You are on page 1of 63

Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu

Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:1-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 6,313.98 2,268.88 4,045.10 Brickwork & plaster 8
Brick (Nos) 91,602.97 186,000 31863.6 245,739.38 Rebar Manpower: 3
Coarse aggregate(m3) 4,140.83 191 3,949.44 Skilled 20
Sand(m3) 491.87 96.53 395.33 Unskilled -17
Rebar (Ton) Formwork 40
8mm 8 Skilled 20
10mm 265.82 Unkilled 20
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:1st-November-2022 Date:2nd-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line
Reinforcement work slab block A and beam block B fifth floor
Reinforcement work slab -A
30

Formwork beam slab -A 25.00 Formwork beam block A fifth floor


Curing and 1 Brickwork at ground floor and first floor

Sub-Total 56

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Rebar work in staircase
Concreting of column (Block A) and staircase (block B) 10

Curing and Housekeeping 3


Formwork installation in column of Block B
Rebar work in staircase (Block A) 2 Curing and housekeeping

Sub-Total 15
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:9-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 4,045.10 4,045.10 Brickwork & plaster 39
Brick (Nos) 245,739.38 43587 202,152.38 Rebar Manpower: 45
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 20
Sand(m3) 395.33 395.33 Unskilled 25
Rebar (Ton) Formwork 37
8mm 8 Skilled 20
10mm 265.82 Unkilled 17
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:1st-November-2022 Date:3rd-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Reinforcement work slab -A fifth floor Reinforcement work at fifth floor block A and B
35

Formwork beam slab -A fifth floor 25.00 Formwork beam block A


Curing and housekeeping 4 Brickwork at ground floor , first floor and second floor

Brickwork at ground floor , first floor and second floor


B/W: 5.3m3 24 Curing and housekeeping

Sub-Total 88

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Rebar work in staircase
Reinforcement of staircase Fourth floor to Fifth Floor 10

Curing and Housekeeping 3


Formwork installation in column of Block B
Formwork of Columns Fourth floor to Fifth 12 Curing and housekeeping

Brickwork at Ground and First floor . B/W:3.4m3 15

Sub-Total 40
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:3-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 4,033.50 125.45 3,908.05 Brickwork & plaster 39
Brick (Nos) 204,438.78 4437 200,001.78 Rebar Manpower: 45
Coarse aggregate(m3) 3,949.44 10 3,939.84 Skilled 20
Sand(m3) 395.33 4.84 390.49 Unskilled 25
Rebar (Ton) Formwork 37
8mm 8 Skilled 20
10mm 265.82 Unkilled 17
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:3-November-2022 Date:4th-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Reinforcement work slab -A fifth floor Reinforcement work at fifth floor block A and B
35

Formwork beam slab -A fifth floor 25.00 Formwork beam block A


Curing and housekeeping 4 Brickwork at ground floor , first floor and second floor

Brickwork at ground floor , first floor and second floor


B/W: 5.3m3 24 Curing and housekeeping

Sub-Total 88

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Rebar work in staircase
Reinforcement of staircase Fourth floor to Fifth Floor 10

Curing and Housekeeping 3


Formwork installation in column of Block B
Formwork of Columns Fourth floor to Fifth 12 Curing and housekeeping

Brickwork at Ground and First floor . B/W:3.4m3 15


Concreting of columns FF to top floor. M25:14m3 18

Sub-Total 58
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:4-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 3,908.05 1,329.01 2,579.04 Brickwork & plaster 39
Brick (Nos) 200,001.78 4437 195,564.78 Rebar Manpower: 45
Coarse aggregate(m3) 3,939.84 111 3,828.70 Skilled 20
Sand(m3) 390.49 56.05 334.44 Unskilled 25
Rebar (Ton) Formwork 37
8mm 8 Skilled 20
10mm 265.82 Unkilled 17
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:4-November-2022 Date:5th-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Reinforcement work slab -B fifth floor Reinforcement work at fifth floor block A and B
35

Formwork beam slab -A fifth floor and B 25.00 Formwork beam block A
Curing and housekeeping 4 Brickwork at ground floor , first floor and second floor

Brickwork at ground floor , first floor and second floor


B/W: 5.3m3 24 Curing and housekeeping

Concreting of Fifth Floor slab block A. M25:155m3 18.00

Sub-Total 106

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Rebar work in staircase
Reinforcement of staircase Fourth floor to Fifth Floor 10

Curing and Housekeeping 3


Formwork installation in column of Block B
Formwork of Columns Fourth floor to Fifth 12 Curing and housekeeping

