AL HENNA CONSTRUCTION COMPANY

DAILY ACTIVITY REPORT

DATE:
MONTH DAY YEAR
WEATHER
GOOD . HIGH .
SEPTEMBER 24 2022 BAD LOW
MANPOWER EQUIPMENTS
ENGINEER 7 EXCAVATOR 2
DRAFTSMAN 0 DUMPTRUCK 2
SURVEYOR 1 ROAD ROLLER 1
SUPERVISOR 1 GRADER 1
DOCUMENT CONTROLLER 1 LOADER (shovel) 3
SAFETY ENGINEER 1 BOBCAT 1
OPERATOR 3 WATER TANKER 1
CARPENTER 6 MINI HAND ROLLER 1
MASON 3 HAND COMPACTOR 3
GUARD 1
DRIVER 3
WELDER 0
PAINTER 0
LABOUR 2
GRAND TOTAL 29 15

ACTIVITY STATUS
1.Bldg 005 (B) Blinding area of concrete casting. FINISH
2. Bldg 031B excavation of foundation. ON GOING
3. Soil is backfilling and compaction in the old bldg no 4,5 &6. ON GOING
4. Soil is backfilling and compaction in the old bldg no 7,8 & 9. ON GOING
5. soil filtration work in progress. ON GOING
6. Hauling of soil inside of the site. ON GOING

REMARKS

prepared by; civil department


Al henna contracting company