DAILY ACTIVITY REPORT # P021.46-DB54-DAR-186 Project No. P021.

46
Project Name 25 VILLAS BEL AIR CLUSTER DAMAC HILLS. Date 11/18/2022
Day FRIDAY
MAIN CONTRACTOR Delta Al Emarate Building Contracting L.L.C TEMPERATURE:
CONSULTANT Arif & Bintoak Consulting Architects & Engineers MAX 45

CONTRACTOR'S MANPOWER EQUIPMENT I=IDLE R=REPAIR

STAFF NO INDIRECT LABOUR NO TYPE QTY WH EACH STATUS

PROJECT MANAGER 1 FOREMAN 3 BACKHOE 0


CONSRUCTION MANAGER 1 STORE KEEPER 1 Excavator 0
SITE TECH. MANAGER 1 QA/QC Assist 1 WHEEL LOADER 1
SITE QA/AC MANAGER 1 First Aider 1 TIPPER 1
SITE HSE MANAGER 1 Safety Assist 1 ROLLER COMPACTOR 1
PROJ ENGINEER 1 Time Keeper 1 MOBILE CRANE 0
QA/QC ENGINEER 1 Surveyor Helper 1 TOWER CRANE 0
SITE ENGINEERS 1 Flag Man 4 TRANSIT MIXERS 0
QA/QC INSPECTOR 1 OPERATOR 4 CONCRETE VIBRATOR 5
STRUCTURE ENGINEER 1 DRIVERS 2 WELDING MACHINE 0
LAND SURVEYOR 1 STORE ASSITANT 1 GENERATOR 3
DOCUMENT CONTROLLER 1 NIGHT WATCHMAN 1 BAR BENDING/CUTTING 4
ASSIT DOCUMENT CONTROLLER 1 DAY WATCHMAN 1 PICK UP TRUCKS 1
DRAFTSMANS 1 OFFICE BOY 1 BOBCAT TELESCOPIC 2
SAFETY OFFICER 1 ELECTRICIAN 1 STEEL CUTTING MACHINE 2
MEP CORDINATOR 1 PLUMBER 1 FORKLIFT 1
PLANING ENGINEER 1 CLEANER 1 1 ton Pick up 1
QUANTITY SURVEYOR 1 MECHANIC 1
COST CONTROL ENGINEER 1 HELPER 7
JR. ARCHITECT ENGINEER 0
Total (Indirect Labor) 34
DIRECT LABOUR
CHARGE HAND 3
CARPENTER 31
STEEL FIXER 42
MASON 6
Painter 0
HELPER 49
Total (Staffs) 19 Total (Direct Labor) 131
Grand Total (DELTA) 184 165
SUBCONTRACTOR'S MANPOWER - NASCON
STAFF INDIRECT LABOUR DIRECT LABOUR
Project Manager 1 Foreman 3 Charge Hand 1
Project Engineer 1 Store Keeper 0 Electrician 20
Elec Engineer 1 Store Helper 0 Plumber 46
Mech Engineer 1 Driver 0
QA/QC Engineer 1 Office Boy 0
Draftsman’s 1
Safety officer 1
Document controller
Total 7 Total 3 Total 67

Grand Total (NASCON) 77

Grand Total 261


MATERIALS DELIVERED TO SITE VISITORS TO SITE

ITEM UNIT QTY NAME COMPANY


SOLID BLOCK Nos 1200
GI Block Mesh Roll 60
CONSTRUCTION ACTIVITIES: (See next page)

Consultant: Signature: Date:


Contractor: Signature: Date

CONSTRUCTION ACTIVITIES LEVEL LOCATION

1.      Excavation and Mobilization work


2.      House Keeping
3. shutering for colums 805,804
4.      shutter & steel fixing for1 st floor slab 813
5.      shutter & steel fixing for1 st floor slab 814
6.      shuttering for columns 815
7.     tie beam work for villa 709
8.    block work layout at G6 zone 3 
9.      shutter & steel fixing for slab 807,806
10. Steel work slab
11. MEP block work chiseling
12. Curing for columns at first floor
13. Lintel work

5.MEP CONSTRUCTION ACTIVITIES

Mechanical – First floor slab marking G6 Zone 2


G10 underground drainage work, gravity test,
G2 Underground drainage work

Electrical – Zone 1 Group 13 Roof floor slab work

NEXT DAY ACTIVITIES: (See next page)

Consultant (Name): Signature: Date:

Contractor (Name): Signature:


NEXT DAY ACTIVITIES LEVEL LOCATION

1.      Excavation and Mobilization work


2.      House Keeping
3. shutering for colums 805,804
4.      shutter & steel fixing for1 st floor slab 813
5.      shutter & steel fixing for1 st floor slab 814
6.      shuttering for columns 815
7.     tie beam work for villa 709
8.    block work layout at G6 zone 3 
9.      shutter & steel fixing for slab 807,806
10. Steel work slab
11. MEP block work chiseling
12. Curing for columns at first floor
13. Lintel work
14.  Painting works

5.MEP CONSTRUCTION ACTIVITIES

Mechanical – First floor slab marking G6 Zone 2


G10 underground drainage work, gravity test,
G2 Underground drainage work

Electrical – Zone 1 Group 13 Roof floor slab work

Consultant Comments

Consultant (Name): Signature: Date:

Contractor (Name): Signature: Date: