Daily Work Report

RSG-CN-FRM-0015

AMAALA
General Information
Program Name TB-Central Project Code 011C44 Project Name TB-Rosewood Resort
Contract ref. TB-Rosewood Package Builder Works
Contractor Abdul Mohsen Abdullah Al-Horaish Al-Tamimi & Partners Report No. 167
Contract No. 1TB02-011C44 Report Date 28-Feb-2024

To the Engineer Mohamed Ali (Sr. Planning Manager) & Shamiullha (Planning Manager) Contract

Weather Ovarcast Humidity Low


Prepared By Eng.Belal Eid Temperature 28.°C
General Description of Work Activities

Block Work

. Personnel on Site
Equipment Qty. Personnel Qty.
Generator 10 Indirect Personnel 40
HAND JACK HAMMER 14 Area Manager 1
POTABLE WATER TANKE 10 Project Manager 1
TRAILER / TRUCK (HIGH/LOW BED) 3 Construction Manager 1
FORKLIFT 0 Planning Manager
TELEHANDLER 4 Safety Manager 1
VIBRATOR 2 QA/QC Manager 1
AIR COMPRESSOR 3 Planning Engineer 1
BUS 7 Quantity surveyour 1
LIGHT VEHICLE / SUV / CAR 3 Project Engineer 1
1 TON PICK UP 6 Safety Assistant 1
AMBULANCE 1 QC Inspector 3
Bobcat 2 Site Engineer 3
Loader 2 Lead Environmental 1
Water Tanker 3 Surveyor 2
Safety Officer 5
Project Coordinator 1
Procument Engineer 1
Logistic Manager 1
Technical Engineer 1
Safety Deputy Manger 1
Timekeeper 1
Chief Surveryor 1
Senior land surveyor 1
Local Purchiser 1
General Foreman 1
Foreman 4
Architecture Forman 1
Admin 1
Storekeeper 1
Direct Personnel 331
Mason 6
Helper 27
Plaster Technician 26
Painter 16
Carpenter 23
Steel fixer 16
Scaffolding Inspector 1
Scaffolding Supervisor 1
Scaffolding erector 34
Scaffolding helper 4
Storekeeper 1
Housekeeping 25
Electrician 3
Operator 5
labors for Casting 14
Labors for Opening 30
Labors for closing 56
Fall Arrest system 8
FIRE RATED-SEALANT +Gypsum board SEALANT 4
,Welder
-labor 10
External water proffing workers 14
Total number of Equipment 70 Driver 7
Total man hours for the day 3310
Total Man Hours Worked Since Last DPR Report 348580
Total man hours from the start of the project 351890
Section Event
Health and Safety Pre task briefing prior to start the activity, Safety monitoring for compliance in safe system of work.
Environment Housekeeping and Waste segregation at source and waste storage area.
Inspections
Material Delivery
NCR
Testing

Activities and Tasks

Actual Progress Till Date Next Day Forecast Progress


(%)
Forecast Finish/ QYT
Task Description (%) Complete QYT Start Date Complete (
Date ( Tomorrow )
Tomorrow )
2 Continue Block work Ups Room Block Work 1,2 (HOH) 90% 19-Dec-2023 7-Feb-2024 50% 40 ( M2 )

3 Continue Block work Automated casher (HOH) 90% 23-Dec-2023 11-Feb-2024 50% 40 ( M2 )

4 Continue Block work Training Room (HOH) 90% 23-Dec-2023 11-Feb-2024 50% 40 ( M2 )

5 Continue Block work Security Control Room (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

6 Continue Block work ICe Cream Room (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

7 Continue Block work Banking Room (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

8 Continue Block work Fire Control Room (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

9 Continue Block work Pastry Store (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

10 Continue Block work Drainage Vacuum (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

11 Continue Block work Fish prep (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

12 Continue Block work Poultry prep (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

13 Continue Block work Meat prep (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

14 Continue Block work Veg prep (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

15 Continue Block work Sanitization Area (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

16 Continue Block work Veg/meat...etc Chiller (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

17 Continue Block work Cold kitchen (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

18 Continue Block work China glass (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

19 Continue Block work Chef's office (HOH) 90% 24-Dec-2023 12-Feb-2024 50% 40 ( M2 )

20 Continue Block work General chiller (HOH) 90% 28-Dec-2023 16-Feb-2024 50% 40 ( M2 )

21 Continue Block work Chemical (HOH) 90% 28-Dec-2023 16-Feb-2024 50% 40 ( M2 )

22 Continue Block work Lost and Found (HOH) 90% 28-Dec-2023 16-Feb-2024 50% 40 ( M2 )

23 Continue Block work Valet Laundry (HOH) 90% 28-Dec-2023 16-Feb-2024 50% 40 ( M2 )

24 Continue Block work Chilled water pump (HOH) 90% 28-Dec-2023 16-Feb-2024 50% 40 ( M2 )

25 Continue Block work Male prayer Room (HOH) 90% 28-Dec-2023 16-Feb-2024 50% 40 ( M2 )

26 Continue Block work Foyer/jan/loby (HOH) 90% 28-Dec-2023 16-Feb-2024 50% 40 ( M2 )

27 Continue Block work Ber Room (HOH) 90% 28-Dec-2023 16-Feb-2024 50% 40 ( M2 )

28 Continue Block work Network Room (HOH) 90% 28-Dec-2023 16-Feb-2024 50% 40 ( M2 )

29 Continue Block work House Keeping Mang (HOH) 90% 28-Dec-2023 16-Feb-2024 50% 40 ( M2 )

30 Continue Block work CLEAN/SOILED LINEN (HOH) 90% 4-Jan-2024 23-Feb-2024 50% 40 ( M2 )

31 Continue Block work ENGINEERING STORE (HOH) 90% 4-Jan-2024 23-Feb-2024 50% 40 ( M2 )
Continue Block work NIGHT CLEANER CLOTH-
32 90% 4-Jan-2024 23-Feb-2024 50% 40 ( M2 )
(HOH)
Continue Block work CHILLED WATER PUMP RM
33 90% 4-Jan-2024 23-Feb-2024 50% 40 ( M2 )
(HOH)
Continue Block work CARPENTRY WORK SHOP
34 90% 4-Jan-2024 23-Feb-2024 50% 40 ( M2 )
(HOH)
35 Continue Block work FURNITURE STORE (HOH) 90% 4-Jan-2024 23-Feb-2024 50% 40 ( M2 )
Continue Ceilling Paint domestic water/ firepump room
35 50% 22-Feb-2024 23-Mar-2024 80% 40 ( M2 )
(HOH)
35 Continue Ceilling Paint drainage vaccum station (HOH) 50% 22-Feb-2024 23-Mar-2024 80% 40 ( M2 )

