You are on page 1of 1

QUALITY CONTROL INSPECTION CHECKLIST

Project : Doc. no.


Rev. 00
Date 23/08/2022
Construction Process : LINE MARKING CHECKLIST Page 1 of 1

Location :

Date of Inspection:

Drawing Reference No:


Item Description SMPP MSA
Yes No Yes No
1. SITE PREPARATION
Area is clear from dirt, debris and other materials
2. SETTING OUT
Setting out location
Entire road marking as per size and standard
Other

3. MATERIAL
Approved material (thermo plastic) for road marking as specification
Mix and prepare marking material as per manufacturer’s specification
Heated material as per manufacturer’s specification to allow for easy
and consistent application
PLANT, MACHINERY AND EQUIPMENT
4. Selected tools, plant and equipment consistent with marking work
requirement
5. INSTALLATION
Road marking material applied properly and evenly to surface
Marking thickness and size as per standard
Remove pre-existing visible marks/line where required
6. OTHERS

Reason for Failure/Re-inspection

ALLOWED to proceed with the next stage of work NOT ALLOWED to proceed with the next stage of work

YES NO
Non-Conformance Report Raised NCR no.:

Name/Signature of
Designation: Date:
Works Contractor
Representative

Name/Signature of
Designation: Date:
Supervising Consultant
Representative
Please  off where appropriate