FORMWORK & SUPPORTWORK INSPECTION CHECKLIST

To be completed before and after every concrete pour by the appointed person
COMPANY:
RESPONSIBLE PERSON:
SITE: Arch Drwg. No.:
LOC./GRID: Eng. Drwg. No.:

Remarks (and
Checked Accepted
No. Item Inspected N/A Date provisional / part
By (Initial) By (Initial)
approval)
1. SUPPORT WORK
Lacing & cross braces
Wedges & jacks
Plumb
Stability
Soleplates & Compaction
Ties, props, etc checked for
tightness
Backdropping
Construction joint & stop
end
Access scaffold
2. FORMWORK
Orientation & alignment
Size
Elevation
Cleanliness
Shutters oiled
Chamfer
Joint water tightness
Plumb/level
Soldier spacing & konstal
ties
Bracing/stays
3. OTHER CHECKS &
SAFETY CHECKS
Dwgs latest revision?
Designer checked?
Any deviation from design?
Equipment
examined/tested?
Slipping hazard?
Access ladders secure?
Shutter oil toxicity checked?
Employees trained?

APPROVAL TO PLACE CONCRETE: