Work locations: P289 - Product Pump House, Metering, Loading and Unloading Gantry
Vehicles, Equipment and Tools to be used Wheelbarrow, Measuring tape,Trowel,Spade, Sprit Level, Wooden Float, Mixer Machine, Jack
Hammer, Chisel, Hammer, Water Drum, Water cooler, First Aid Box, Fire extinguisher and
other general hand tools
Expected Number of People 10
Hot Work
General comments
Any information entered should not affect the Ensure initial Gas testing
assigned risk level, identified hazard/controls Ensure Proper PPEs suitable with the task
or permit type:
Initial signatures
Type Name: Date: Dep./Company:
Request by Permit Requester Muhammad Ramzan 15 Mar 2024 09:33 Naseem and Son
Signature History
Type Name: Date: Dep./Company: Remarks:
Request by Permit Requester Muhammad Ramzan 15 Mar 2024 09:33 Naseem and Son
All members of the work party have participated in the LMRA and are Name of holder
familiar with the Jobscope and Hazard&Controls.
Company
Name Initials Name Initials
Permit number P289-00-6723327
......................... ......................... ......................... .........................
Date
......................... ......................... ......................... .........................
......................... ......................... ......................... ......................... What kind of work are you going to do?
......................... ......................... ......................... ......................... Demolishing and construction new flooring for Pump house
Has the Permit Issuer discussed the hazards & Does the work party know the emergency alarm
controls with the Permit Holder? Yes n/a and action required in event of an alarm or Yes n/a
accident?
Has the Permit Holder warned others that may be
affected by your work? Yes n/a Does the work party know the most effective Yes n/a
escape route and the location of the nearest
muster point?
Is there conflicting work that may affect you? Yes n/a Yes n/a
Does the work party know the location of the
If yes describe hazards and controls below.
nearest eyewash station, emergency shower, first
aid kit and AED device?
Are there additional hazards that need to be controlled? If newly identified hazards are material changes to the permit, contact Permit Issuer!
.............................................................................................................. ..............................................................................................................
.............................................................................................................. ..............................................................................................................
.............................................................................................................. ..............................................................................................................
Pictograms for key hazards Indicate which Life Saving Rules are applicable.
Verify isolation and zero Control flammables and Keep yourself and others out
energy before work ignition sources of the line of fire
begins
Safe Mechanical Work Authorisation Working At Height
Lifting
Plan lifting operations and Work with a valid permit Protect yourself against a fall
control the area when required when working at height
Energy Isolation
I have confirmed:
1 The Hot Work has been evaluated for Energy Isolation requirements.
Does Hot Work require Energy Isolation? If Yes: Complete Energy
Isolation Start-Work Check. If No: Continue to the next step2.
Hot Work
I have confirmed:
2 The hazards have been identified, controlled and it is safe to start.
3 Is the Hot Work in a Hazardous area? If Yes: Confirm the initial gas
test has been completed. If No: Move to Step 5
4 The Hot Work atmosphere will be continually monitored.
5 Ignition sources are identified and controlled.
6 Flammable/combustible materials have been removed or isolated.
Stop and seek help if any of the above controls/safeguards are not in place
Hot Work
2 The hazards have been identified, controlled and it is safe to start. • Complete a task risk assessment specific to the scope of work
• Discuss hazards with the work team prior to the start of work
• Check for simultaneous operations that may introduce an additional hazards
3 Is the Hot Work in a Hazardous area? If Yes: Confirm the initial gas test • The initial gas test has been completed by a Qualified Gas Tester.
has been completed. If No: Move to Step 5 • At all openings below and above the hot work area
• At a minimum distance around the hot work area
• Gas readings are within the required range
Note: Confirm gas testing outside of defined hazardous area if required for other reasons. Gas testing should be in compliance with company
requirements and applicable regulations.
4 The Hot Work atmosphere will be continually monitored. • Follow-up test frequency is documented (e.g., permit) before starting work.
Note: 'Continually' monitored means periodic monitoring of the atmosphere with a defined frequency or continuous monitoring throughout the duration
of work activities.
5 Ignition sources are identified and controlled. • Barriers are in place to prevent ignition in the hot work area:
•Drains, gaps, openings in tanks or piping have been covered/sealed
•Vents are isolated/routed away from the area
• A trained Fire Watch has been designated and is at the work location.
• Firefighting equipment is inspected, on site and fully functional.
6 Flammable/combustible materials have been removed or isolated. • All flammable/combustible materials have been removed or, if not removed, measures (e.g., fire blankets) are in place to shield them from ignition
sources
Team: Abdul Basit (Naseem & Son), Ali Murad Baloch, anwar Mughal, Fayyaz Approval:
Bhatti, Muhammad Ramzan
Joint Site Visit, [.PE.07] Hazardous Weather (PEOPLE) [.PE.07.02] Set weather limitations (lightning, rain, wind speed) S Permit Holder
Preparation, Mobilization and stop work when limit is exceeded.
of manpower to site
[.MO.12] Slips & Trips (MOTION) [.MO.12.01] Remove any trip hazards in the area, clean up any S Permit Holder
spills, wear anti-slip safety shoes
[.PE.01] Communication (PEOPLE) [.PE.01.01] During permit issuance and toolbox talk/Last Minute S Permit Holder
Risk Assessment discuss and agree the methods of
communication within the work party, with Operations (if
necessary) and with Emergency Responders (if necessary)
[.PE.05] Fatigue (PEOPLE) Ensure Proper rest breaks S Permit Holder
[.PE.05.02] Prior to start of work request work party to self S Permit Holder
report if they are suffering from fatigue
[.PE.05.04] Monitor for signs of fatigue and intervene/stop work S Permit Holder
if necessary.
- Ensure Intimal Gas Presence of Hazardous gases Ensure Initial gas testing before starting work S Permit Issuer
Testing By Permit Issuer
before starting work
Ensure Gas tester is calibrated and certificate is attached with S Permit Holder
permit
[.MO.05] Hand Tools - ALL (MOTION) Never use damaged tools and equipment S Permit Holder
[.MO.05.02] The use of knives is prohibited S Permit Holder
[.MO.05.03] Wear appropriate hand protection suitable for task S Permit Holder
[.MO.12] Slips & Trips (MOTION) [.MO.12.01] Remove any trip hazards in the area, clean up any S Permit Holder
spills, wear anti-slip safety shoes
Shifting of material & Damaged tools and equipment Never use or mobilize damaged tools and equipment S Permit Holder
tools to work site
manually by labor and
using of hand lifters and
wheelbarrows.
Inspection should be done before mobilization of all the tools S Permit Holder
and equipment's
Unnecessary tool and equipment Plan work and only mobilize equipment written in permit and fit S Permit Holder
for use
Preparation for activity of floor dismantling Ensure A fire watch & 2-fire extinguishers must be on-site S Permit Holder
before starting activity
[.MO.12] Slips & Trips (MOTION) [.MO.12.01] Remove any trip hazards in the area, clean up any S Permit Holder
spills, wear anti-slip safety shoes
[.EL.02] Electric shock (ELECTRICAL) Ensure electric connection done by authorized person only • S Permit Holder
Never make loose connections • Ensure all cables is double
insulated • Ensure inspection for any cut or lose connection
before use • Ensure Electrical panel board is third party certified
and certificate is attached with the permit • Make sure ELCB is
installed in the Electrical DB
[.PE.07] Hazardous Weather (PEOPLE) [.PE.07.02] Set weather limitations (lightning, rain, wind speed) S Permit Holder
and stop work when limit is exceeded.
- Start Dismantling of Dismantling of floor using hilti machine Start dismantling the damaged floor from a side to the other end S Permit Holder
floor with the help of Hilti with the help of Hilti (Jack Hammer) Manually by man-power •
machine or manually Ensure Proper PPEs suitable with the task • While using jack
hammer ensure face sheet and ear plugs • Ensure Inspection
before use of any damage or crack • Ensure Hilti machine is
third party certified and certificate is attached with the permit •
Ensure competent person is performing the task
[.MO.05] Hand Tools - ALL (MOTION) Never use damaged tools and equipment S Permit Holder
Dust Ensure Proper Dust Mask to prevent dust inhalation with other S Permit Holder
mandatory PPEs • Ensure Proper Housekeeping
[.MO.05] Hand Tools - ALL (MOTION) Never use damaged tools and equipment S Permit Holder
S Permit Holder
Ensure Proper PPEs suitable with the task
[.MO.05.02] The use of knives is prohibited S Permit Holder
[.MO.05.03] Wear appropriate hand protection suitable for task S Permit Holder
[.MO.12] Slips & Trips (MOTION) [.MO.12.01] Remove any trip hazards in the area, clean up any S Permit Holder
spills, wear anti-slip safety shoes
Ensure proper houskeeping S Permit Holder
[.PE.05] Fatigue (PEOPLE) [.PE.05.02] Prior to start of work request work party to self S Permit Holder
report if they are suffering from fatigue
[.PE.05.04] Monitor for signs of fatigue and intervene/stop work S Permit Holder
if necessary.
