SPECIEFIC TASK METHOD STATEMENT

Contractor’s Company Project/ contract


Date of the work scheduled: Feb-18-2024 name DOCG number 1322

Facility/Area/Location Block9/ OGM-3

SAP Work Order №: As required (Optional to be filled if the job has an SAP order #).

General Work Title:


Carry out drilling work for installation of deep well anode

Equipment Info/№: Hand Tools, Drilling machine, Water tank truck.

 If Applicable: ✔
Type of Permit: CWP. SPWP. ✔ HWP.
Type of Certificate: CSEC. EXC. RC. Scaffolding Cert. N/A ✔
Type of Isolation: EIC. MIC. N/A. ✔
 PO & PA confirm that the task will be carried out as per the defined steps in this MS
Permit Originator
Name Signature
/ Performing Authority
 IA accepts and endorses steps of work defined in this MS
Issuing Authority Name Signature

 Breck down the job steps:


№ Main steps of the work process Equipment / Tools Required
1 Gas Testing, Pre-Job Safety Meeting. Multi Gas tester
2 Prepare the working area and make it ready for drilling activity Hand Tools
3 Transport the drilling machine to work location. Drilling machine
4 Inspect and check the drilling machine before start the Job. Drilling machine
5 Identify and isolate the working area using warning tape. Hand Tools
6 Start up the drilling machine,drill to the depth of 6m, then pull out the drill, remove the soil , add Drilling machine

water, then drill to another 6m depth. Repeat the above steps 5 time to complete the total 50m Water tank truck

depth and 300mm diameter.


7 Pull out the drill and demobilized the drilling machine. Drilling machine
8 Housekeeping and hand over the area clean and tidy. Hand Tools