Sulut-3 Coal Fired Steam Power Plant (2x50MW)

SITE CONSTRUCTION DAILY REPORT (2018-10-10)


Weather :Clear  Cloudy □ Overcast□ Rainy□ Heavy Rain□ Temperature:26-34℃
Accumalative Tomorrow
Today Work Today Work Today Work Accumulative
No. Project Name Total Quantity Compelete Work Remark
Items Planing Actual Completion
Percentation Planning
1. Site Construction

1.1 Excavation 780,000 m3 Continue Excavation 10,000 m3 13,000 m3 306,910 m3 39.3% 10,000 m3

1.2 Backfill

1.2.1 Coal Yard Backfill 100,000 m3 Continue Backfill 5,000 m3 5,000 m3 16,300 m3 16.3% 5,000 m3

1.3 Drilling Holes

SK 04 (Offshore) Continue Drilling 15 m 13 m 55,5 m Finished

SK 17 (Offshore) Continue Drilling 20 m 16 m 45 m 10 m

2. Configure Equipment

Equipment name and code Today Equip the Equipment Unit Tomorrow Equip the Equipment Remark

2.1 Excavation
ACT 320 Excavator 4 Unit 4 1 Unit ACT 320 is in Maintenance
1 Unit 330 Kobelco Excavator is in
330 Kobelco Excavator 3 Unit 4 Maintenance,1 Unit 330 Kobelco
Arrived at Site
330 Hitachi Excavator 1 Unit 1
Volvo 220 Excavator 1 Unit 1
Hitachi 210 Excavator 2 Unit 2
Sany SY365-H Excavator 1 Unit 1
Dump Truck 26 Unit 26
Komatsu PC200 Excavator 2 Unit 2
D-85-SS Dozer 2 Unit 2
2 Unit D-65-PX Dozer is in
D65PX Dozer 3 Unit 3
Maintenance
Water Truck 1 Unit 1
Roller 2 Unit 2
2.2 Drilling Holes
Drilling Machine 2 unit 2
3. Manpower

Division Today Total Person Unit Tomorrow Planning Remark

3.1 Management 30 Person 30


3.2 Local Staff Workers 11 Person 11
3.3 Subcontractor
Excavation and Backfill 79 Person 80
Drilling Holes 13 Person 13