Brickwork at Ground and First floor . B/W:3.4m3 15


Concreting of staircase FF to top floor. M25:7m3 18

Sub-Total 58
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:5-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 2,579.04 2,579.04 Brickwork & plaster 0
Brick (Nos) 195,564.78 195,564.78 Rebar Manpower: 40
Coarse aggregate(m3) 3,828.70 3,828.70 Skilled 20
Sand(m3) 334.44 334.44 Unskilled 20
Rebar (Ton) Formwork 47
8mm 8 Skilled 20
10mm 265.82 Unkilled 27
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:5-November-2022 Date:6th-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Reinforcement work slab -B fifth floor Reinforcement work at fifth floor block A and B
32

Formwork beam slab fifth floor block B 25.00 Formwork beam block A
Curing and housekeeping 4 Brickwork at ground floor , first floor and second floor

Brickwork on hold
Curing and housekeeping

Sub-Total 61

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Rebar work in staircase
Reinforcement of staircase Fourth floor to Fifth Floor 8

Curing and Housekeeping 3


Formwork installation in column of Block B
Formwork of Columns Fourth floor to Fifth 22 Curing and housekeeping

Brickwork on hold

Sub-Total 33
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:6-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 2,579.04 8.93 2,570.11 Brickwork & plaster 39
Brick (Nos) 195,564.78 3417 192,147.78 Rebar Manpower: 40
Coarse aggregate(m3) 3,828.70 3,828.70 Skilled 20
Sand(m3) 334.44 334.44 Unskilled 20
Rebar (Ton) Formwork 47
8mm 8 Skilled 20
10mm 265.82 Unkilled 27
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:6-November-2022 Date:7th-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Reinforcement work beam and slab -B fifth floor Reinforcement work at fifth floor block A and B
32

Formwork beam slab fifth floor block B 25.00 Formwork beam block A
Curing and housekeeping 4 Brickwork at ground floor , first floor and second floor

Brickwork at ground floor , first floor and second floor


B/W: 3.3m3 24 Curing and housekeeping

Sub-Total 85

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Rebar work in staircase
Reinforcement of staircase Fourth floor to Fifth Floor 8

Curing and Housekeeping 3


Formwork installation in column of Block B
Formwork of Columns Fourth floor to Fifth 22 Curing and housekeeping

Brickwork at Ground and First floor . B/W:3.4m3 15

Sub-Total 48
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:7-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 2,570.11 12.93 2,557.18 Brickwork & plaster 39
Brick (Nos) 192,147.78 4947 187,200.78 Rebar Manpower: 40
Coarse aggregate(m3) 3,828.70 3,828.70 Skilled 20
Sand(m3) 334.44 334.44 Unskilled 20
Rebar (Ton) Formwork 47
8mm 8 Skilled 20
10mm 265.82 Unkilled 27
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:7-November-2022 Date:8th-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Reinforcement work beam and slab -B fifth floor Reinforcement work at fifth floor block A and B
32

Formwork beam slab fifth floor block B 25.00 Formwork beam block A
Curing and housekeeping 4 Brickwork at ground floor , first floor and second floor

Brickwork at ground floor , first floor and second floor


B/W: 5.3m3 24 Curing and housekeeping

Sub-Total 85

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Rebar work in staircase
Reinforcement of staircase Fourth floor to Fifth Floor 8

Curing and Housekeeping 3


Formwork installation in column of Block B
Formwork of Columns Fourth floor to Fifth 22 Curing and housekeeping

Brickwork at Ground and First floor . B/W:4.4m3 15

Sub-Total 48
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:8-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 2,570.11 1,490.00 11.60 4,048.51 Brickwork & plaster 39
Brick (Nos) 192,147.78 10,000 4437 197,710.78 Rebar Manpower: 40
Coarse aggregate(m3) 3,828.70 3,828.70 Skilled 20
Sand(m3) 334.44 334.44 Unskilled 20
Rebar (Ton) Formwork 47
8mm 8 Skilled 20
10mm 265.82 Unkilled 27
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:8-November-2022 Date:9th-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Reinforcement work beam and slab -B fifth floor Reinforcement work at fifth floor block A and B
32

Formwork beam slab fifth floor block B 25.00 Formwork beam block A
Curing and housekeeping 4 Brickwork at ground floor , first floor and second floor

Brickwork at ground floor , first floor and second floor


B/W: 3.4m3 24 Curing and housekeeping

Sub-Total 85

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Rebar work in staircase
Reinforcement of staircase Fourth floor to Fifth Floor 8

Curing and Housekeeping 3


Formwork installation in column of Block B
Formwork of Columns Fourth floor to Fifth 22 Curing and housekeeping

Brickwork at Ground and First floor . B/W:5.3m3 15

Sub-Total 48
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:9-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit
Er. Pabitra Basnet.

