Professional Documents
Culture Documents
Sr.No. AFC Document Number Document Title Revision Code (A/B) Remarks
CODE Implications
A: For Approval
C: Information or Reference
CONSULTING
ENGINEERING GROUP CONTRACTOR INDEPENDENT CONTROL OFFICER (CICO)
1. INTRODUCTION
2. PURPOSE
3. RESPONSIBLITY
4. REFERENCE DOCUMENTS
6. MATERIALS
8. SAFETY PRECAUTIONS
9. WORK METHODOLOGY
11. RECORDS
To draw a suitable method statement for preparation and construction of Lateritic Berm
layer with approved Borrow area material along the bituminous pavement edge. It also
assesses the risks involved in this task and states the safety precautions to be taken
care of while performing the activities.
2. PURPOSE:
3. RESPONSIBILITY:
Survey Engineer : Providing the chainage locations of the stretch at which the Berm
need to be constructed as per drawings/ specifications.
Site Engineer : Responsible for the organization, coordination and execution of
the entire work detailed in this method statement, related logistic
matters, instructing the foreman about the requirements of the
contract, including all restrictions, safety regulation, time schedule.
Foremen : Responsible for day to day implementation and supervision of the
works detailed in this method statement.
QA/QC Engineer : Ensure all works of Berm preparation, ensuring the Quality of
works executing as per specified Project requirements and to
Monitor the implementation of the controls as required.
Safety Engineer : Ensure the safety of workers during the progress of work and assist
the construction team to develop safe methods of working.
5 5 10 15 20 25
1 to 8 Low Risk - Some Risk controls may still justify
SEVERITY
SR = Severity Rating 4 4 8 12 16 20
1 to 5: - 1 is lowest & 5 is highest 3 3 6 9 12 15 Moderate impact Risk - Conduct formal risk analysis; may
9 to 15
2 2 4 6 8 10 require risk controls
PR = Probability Rating 1 1 2 3 4 5 High Impact Risk - Must implement extensive risk control
16 to 20
1 to 5: - 1 is lowest & 5 is highest 1 2 3 5 measures.
4
HIGH
LOW PROBABILITY
LOW
8. SAFETY PRECAUTIONS:
All Labors, Technicians shall use full PPEs like safety shoes, hard helmets, reflecting
jackets, protective hand gloves, goggles & dust masks etc.
All persons working on the site shall be trained by conducting the training course for
safety to ensure that they are fully aware of the contents.
The appropriate safety precautions and other safeguards shall be provided as
required by the nature and location of work.
9. WORK METHODOLOGY:
The Contractor’s ICO representative shall witness sampling, testing activities in laboratory to
ensure the required properties are meeting as per specifications
The Contractor’s ICO representative shall witness testing activities in site after final bed
preparation to ensure the required level and compaction are achieving as per specifications
The necessary coordination shall be done by Site Execution Engineer by requesting them to
witness before starting of the activities.
11. RECORDS:
RFI
Lab test results.
Quality Control checking.
Thickness Measurement at regular intervals
CONSULTING
ENGINEERING GROUP CONTRACTOR INDEPENDENT CONTROL OFFICER (CICO)
INDICE
2. BUT
3. RESPONSABILITÉ
4. DOCUMENTS DE RÉFÉRENCE
6. MATÉRIAUX
8. PRÉCAUTIONS DE SÉCURITÉ
9. MÉTHODOLOGIE DE TRAVAIL
11. DOCUMENTATION
2. BUT:
Cette déclaration de méthode décrit la procédure et les instructions impliquées dans le
transport de la latérite, la mise en place et la préparation de la couche de berme le long
du bord de la chaussée bitumineuse dans tout le corridor du projet conformément aux
dessins approuvés. Les activités doivent être réalisées après la pose de la couche de
roulement en asphalte de la chaussée conformément aux exigences des plans
approuvés. Il couvre les activités chronologiques impliquées au cours des opérations
connexes.
3. RESPONSABILITÉ:
4. DOCUMENTS DE RÉFÉRENCE:
Exigences de l'employeur Partie III.02 : Spécifications de performance
Dessins approuvés. (SAG-011-5267-DSN-PW-DWG-TCS-OL-001 À 007)
8. PRÉCAUTIONS DE SÉCURITÉ:
Tous les ouvriers et techniciens doivent utiliser des EPI complets comme des
chaussures de sécurité, des casques durs, des vestes réfléchissantes, des gants de
protection, des lunettes et des masques anti-poussière, etc.
Toutes les personnes travaillant sur le site doivent être formées en réalisant le cours
de formation à la sécurité afin de s'assurer qu'elles en connaissent parfaitement le
contenu.
Les précautions de sécurité appropriées et autres mesures de protection doivent être
fournies en fonction de la nature et de l'emplacement des travaux.
9. MÉTHODOLOGIE DE TRAVAIL :
Des dispositifs de sécurité adaptés doivent être prévus avant le début des travaux.
Le site doit se préparer à la couche de berme en enlevant les débris, les matériaux de
surcharge.
11. DOCUMENTATIONS :
RFI
Résultats des tests de laboratoire.
Vérification du contrôle qualité.
Mesure d'épaisseur à intervalles réguliers