You are on page 1of 14

METHOD STATEMENT RISK ASSESSMENT FORM

Section A. Details
Project Name: Project Number: Location: MSRA Reference: Rev:
13TH FLOOR-SOUTH KPS-IWIN-MSRA-T&C-05 00
DSP - TECOM K22-006 TOWER, DUBAI Date of Submittal:
SCIENCE PARK
10-06-2022
Consultant: Main Contractor: Sub-Contractor:
M/S TUV M/S KPS IWIN ELECTROMECHANICAL LLC

Trades/Services: Architectural Civil/Structural M.E.P. Other: Spec. Reference:

Attachments: Catalogues Drawings Samples Compliance Statement Other: ITP, CHECK LIST

Description:
MSRA for testing
and commissioning REV 00
of HVAC system

Section B. Material Submittal Attachment Details (tick as applicable)

Section C. Approval Details

Part A Cover Sheet


Part B Project Specification Spec. Compliance Statement Original Catalogue
Part C Product Data Sheet / Schedules Calculations & Test Results Supplementary Drawings
Part D Supplementary Design Data Supporting Documentation (for deviations)
Part E References Cardinals & Certifications

Consultant

Status Comments Authorized Signature


Lead Consultant:
Approved (A)

Approved as Noted (B)


Sub-Consultant:
Rejected – resubmit (C)

TAMDEEN and DTS Technical Reviewer

Status Comments Authorized Signature


Technical Reviewer:
No Objection

No Objection w/
comments

Objection

The above review / comments do not in any way imply acceptance of material / equipment installation / performance and
do not in any way absolve the contractor’s responsibility of fulfilling the contractual obligation and consultant’s
responsibility of fulfilling the design & supervision liability requirements.
TAMDEEN and DTS Project Manager

Status Comments Authorized Signature


Project Manager:
No Objection

No Objection w/
comments

Objection

Materials rejected must be resubmitted for approval with all requested documents & data. Contractor remains fully
responsible for approved materials under terms and conditions of the contract.
Note: For submittals requiring TAMDEEN and DTS review, consultant approval status shall reflect TAMDEEN and DTS approval status.
Note: If there are additional comments, please use continuation sheet.

DTS-AD-F-17 REV 1 Issued 10/11/19 page 1 of 1


TABLE OF CONTENTS

SECTION- 1: Introduction

SECTION- 2: Scope

SECTION- 3: Chilled water System procedure

SECTION 4: Mechanical Checks

SECTION 5: Setting to Work

SECTION - 6: Regulation of Chilled Water Flow

SECTION -7: Instrumentations

SECTION -8: Chilled water balancing data recording.

SECTION -9: Reference standards


1: INTRODUCTION

The test procedure is prepared to ensure the requirements for the testing and
commissioning for the HVAC system of the Tecom Group offices is carried out in
the prescribed manner and in compliance with the project technical specification,
design, standards, international and local codes.

2: SCOPE

The Scope of work involves the testing and commissioning of the HVAC system within
relevant specifications. The HVAC system on Tecom Group offices is located in DMC
Building @5 Basemnet to roof

These procedures are to be applied to the following systems, where applicable.

3.1 Pre-Commissioning Water

The installer should carry out inspections to ensure that,

a) All plant items are in accordance with the design specification


b) Correct installation procedures have been followed
c) Standards of installation and site cleanliness are acceptable
d) That the installation is fully complete and that all requite checks have been undertaken
prior to system filling
e) The system cleanliness has been implemented by an adequate flushing and cleaning
process in the absence of a Code of Practice on flushing, the procedures as

Guide 1/89 should provide a guide to standards.

3:2 Installers Detailed Checks

In accordance with CIBSE code W, the installer should undertake detailed checks to confirm with
his responsibilities regarding the state of the system. These checks are by requirement, more
detailed than those that will subsequently be undertaken by the commissioning engineers
checks, are directly related to the commission-ability of the system and will not establish that the
installation to the requirements of the specification.

3:3 Checks before Filling

Particular checks to be undertaken by the installer should include but not be limited to ensuring
that the following have been fulfilled:
a)
instructions
b) Flow measurement devices have been installed in accordance with manufacturer
instructions.
c) Probe pockets, pressure gauges, siphons and test points are installed.
d) Manual and automatic air vents are fitted at high points as indicated in the drawings and
specifications.
e) Drain valves and overflows of correct size are fitted.
f) Control, double regulating and PICV are installed in accordance with the flow direction
arrows or other indications marked on the devices.
g) Strainers with the mesh as specified are installed in an isolatable section. Changeover
devices for duplex strainers are fitted. (Drain down cocks, are recommended for larger
strainers).
h) The cold feed or mains connection is located correctly.
i) All pipe-work and fittings are adequately supported and anchored where applicable in
accordance with the specification.
j) All test points are accessible to probes.
k) All pipe-work is correctly identified and marked.
l) Adequate access is maintained to all manual valve wheels and to actuators on
automatically controlled valves.

4: Mechanical Checks

4:1 Automatic Control Valves check:

a) All valve ports are correctly oriented with respect to water flow
b) All valve spindles are free to move
c)
connections.

4:2 Electrical Checks (to be undertaken by the electrical installer)

Before the first operation of any electrical component or appliance the following procedure should
be adopted. All requirements of the Health and Safety at Work Act regarding the safety of the
engineer and other personnel must be strictly observed.

4:3 Checks with all Electrical Supplies Isolated


Check to ensure that:
a) Appliance and control circuits are locally isolated
b) There are no un-shrouded live components within the panels.
c) The panels and switchgear are clean
d) The appliance and surrounding area are clean and dry
e) The transit packing has been removed from contractors and other equipment
f) All the connections on bus-bar and writing are tight
g) All the power and control writing has been completed in detail in accordance with the
circuit diagram paying special attention to circuits for star-delta connected or specially
wound motor
h) All fuse ratings are correct
i) All mechanical checks on the pump and motorized valves are complete
j) Set starter overloads to the motor full load current
k) The adjustable thermal cut-outs are set correctly. (Check manufacturers test certificates)
l) All electrical water heating appliances are free from damage and all associated
thermostatic controls have a suitable temperature range.
m) All the cover plates are replaced

5:0 Setting to Work

Check that:

a) All normally open valves are fully open


b) All bypass and normally closed valves are closed
c) All thermostatically controlled valve are fully open
d) A method of operating electrically controlled valves is available and that these are
motored to normal operating mode

5:1 Statement

The aim of chilled water balancing is to apply a disciplined procedure of adjustment to water flow
rates throughout the chilled water system to meet particular requirements of the design.

6:0 Regulation of Water Flow

6:1. Method of Measurement

Water flow Mano meter is used for taking measurement of differential pressure across balancing
valves.

6:2 Warning:
Balancing a system requires the insertion of manometers with probes into pressure test points.
In a charged system the water temperature must be below 60ºC when this is done.

6:4 Preliminary Flow Rate Check

With all valves fully open, measure and record the total actual flow rate from the Main DRV
(located in each floor) and compare this with the total system design flow requirement. Where
necessary, close the main regulation valve to provide a flow of approximately 110% design flow
rate.

6:5 Balancing the chilled water main branches, sub branches, risers and terminals by
proportionally

a) Keep all the DRV, s and isolation valves at fully open position
b) Record the flow and compare with the design flow.
c) For each measuring station evaluate the percentage design flow rate DFR (%)+100 fa/fd,
where fa is the actual and fd the design flow rate.

d) Measure the initial flow at all terminals.


e) Find out the index branch risers where we get Lower percentage of volume as per the
design flow rate

f) Keep the DRV of the index terminal at fully open position

g) Throttle the other terminals proportionally where we get higher percentage of volume.

h) Monitor the index percentage after throttling each terminal as its increases gradually.

i) By the time of last terminal complete, the flow will be balanced at all terminal including the
index terminal with an equal percentage of design, within the allowable tolerances

6:6 PICV Balancing procedure.

Note: Calibration certificate to be attached in the Work Inspection Request (WIR) for all
instrument used on site.

8:0 chilled water balancing data recording.

a) PICV or DRV make & model.


b) Volume of flow from each terminal.
c) PICV Differential pressure.

9:0 Reference standards

a) CIBSE Commissioning Code W Water Distribution Systems


b) BSRIA AG 2/89.3 Commissioning of water system
1.0 GENERAL PROCEDURES FAN COIL UNITS

These procedures are to be applied to the following systems where applicable:

1:1 Pre- Commissioning Air

The purpose of these procedures is to check that the installation is in a satisfactory


and safe condition before starting up. It is presumed that the installer has thoroughly
checked the installations and that they are deemed commission able in that:

a) All plant items are in acc


b) correct installation procedures have been followed
c) Standards of installation and site cleanliness are acceptable.

1:2 System Cleanliness

Prior to the fitting of filter elements, the following will be checked by the installer
for cleanliness.

a) fan coil unit,


b) condensate drain,
c) cooling coil trays,
d) dampers,
e) ducting and other airways,
f) Sensing elements.

1:3 Plant Components

The following checks will be undertaken.

a) turning vanes, coil fins and sensing elements have been fitted and are
undamaged,
b) filters installed correctly in relation to air flow,
c) damper free movement, clearances, seating, pinning to damper spindles,
position of blades with respect to quadrant indication.
d) dampers throughout the system secured in open position,
e) all adjustable louvers set without deflection, i.e. normal to face of grille,
f) test holes provided for measurement of total airflow.(IF REQUIRED)

1:4 Visual Checks

The following checks will be undertaken,

a) Motorized damper access doors


b) all components, bolts, fixing etc., are secure,
c) anti-vibration mountings,

1:5 Electrical Checks (To be undertaken by Electrical Contractor)

Prior to running of the fans, the following procedures will be adopted and checks
made with all electrical supplies isolated.

a) transit packing removed by contractor,


b) all mechanical checks on fans complete,
c) all wiring connections are tight
d) all power and control wiring completed in detail to the circuit diagram,
e) all cover plates fitted.

2:0 Setting to Work

2:1 Initial Running of Fan Set

On activating the fan coil unit, we will check,

a) direction of rotation of blower,


b) fan free from vibration or undue noise,

3:0 Regulation of Air Flow


3:1 Method of Velocity measurements in Ducts

The total airflow of the fan will be measured through duct traverse method by using
Micro manometer and pitot tubes. (if required)

3:2 Measurement of Airflow at Terminals

Depending upon location and access to air terminals, various types of airflow
measuring instruments will be used to record the actual flow at terminals. Assuming
adequate access provided, a direct reading balometer would be used which gives a
direct reading of volume rather than velocity, which cancels out the needs for
effective grills areas and velocity correction

If the access is restricted then the rotating vane anemometer shall be used the
velocity reading obtained would be converted to volume(velocity x free area =
volume) and a comparison between the pitot traverse reading will be made to obtain
a correction factor which would be incorporated to give a true velocity reading
.Alternatively effective area provided by the register /grille manufacturer will be
incorporated in design velocity calculation.

3:3 Regulation Procedure

Before starting regulation, it is essential that the building is a complete, ceiling,


partitions, doors and windows installed, windows glazed, doors or windows in their
normal or closed state. If spaces are not architecturally sealed, abnormal pressure
distributions will unbalance the system and lead to inconsistent and UN-
reproducible results.

3:4 Balancing the terminals by proportionally

a) Keep all outlet dampers in the grill at fully open position


b) Select the specified speed of the fan coil
c) Take the initial total flow of the unit by adding up all the measured volume
from each outlet
d) Compare the reading against the design flow. Find out the percentage of the
design flow.
e) For each measuring station evaluate the percentage design flow rate DFR
(%)x100 fa/fd, where fa is the actual and fd the design flow rate.
f) Find out the index branch where we get Lower percentage of volume as per
the design flow rate
g) Keep the damper of the index outlet damper at fully open position
h) Throttle the air volume at each outlet to get the design percentage of flow
proportionally by using flow hood (Balometer)
i) Monitor the index percentage after throttling each outlet as its increases
gradually.
j) By the time of last outlet completed, the flow will be balanced at all outlets
including the index branch with an equal percentage of design, within the
allowable tolerances
k) Note all the readings at all put lets and keep record.

4.0 Air balancing data recording.

a) Motor voltage and current.


b) Volume of individual Grill / diffuser airflow

5.0 INSTRUMENTATIONS

Micro manometer with pitot tube


Balometer
Rotating vane anemometer
Clamp Tester

Note: Calibration certificate to be attached in the Work Inspection


Request (WIR) for all instrument used on site.

Reference standards

a) CIBSE Commissioning Code A Air Distribution Systems


b) BSRIA AG 3/89.3 Commissioning of Air system,
These procedures are to be applied to the following systems where applicable:

1.0 Pre-Commissioning Air

The purpose of these procedures is to check that the installation is in a satisfactory and safe
condition before starting up. It is presumed that the installer has thoroughly checked the
installations and that they are deemed commission-able in that:
a) all plant specification.
b) correct installation procedures have been followed
c) standards of installation and site cleanliness are acceptable.

A. System Cleanliness

Prior to the fitting of filter elements, the following will be checked by the installer for cleanliness.
a) air intake screens,,
b) dampers,
c) ducting and other airways,
d) sensing elements.

B. Visual Checks

The following checks will be undertaken

a) plant access doors sealed around the whole periphery


b) all components, bolts, fixing, etc., are secure
2.0 Setting to Work

A. Preliminaries

a) Open branch all duct system and terminal dampers, ensuring that the fan output can be
limited, and an overload situation does not occur.

b) Set plant dampers to a non-modulating position preferably full fresh air/discharge

c) Undertake preliminary inspection checking that air is flowing at each terminal. Any dead
terminals or branches should be investigated.Measure the total flow rate at the branch by
a duct pitot traverse.

3.0 Regulation of Air Flow

A. Method of Velocity measurements in Ducts

The total airflow of the level-3 branch will be measured through duct traverse method by using
Micro manometer and pitot tubes.

A. Test Holes

Test holes, where not already provided will normally be formed by drilling and will be sealed by
insertion of removal tapered plastic plugs. Test holes will preferably be located a minimum of ten
diameters downstream from any source of disturbance to airflow. The number of test holes will
be determined by size and shape of the duct to be measured.

B. Measurement of Airflow at Terminals

Depending upon location and access to air terminals, various types of airflow measuring
instruments will be used to record the actual flow at terminals. Assuming adequate access
provided, a direct reading balometer would be used which gives a direct reading of volume rather
than velocity, which cancels out the needs for effective grills areas and velocity correction

If the access is restricted then the rotating vane anemometer shall be used the velocity reading
obtained would be converted to volume (velocity x free area = volume) and a comparison
between the pitot traverse reading will be made to obtain a correction factor which would be
incorporated to give a true velocity reading .Alternatively effective area provided by the register
/grille manufacturer will be incorporated in design velocity calculation
C. Preliminary Flow Rate Check

With all Dampers fully open, measure and record the total actual flow rate of the level-39

requirement. Where necessary, close the branch regulation damper to provide a flow of
approximately 110% design flow rate.

D. Balancing the sub-branch and terminals by proportionally

a) Keep all the level-3 branch duct dampers and outlet dampers at the fully open position
b) Record the flow and compare it with the design flow.
c) For each measuring station evaluates the percentage design flow rate DFR (%)+100 fa/fd,
where fa is the actual and fd the design flow rate.
d) Measure the initial flow at main branches
e) Find out the index terminal where we get a Lower percentage of volume as per the design flow
rate

f) Keep the damper of the index terminal at the fully open position
g) Throttle the other terminals proportionally where we get a higher percentage of volume.
h) Monitor the index percentage after throttling each terminal as its increases gradually.

i) By the time of last terminal complete, the flow will be balanced at all terminals including the
index terminal with an equal percentage of design, within the allowable tolerances

j) The same method (proportional balancing) can be followed for Fresh and Exhaust sub-
branches and outlets are located on ground floor to level 3rd floor.

4.0 Duct System

The following checks will be made:

Main branch ductwork is complete and installed correctly, and that there are no openings
in the ductwork or end caps missing. All-access doors must be closed and secure tight.

branch ductworks have been leak-tested and cleaned.

als are installed.


plenums, etc.

All, b

i. It will be confirmed that adequate balancing dampers and fire dampers have been provided &
tagged and that all volume dampers and fire dampers are installed at the correct location. It will
also be verified that they are in the open position and that adequate access has been provided.

ii. It will be verified that all terminal devices are installed and that their dampers are open. Verify
that the terminals are of the same size and type as specified.

iii. It will be confirmed that any openings between partitions, etc. have been installed and are
open to ensure proper air passage.

5.0 Air balancing data recording.

a) reading.
b) Fresh and extract air flow from the terminals.
.

The above values shall be recorded in the Standard test sheet.

6.0 INSTRUMENTATIONS

6.1.1 Micro manometer with pitot tube


6.1.2 Balometer
6.1.3 Rotating vane anemometer
6.1.4 Clamp Tester
6.1.5 Tachometer

Note: Calibration certificate to be attached in the Work Inspection Request (WIR) for all
instrument used on site.

7.0 Reference standards

7.1.1 CIBSE Commissioning Code A Air Distribution Systems


7.1.2 BSRIA AG 3/89.3 Commissioning of Air system,

You might also like