Total - A 10
B - Workmen Amana Subcon. Total 4 0 4
B1 - Direct
Mason 1 1 Transporting equipment / Vehicles Amana Subcon. Total No.
Carpenter 6 6 Truck - Trailer
Steel Erector & Welder APK. Mob. Team 5 5
Steel Fixer 10 10 Truck with crane
Asst. QAQC 0
Civil Helper 15 15 Truck
Civil Chargehand 1 1 Pick-up Civil 0 0
Scaffolder 0 Bus 1 1
Office Cleaner ( Civil Helpers ) 2 2 Transit Mixer
Asst. Surveyors 1 1 Mobile Pump 1 1
Time keeper 1 1 Water Tanker 1 1
Office Boy 1 1
Safety Marshal 1 1
Carpenter ( Office Boy ) 0
painter 0 0
Total - B1 44 0 44 3 0 3
B2 - Indirect
Plumber 1 1 Others Amana Subcon. Total No.
MEP Chargehand 0 0
Ductman / ( MEP Welder ) 0 0 Survey equipment 2 2
Pipe Fitter MEP 0 0 Table Circular saw
Driver (General purpose) 2 2 Dewatering equipment
Electrician MEP 1 1 Generators 4 4
MEP Helper 0 0 Air Compressors Small & Big 1 1
Mechanic 0 0 Welding Machines 1 1
Operators 3 3
Bus Driver 1 1
Store keeper 1 1
Bar-cutting machines 1 1
Bar-bending machines 1 1
Power Float
Concrete Mixer
Concrete Vibrator 1 1
Jumping Compactor
Plate Compactor 1 1
Roller Compactor
1/5
DAILY CONSTRUCTION REPORT (DCR)
Contractor : Saudi Amana Contracting Co. LLC
Package TitleVeolia Central Utilities & Valorisation Plant Package No: Veolia
Civil Work
Work Discription Location Date Started Date of Finish Quantity or % Complete
Column Neck Reinforcement Rebar of Admin Building ( Stag Admin Building 4-Jun-20 80.0%
Excavation Works for Shredder Building (Stage 2) Shredder 4-Jun-20 40.0%
Scaffolding for Lab Building Footings Lab Building 4-Jun-20 18-Jun-20 70.0%
Steel Reinforcement for Lab Footings Lab Building 4-Jun-20 18-Jun-20 70.0%
Concrete Pouring of Lab Footings Lab Building 10-Jun-20 20-Jun-20 40.0%
MEP Work
Work Discription Location Date Started/Completed Quantity or % Complete
Contractor : Consultant :
Name: Abdulah Alkilani Name:
Signature: Signature:
Designation: Project Manager Designation: