Daily Progress Report - Tech Tower-2 Date: 02.02.

2023

Name of the contractor - GMS Elegant Man Power


Sr.No Total Remarks
builders I Pvt Ltd Today Yesterday

1 Mason 5 3 8

2 Unskilled(MM) 23 13 36

3 Carpenter 5 3 8

4 Helper 6 3 9

5 Barbender 26 21 47

6 Helper 28 23 51

7 Flooring polish team 0

8 Welder 2 2 4

9 Painter 0

10 Others 0

11 Eletrician 0

12 JCB operator 0

13 Roller operator 0

14 Tracter Driver 0

Total 95 68 163

S.No Machinery Details Nos

1 JCB 1

2 Hitachi 140 1

3 Hitachi 220 1

16 Tractor 1

tipper (tauraus) 12 wheels 2

2 Vibro max Roller( 12 to 33) Ton 0

3 Bar bending mechine 3

4 Bar cutting mechine 3

5 Auto Leveling instrument 2

6 Total station 1

7 Hand cutting mechine for steel(14" DIA) 2

7 Hand cutting mechine for steel(6" DIA) 3

8 Wood cutting mechine 2

9 Mixer mechine 0

10 Concrete Breaker Machine 6 KG 1

12 Air blower 1

13 Drilling mechine 2

14 Electrical Vibrator 5

15 Petrol vibrator 3

17 Water tanker 0

18 Mud pump 5

B. Progress

  Progress Achieved on Previous day

Cumulative Qty
Sr.no Activity Unit Total Qty Yesterday's Qty
(till date) Balance to
Hindrance Remarks / Reasons of Delay (if any)
finish
TECH TOWER 2 Planned Actual Planned Actual

1 EARTHWORK CUM 8419 8419 8419 8419 8419 8419 0


2 LDPE SHEET SQM 2980 2980 2980 2980 2980 2980 0
3 M SAND FILLING CUM 338 318 292 292 292 292 46

4 PCC CUM 553 270 507 507 507 507 46

5 REINFORCEMENT MT 750 500 460 455 460 455 295


6 RCC CUM 3040 700 1883 1877 1883 1877 1163
Cumulative Qty
Sr.no Activity Unit Total Qty Yesterday's Qty
(till date) Balance to
Hindrance Remarks / Reasons of Delay (if any)
finish
TECH TOWER 2 Planned Actual Planned Actual

7 SHUTTERING SQM 170 50 125 120 120 120 50


TODAYS PROGRAM
Balance
Total Planned Actual
S.no Activity Unit Quantity to
Quantity Quantity
Remarks / Reasons of Delay (if any)
Quantity be done

TECH TOWER 2

1 EARTHWORK CUM 8419 0

2 LDPE SHEET SQM 2680 0

3 M SAND FILLING CUM 270 46

4 PCC CUM 405 46

5 REINFORCEMENT MT 500 295 26

6 RCC CUM 1200 865 400

7 SHUTTERING SQM 170 50 6


Cumulative Qty
Sr.no Activity Unit Total Qty Yesterday's Qty
(till date) Balance to
Hindrance Remarks / Reasons of Delay (if any)
finish
TECH TOWER 2 Planned Actual Planned Actual

8 BASEMENT BRICK WORKS CUM 345 0 9

TOMORROW PROGRAM
Planned
S.no Activity Unit Total Qty Remarks
Qty

1 EARTHWORK CUM 8419

2 LDPE SHEET SQM 2680


3 M SAND FILLING CUM 270
4 PCC CUM 405
5 REINFORCEMENT MT 500 15
6 RCC CUM 1200 8
7 SHUTTERING SQM 170 11
8 BASEMENT BRICK WORKS CUM 345 11