Project Name : EPCC Contract for Processing of Sludge from WWTP in DCU at SR2 TOCO Reference No.

:T2102070100
Client : OQ Refinery Rev : 0
Location : Sohar DATE : 5 APRIL 2021

DIRECT MANPOWER DEPLOYMENT SCHEDULE

TOTAL
SR. DESCRIPTION PEAK MAN M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16
MONTHS
Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22

A DIRECT MANPOWER (TOCO) 1


1 EQUIPMENT WORKS 1
MECHANICAL FOREMAN 2 3 1 2
FITTERS 3 5 2 3
MILLWRIGHT FITTER 3 5 2 3
RIGGER 2 3 1 2
HELPER 2 4 2 2
EQUIPMENT OPERATOR 2 2 2

2 PIPING WORKS (FAB & ERECTION) 1


PIPING FOREMAN 3 15 1 1 2 3 3 2 1 1 1
TIG, 6G WELDER 3 16 1 2 2 3 3 2 1 1 1
SMAW, 6G WELDER 3 16 1 2 2 3 3 2 1 1 1
FITTER 5 24 1 2 3 5 5 4 2 1 1
FABRICATOR 2 13 1 1 2 2 2 2 1 1 1
GRINDER 2 12 1 1 2 2 2 2 1 1
HYDRO TEST TECH. 1 6 1 1 1 1 1 1
RIGGER 5 25 1 3 3 5 5 4 2 1 1
HELPER 4 21 1 3 3 4 4 3 2 1
HTV DRIVER 1 5 0 0 0 1 1 1 1
EQUIPMENT OPERATOR 5 14 1 1 1 1 1 5 3 1

2 ELECTRICAL & INSTRUMENTATION WORKS 1


E&I FOREMAN 2 10 1 2 2 2 2 1
ELECTRICAL TECHNICIAN 3 12 1 3 3 2 2 1
INSTRUMENT TECHNICIAN 3 12 1 3 3 2 2 1
CABLE TRAY FITTER 3 10 1 3 3 2 1
FABRICATOR 1 2 1 1
WELDER 1 2 1 1
HELPER 2 4 4 4 3 1
3 GENERAL DRIVERS & OPERATORS 1
LTV DRIVER 2 11 1 1 1 2 2 2 2
HTV DRIVER 1 7 1 1 1 1 1 1 1

TOTAL DIRECT MANPOWER (TOCO) 259 11 18 23 47 64 48 31 19 12


B SUBCONTRACTORS 1
1 SCAFFOLDING WORKS 1
FOREMAN SCAFFOLDING 2 11 1 1 2 2 2 2 1
SCAFFOLDER 8 50 6 6 8 8 8 8 6
2 PAINTING WORKS 1
FOREMAN PAINTING 1 2 1 1
PAINTER / BLASTER 4 8 4 4
1/2
Project Name : EPCC Contract for Processing of Sludge from WWTP in DCU at SR2 TOCO Reference No. :T2102070100
Client : OQ Refinery Rev : 0
Location : Sohar DATE : 5 APRIL 2021

DIRECT MANPOWER DEPLOYMENT SCHEDULE

TOTAL
SR. DESCRIPTION PEAK MAN M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16
MONTHS
Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22
3 CIVIL & STRUCURAL WORKS 1
FOREMAN CIVIL 2 6 2 2 2
STEEL FIXER 6 18 6 6 6
CARPENTER 4 12 4 4 4
FITTERS 8 8
MASON 8 24 8 8 8
HELPER 12 36 12 12 12
4 NDT 1
NDT TECHNICIAN 2 10 2 2 2 2 2

TOTAL DIRECT MANPOWER - SUBCONTRACTORS 177 32 40 47 9 12 12 12 17 12


1
TOTAL "A + B + C " = 436 - - - - - - 43 58 70 56 76 60 43 36 24 -