Take proper rest break S Permit Holder
[.PE.07] Hazardous Weather (PEOPLE) [.PE.07.02] Set weather limitations (lightning, rain, wind speed) S Permit Holder
and stop work when limit is exceeded.
- Mixing of Supplied Mixing of Supplied material for pouring 1:2:4 up to 4” Ensure Proper Mixing of Material for pouring with mixture S Permit Holder
material for pouring 1:2:4 machine • Make sure the ratio of mixing is 1:2:4 for pouring upto
up to 4” 4” floor • Ensure Proper PPEs suitable with the task • Ensure
Nitrile gloves for mixing or handling cement and proper dust
mask to avoid inhalation of dry cement dust
[.MO.12] Slips & Trips (MOTION) [.MO.12.01] Remove any trip hazards in the area, clean up any S Permit Holder
spills, wear anti-slip safety shoes
Ensure proper houskeeping S Permit Holder
[.PE.01] Communication (PEOPLE) [.PE.01.01] During permit issuance and toolbox talk/Last Minute S Permit Holder
Risk Assessment discuss and agree the methods of
communication within the work party, with Operations (if
necessary) and with Emergency Responders (if necessary)
[.PE.05] Fatigue (PEOPLE) [.PE.05.02] Prior to start of work request work party to self S Permit Holder
report if they are suffering from fatigue
[.PE.05.04] Monitor for signs of fatigue and intervene/stop work S Permit Holder
if necessary.
Take proper rest break. S Permit Holder
[.PE.07] Hazardous Weather (PEOPLE) [.PE.07.02] Set weather limitations (lightning, rain, wind speed) S Permit Holder
and stop work when limit is exceeded.
- Flooring (4” Pouring of Flooring After mixing material according to the ratio 1:2:4 start pouring • S Permit Holder
1:2:4 Ratio) and also Ensure Pouring done by mason only • Ensure proper pouring of
rising the height of 4 4” • During pouring the also rise the height of 4 manhole covers
manhole covers as per as per new floor level • Ensure Housekeeping
new floor level
Chemical Handling ( Cement ) • Ensure nitrlle gloves for chemical handling and proper Dust S Permit Holder
mask to avoid inhalation of dust • Ensure Housekeeping
[.PE.05] Fatigue (PEOPLE) [.PE.05.02] Prior to start of work request work party to self S Permit Holder
report if they are suffering from fatigue
[.PE.05.04] Monitor for signs of fatigue and intervene/stop work S Permit Holder
if necessary.
Take proper rest break. S Permit Holder
[.PE.07] Hazardous Weather (PEOPLE) [.PE.07.02] Set weather limitations (lightning, rain, wind speed) S Permit Holder
and stop work when limit is exceeded.
[.MO.12] Slips & Trips (MOTION) [.MO.12.01] Remove any trip hazards in the area, clean up any S Permit Holder
spills, wear anti-slip safety shoes
Housekeeping should be done after completion of work. S Permit Holder
Curing of New Floor with [.PE.01] Communication (PEOPLE) [.PE.01.01] During permit issuance and toolbox talk/Last Minute S Permit Holder
water Risk Assessment discuss and agree the methods of
communication within the work party, with Operations (if
necessary) and with Emergency Responders (if necessary)
[.PE.05] Fatigue (PEOPLE) [.PE.05.02] Prior to start of work request work party to self S Permit Holder
report if they are suffering from fatigue
[.PE.05.04] Monitor for signs of fatigue and intervene/stop work S Permit Holder
if necessary.
Take proper rest break. S Permit Holder
[.PE.07] Hazardous Weather (PEOPLE) [.PE.07.02] Set weather limitations (lightning, rain, wind speed) S Permit Holder
and stop work when limit is exceeded.
- Mobilization & Mobilization & Placement of New manhole covers manually by • Mobilize equipment and hand tools and material to site S Permit Holder
Placement of New manpower using wheel barrow manually on wheel barrow by manpower • Trained and
manhole covers manually competent resources must be deployed • Verify sizes before
by manpower using mobilization to site and the mobilize to site
wheel barrow
[.PE.01] Communication (PEOPLE) [.PE.01.01] During permit issuance and toolbox talk/Last Minute S Permit Holder
Risk Assessment discuss and agree the methods of
communication within the work party, with Operations (if
necessary) and with Emergency Responders (if necessary)
[.PE.05] Fatigue (PEOPLE) [.PE.05.02] Prior to start of work request work party to self S Permit Holder
report if they are suffering from fatigue
[.PE.05.04] Monitor for signs of fatigue and intervene/stop work S Permit Holder
if necessary.
Take proper rest break. S Permit Holder
[.PE.07] Hazardous Weather (PEOPLE) [.PE.07.02] Set weather limitations (lightning, rain, wind speed) S Permit Holder
and stop work when limit is exceeded.
- Housekeeping [.PE.05] Fatigue (PEOPLE) [.PE.05.02] Prior to start of work request work party to self S Permit Holder
report if they are suffering from fatigue
[.PE.05.04] Monitor for signs of fatigue and intervene/stop work S Permit Holder
if necessary.
Take proper rest break. S Permit Holder
[.PE.07] Hazardous Weather (PEOPLE) [.PE.07.02] Set weather limitations (lightning, rain, wind speed) S Permit Holder
and stop work when limit is exceeded.
[.MO.12] Slips & Trips (MOTION) [.MO.12.01] Remove any trip hazards in the area, clean up any S Permit Holder
spills, wear anti-slip safety shoes
Sr. Remarks
Type of Equipment Manufacturer Model TAG No.
No.
Demolition Hammer PRESCOTT PT0506502 ENV/NS/DH/001/23 Satisfactory
01
Findings / Remarks:
Subject Demolition Hammer is approved for operations after visual inspection and operational Check, against provided
Specification by Client/Supplier.
Recommendation:
1) Make sure bit/blade/Disc in use suitable for the type(s) of material that is being cut.
2) Make Sure bit/blade/Disc in use rated at the same (or greater) speed as the rpm rating.
3) Bit/Blade/Disc occasionally inspected to make certain it has not loosened, and retightened when necessary.
Conclusion:
It is found in Satisfactory Condition at the time of inspection for intended use only.
VALIDITY OF THIS CERTIFICATE 01 YEAR, FROM DATE OF INSPECTION 08th Dec, 2023 to 07th Dec, 2024
This Certificate does not make any warranty/indemnity expressed or implied, relating to the above equipment. This Certificate
does not relieve seller/suppliers from their contractual responsibilities with regard to quality/quantity of this delivery nor does it
discrimination the buyer’s right of claim towards their seller/suppliers for compensation for any apparent and/or hidden defects
not detected during our inspection & testing or occurring thereafter.
INSPECTED BY REVIEWED BY
P289-00-6723327 Page
03/15/2024 1 of 1
10:20 Page 15 of 53
P289-00-6723327 03/15/2024 10:20 Page 16 of 53
P289-00-6723327 03/15/2024 10:20 Page 17 of 53
P289-00-6723327 03/15/2024 10:20 Page 18 of 53 CamScanner
P289-00-6723327 03/15/2024 10:20 Page 19 of 53
Document Reference LEEA-030.2c1
Reason for Examination Installation: A Six (6) Monthly: B Twelve (12) Monthly: C Written Scheme: D Exceptional Circumstance: E
Name & qualifications of the person making this report: Name of the person authenticating this report:
Wahaj Khan Muhammad Sadiq
Senior Inspection Engineer Operation Manager
Signature: Signature:
********************END OF REPORT*******************
Page 1 of 1
This Report does not make any warranty, expressed or implied, concerning the above equipment. This Report does not relieve seller/suppliers from their contractual responsibilities with regard to quality/quantity of this
P289-00-6723327 03/15/2024
delivery nor does it prejudice the buyer’s right of claim towards their 10:20 for compensation for any apparent and/or
seller/suppliers Page 20 defects
hidden of 53 not detected during our inspection or occurring thereafter
Naseem & son
Emergency Response Plan
Naseem & Son
(ERP)
Naseem & Son
Plan (WAH)
Emergency of fire at
workplace
Method of Rescue
The Supervisor will be responsible for coordinating any emergency response.
The N&S emergency response plan for this Tank is below.
If any worker Injured/Unconscious inside the tank, then following action should be taken
● Make verbal contact with the employee to help them stay calm.
● SBM (stand by man) stop the work and inform to the rescuers rescue the victim person.
● All rescue equipment (such as breathing apparatus) is present at nearest to entrance point to
recovering the victim person.
