You are on page 1of 2

P-01

N&S Date: 3 January 2023


Weather Condition: Clear
DPR - Summary Sheet s

Client: SHELL PAKISTAN LTD.

Contractor: NASEEM & SON.

Project: Maintenance of C-01 Base Oil Tank at CFP Tank Farm Area LOBP

Prev. Today’s
Description Of Work Progress Progress Total Remarks

Permit issuance and Isolation. 100% - 100% Today : 3 January 2023


Cleaning of Tank 50% - 50% Blasting of 03 plates & 30’ railing done. &
Primer applied on 5 plates and 54’railing.
Installation of net Screen 100% 100% Blasting of 41 plates completed & 7 plates
Grit Blasting of tank & application of remaining.
Primer 82% 4% 86%
i. Yesterday : 3 January 2023
Welding of patch plates and doublers 100% 100% i. Blasting 0f 02 Plates and 24’ railing completed.
Power Brushing of Welding Seam of
bottom plates 100% ii. Blasting of 38 plates completed & 10 remaining.
iii. Blasting of base plates for vertical post of railing
Inspection (VBT) of Bottom By Third Party 100% - 100% done today.
Closing of expansion joint by sika -
Application of mid coat & Final coat of
paint -
Supply of gasket stud for Box up -
Removal of scaffolding -
Housekeeping & De-mobilization

Progress Pictures
Equipment Deployed Staff Labour
Deployed Deployed
Mobile Crane 0 Project Manager 0 Rescuers 4

Site Office 0 Construction Manager 0 Fabricator 0

Warehouse 0 Planning & Co-ordination Engr 0 Fitter 0

Paint Store 0 Manager HR / Admin 0 Grit blaster/Painter 2

Vehicles 0 Mechanical Engineer 1 Welder 0

Grinders 0 Trainee 0 Mechanical Tech 0

Compressor 1 Foreman / In-charge Rigger / Scaffold 0

Scaffolding with Planks 1 Supervisor 1 Helper 1

Paint MixtureMachine 1 Safety In-charge 1 Cook 0

Vacuum Machine 0 Fire Watcher 1 Driver 0

Hopper 1 Store Keeper 0 Office Boy 0

Hand Tools 10 Accountant/Site Admin 0 Painter 2

-
Representative
Representative
Abdul Hadi
Ali RAZA Shell Pakistan Ltd.
Naseem & Son