You are on page 1of 1

@copyright by: Prof.

Voek Pitou
Telegram Channel: Professional Engineering (PMP)

SITE STAFF PLAN FOR PROJECT CONSTRUCTION

PROJECT NAME:
OWNER:
MAIN CONTRACTOR:

Date: Rev.No.:

YEAR 2023 2023

CATEGORY NOS. MONTH JAN FEB MAR APRIL MAY JUN JULY AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Staff

MONTH # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Totals:

A 1 Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

B TECHNICAL SECTION

1 Technical Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

2 Technical Engineer 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 48

1 Site architect 1 1 1 1 1 1 1 1 1 1 1 1 12

2 Surveyor 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 48

C CONSTRUCTION SECTION

1 SITE MANAGER 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

2 SITE STRUCTURAL ENGINEERS 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 32

2 SITE FINISHING ENGINEERS 2 2 2 2 2 2 2 2 2 2 2 2 24

D QA/QC SECTION

1 QA/QC Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

2 QA/QC Engineers 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 48

E QS SECTION

1 QS Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

2 QS Engineers 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 48

F HSE SECTION

1 HSE Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

1 HSE Engineers 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

G CONTRACT SECTION

1 Contract Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

2 Contract Engineers 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 48

H HR SECTION

1 HR Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

1 Site Administrator 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

MONTHLY TOTAL 22 22 22 22 22 22 22 22 22 22 22 22 25 25 25 25 23 23 23 23 23 23 23 23 548

Staffing

You might also like