HVAC HEAT EXCHANGER

QUALITY CONTROL REPORT

Project Title: Date:


Building/Structure: Report No.:
INSTRUCTIONS: Before making inspections, the quality-control inspector should have reviewed the drawings
and specifications and should be sure that he understands them. Clarify all questions with the engineering office
that prepared them. Provide a copy of the completed report to the construction overseer, quality-control
coordinator, and any others as directed.

ITEM(S) COVERED BY THIS TEST

CHECKLIST
1.  Yes  No  N/A Have the systems been installed in accordance with the drawings and
specifications?
If no, please explain why:

2.  Yes  No  N/A Are the systems ready to be tested, adjusted, and balanced?
3.  Yes  No  N/A Have the size and physical data been confirmed?
4.  Yes  No  N/A Has the flow direction been verified?
5.  Yes  No  N/A Have the face areas been inspected for fin damage, air leakage from tube sheets,
fluid leakage from tubes or piping, foreign matter, and so forth?
6.  Yes  No  N/A Have provisions for pressure and temperature measurements been made?
7.  Yes  No  N/A Have the operation type and size of automatic valve, expansion valves, relief
valves, and other control equipment been verified?

Signature of Quality-Control Inspector Signature of Crew Overseer