Rev No :
KAK-AYT-REC-CMS-0002
A01
FOR Date : 24-June-2021
INSTALLATION OF PRE-CAST
Page No : 1 of 10
DUCT BANK
Contract No : C&F-45204
INSTALLATION OF PRE-CAST
Page No : 2 of 10
DUCT BANK
TABLE OF CONTENTS:
1.0 SCOPE ……………………………………………………………………………………….…………………………………… 03
INSTALLATION OF PRE-CAST
Page No : 3 of 10
DUCT BANK
1.0 SCOPE
This method statement shall outline activity steps and sequence of work including excavation,
compaction and backfilling of soil, delivery lifting, unloading and installation of pre-cast duct banks
covered by the scope of the project.
2.0 PURPOSE
The methods and sequence of activities contained in this document shall serve as guidance and
reference to ensure proper execution of all related activities are in accordance with contract
requirement, safety & quality assurance. This method statement shall detail the work and concerns that
is to be given attention in each activity as to the following:
2.1 Before starting any activity permit to work should obtained at site.
2.2 Identification of work area, boundary and limits
2.3 Excavation of soil to required depth and dimension as shown on construction drawings
2.4 Sub-grade preparation and compaction in preparation for sub-sequent civil and/or mechanical
construction work and FDT verification.
2.5 Inspections, material sampling and testing activities required implementation of project quality
procedure to comply with Client, Owner quality requirements and ITP.
2.6 Installation of Pre-Cast Duct Banks, coating on top surface (red/green)/bituminous coating.
2.7 Fill, backfill and compaction requirements
2.8 Grading and compaction of soil required on paved areas (Asphalt Area)
2.9 Implementation of safety measures, PPE’s and compliance to HSE procedural requirements
2.10 Identification and preparation of required manpower, equipment and materials for all of the
above
3.0 REFERENCES
ASTM D6938 - Standard Test Methods for Density of Soil and Soil-Aggregate in-place
by Nuclear Method
ASTM C136-14 - Standard Test Method for Sieve Analysis of Fine and Coarse
Aggregates.
ASTM D4318 - Standard Test Methods for Liquid Limit, Plastic Limit and Plasticity
Index of soils
OSHA 29 - OSHA Safety and Health Regulations for Construction
CIV-SU-581-E - Site Preparation, Excavation and Backfill
CIV-SU-850-N - Plain and Reinforced Concrete
NCP-00-A4-50-1101 - STD Road Asphalt
METHOD STATEMENT Doc No :
Rev No :
KAK-AYT-REC-CMS-0002
A01
FOR Date : 24-June-2021
INSTALLATION OF PRE-CAST
Page No : 4 of 10
DUCT BANK
INSTALLATION OF PRE-CAST
Page No : 5 of 10
DUCT BANK
INSTALLATION OF PRE-CAST
Page No : 6 of 10
DUCT BANK
INSTALLATION OF PRE-CAST
Page No : 7 of 10
DUCT BANK
1. Conduct survey to mark locations, grids and layout of the road that to be close partially.
2. Road Crossing or asphalt paved, mechanical equipment shall be use asphalt/concrete cutter &
backhoe to remove the existing pavement. Asphalt/Concrete cutter will cut to desire depth and
remove by the backhoe and excavate up to require depth and the rest will do manually.
3. Excavate the soil manually to hardcore depth and to the required dimensions as shown on IFC
drawings.
4. Excavated material shall not be left stockpiled above the excavated pits to avoid risk of
collapsing /caving-in to the pits. All stockpiles shall be regularly moved away from the
excavation areas by at least 1.0m distance.
5. While workers are inside the pits, no vibratory activities and/or heavy equipment operations
shall be performed on adjacent areas above the pit as these will increase the risk of soil cave-ins.
6. When soft and compressible soil is encountered at footing grades, the soil shall be removed and
replaced with compacted structural fill.
7. Where excavation is to be done adjacent to existing structures, excavation shall not be deeper
than the lowest elevation of adjacent existing foundations unless underpinning requirements
have been established and performed.
8. It shall be ensured that size of excavated pit shall accommodate the required dimension of
structure as well as the working space for performing construction activities within are taken
into consideration.
9. Once required depth of excavation is attained for first half cover the trench with thick steel plate
to open for traffic. Level the soil and compact to required field density of 90% relative density if
soil is found non-cohesive or at 95% modified dry density is soil is found to be cohesive. A third-
party testing shall be required and witnessed by Client inspector for field density tests of existing
sub-grade soil.
10. Then the second half of the road shall be closed for traffic and start the cutting and excavation
same as first half is done.
11. Upon completion of excavation to the required level of second half of the road. Close the road
completely for traffic from both sides and remove steel plates already installed.
12. Compact the sub-grade using plate compactor as per line and elevation required and test using
third party witnessed by client.
13. Now the site is ready to install pre-cast duct bank in full width of the road one time.
METHOD STATEMENT Doc No :
Rev No :
KAK-AYT-REC-CMS-0002
A01
FOR Date : 24-June-2021
INSTALLATION OF PRE-CAST
Page No : 8 of 10
DUCT BANK
7.3 Backfilling
1. Fill and backfill operations shall be performed after pre-cast duct bank installation work has
been completed.
2. While filling structures installed within excavated pits, the temporary shores and supports if
used shall be accordingly removed in parallel. Do not leave any unnecessary materials buried
with the pits.
3. Fill or backfill material shall not contain any deleterious materials such as waste materials, large
boulders, organic materials, construction debris, etc.
4. Filling shall be done in a proper manner so as not to damage the waterproof coating applied on
the structures or chipping and scratching the structure itself.
5. Do not compact backfilled soil directly beside the structures up to 300m distance away. These
shall be water compacted and tampered manually to avoid motion caused by force from
mechanical compactors and damage to the coating.
6. Fill and backfill activities shall be done in layers of 300mm for non-cohesive material or 200mm
layers of cohesive material.
7. Each layer of fill and backfill are to be compacted sufficiently. At every 3 lifts and at the final
layer of fill or backfill, a compaction test shall be performed with third-party inspector.
8. The final layer of fill or backfill shall follow details and elevations shown on IFC drawings making
sure subsequent construction activities are taken into consideration.
9. The top layer of fill or backfill shall follow level and grades shown on IFC drawings and any
difference shall be within allowed vertical tolerance of not more than ±15 mm.
10. All disturbed soil shall be regularly wetted with water to avoid the sand/soil particles to cause
hazards from free flying dust and fine soil particles.
11. Backfill until the existing top level of ground and compact the top layer with plate compactors.
Field density test shall be performed on the compacted top layer if the area is going to receive
further construction works (i.e. paving)
12. Reinstate the top surface of ground to its original condition is asphalt layer and all excess
earthwork or construction materials shall be taken out of the area.
METHOD STATEMENT Doc No :
Rev No :
KAK-AYT-REC-CMS-0002
A01
FOR Date : 24-June-2021
INSTALLATION OF PRE-CAST
Page No : 9 of 10
DUCT BANK
1. Site Preparation
1.1 Prior for any lifting activities, all lifting certificates and vehicle entry permits should be
made ready on the site. All lifting equipments such as cranes, boom trucks, are all
inspected with stickers required.
1.2 Equipment operators shall have certification and ID for plant access to perform work.
1.3 Site shall be barricaded and safety signage to be posted for intended lifting activity.
1.4 The lifting radius of cranes shall be barricaded to avoid other persons entering the site
during activity execution.
1.5 The site shall be made ready to receive and to be installed. Soil sub-grade compaction
preparation shall be made available before the work.
1.6 Lifting operation shall be postponed during high winds and unfavorable weather
conditions.
INSTALLATION OF PRE-CAST
Page No : 10 of 10
DUCT BANK
8.1 Permit to work shall be secured prior to starting any site activity.
8.2 All workers shall comply with the requirements of the approved project safety manual, job
safety analysis and permit conditions.
8.3 All workers shall wear required PPE’s at all times while engaged on the work.
8.4 Hand tools shall be in good working conditions.
8.5 All mechanical/electrical tools used are in good conditions and inspected by SAFETY (Competent
Persons).
8.6 Cranes and boom truck third party certification shall be available with equipments.
8.7 Riggers, flagman and safety officers shall be vigilant to ensure that all lifting activity is performed
in safe manner not to damage any other facilities and plant equipments.
8.8 Crane, boom truck outrigger positions should be provided with wooden or steel pads to avoid
punching through ground, pavements or road.
8.9 Barricades shall be provided with the lifting radius and no personnel will walk or stay below
lifted load or crane boom.
8.10 All lifting accessories such as shackles, slings, chains and lifting beam when used are in good
working condition and inspected by third party.
8.11 Ensure all lifting and rigging activities postponed during presence of heavy winds and
unfavorable weather conditions.
8.12 Concrete barrier or plastic jersey filled with water to be installed along with enough signature
and blinking lights
8.13 Flagman should be always available at the site.
8.14 To follow below S-CHEM procedure and guidelines:
GI-1217 - Excavation and Trenching
GI-1219 - Job Safety Analysis
GI-1217 - For Skip
GI-1208 - For Barricade
GI-3388 - For Mobile Crane