35 Continue Ceilling Paint generator room (HOH) 50% 22-Feb-2024 23-Mar-2024 80% 40 ( M2 )

35 Continue Ceilling Paint LV room (HOH) 10% 22-Feb-2024 23-Mar-2024 80% 40 ( M2 )

35 Continue Ceilling Paint security control room (HOH) 10% 22-Feb-2024 23-Mar-2024 80% 40 ( M2 )

35 Continue Ceilling Paint ups room (HOH) 10% 22-Feb-2024 23-Mar-2024 80% 40 ( M2 )

35 Continue Ceilling Paint MTR/ISR room (HOH) 10% 22-Feb-2024 23-Mar-2024 80% 40 ( M2 )

35 Continue Plinths ahu room (HOH) 70% 22-Feb-2024 23-Mar-2024 80% 40 ( M2 )

35 Continue Plinths fuel room (HOH) 70% 22-Feb-2024 23-Mar-2024 80% 40 ( M2 )


35 Continue Plinths generator room (HOH) 70% 22-Feb-2024 23-Mar-2024 80% 40 ( M2 )

35 Continue Plinths chilled water pump room (HOH) 70% 22-Feb-2024 23-Mar-2024 80% 40 ( M2 )

36 Continue Block work (FD 02) 85% 21-Dec-2023 29-Jan-2024 80% 40 ( M2 )


40 Continue Block work ( HL ) 60% 14-Jan-2024 29-Jan-2024 100% 40 ( M2 )

41 Continue External Water Proofing (CB 05 ) 85% 22-Jan-2024 1-Feb-2024 80% 40 ( M2 )

42 Continue External Water Proofing (CD 01 ) 90% 24-Jan-2024 3-Feb-2024 80% 40 ( M2 )

43 Continue External Water Proofing (CC 07 ) 85% 3-Feb-2024 13-Feb-2024 80% 40 ( M2 )

44 Continue External Water Proofing (CC 09 ) 85% 3-Feb-2024 13-Feb-2024 80% 40 ( M2 )

45 Continue External Water Proofing (CD 02 ) 35% 5-Feb-2024 15-Feb-2024 80% 40 ( M2 )

46 Continue External Water Proofing (CC 01 ) 85% 24-Feb-2024 5-Mar-2024 90% 40 ( M2 )

46 Continue External Water Proofing (CC 05 ) 40% 27-Feb-2024 8-Mar-2024 90% 40 ( M2 )

50 Continue External Water Proofing (RB 07 ) 90% 20-Jan-2024 30-Jan-2024 80% 40 ( M2 )

51 Continue External Water Proofing (RC 07 ) 90% 21-Jan-2024 31-Jan-2024 80% 40 ( M2 )

52 Continue External Water Proofing (RC 06 ) 90% 21-Jan-2024 31-Jan-2024 80% 40 ( M2 )

53 Continue External Water Proofing (RC 05 ) 80% 22-Jan-2024 1-Feb-2024 80% 40 ( M2 )

54 Continue External Water Proofing (RE 02 ) 80% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

55 Continue External Water Proofing (RB 04 ) 80% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

56 Continue External Water Proofing (RC 02 ) 80% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

57 Continue External Water Proofing (RB 05 ) 70% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

58 Continue External Water Proofing (RB 06 ) 70% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

59 Continue External Water Proofing (RC 04 ) 80% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

60 Continue External Water Proofing (RC 03 ) 80% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

61 Continue External Water Proofing (RB 02 ) 80% 28-Jan-2024 7-Feb-2024 80% 40 ( M2 )

62 Continue External Water Proofing (RB 03 ) 80% 28-Jan-2024 7-Feb-2024 80% 40 ( M2 )

63 Continue External Water Proofing (RD 08 ) 70% 29-Jan-2024 8-Feb-2024 80% 40 ( M2 )

64 Continue External Water Proofing (RB 08 ) 90% 3-Feb-2024 13-Feb-2024 80% 40 ( M2 )

64 Continue External Water Proofing (RB 01 ) 90% 15-Feb-2024 25-Feb-2024 80% 40 ( M2 )

64 Continue External Water Proofing (RD 01 ) 90% 15-Feb-2024 25-Feb-2024 80% 40 ( M2 )

64 Continue External Water Proofing (RD 02 ) 90% 15-Feb-2024 25-Feb-2024 80% 40 ( M2 )

64 Continue External Water Proofing (RD 03 ) 90% 15-Feb-2024 25-Feb-2024 80% 40 ( M2 )

64 Continue External Water Proofing (RD 04 ) 90% 15-Feb-2024 25-Feb-2024 80% 40 ( M2 )

64 Continue External Water Proofing (RC 01 ) 90% 10 (M2) 25-Feb-2024 6-Mar-2024 100% 40 ( M2 )

64 Continue External Water Proofing (RE 01 ) 90% 10 (M2) 25-Feb-2024 6-Mar-2024 100% 40 ( M2 )

64 Continue External Water Proofing (RD 02 ) 70% 10 (M2) 25-Feb-2024 6-Mar-2024 100% 40 ( M2 )

64 Continue External Water Proofing (RD 05 ) 70% 10 (M2) 25-Feb-2024 6-Mar-2024 100% 40 ( M2 )

64 Continue External Water Proofing (RD 06 ) 50% 10 (M2) 25-Feb-2024 6-Mar-2024 100% 40 ( M2 )

65 Continue Fire rated Sealant (RB 08 ) 80% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

65 Continue Fire rated Sealant (HOH ) 5% 15-Feb-2024 25-Feb-2024 80% 40 ( M2 )

66 Continue Acoustic Sealant (Interior sealant )(CC 09 ) 25% 5-Feb-2024 15-Feb-2024 80% 40 ( M2 )

67 Continue Acoustic Sealant (Interior sealant )(CC 01 ) 100% 8-Feb-2024 24-Feb-2024

68 Continue Acoustic Sealant (Interior sealant )(CC 03 ) 100% 17-Feb-2024 24-Feb-2024

68 Continue Acoustic Sealant (Interior sealant )(CC 04 ) 35% 17-Feb-2024 27-Feb-2024 80% 40 ( M2 )

69 Continue Acoustic Sealant (Interior sealant )(RB 08 ) 90% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

70 Continue Acoustic Sealant (Interior sealant (RB 07 ) 90% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

71 Continue Acoustic Sealant (Interior sealant (RC 07 ) 90% 3-Feb-2024 13-Feb-2024 80% 40 ( M2 )

72 Continue Acoustic Sealant (Interior sealant (RC 06 ) 90% 3-Feb-2024 13-Feb-2024 80% 40 ( M2 )

73 Continue Acoustic Sealant (Interior sealant (RC 05 ) 90% 3-Feb-2024 13-Feb-2024 80% 40 ( M2 )

74 Continue Acoustic Sealant (RC 07 ) 90% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

75 Continue Acoustic Sealant (Exterior sealant )(RB 08) 90% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

76 Continue Acoustic Sealant (Exterior sealant )(RB 07) 50% 3-Feb-2024 13-Feb-2024 80% 40 ( M2 )

77 Continue Acoustic Sealant (Exterior sealant )(RC 07) 90% 10-Feb-2024 20-Feb-2024 80% 40 ( M2 )
78 Continue Acoustic Sealant (Interior sealant )(RC 06 ) 90% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )
79 Continue Acoustic Sealant (Interior sealant )(RC 05 ) 90% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