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 4,048.51 14.26 4,034.25 Brickwork & plaster 39
Brick (Nos) 197,710.78 12,000 5457 204,253.78 Rebar Manpower: 34
Coarse aggregate(m3) 3,828.70 3,828.70 Skilled 20
Sand(m3) 334.44 334.44 Unskilled 14
Rebar (Ton) Formwork 44
8mm 8 Skilled 20
10mm 265.82 Unkilled 24
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:9-November-2022 Date:10th-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Reinforcement work beam and slab -B fifth floor


10

Formwork beam slab fifth floor block B 22.00 Formwork beam and slab block B
Curing and housekeeping 4 Brickwork at ground floor , first floor and second floor

Brickwork at ground floor , first floor and second floor


B/W: 6.4m3 24 Curing and housekeeping
Laying of electrical conduit at Block B fifth floor beam and
Concreting of Block B beam and slab Fifth floor.
slab. 6.00

Sub-Total 66

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Rebar work in beam fifth floor
Reinforcement of beam and slab block /A fifth floor . 24

Curing and Housekeeping 3


Formwork installation in column of Block B
Formwork of Columns Fourth floor to Fifth 22 Curing and housekeeping

Brickwork at Ground and First floor . B/W:4.3m3 15

Sub-Total 64
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:10-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 4,045.10 740.03 3,305.07 Brickwork & plaster 39
Brick (Nos) 202,152.38 4859.7 197,292.68 Rebar Manpower: 28
Coarse aggregate(m3) 3,949.44 62 3,887.01 Skilled 20
Sand(m3) 395.33 31.49 363.85 Unskilled 8
Rebar (Ton) Formwork 16
8mm 8 Skilled 20
10mm 265.82 Unkilled -4
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:10-November-2022 Date:11th-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Reinforcement work beam and slab Reinforcement work at fifth floor block A and B
4

Formwork beam slab fifth floor 4.00 Formwork beam block A


Curing and housekeeping 4 Brickwork at ground floor , first floor and second floor

Brickwork at ground floor , first floor and second floor


B/W: 5.3m3 24 Curing and housekeeping
PCC and concreting of boundary wall column pads.
Concreting of fifth floor slab Block B M25:91m3 18.00

Sub-Total 54

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement of staircase Fourth floor to Fifth Floor and Fifth Rebar work in staircase and fifth floor beam and slab.
24
floor beam .
Curing and Housekeeping 3
Formwork installation in column of Block B
Formwork of Columns Fourth floor to Fifth 12 Curing and housekeeping

Brickwork at Ground and First floor . B/W:4.4m3 15

Sub-Total 54
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:11-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 3,305.07 13.86 3,291.21 Brickwork & plaster 39
Brick (Nos) 197,292.68 5304 191,988.68 Rebar Manpower: 28
Coarse aggregate(m3) 3,887.01 3,887.01 Skilled 20
Sand(m3) 363.85 363.85 Unskilled 8
Rebar (Ton) Formwork 16
8mm 8 Skilled 20
10mm 265.82 Unkilled -4
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:11-November-2022 Date:11th-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Reinforcement work beam and slab Reinforcement work at fifth floor block A and B
4

Formwork beam slab fifth floor 4.00 Formwork beam block A


Curing and housekeeping 4 Brickwork at ground floor , first floor and second floor

Brickwork at ground floor , first floor and second floor


B/W: 5.3m3 24 Curing and housekeeping
PCC and concreting of boundary wall column pads.
Concreting of fifth floor slab Block B M25:91m3 18.00

Sub-Total 54

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement of staircase Fourth floor to Fifth Floor and Fifth Rebar work in staircase and fifth floor beam and slab.
24
floor beam .
Curing and Housekeeping 3
Formwork installation in column of Block B
Formwork of Columns Fourth floor to Fifth 12 Curing and housekeeping
Grid:- F5 to G5,F7 to
G7,F10 to G10,F11 to
Brickwork at Ground and First floor . B/W:4.4m3 15 G11,F12 to G12,F13 to
G13

Sub-Total 54
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:12-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 2,387.00 7.90 2,379.10 Brickwork & plaster 31
Brick (Nos) 202,152.38 12,000 3024.3 211,128.08 Rebar Manpower: 32
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 28
Rebar (Ton) - Formwork 30
8mm 8 Skilled 4
10mm 265.82 Unkilled 26
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:12-November-2022 Date:13th-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Formwork and Deshuttering at third and fourth floor slab. Brickwork at first , second and third floor
8

Curing and housekeeping 3.00 Curing and housekeeping


Scaffolding around the Jco line buildings 4 Formwork and Deshuttering at third and fourth floor slab.
Grid:-1-2(E-E),1-2(F-F),1
Brickwork at first floor and second floor
B/W: 1.547m 19 Scaffolding around the Jco line buildings

Sub-Total 34

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Formwork installation for slab,column and Staircase of 5th Rebar work in staircase and fifth floor beam and slab.
22
floor
Rebar work in beam and column of 5th floor 32
Formwork installation in column of Block B
Curing and housekeeping at basement,fifth floor. 3 Curing and housekeeping
Grid:- 7(F-G),10(F-
B/ G),11(F-G)
Brickwork at Second floor W:4.38m3 12 Brickwork at Second floor

