Checking the application logic are done as per the approved control philosophy provide by
the Company.
2. Modbus signals are available for the existing MODBUS Master system, shall be tested by
any modbus compatible device.
Objective: - To verify the logics built inside the controller is according the control philosophy provided by
the Company and its meeting the required application. Logic will be tested by simulation on
inputs to the PLC by activating simulation in SCADA / simulator panel.
Practice: - 1. Simulate the logics from the test jig/ Software simulation for testing the application.
Sample for random application can be performed.
2. Check the Alarms and trip for each input
3. Check the Communication between compressor local panel to PLC
Principle: - The controller should perform and produce output as expected in the control philosophy.
Comments:-
Page 20 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
Page 21 of 22
PROJECT: SAFFRON B PROJECT
Doc. No: XXXX_FAT END USER : SHPP Singapore Pte Ltd Rev.0
9.0.0 CONCLUSION
The Factory Acceptance Test was conducted by Base Control Tech (FZC) in front of Johnson
Controls Inc.
The Factory acceptance test was conducted and ensured the objectives given in each title and
there is no deviations found with the approved documents and standards. The Factory Acceptance Test
was done as per the documents and all test results were met the requirements, specifications and standards
of Johnson Controls.
TEST WITNESSED BY
Page 22 of 22