QUALITY CONTROL INSPECTION CHECKLIST

Project : Doc. no.


Rev. 00
Date 05/05/2023
Construction Process : ARCHITECTURAL- DRYWALL INSTALLATION
Page 1 of 1
(FINAL & ACCEPTANCE)

Location :

Date of Inspection:

Drawing Reference No:


Item Description SMPP MSA
Yes No Yes No
1. All drywall component fixed in correct position and good condition
2. Steel/brackets fixed in correct position and good condition
Insulation/ acoustic barrier and flashing fixed in correct position and
3
good condition
4. Rockwood fire stop fixed in correct position and good condition
5. Fastener proper tightened and correct type
6 Remove protective tape and cleaning
7 No damage drywall component
8 Smooth silicone sealant surface and joint -visual

Reason for Failure/Re-inspection

ALLOWED to proceed with the next stage of work NOT ALLOWED to proceed with the next stage of work

YES NO
Non-Conformance Report Raised NCR no.:

Name/Signature of
Designation: Date:
Works Contractor
Representative

Name/Signature of
Designation: Date:
Supervising Consultant
Representative
Please  off where appropriate