:T2102070100
Client : OQ Refinery Rev : 0
Location : Sohar DATE : 5 APRIL 2021
TOTAL
SR. DESCRIPTION PEAK MAN M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16
MONTHS
Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22
TOTAL
SR. DESCRIPTION PEAK MAN M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16
MONTHS
Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22 May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22
3 CIVIL & STRUCURAL WORKS 1
FOREMAN CIVIL 2 6 2 2 2
STEEL FIXER 6 18 6 6 6
CARPENTER 4 12 4 4 4
FITTERS 8 8
MASON 8 24 8 8 8
HELPER 12 36 12 12 12
4 NDT 1
NDT TECHNICIAN 2 10 2 2 2 2 2