PLN – PEMBANGKITAN KALIMANTAN UTARA

PLN TARAKAN

PROJECT PROGRESS REPORT


Name of Project
Tarakan 3 x J620 ENGINES
-INSTALLATION AT Binalatung PLTMG-
Customer
PLN – PEMBANGKITAN KALIMANTAN UTARA
PLN –TARAKAN
Project Nr. Type of Site / (Hydro / Cavern / etc.) Customer – Project Nr.

PLTMG (in Enclosure)


Contract Nr.

Day Nr. From (day/month) Until (day/month) Year Day & Night shift (Y / N)

03 April 03 April 2015 D


Weather condition Temperature in 0C
Clear - hot Min 30 – Max 33
Site Coordinator Navigat Project Commissioning Navigat QHSE Civil Sub-Contractor
Engineers Staff
0
Maringan 3 of Max 0 (local) 0
3 of Navigat M/E Sub-Contractor
power Project Staff
Service
Team
41

Working Hours / Working Hours /


Management & Administrative Staff
Day Week
Project Management 1 10 8.00-22.00
Project Support 2 10 8.00-22.00
ITP 0
QHSE 0
Production Personnel

Civil Work Staff

Supervisor Mechanic / Electric 2 12


Foreman Mechanic / Electric 2 12
Mechanic / Electric 16 12
Welder 2 12
Pipe Fitter 2 12
Scaffold and Painter 0
Machine (Crane) Operator 1 12
Semi Skilled Worker 8 12
Unskilled Worker 9 12
Janitor, Security 0
Totals 41
Working : PLN Pembangkitan Kalimantan Utara
PLN – PEMBANGKITAN KALIMANTAN UTARA
PLN TARAKAN

Area PLN Tarakan PROJECT PROGRESS


Location : Binalatung - Tarakan
-Tarakan 6MW-
Percentage
Activities Unit-1 Unit 2 Unit-3
Mechanical Work
Engines - Generators get down on foundation 100 % 40 % 100 %

Engine & Generator alignments 70 % 0% 20 %

Engine base frame – setting & connecting 100 % 100 % 100 %

Engine enclosure – steel structures erection 100 % 100 % 100 %

Sandwich panels installation + Doors 100 % 100 % 100 %

Air Inlet attenuators + ductings + Louvers 100 % 100 % 100 %

Radiators get top on enclosure 100 % 100 % 100 %

Install HT-LT and Lube Oil tanks 0% 0% 0%

Install HT-LT water to Radiator pipes 30 % 30 % 20 %

Install Jacketting water pipes 0% 0% 0%

Install HT-LT Circulation pumps 5% 5% 0%

Install Lube Oil pipes inner engine enclosure 0% 0% 0%

Install daily lube oil and supply-water pipes 0% 0% 0%

Install Water drainage pipes 0% 0% 0%

Install Gas Header pipes 30 % 30 % 30 %

Install Gas pipes + Gas trains & Supports 5% 5% 5%

Install Exhaust Y-pipes + Silencers & Supports 30 % 0% 20 %

Rockwool & Jacketting the exhausts 0% 0% 0%

Install Air Intake Fans and Elbow-Ductings 100 % 100 % 100 %

Air Outlet attenuators + ductings + Louvers 100 % 0% 100 %

Flushing & pressure test on HT-LT pipes 0% 0% 0%

Flushing & pressure test on gas header pipes 0% 0% 0%

MV enclosure installation 100%

Storage container 40’ get on foundation 100 %

Office container 20’ get on foundation 100 %

Electrical Work
PLN – PEMBANGKITAN KALIMANTAN UTARA
PLN TARAKAN

Aux. Transformers and the Transformers get 100 %


down on the foundations
MV & LV panels get position in MV enclosure 100 %

JB, SLDB, & MCP panels get position in engine


100 % 100 % 100 %
enclosures
Cable trays installation under MV enclosure 100 %

Cable trays installation onto engine


95 % 95 % 95 %
enclosures
Cable trays installation NGR to Transformer 100 %

Pulling and connecting all control cables going


5% 5% 5%
into MCP
Pulling and connecting all power cables from
60 % 60 % 60 %
JBs to generators and trafos
Pulling and connecting all LV/HV cables from 80 %
Aux. transformers to LVMD panels
Pulling and connecting all power cables from
60% 60% 60%
MV panels to trafos
Pulling and connecting all control cables from
engine enclosures location to MV enclosures 0% 0% 0%
locations
Pulling and connecting all power cables from
0% 0% 0%
MV enclosure to PLN’s end pole
ITP
Electrical and control precommissioning 0% 0% 0%

Test gas in 0% 0% 0%

Engine iddle running & synchronizing 0% 0% 0%

Reliability Running (RR) test 0% 0% 0%

Mechanical/electrical/civil Works

Remarks:
PLN – PEMBANGKITAN KALIMANTAN UTARA
PLN TARAKAN

Rolitrans continues to skid the engine (x-Langgam) into unit-2. They target to
finish skidding by tommorow, Saturday 04 April 2015.

Continue to fit and weld gas header pipe 6” and gas pipe 3”.

Three (3) of chimney have been seate at the top and the HT pipes are being
installed to the Radiators.
PLN – PEMBANGKITAN KALIMANTAN UTARA
PLN TARAKAN

Do cable ties to all the power cables.

Pulling cables NGR-Trafos.

Do clamping on power cables to LVMD.

Claim relevant – Report….*) Photo Sketch


Others
Deviation and reason for
delay acc. time schedule
-

Obstructions by others /
waiting time -
Deviations from scope of
supply acc. Contract
-

Missing performance
caused by other contractors
/ companies
PLN – PEMBANGKITAN KALIMANTAN UTARA
PLN TARAKAN

Other hindrances
-

Reasons and Cause for Additional Costs….*) Photo Sketch


Others

Documentation not
complete / faulty/ missing

Personal not qualified

Tools & Instruments


missing/ unproper

Material – Delay of
supply/ missing

Damages during
transportation

Unforeseen events

Health and Safety Photo Sketch Others

Incidents this week 0

Incidents to date

H&S Equipment on site


Complete

Regards,

Maringan