Sub-Total 69
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:11-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 2,387.00 7.90 2,379.10 Brickwork & plaster 39
Brick (Nos) 202,152.38 3024.3 199,128.08 Rebar Manpower: 28
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 20
Sand(m3) 395.33 395.33 Unskilled 8
Rebar (Ton) Formwork 16
8mm 8 Skilled 20
10mm 265.82 Unkilled -4
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:11-November-2022 Date:11th-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Reinforcement work beam and slab Reinforcement work at fifth floor block A and B
4

Formwork beam slab fifth floor 4.00 Formwork beam block A


Curing and housekeeping 4 Brickwork at ground floor , first floor and second floor

Brickwork at ground floor , first floor and second floor


B/W: 5.3m3 24 Curing and housekeeping
PCC and concreting of boundary wall column pads.
Concreting of fifth floor slab Block B M25:91m3 18.00

Sub-Total 54

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement of staircase Fourth floor to Fifth Floor and Fifth Rebar work in staircase and fifth floor beam and slab.
24
floor beam .
Curing and Housekeeping 3
Formwork installation in column of Block B
Formwork of Columns Fourth floor to Fifth 12 Curing and housekeeping

Brickwork at Ground and First floor . B/W:4.4m3 15

Sub-Total 54
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:13-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 2,379.10 14.54 2,364.56 Brickwork & plaster 39
Brick (Nos) 211,128.08 5564.1 205,563.98 Rebar Manpower: 32
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 28
Rebar (Ton) Formwork 30
8mm 8 Skilled 4
10mm 265.82 Unkilled 26
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:13-November-2022 Date:14th-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Formwork and Deshuttering at third floor Brickwork at ground floor , first floor and second floor
8

Scaffolding around the Jco line buildings 4.00 Curing and housekeeping at basement
Curing and housekeeping at basement and 3rd floor 4
Grid:-2-3(G-G),12-14(G-G)
Brickwork at ground floor
B/W: 3.62m3 24

Sub-Total 40

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Rebar work in staircase and fifth floor beam and slab.
Rebar work in beam and column 32

Curing and Housekeeping at basement 3


Formwork installation in column of Block B

Formwork installation for slab,beam,projection and column


12 Curing and housekeeping
Grid:-F4 to G4,F3 to
B/W:7.29 G3,F2 to G2 (2nd floor)
Brickwork at 1st Ground and 2nd floor . M3 15 (1st floor):- F7 to F9,F5 to Brickwork at 1st Ground and 2nd floor .
F7,F2 to F3

Sub-Total 62
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:14-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 2,379.10 14.54 2,364.56 Brickwork & plaster 37
Brick (Nos) 205,563.98 5048.49 200,515.49 Rebar Manpower: 24
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 20
Rebar (Ton) Formwork 15
8mm 8 Skilled 3
10mm 265.82 Unkilled 12
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:14-November-2022 Date:15th-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing and housekeeping at basement Brickwork at ground floor , first floor and second floor
4

Formwork deshuttering 2.00 Curing and housekeeping at basement


Boundary wall B/W: 1.23m3 3
Grid:-4-5(F-F),3-3(E-F),5-
Brick work at Ground floor
B/W: 3.838m 24

Sub-Total 33

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Rebar work in staircase and fifth floor beam and slab.
Rebar work in column,staircase,slab of 5th floor (block A) 24

Formwork installation for slab,beam and column of 5th floor


15
(block B) Formwork installation in column of Block B

Concreting of staircase of 5th floor (block B)


M25:6.5m3 8 Curing and housekeeping

Curing,Housekeeping and cleaning of slab 6 Brickwork at 1st Ground and 2nd floor .
Grid:-F14 to G14,F13 to F14,F12
B/W:4.831 to F13,F11 to F12,F10 to F11,F7
to F9
Brickwork at 2nd floor M3 10

Sub-Total 63
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:15-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 2,379.10 14.54 2,364.56 Brickwork & plaster 34
Brick (Nos) 200,515.49 5564.1 194,951.39 Rebar Manpower: 24
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 20
Rebar (Ton) Formwork 15
8mm 8 Skilled 3
10mm 265.82 Unkilled 12
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:15-November-2022 Date:16-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing and housekeeping at basement Brickwork at ground floor , first floor and second floor
4

Formwork deshuttering 2.00 Curing and housekeeping at basement


Brickwork at first floor and Ground floor Grid:-13-14/G-F
B/W: 5.509m (Ground floor), 1st floor E(1-2),5-9(G-G),10-11(G-G),12-14(G-G)
24

Sub-Total 30

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase
reinforcement wok in staircase ,slab (5th floor),block A 24

Formwork installation of beam,column,slab and staircase of


16
5th floor block B Formwork of beam slab,projection block B

Curing,housekeeping 6 Curing and housekeeping


Grid:-F5 to F7,F4 to
F5,F3 to F4,F2 to F3,F1 to
Brickwork at 2nd floor B/W: 6.546m 10.00 F2, G11 to G12,G10 to Brickwork at 1st Ground and 2nd floor .
G11, G7 to G9

Sub-Total 56
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:16-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 2,364.56 9.59 2,354.98 Brickwork & plaster 30
Brick (Nos) 193,563.98 6,000 3667.41 195,896.57 Rebar Manpower: 24
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 20
Rebar (Ton) Formwork 15
8mm 8 Skilled 3
10mm 265.82 Unkilled 12
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:16-November-2022 Date:17-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing and housekeeping at basement Brickwork at ground floor , first floor and second floor
4

Formwork deshuttering 2.00 Curing and housekeeping at basement


Brickwork at first floor and Ground floor B/W: 2.981m 10 Grid:-1-3/G-G (Projection)

Sub-Total 16

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase
Rebar work in slab,beam,staircase and column 24

Formwork installation around beam of 5th floor 16


Formwork of beam slab,projection block B

Curing,housekeeping and cleaning of slab 8 Curing and housekeeping


Grid:-F5 to F7,F4 to F5

Brickwork at 2nd floor B/W: 4.21m3 20.00 Brickwork at 1st Ground and 2nd floor .

Concreting of fifth floor slab Block A

Sub-Total 68
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:17-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 2,354.98 14.30 2,340.68 Brickwork & plaster 30
Brick (Nos) 189,896.57 6,000 5477 190,419.57 Rebar Manpower: 24
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 20
Rebar (Ton) Formwork 18
8mm 8 Skilled 3
10mm 265.82 Unkilled 15
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:17-November-2022 Date:18-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing and housekeeping at basement Brickwork at ground floor , first floor and second floor
4

Formwork deshuttering 2.00 Curing and housekeeping at basement


Brickwork at first floor and Ground floor B/W: 7.24m3 10

Sub-Total 16

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase
Rebar work in slab,beam,staircase and column 24

Formwork installation around beam of 5th floor 16


Formwork of beam slab,projection block B

Curing,housekeeping and cleaning of slab 8 Curing and housekeeping


Grid:- 1 (D-G),1-2(E-
E),2(D-E)
Brickwork at 2nd floor B/W:3.5 m3 20.00 Brickwork at 1st Ground and 2nd floor .

Concreting of fifth floor slab Block A

Sub-Total 68
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:18-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 2,340.68 1,258.23 1,082.45 Brickwork & plaster 30
Brick (Nos) 189,896.57 6,000 5361.12 190,535.45 Rebar Manpower: 25
Coarse aggregate(m3) 3,949.44 105 3,844.48 Skilled 4
Sand(m3) 395.33 52.93 342.40 Unskilled 21
Rebar (Ton) Formwork 8
8mm 8 Skilled 2
10mm 265.82 Unkilled 6
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:18-November-2022 Date:19-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing and housekeeping at basement Brickwork at ground floor , first floor and second floor
4

Formwork deshuttering 2.00 Curing and housekeeping at basement


Brickwork at first floor and Ground floor 5.012 cum 10

Sub-Total 16

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase,block B
Concreting of slab 5th floor block A 18
149 cum
Reinforcement work in beam,staircase coumn of 5th floor
25
block B Formwork of beam slab,projection block B

Formwork instillation of butchers shop 6 Curing and housekeeping

Curing,ponding,housekeeping 10.00 Brickwork at 1st Ground and 2nd floor .


2/Toilet/D-E,3-4-
Brickwork at 1st and 2nd floor 5.5 cum 20 5 / F-G

Sub-Total 79
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:19-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 1,082.45 12.25 1,070.20 Brickwork & plaster 32
Brick (Nos) 190,565.45 10,000 4699.65 195,865.80 Rebar Manpower: 20
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 16
Rebar (Ton) Formwork 15
8mm 8 Skilled 3
10mm 265.82 Unkilled 12
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:19-November-2022 Date:20-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing and housekeeping at basement Brickwork at ground floor , first floor and second floor
4

Formwork deshuttering 2.00 Curing and housekeeping at basement


Brickwork at first floor and Ground floor 5.203 cum 17 Reinforcement work of column top floor up to 1.8m

Carporch formwork

Sub-Total 23

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase,block B
Formwork of beam,slab,staircase top floor block B 13

Reinforcement work of slab,beam top floor slab,block B 20


Formwork of beam slab,projection block B

Curing and housekeeping 8 Curing and housekeeping

Brickwork in 1st and second floor 4.012cum 15.00 Brickwork at 1st Ground and 2nd floor .

Sub-Total 56
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:20-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 1,070.20 1,070.20 Brickwork & plaster 30
Brick (Nos) 189,896.57 189,896.57 Rebar Manpower: 24
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 20
Rebar (Ton) Formwork 15
8mm 8 Skilled 3
10mm 265.82 Unkilled 12
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:20-November-2022 Date:21-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Brickwork at ground floor , first floor and second floor

Curing and housekeeping at basement


Reinforcement work of column top floor up to 1.8m
Parliamentary Election Holiday

Carporch formwork

Sub-Total

Site Engineer
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase,block B

Formwork of beam slab,projection block B

Parliamentary Election Holiday Curing and housekeeping

Brickwork at 1st Ground and 2nd floor .

Sub-Total
Site Engineer
Sub-Engineer

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:21-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 1,070.20 15.52 1,054.68 Brickwork & plaster 30
Brick (Nos) 189,896.57 16,000 5951.7 199,944.87 Rebar Manpower: 24
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 20
Rebar (Ton) Formwork 15
8mm 8 Skilled 3
10mm 265.82 Unkilled 12
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:21-November-2022 Date:22-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing and housekeeping at basement Brickwork at ground floor , first floor and second floor
4

Formwork deshuttering 2.00 Curing and housekeeping at basement


Brickwork at first floor and Ground floor 6.31 cum 17 Reinforcement work of column top floor up to 1.8m

Carporch formwork

Sub-Total 23

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase,block B
Formwork installation in butcher area 13

Rebar work for beam,slab, and column 24


Formwork of beam slab,projection block B

Curing, housekeeping and cleaning of slab 7 Grid:- 10/C- Curing and housekeeping
D,10/D-E, 10/C-D,
Ponding 2.00 10/D-E, 5/C-D, 11- Brickwork at 1st Ground and 2nd floor .
12/F-F, 11-12/F-F,
10-11/F-F,7-9/F-F,
Brickwork in 1st, Ground and second floor 5.36 cum 13 13/D-E

Sub-Total 59
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:22-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 1,054.68 10.99 1,043.69 Brickwork & plaster 30
Brick (Nos) 199,944.87 2,000 4217.19 197,727.68 Rebar Manpower: 24
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 20
Rebar (Ton) Formwork 19
8mm 8 Skilled 4
10mm 265.82 Unkilled 15
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:22-November-2022 Date:23-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing and housekeeping at basement Brickwork at ground floor , first floor and second floor
4

Formwork deshuttering 2.00 Curing and housekeeping at basement


Brickwork at first floor and Ground floor 3.44cum 15 Reinforcement work of column top floor up to 1.8m

Sub-Total 21

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase,block B
Formwork installation in staircase and slab of 5th floor 19

Rebar work for beam,slab, and column 24


Formwork of beam slab,projection block B

Curing, housekeeping and cleaning of slab of 3rd floor 8 Curing and housekeeping

Grid:-12-14(G-G) Brickwork at 1st Ground and 2nd floor .


outside,7-9(F-F),11-
12(G-G),10-11(G-
Brickwork at ground floor 4.829cum 15 G),1-2(F-F)

Sub-Total 66
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:23-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 1,043.69 11.94 1,031.75 Brickwork & plaster 30
Brick (Nos) 197,727.68 4579.8 193,147.88 Rebar Manpower: 15
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 3
Sand(m3) 395.33 395.33 Unskilled 12
Rebar (Ton) Formwork 15
8mm 8 Skilled 3
10mm 265.82 Unkilled 12
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:23-November-2022 Date:24-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing of brick wall and housekeeping at basement Brickwork at ground floor , first floor and second floor
2

Formwork deshuttering 2.00 Curing and housekeeping at basement


Brickwork at ground floor partation wall 3.89cum 16 Reinforcement
Grid:-11-13(D-E) partation wall work of column top floor up to 1.8m

Sub-Total 20

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase,block B
Formwork installation in staircase and slab of 5th floor 15

Rebar work for beam,slab, and column 15


Formwork of beam slab,projection block B
Curing of brick wall, housekeeping and cleaning of slab of 3rd
floor 3 Curing and housekeeping
Grid:- 1-3 (G-
G)outside,13(D-E),13(F-
Brickwork at ground floor 5.09cum 14 G),4(C-D),5(D-E) Brickwork at 1st Ground and 2nd floor .

Sub-Total 47
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:24-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 1,031.75 10.34 1,021.41 Brickwork & plaster 32
Brick (Nos) 193,147.88 5273.4 187,874.48 Rebar Manpower: 24
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 20
Rebar (Ton) Formwork 19
8mm 8 Skilled 4
10mm 265.82 Unkilled 15
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:24-November-2022 Date:25-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing of brick wall and housekeeping at basement Brickwork at ground floor , first floor and second floor
2

Formwork deshuttering 2.00 Curing of brick wall and housekeeping at basement


Brickwork at ground floor and 1st floor 3.55cum 22

Sub-Total 26

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase,block B
Formwork installation in staircase and slab of 5th floor 19

Rebar work for beam,slab,columnand projection 24


Formwork of beam slab,projection block B
Curing of brick wall, housekeeping and cleaning of slab of 3rd
floor 8 Curing of brick wall and housekeeping
Grid:-2(D-E),2 Toilet
partation,2-3(D-D),
Brickwork at ground floor 4.23cum 10 3Toilet partation Brickwork at 1st Ground and 2nd floor .

Sub-Total 61
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:25-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 1,021.41 10.34 1,011.07 Brickwork & plaster 32
Brick (Nos) 193,147.88 5273.4 187,874.48 Rebar Manpower: 24
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 20
Rebar (Ton) Formwork 7
8mm 8 Skilled 1
10mm 265.82 Unkilled 6
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:25-November-2022 Date:26-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing of brick wall and housekeeping at basement Brickwork at ground floor , first floor and second floor
2

Formwork deshuttering 2.00 Curing of brick wall and housekeeping at basement


Brickwork at ground floor and 1st floor 3.73cum 22
Formwork of carpoach
5

Sub-Total 31

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase,block B
Formwork installation in staircase and slab of 5th floor 19

Rebar work for beam,slab,columnand projection 24


Formwork of beam slab,projection block B
Curing of brick wall, housekeeping and cleaning of slab of 3rd
floor 8 Curing of brick wall and housekeeping
Grid:-2(D-E),2 Toilet
partation,2-3(D-D),
Brickwork at ground floor 4.23cum 10 3Toilet partation Brickwork at 1st Ground and 2nd floor .

Sub-Total 61
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:26-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 1,011.07 10.34 1,000.73 Brickwork & plaster 32
Brick (Nos) 193,147.88 5273.4 187,874.48 Rebar Manpower: 24
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 20
Rebar (Ton) Formwork 7
8mm 8 Skilled 1
10mm 265.82 Unkilled 6
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:26-November-2022 Date:27-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing of brick wall and housekeeping at basement Brickwork at ground floor , first floor and second floor
2

Formwork deshuttering 2.00 Curing of brick wall and housekeeping at basement


Brickwork at ground floor and 1st floor 5.35 cum 16
Formwork of carpoach
5

Sub-Total 25

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase,block B
Formwork installation in staircase and slab of 5th floor 19

Rebar work for beam,slab,columnand projection 24


Formwork of beam slab,projection block B
Curing of brick wall, housekeeping and cleaning of slab of 3rd
floor 8 Curing of brick wall and housekeeping

Brickwork at ground floor 4.75 cum 13 Brickwork at 1st Ground and 2nd floor .

Sub-Total 64
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:27-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 1,000.73 9.77 990.96 Brickwork & plaster 28
Brick (Nos) 187,874.48 8,000 3748.5 192,125.98 Rebar Manpower: 24
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 4
Sand(m3) 395.33 395.33 Unskilled 20
Rebar (Ton) Formwork 2
8mm 8 Skilled
10mm 265.82 Unkilled 2
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:27-November-2022 Date:28-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing of brick wall and housekeeping at basement Brickwork at ground floor , first floor and second floor
2

Formwork deshuttering 2.00 Curing of brick wall and housekeeping at basement


Brickwork at ground floor and 1st floor 6.3 cum 17 Concreting of Emergency staircase footing

Sub-Total 21

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase,block B
Formwork installation in staircase and slab of 5th floor 19

Rebar work for beam,slab,columnand projection 24


Formwork of beam slab,projection block B
Curing of brick wall, housekeeping and cleaning of slab of 3rd
floor 8 Curing of brick wall and housekeeping

Brickwork at ground floor 2.5 cum 11 Brickwork at 1st Ground and 2nd floor .

Concreting of slab 5th floor block B

Sub-Total 62
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:28-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 990.96 9.68 981.28 Brickwork & plaster 28
Brick (Nos) 192,125.98 7,000 3712.8 195,413.18 Rebar Manpower:
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled

Sand(m3) 395.33 395.33 Unskilled


Rebar (Ton) Formwork 2
8mm 8 Skilled
10mm 265.82 Unkilled 2
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:28-November-2022 Date:29-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing of brick wall and housekeeping at basement Brickwork at ground floor , first floor and second floor
2

Formwork deshuttering 2.00 Curing of brick wall and housekeeping at basement


Brickwork at ground floor and 1st floor 5.5cum 17

Concreting of footing jco line Emergency staircase 12cum 5.00

Sub-Total 26

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase,block B
Concreting of slab 5th floor block B 16
97cum
2
Curing of brick wall, housekeeping Formwork of beam slab,projection block B

Brickwork at ground floor and 1st floor 7 cum 11 Curing of brick wall and housekeeping

Projection of 1st floor and column 5.00 Brickwork at 1st Ground and 2nd floor .

Sub-Total 34
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:29-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 990.96 9.68 981.28 Brickwork & plaster 26
Brick (Nos) 192,125.98 7,000 3712.8 195,413.18 Rebar Manpower: 7
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 2
Sand(m3) 395.33 395.33 Unskilled 5
Rebar (Ton) Formwork 2
8mm 8 Skilled
10mm 265.82 Unkilled 2
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:29-November-2022 Date:30-November-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing of brick wall and housekeeping at basement Brickwork at ground floor , first floor and second floor
2

Formwork deshuttering 2.00 Curing of brick wall and housekeeping at basement


Brickwork at ground floor and 1st floor 6 cum 15 Reinforcement work in carpoach

Boundary wall
4 Footing work

Reinforcement work in carpoach 3.00

Sub-Total 26

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase,block B
Rebar work in column and staircase 4

Ponding in 5th floor slab (Block B) 2


Formwork of beam slab,projection block B
Curing of brick wall, housekeeping and cleaning of slab of 3rd
floor 8 Curing of brick wall and housekeeping

Brickwork at ground floor and 1st floor 3.5cum 11 Brickwork at 1st Ground and 2nd floor .

Sub-Total 25
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report


Date:30-November-2022 Weather: sunny.
Equipments / Staffs / Material Details
Equipment No. Condition Remarks Supervisory Staffs No. Remarks
Contractor's
Total Station 1
1 working Representative.
Level Machine 2 working Site Engineer 3
Excavator 1 working Site Manager 1
Generator 1 working Sub Engineer 3
Loader 1 working Billing Engineer 1
Rebar cutting machine 2 working BBS Expert 1
Rebar draw machine 2 working Store Assistant 1
Pump 3 working Supervisors 3
Water tank 1 working Surveyors 1
Tipper 1 working QC/ Lab Technician 1
Transit mixture 2 working Safety Officer 1
Batching plant 1 working Electrician 1
boom pump 1 working
Service vehicle 1 working
Drilling Machine 6 working
Problems Encountered Client Site Visit

Materials Stock Delivered Consume Net Stock Labours No. Remarks


Cement (bag) 990.96 590.00 12.63 1,568.33 Brickwork & plaster 26
Brick (Nos) 195,413.18 4845 190,568.18 Rebar Manpower: 8
Coarse aggregate(m3) 3,949.44 3,949.44 Skilled 3
Sand(m3) 395.33 395.33 Unskilled 5
Rebar (Ton) Formwork 2
8mm 8 Skilled
10mm 265.82 Unkilled 2
12mm 30 General -skilled 7
16mm 118.1 General- unskilled 19
20mm 58.5
25mm 98.24
28mm 65 Safety /Sanitation Report
Total 643.66 - 643.66 No any accident occurred at site
Crusher run Gravel(m3) 10.00 10.00
CGI sheet 112.00 112.00
MS Pipe (Pcs) 600.00 0 600.00
Bentonite 19.00 19.00
Ply wood(4'*8') 690.00 690.00

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
Construction of Building for Chandidal Gad at Singhadurbar, Kathmandu
Contract ID: DUDBC/SBC/WORKS/NCB/02/078-79

Daily Site Report

Schedule Programme for Date:


Date:30-November-2022 Date:1-December-2022
Activities of works Quantity Worker Remarks Schedule Programme for Date:
Jawan Line,JCO line Jawan Line,JCO line

Curing of brick wall and housekeeping at basement Brickwork at ground floor , first floor and second floor
2

Formwork deshuttering 2.00 Curing of brick wall and housekeeping at basement


Brickwork at ground floor and 1st floor 4.5cum 15
Boundary wall Excavation
1

Reinforcement work in carpoach 3.00

Sub-Total 23

Site Engineer 1
Sub-Engineer
JAWAN LINE WITH CENTRAL MESS CJAWAN LINE WITH CENTRAL MESS
Reinforcement work of slab,beam,staircase,block B
Soling work for Water tank 3

Rebar work in column 5


Formwork of beam slab,projection block B
Curing of brick wall, housekeeping and cleaning of slab of 3rd
floor 8 Curing of brick wall and housekeeping

Brickwork at ground floor and 1st floor 5 cum 11 Brickwork at 1st Ground and 2nd floor .

Sub-Total 27
Site Engineer 1
Sub-Engineer 1

Prepared by: Bikram Shrestha Verified by:Santosh Dhital.

Position: Civil Engineer Position:Civil Engineer

Signature....................... Signature....................

TUNDI-RASUWA-BKOI JV Employer:DUDBC
SUMMARY OF MONTH NOVEMBER

S.N PARTICULARS TOTAL QUANTITY UNIT


CONCRETE
M25 542.64 CUM
1 M20 CUM
-
M15 - CUM

2 Brick
260.38 CUM

You might also like