WELCOME TO ALL

38th Monthly Progress Review Presentation


Period 26.12.13 to 25.01.14

04.02.2014

1
DHDT/HCDS UNIT, EPCM-2 Monthly Review Meeting – 04/02/2014

OWNER INDIAN OIL CORPORATION LIMITED

PROJECT MANAGEMENT CONSULTANT UHDE INDIA PRIVATE LIMITED

MECHANICAL CONTRACTOR TECH SHARP ENGINEERS PVT. LTD.

2
AGENDA
1. Safety Statistics

2. Project Overview

3. Overall Progress S curve

4. Liquidation plan for balance activities

5. Critical path

6. Loop wise Quantity installation status

7. Man power - Plan vs. Actual

8. Action taken against previous MOM

9. Areas of Concern

10. Billing Status

3
SAFETY STATISTICS

All Near miss cases are minor and of low potential.


4
Project Overview and Schedule

• Date of LOI : 06.09.2010

• Duration : 17 Months

• Revised Duration : 43 Months

• Time Elapsed:41 Months

• Contractual Mechanical Completion Date : 05.02.2012

• Expected Mechanical Clearance date : 28th Feb 2014

5
4
’ 14 ’14 ar’1
n b M
Ja Fe

Actual progress for Jan’14 : 1.33% Mechanical clearance of HT loops – Feb’14


Cumm. Plan up to Jan’14 : 90 %
Mechanical completion – Mar’14
Cumm Front up to Jan’14 :95 %
Cumm. Progress up to Jan’14 :85.29 %
6
Liquidation Plan for Balance activities

7
CRITICAL PATH

PIPING FABRICATION – NOV 2010 TO DEC 2011 (Baseline Plan)

NOV 2010 TO DEC 2012 - COMPLETED

( AS PER PROJECTED PLAN dt. 20/09/12)

PIPING ERECTION – APRIL 2011 TO JAN 2012 (Baseline Plan)

JULY 2011 TO 28th Feb 2014 (As per latest revision)

Expected completion : 31st Mar 2014

8
LOOPWISE QUANTITY INSTALLATION STATUS

Cumulative on 25th Jan/ as on date


Unit Scope

Format Format Format Cleared for Pressure


. A B C Pressure Test tested

395
DHDT
180/184 179/179 140/154 134/144 125/133
Nos.

107
HCDS 107/107 107/107 87/90 87/88 87/87
Nos.

9
PRESENT STAFF STRENGTH
Staff strength planned : 53
Available : 47
S.NO DESIGNATION Plan Actual S.NO. DESIGNATION Plan Actual
. 14 Asst. Engineer-Piping 4 6
1 General Manager 0 1
15 Asst. Engineer- 5 5
2 Project Manager 1 1 QA/QC
3 Const. Manager 1 0 16 Asst. Safety Officer 3 2
4 Lead Engineer- 1 1
Planning 17 Draughtsman at HO 1 1

5 Lead Engineer-QA/QC 1 1 18 Welding Foreman 4 2


6 Lead Engineer-Piping 2 2 19 Rigging Foreman 3 2
7 Lead Engineer-Mech 2 2
Erection 20 Supervisor – piping 6 4

8 Lead Engineer- 2 2 21 Supervisor- Painting 2 2


Structure
22 Admin Officer 1 0
9 Lead Safety Officer 1 1

10 Material Manager 1 1 23 Accounts Officer 1 1

11 Asst. Engineer- 2 2 24 Asst. Admin 1 1


planning
12 Asst. Engineer-Mech 1 1 25 Storekeeper 2 2
Erection
26 Material Chaser/ 3 3
13 Asst. Engineer- 1 1 Store man
Structure
27 Time keeper 1 1
10
PRESENT WORKMEN STRENGTH
Workmen strength planned : 345
Available : 296
S.NO DESIGNATION Plan Actual
S.NO. DESIGNATION Plan Actual
1 CS WELDER ( TIG & 12 11
ARC) 15 GRINDER 15 12
2 SS / AS WELDER 1 1
16 ELECTRICIAN 6 6
3 TACK WELDERS 15 13
4 STRUCTURAL WELDER 1 1 17 DIESEL MECHANIC 1 1

5 FABRICATOR 12 11 18 BLAST CLEANER 4 3


6 PIPE FITTER 16 14
19 PAINTER 5 3
7 STRUCTURAL FITTER 3 3
20 HELPER/UNSKILLED 75 63
8 MILLWRIGHT FITTER 3 4

9 HYDRA OPERATOR 3 2 21 RADIOGRAPHER 2 2

10 CRANE OPERATOR 2 2 22 PWHT TECHNICIAN 6 6


11 TRACTOR / VAN 5 3
DRIVER 23 WATCHMAN 7 7

12 RIGGER/SCAFFOLDER 140 122

13 KHALASI 5 3

14 GASCUTTER 6 4
11
Action taken against previous MOM

S.NO Action by
Action taken against previous MOM

1 Bolt Tensioning agency reported at site Tech-Sharp

2 One additional Hydrotest Gang Mobilized Tech-Sharp

UIPL/IOCL reported bolts for 3 Nos. PSV mating flanges arrived at store
3 UIPL/IOCL
on 3/2/2014

Deduction against additional advance deferred for 2 months as


4 IOCL
agreed

12
AREAS OF CONCERN
• Few Free Issue materials are still not available with UIPL/IOCL

• Piping erection on Hold due to mismatch in PSV Flanges on structure E


( letter No. L-UIPL-01020 dated 17/12/2013)

• Road construction work denying access for crane movement for piping erection
on Structure F (see photograph)

• Cleaning of fire proofing materials from piperack/piping and equipment all over
DHDT, prior to painting (see photograph)

• Concrete pedestals for pipe supports throughout in DHDT are not in place.
Rectification works are still in progress holding up mechanical completion of
various hydro-test loops(see photograph)

• At some locations in DHDT, steam condensate manifolds and utility stations are
fouling with electrical installations like Cable trays, Lighting fixtures, junction
boxes etc. (see photograph)

• Pending payment of Rs.18.92 Lacs for extra claims for Additional works in Reactors
13
• Indecision on mode of payment for other agency’s work done by us for
installation of prefabricated Instrumentation hook up spools
14
15
16
17
18
PEDESTAL CONCRETING IN PROGRESS

19
PEDESTAL CONCRETING IN PROGRESS

21
JUNCTION BOX TO BE REMOVED

22
23
BILLING STATUS

a. Progress Billing : Rs. 25,27,61,582.00

b. Gross Billing : Rs. 32,99,24,642.00 (Including Advance)

c. Amount Received : Rs. 28,90,71,902.00 (including advance)

24
THANK YOU….