● Workers perform duty inside the tank free of safety belt and lifeline.
● When a victim person injured/unconscious inside the tank then rescuer’s wearing their BA set
and rescue him by either pushing/lifting to the entrance point and the other two rescuers recover
him from manhole.
● After rescue the victim person shifted to suitable fresh air environment by stretche.
● Inform to the emergency response team of SHELL all about the accident and submit one copy of
accident investigation report to management with on seven days.
Rescue Team:
Rescue Equipment:
• Lifeline
• Stretcher
• 2 sets of safety harness
• First aid kit
1. Leave the area and close doors In Non-fire situations threatening safety, such as
2. Activate wall mounted fire alarm building services interruption or hazardous
material spill, building are evacuated under
3. Fire watcher will extinguish fire or another person if
he can do direction of fire warden and emergency response
team. The fire alarm should not be used toFIRE and
4. Report any information about fire to Shell
Safety Department evacuates a building without approval.
M Ramzan
A.Basit
Worker to move
stretcher attank
Rescuer entrance coordinator)
Stretcher
Workers
4 Ambulance 115/0726-513867
9 Fire Brigade 16
10 Police 15
11 Dr. Latif Dino 0302-3356417
12 Rescue 1122
13 Civil Hospital Khanpur 0311-8120585
14 Fire 072-6920248
Findings / Remarks:
Subject Mixture Machine is approved for operations after visual inspection and operational Check, against provided Specification
by Client/Supplier.
Recommendation:
1) Ensure all safety instructions are clearly understood and that the operators are familiar with the mixture machine controls.
2) Keep body parts and clothing away from all moving parts.
3) Never exceed the maximum load specified for the mixture machine.
4) Always wear approved, appropriate Personal Protective Equipment (PPE)
5) Always ensure clear communication between the machine operator and other personnel involved with the task.
Conclusion:
It is found in Satisfactory Condition at the time of inspection for intended use only.
VALIDITY OF THIS CERTIFICATE 01 YEAR, FROM DATE OF INSPECTION 12th March, 2024 to 11th March, 2025
This Certificate does not make any warranty/indemnity expressed or implied, relating to the above equipment. This Certificate
does not relieve seller/suppliers from their contractual responsibilities with regard to quality/quantity of this delivery nor does it
discrimination the buyer’s right of claim towards their seller/suppliers for compensation for any apparent and/or hidden defects
not detected during our inspection & testing or occurring thereafter.
INSPECTED BY REVIEWED BY
P289-00-6723327 Page
03/15/2024 1 of 1
10:20 Page 30 of 53
FIRST AID TRAINING
From
The ENV International, Pakistan
At SHELL LOBP KEMARI
Karachi - Pakistan
REMARKS: This certificate is issued after theoretical and practical evaluation of the individual. Where refresher session
Head of Inspection, Training &
is recommended after 01 year.
Certification
Date of Assessment:
Assessor(s): M.Ramzan , Mushtaq Hussain, Anwar Mughal, Abdul Basit 05.03.2024
Description of activity:
1- Joint Site Visit, Preparation, Mobilization of manpower to site
2- Ensure Intimal Gas Testing by Permit Issuer before starting work
3- Shifting of material & tools to work site manually by labor and using of hand lifters and wheelbarrows.
4- The area will be barricaded, Safety Sign Boards will be displayed, A fire watch & 2-fire extinguishers must be on-site during work.
5- First, inform to gantry supervisor about daily working activity in Pump House and Take permission to Start work. & Work will be scheduled according to the
window provided by
Filling Gantry Operation Team in the allocated
6- Take electric Connection for using Hilti machine.
7- Start Dismantling of floor with the help of Hilti machine or manually
8- Disposal of Debris (Debris will be mobilized on wheelbarrow by manpower manually to designated place
9- Mixing of Supplied material for pouring 1:2:4 up to 4”
10- Flooring (4” Pouring of 1:2:4 Ratio) and also rising the height of 4 manhole covers as per new floor level
11- Curing of New Floor with water
12- Mobilization & Placement of New manhole covers manually by manpower using wheel barrow
13- Housekeeping and De-mobilization of material and manpower
Description of equipment:
Wheelbarrow, Measuring tape, Trowel, Spade, Sprit Level, Wooden Float, Mixer Machine, Jack Hammer, Chisel, Hammer, Water Drum, Water cooler,
First Aid Box, Fire extinguisher and other general hand tools
Form G – Risk Assessment Distribution Permit to Work System Reviewed by: Mushtaq Hussain
Form G – Risk Assessment Distribution Permit to Work System Reviewed by: Mushtaq Hussain
Those Recommendatio
Hazards & Risks Those at Controls in place Ris
Responsibl n
Risk k
e
General Hazards
Form G – Risk Assessment Distribution Permit to Work System Reviewed by: Mushtaq Hussain
Form G – Risk Assessment Distribution Permit to Work System Reviewed by: Mushtaq Hussain
TASK 2: Ensure Intimal Gas Testing by Permit Issuer before starting work
Improper starting of work / presence • AGT shall perform Gas testing prior to starting of the activity and 3C Ensure Gas
of hazardous gases / lack of oxygen Personnel Workperformer (permit holder) shall maintain log sheet of gas AGT/ testing before
Injury / testing Shell starting of work
Property • Ensure Gas tester is calibrated and calibration certificate is person
attached with the permit
• Unauthorized person is not allowed before the gas test sign boards
is Placed
Form G – Risk Assessment Distribution Permit to Work System Reviewed by: Mushtaq Hussain
Form G – Risk Assessment Distribution Permit to Work System Reviewed by: Mushtaq Hussain
TASK: 4-
- The area will be barricaded, Safety Sign Boards will be displayed, A fire watch & 2-fire extinguishers must be on-site during work.
Unauthorized entry in PersonnelInjury / • Ensure Proper Area barrication before starting work 2B Person Ensure area
working area Property Damages • Ensure Proper Supervision Incharge barrication
• work area must be cordoned-off with soft barricade and
entry ofunauthorized person will be restricted in that area.
Lack of Awareness PersonnelInjury / • Ensure Safety sign boards is displayed 2B Person Ensure
Property Damages • Ensure Tool box talk done on daily basis about work related Incharge Safety sign
hazard and controls board
• Ensure Proper housekeeping and lighting according to
• Restrict activity to day light only work related
hazards and
controls
Preparation for work PersonnelInjury / • Ensure Gas Testing before starting work by PI 2B Person Ensure
activity Property Damages • A fire watch & 2-fire extinguishers must be on-site during Incharge Proper
work Housekeepin
• Ensure Area is barricaded g
• Ensure Fire extinguisher inspecting on daily basis
TASK: 5-
First, inform to gantry supervisor about daily working activity in Pump House and Take permission to Start work. & Work will be scheduled according to
the window provided by Filling Gantry Operation Team in the allocated
Form G – Risk Assessment Distribution Permit to Work System Reviewed by: Mushtaq Hussain
TASK: 6-
Take electric Connection for using Hilti machine.
Electric Shock Personnel Injury / • Ensure electric connection done by authorized person only 3C Person Ensure
Property Damages • Never make loose connections Incharge proper
• Ensure all cables is double insulated Supervision
• Ensure inspection for any cut or lose connection before use
• Ensure Electrical panel board is third party certified and
certificate is attached with the permit
• Make sure ELCB is installed in the Electrical DB
Slip & trip Personnel Injury / • Ensure proper Housekeeping 2B Person Ensure
Property Damages • Ensure cables is not in walkways Incharge proper
• Restrict work to day light only Supervision
Fatigue Personnel Injury • Ensure Proper Rest Breaks 2B Person Ensure
• Ensure reporting to permit issuer if team is suffering from Incharge proper
fatigue Supervision
TASK: 7-
Start Dismantling of floor with the help of Hilti machine or manually
Dismantling of floor Personal injury and • Start dismantling the damaged floor from a side to the other 2B Person Ensure
property damage end with the help of Hilti (Jack Hammer) Manually by man- Incharge proper
power Supervision
• Ensure Proper PPEs suitable with the task
• Ensure competent person is performing the task
Form G – Risk Assessment Distribution Permit to Work System Reviewed by: Mushtaq Hussain
Fire Personal injury and • Ensure Fire watcher on site 3C Person Ensure
property damage • Ensue 2 fire extinguisher on site Incharge proper
• Ensure No flammable item in area or cover it with fire banket Supervision
• Ensure Housekeeping
Hazardous weather Personal injury and • Stop work when the weather limits exceeds like rain or 2B Person Ensure
property damage lightening, wind Incharge proper
Supervision
Dust Personal injury and • Ensure Proper dust mask while working 2B Person Ensure
property damage • Ensure safety goggles and facesheet while using hilti machine Incharge proper
Supervision
Noice Personal injury and • Ensure ear plugs while using hilti machine 2B Person Ensure
property damage Incharge proper
Supervision
Vibration Person • Ensure proper PPEs suitable with the task 2B Person Ensure
• Ensure impact resistant gloves Incharge proper
Supervision
Pinch Point PersonnelInjury / • No Dusty/rusty/fabricated tools shall be used. 2B PersonIn Ensure
Property Damages • There must be close coordination among working team. charge Proper
• Manual lifting techniques will be followed LITE (Load, Supervision
Individual,Task and Environment)
• Only competent person shall execute the job.
Improper Hand Tools PersonnelInjury / • All hand Tools pre-inspected & Colour coded. 3C Personin Ensure
Property Damages • Appropriate securing of equipment & tools will be ensured charge Proper
• Use correct posture/ way and the techniques. Supervision
Form G – Risk Assessment Distribution Permit to Work System Reviewed by: Mushtaq Hussain
Improper Disposal of Person / Asset Disposal of Debris (Debris will be mobilized on 2B Person Incharge Ensure proper Disposal
Debris wheelbarrow by manpower manually to of debris
designated place
Mobilization and Person / asset Mobilization & Placement of New manhole covers 2B Person Incharge Ensure Proper
placement of manhole manually by manpower using wheel barrow Supervision
cover
• Mobilize equipment and hand tools and material to
site manually on wheel barrow by manpower
• Trained and competent resources must be deployed
• Verify sizes before mobilization to site and the
mobilize to site
• Ensure Proper PPEs suitable with the task
Ensure Proper Placement of Manhole covers manually by
manpower
Dust Personal Injury • Ensure proper Dust mask to avoid inhilation of 2B Person Incharge Ensure Proper
cement dust Supervision
• Ensure Proper housekeeping
Pinch Point PersonnelInjury / • No Dusty/rusty/fabricated tools shall be used. 2B PersonIn charge Ensure Proper
Property • There must be close coordination among working Supervision
Damages team.
• Manual lifting techniques will be followed LITE
(Load, Individual,Task and Environment)
• Only competent person shall execute the job.
Improper Hand Tools PersonnelInjury / • All hand Tools pre-inspected & Colour coded. 3C Personin charge Ensure Proper
Property • Appropriate securing of equipment & tools will Supervision
Damages be ensured
• Use correct posture/ way and the techniques.
Form G – Risk Assessment Distribution Permit to Work System Reviewed by: Mushtaq Hussain
Follow
IOGP and
CSSS
Standards
practises
Form G – Risk Assessment Distribution Permit to Work System Reviewed by: Mushtaq Hussain
1. Electricity 10. High Pressure 19. Extremes of temperature 28. Other (specify)
2. Noise 11. Explosion 20. Confined spaces
3. Lasers 12. Fire 21. Working environment
4. Radiation 13. Gas vapour release 22. Manual Handling
5. Vacuum 14. Toxic chemicals 23. Gravity (height or above excavations)
6. Legionella 15. Flammable substances 24. Moving vehicles
7. Wiels disease 16. Hazards to eyes 25. Cleaning devices
8. Other Biological (specify) 17. Hand tools 26. Slips, Trips & Falls
• The assessment should be carried out in good time prior to the relevant decision being made
• When a specific assessment is needed then such an assessment, rather than a generic assessment should be made
• The risk from each activity should be considered
• A team of people or employees with practical knowledge of the process/activity being assessed should be used as appropriate
• Consultants should be used where necessary
• All the hazards associated with a particular activity should be considered
• Hazards and risk controls should be linked
• The results of the assessment should be properly used.
Form G – Risk Assessment Distribution Permit to Work System Reviewed by: Mushtaq Hussain
PROJECT TITLE:
Demolishing and construction new flooring for Pump house.
METHOD STATEMENT:
Demolishing and construction new flooring for Pump house.
Sign
Ramzan
0 05/03/2024
ISSUED FOR M. Ramzan
APPROVAL
& Anwar
First submission
Rev Revision Description Prepared by Reviewed by Approved by
Date
1. Description of works
• Wheelbarrow, Measuring tape, Trowel, Spade, Sprit Level, Wooden Float, Mixer Machine, Jack
Hammer, Chisel, Hammer, Water Drum, Water cooler, First Aid Box, Fire extinguisher and other
general hand tools
• Cherry pickers used (yes/No)?
No
• Scaffolding:
No
• Loading of materials:
Manually load by labor
• Others, specify
Fire Extinguisher, First Aid Box and Water Cooler
What certificates, if any, are required for plant or equipment?
• Jack Hammer (Hilti Machine)
• Mixture Machine
• Gas tester Calibration Certificate
• Electrical distribution bord DB
third party’ certificates is required
Method statement & JSA will be communicated to all workers in daily toolbox talk by the Supervisor. The daily
hazards & procedure shall be communicated to the workers through:
• Daily Toolbox talks on daily basis as per PTW activities.
• Daily HITS
• Compliance of LSR 100%
• PPE’s Compliance 100%
• MS-JSA explained to all workers before start of job by supervisor.
• Through CSSS and Site induction.
Safety Checks:
• Shell PTW prior to start any activity shall be received from SPL operation by designated permit
holder. Permit filled as per the approved MS-JSA. Daily renew and close by permit holder and
issuer. Shell PTW procedure shall follow.
• Permit issuers review the MS-JSA before issue of permit.
• Permit Holder to monitor all activities should be compliance as per permit and full time available at
site.
• Permit issuer to review the site activities and protocols as per the requirements.
• Ensure all the personnel are aware of work and permit requirements.
• Following documents should be attached with work permit.
• MS, JSA, Equipment Third party certificates, Manpower list etc.
PPE’s Requirement:
• Before mobilization of equipment joint site visit shall be conduct by Shell and operation teams to identify,
eliminate, or control the hazards related to work for preparation of MS-JSA accordingly.
• Pre-Inspection of the equipment shall be conduct by HSE, inspection witness and approve byclient
teams.
• For equipment, valid third-party certificate should be available and must be attach with work permit.
• Access & Egress routes shall be cleared & marked and communicated to all work forces.
• Working area will be hard barricaded and prohibited for un-authorized persons.
• Material Storage area shall be prepared & barricaded at the designated place.
• Equipment stand by area shall be prepare and barricaded at the designated place.
Step 2: Ensure Intimal Gas Testing by Permit Issuer before starting work
Step 3: Shifting of material & tools to work site manually by labor and using of hand lifters and
wheelbarrows.
• Visual inspection of tools and equipment must be performed prior to before entry inside the terminal.
• Mobilize equipment and hand tools and material to site manually on wheel barrow by manpower
• Trained and competent resources must be deployed
• Ensure Equipment’s is third party certified and verified according to third party
• Hand made tools is not allowed
• Ensure Proper PPEs suitable with the task (high visible vest, hard hat, safety shoes, Safety goggles, and
gloves)
Step 4: The area will be barricaded, Safety Sign Boards will be displayed, A fire watch & 2-fire
extinguishers must be on-site during work.
Step 5: First, inform to gantry supervisor about daily working activity in Pump House and Take
permission to Start work & Work will be scheduled according to the window provided by Filling
Gantry Operation Team in the allocated.
• After taking permit then inform the gantry supervisor on site about daily working activity in pump house
and take permission to start work
• Complete all the necessary tools and equipment before start of work
• Schedule and plan work according to the window provided by Operation team
• Start dismantling the damaged floor from a side to the other end with the help of Hilti (Jack Hammer)
Manually by man-power
• Ensure Proper PPEs suitable with the task
• While using jack hammer ensure facesheet and ear plugs
• Ensure Inspection of hilti machine before use that there is no damage in it.
• Ensure Hilti machine is third party certified and certificate is attached with the permit
• Ensure competent person is performing the task
• Debris will be loaded with spade into the wheel barrow by manpower manually
• Wheel barrow will be loaded till a safe level of edges of wheel barrow so the debris don’t fall on ground
during mobilization
• Avoid overloading of wheelbarrow
• Mobilize the debris to its designated place for disposal using wheel barrow by man-power
• Ensure Proper PPEs suitable with the task
• Ensure Proper Dust Mask to prevent dust inhalation with other mandatory PPEs
• Ensure Proper Housekeeping
Step 10: Flooring (4” Pouring of 1:2:4 Ratio) and also rising the height of 4 manhole covers as
per new floor level
Step 12: Mobilization & Placement of New manhole covers manually by manpower using wheel
barrow
• Mobilize equipment and hand tools and material to site manually on wheel barrow by manpower
• Trained and competent resources must be deployed
• Verify sizes before mobilization to site and the mobilize to site
• Ensure Proper PPEs suitable with the task
Form F – Method of Statement Distribution Permit to Work