SERVICING, CALIBRATION AND VERIFICATION OF PROCESS INSTRUMENTS (PANEL & FIELD

MOUNTED), INCLUDING REPLACEMENT OF THERMOWELLS, THERMOCOUPLES, WIRES,


CORRODED/DILAPIDATED CONDUIT PIPING & SUPPORT AT PRIMARY AND SECONDARY SMELTER -
PTA 2024
MANPOWER LOADING SCHEDULE
PROJECT DURATION
Manpower Qty Week 1 Week 2 Week 3 Week 4 Week 5
Project Leader 1 1 1 1 1 1

Project Supervisor/Documents and Report 1 1 1 1 1 1


Safety Officer 2 2 2 2 2 2
QA/QC 1 1 1 1 1 1
Project Coordinator 1 1 1 1 1 1
Calibrator Lead 2 2 2 2 2
Calibrator Technician 4 4 4 4 4
Welder 1 1 1 1 1 1
EIM Technician 2 1 1 1 1 1
House Keeping 2 2 2
TOTAL MANPOWER 17