PROJECT MONTH

PEAK Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24
NO DESCRIPTION MM
TIME
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A SITE CM STAFFING PLAN 00450.17
1 SITE MANAGER 1 16 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 PPC COORD. 1 16 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 PROGRESS & QS ENGINEER 1 13 1 1 1 1 1 1 1 1 1 1 1 1 1
4 PLANNING & SCHEDULER ENGINEER 1 13 1 1 1 1 1 1 1 1 1 1 1 1 1
5 QA/QC COORDINATOR 1 14 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 QC INSPECTOR 4 40 1 2 3 4 4 4 4 4 4 4 4 2
7 SITE PERSONNEL COORDINATOR 1 16 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
8 PAYROLL ADMIN 1 14 1 1 1 1 1 1 1 1 1 1 1 1 1 1
9 RECRUITMENT ADMIN 1 8 1 1 1 1 1 1 1 1
10 FINANCE OFFICER 1 14 1 1 1 1 1 1 1 1 1 1 1 1 1 1
11 SITE SAFETY MANAGER 1 16 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
12 SAFETY INSPECTOR 8 71 1 3 4 5 6 7 8 8 8 7 5 2 2 2 2 1
13 PROCUREMENT OFFICER 1 11 1 1 1 1 1 1 1 1 1 1 1
14 CONSTRUCTION MANAGER 1 11 1 1 1 1 1 1 1 1 1 1 1
15 WELDING SUPERVISOR 1 9 1 1 1 1 1 1 1 1 1
16 MECHANICAL EQUIPMENT ENGINEER 1 16 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
17 PIPING ENGINEER 1 11 1 1 1 1 1 1 1 1 1 1 1
18 DRAFTER 1 8 1 1 1 1 1 1 1 1
19 TANK & STRUCTURE ENGINEER 1 9 1 1 1 1 1 1 1 1 1
20 MECHANICAL SUPERVISOR 4 40 1 2 3 3 4 4 4 4 4 4 2 1 1 1 1 1
21 STRUCTURE SUPERVISOR 1 8 1 1 1 1 1 1 1 1
22 PIPING SUPERVISOR 3 32 1 1 2 3 3 3 3 3 3 3 3 2 1 1
23 SCAFFOLDER ENGINEER 1 11 1 1 1 1 1 1 1 1 1 1 1
24 RIGGING SUPERVISOR 1 11 1 1 1 1 1 1 1 1 1 1 1
25 SCAFOLDING SUPERVISOR 1 14 1 1 1 1 1 1 1 1 1 1 1 1 1 1
26 WAREHOUSE SUPERVISOR 1 11 1 1 1 1 1 1 1 1 1 1 1
27 SURVEYOR SUPERVISOR 1 9 1 1 1 1 1 1 1 1 1
28 ELECTRICAL ENGINEER 1 12 1 1 1 1 1 1 1 1 1 1 1 1
29 ELECTRICAL SUPERVISOR 5 44 1 1 1 2 3 3 5 5 5 5 3 2 2 2 2 2
30 INSTRUMENT ENGINEER 1 8 1 1 1 1 1 1 1 1
31 INSTRUMENT SUPERVISOR 1 11 1 1 1 1 1 1 1 1 1 1 1
32 DOCUMENT & DRAWING CONTROLLER 1 14 1 1 1 1 1 1 1 1 1 1 1 1 1 1
33 ADMINISTRATION STAFF 3 30 1 2 3 3 3 3 3 3 3 3 3
PROJECT MONTH
PEAK Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24
NO DESCRIPTION MM
TIME
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Total for Item A = 50 581 29 36 42 47 50 51 54 54 53 47 41 22 19 17 10 9
PROJECT MONTH
PEAK Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24
NO DESCRIPTION MM
TIME
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
C DIRECT WORKFORCE 00450.18
1 FOREMAN MECHANICAL/PIPING 8 83 2 4 5 6 8 8 8 8 8 7 8 3 3 3 1 1
2 FOREMAN STRUCTURE 2 18 2 2 2 2 2 2 2 2 2
3 WELDER PIPE 12 94 1 6 7 9 12 12 12 12 10 8 1 1 1 1 1
4 WELDER ROBOTIC 3 12 3 3 3 3
5 WELDER PLATE 2 13 1 2 2 2 2 2 2
6 FITTER 24 217 12 15 18 18 24 24 24 24 20 16 6 4 4 4 4
7 LAMINATOR/BOUNDER 12 116 4 6 10 12 12 12 12 12 12 8 4 4 4 2 2
8 MILLWRIGHT 17 160 9 11 13 15 17 17 17 17 15 13 4 4 4 2 2
9 STL STR FITTER 14 119 8 9 11 12 14 14 14 14 12 11
10 RIGGER 15 140 8 10 12 14 15 15 15 15 14 12 2 2 2 2 2
11 SCAFFOLDER 20 193 8 9 11 16 20 20 20 20 18 15 8 8 8 6 6
12 SURVEYOR 6 48 4 4 4 6 6 6 6 6 4 2
13 GENERAL WORKER 80 600 23 28 33 48 80 80 80 80 70 40 8 8 8 8 6
14 FOREMAN ELECTRICAL 11 64 2 9 10 10 11 9 8 1 1 1 1 1
15 ELECTRICIAN SKILLED 50 268 15 30 30 50 50 50 15 6 6 6 6 4
16 INSTRUMENT SKILLED 20 119 6 15 15 20 20 15 6 6 6 6 4
Total for Item C = 296 2,264 5 86 108 130 178 257 267 287 293 265 173 49 47 47 39 33
PROJECT MONTH
PEAK Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Apr-24 May-24 Jun-24
NO DESCRIPTION MM
TIME
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
B INDIRECT WORKFORCE 00450.19
1 TECHNICIAN 4 32 2 2 2 2 2 4 4 4 4 4 2
1 STORE KEEPER 2 22 2 2 2 2 2 2 2 2 2 2 2
2 OFFICE BOY 6 67 2 3 5 6 6 6 6 6 6 6 5 2 2 2 2 2
3 CAR DRIVER 6 61 2 3 3 4 5 6 6 6 6 6 5 3 2 2 1 1
4 BUS/MICROBUS DRIVER 10 93 2 5 5 7 8 9 10 10 10 9 7 3 3 3 1 1
5 SECURITY 2 32 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6 OPERATOR 8 70 2 4 4 5 7 8 8 8 8 7 6 2 1
Total for Item B = 38 377 14 21 23 28 32 37 38 38 38 36 29 12 10 9 6 6