INSULATION AND VAPOR BARRIERS

QUALITY CONTROL REPORT

Project Title: Date:


Building/Structure: Report No.:
INSTRUCTIONS: Before making inspections, the quality-control inspector should have reviewed the drawings
and specifications and should be sure that he understands them. Clarify all questions with the engineering office
that prepared them. Provide a copy of the completed report to the construction overseer, quality-control
coordinator, and any others as directed.

ITEM(S) COVERED BY THIS TEST

CHECKLIST
1.  Yes  No  N/A Have insulation and vapor barriers been installed where required and on the
correct side according to drawings?
If no, please explain why:

2.  Yes  No  N/A Have the correct type, thickness, and size been used?
3.  Yes  No  N/A Are all areas covered, both large and small?
4.  Yes  No  N/A Is insulation tightly fitted?
5.  Yes  No  N/A Are vapor barriers securely fastened?
6.  Yes  No  N/A Are vapor barrier joints taped?
7.  Yes  No  N/A Have all tears or punctures been repaired?

Signature of Quality-Control Inspector Signature of Crew Overseer

Quality Control Report Insulation and Vapor Barriers