80 Continue Acoustic Sealant (Interior sealant )(RE 02 ) 80% 10-Feb-2024 20-Feb-2024 80% 40 ( M2 )

81 Continue Acoustic Sealant (Interior sealant )(RB 04 ) 80% 10-Feb-2024 20-Feb-2024 80% 40 ( M2 )

81 Continue Acoustic Sealant (Interior sealant )(RC 02 ) 80% 14-Feb-2024 24-Feb-2024 80% 40 ( M2 )

81 Continue Acoustic Sealant (Interior sealant )(RB 05 ) 80% 14-Feb-2024 24-Feb-2024 80% 40 ( M2 )

81 Continue Acoustic Sealant (Interior sealant )(RB 06 ) 80% 14-Feb-2024 24-Feb-2024 80% 40 ( M2 )

82 Continue Acoustic sealant ( External walls ) (CB 03 ) 85% 23-Jan-2024 2-Feb-2024 100% 40 ( M2 )

83 Continue Acoustic sealant ( External walls ) (CB 04 ) 85% 23-Jan-2024 2-Feb-2024 100% 40 ( M2 )

84 Continue Acoustic sealant ( External walls ) (CC 06 ) 80% 27-Jan-2024 6-Feb-2024 100% 40 ( M2 )

85 Continue Acoustic sealant ( External walls ) (CD 01 ) 30% 3-Feb-2024 13-Feb-2024 100% 40 ( M2 )

86 Continue Acoustic sealant ( External walls ) (CC 01 ) 30% 6-Feb-2024 16-Feb-2024 100% 40 ( M2 )

86 Continue Acoustic sealant ( External walls ) (CC 07 ) 30% 17-Feb-2024 27-Feb-2024 100% 40 ( M2 )

86 Continue Acoustic sealant ( External walls ) (CC 02 ) 80% 17-Feb-2024 27-Feb-2024 100% 40 ( M2 )

86 Continue Acoustic sealant ( External walls ) (CC 03 ) 70% 17-Feb-2024 27-Feb-2024 100% 40 ( M2 )

89 Continue Concrete above pipes (RC 07 ) 80% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

90 Continue Concrete above pipes (RC 06 ) 80% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

91 Continue Concrete above pipes (RC 05 ) 70% 23-Jan-2024 2-Feb-2024 80% 40 ( M2 )

92 Continue Block work (FA 02) 85% 14-Jan-2024 10-Feb-2024 90% 40 ( M2 )

93 Continue Block work (FG 02) 75% 16-Jan-2024 31-Jan-2024 80% 40 ( M2 )

94 Continue external plaster work (RB 02) 85% 6-Dec-2023 25-Jan-2024 100% 40 ( M2 )

95 Continue external plaster work (RB 03) 85% 13-Dec-2023 25-Jan-2024 100% 40 ( M2 )

101 Continue external plaster work (RE 01) 90% 24-Dec-2023 8-Feb-2024 100% 40 ( M2 )

102 Continue external plaster work (FF 01) 100% 10-Feb-2024 25-Feb-2024

103 Continue external plaster work (FG 03) 60% 30-Jan-2024 9-Feb-2024 100% 40 ( M2 )

104 Continue external plaster work (FA 02) 10% 22-Feb-2024 3-Mar-2024 100% 40 ( M2 )

104 Continue external plaster work (FA 02) 10% 22-Feb-2024 3-Mar-2024 100% 40 ( M2 )

104 Continue external plaster work (FA 03) 10% 22-Feb-2024 3-Mar-2024 100% 40 ( M2 )

104 Continue external plaster work (FA 04) 10% 22-Feb-2024 3-Mar-2024 100% 40 ( M2 )

104 Continue external plaster work (FA 05) 30% 17-Feb-2024 27-Feb-2024 100% 40 ( M2 )

107 Continue external plaster work (FD 01) 10% 19-Feb-2024 29-Feb-2024 100% 40 ( M2 )

107 Continue external plaster work (FD 02) 10% 19-Feb-2024 29-Feb-2024 100% 40 ( M2 )

105 Continue external plaster work (FD 03) 30% 12-Feb-2024 22-Feb-2024 100% 40 ( M2 )

106 Continue external plaster work (FD 04) 100% 12-Feb-2024 25-Feb-2024

107 Continue external plaster work (FD 05) 100% 12-Feb-2024 25-Feb-2024

103 Continue external plaster work (FG 03) 100% 22-Feb-2024 25-Feb-2024

103 Continue external plaster work (FG 04) 10% 22-Feb-2024 22-Feb-2024 100% 40 ( M2 )

107 Continue external plaster work (FG 05) 10% 19-Feb-2024 29-Feb-2024 100% 40 ( M2 )

107 Continue external plaster work (FG 05) 10% 22-Feb-2024 3-Mar-2024 100% 40 ( M2 )

107 Continue external plaster work (FC 01) 10% 19-Feb-2024 29-Feb-2024 100% 40 ( M2 )

107 Continue external plaster work (FC 02) 10% 19-Feb-2024 29-Feb-2024 100% 40 ( M2 )

107 Continue external plaster work (FC 03) 10% 19-Feb-2024 29-Feb-2024 100% 40 ( M2 )

107 Continue external plaster work (FC 04) 10% 22-Feb-2024 3-Mar-2024 100% 40 ( M2 )

107 Continue external plaster work (FC 05) 10% 22-Feb-2024 3-Mar-2024 100% 40 ( M2 )

109 Continue Block work (FC 05) 80% 20-Jan-2024 29-Feb-2024 80% 40 ( M2 )

110 Continue Block work (FG 04) 75% 22-Jan-2024 6-Feb-2024 80% 40 ( M2 )
111 Continue Block work (AC) 75% 22-Jan-2024 6-Feb-2024 80% 40 ( M2 )

111 Continue Block work (SH) 10% 19-Feb-2024 5-Mar-2024 80% 40 ( M2 )

112 Continue Embedded angle ( checkered plate ) (HOH) 75% 22-Jan-2024 6-Feb-2024 80% 40 ( M2 )
RSG-CN-FORM-0015

Continue plinths work ( HOH ) Continue Block work( HOH )

Continue Waterproofing( CC 01,2 ) Continue Waterproofing( CC 01,2 )


Progress Layout